KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN DAN KONSERVASI ENERGI
DIREKTORAT ANEKA ENERGI BARU DAN ENERGI TERBARUKAN (DEA) Jakarta, November 2013
ESDM untuk Kesejahteraan Rakyat
1. CURRENT CONDITION Hydro Power Plant installed capacity 5,711 MW Micro-Mini Hydro Power Plant installed capacity MW
: : 230
2. DEVELOPMENT PROGRAM
Micro-Mini Hydro PP Encouraging investment in Micro-Mini Hydro PP through cooperative, private and other business enterprises in electricity supply based renewable energy, through the establishment of FiT (for on-grid system ) for Micro-Mini Hydro Power Plant appropriate economic price Encouraging capability of domestic manufacturer; Improving capacity building and technical assistance; Providing governmnet fund (APBN)
ESDM untuk Kesejahteraan Rakyat
MICRO-MINI HYDRO POWER PLANT FEED IN TARIFF (MEMR REGULATION 2012)for PriceNO for4 YEARPrice
WILAYAH
High Voltage (Rp/kWh)
Medium Voltage (Rp/kWh)
Jawa and Bali
656
1,004
Sumatera and Sulawesi
787
1,205
Kalimantan, West and East Nusa Tenggara
853
1,305
Maluku and Papua
984
1,506
Incentive Factor (F): Jawa, Bali Sumatera dan Sulawesi Kalimantan, NTB dan NTT Maluku dan Papua
:F=1 : F = 1,2 : F = 1,3 : F = 1,5
Hydro Energy
ESDM untuk Kesejahteraan Rakyat
HYDROPOWER POTENTIAL IDENTIFICATION
Hydro Power Potential Study (1983) : 75.000 MW 1249 Location
Sumatera 4.408,4 MW
Review Hydro Power Potential Study (1999) 3rd Screening : 21.480 MW 167 Location
Kalimantan 431 MW
Hydropower Master Plan Study ( 2011 ) : 12.893,9 MW – 89 Location
Sulawesi 3239,6 MW Papua & West Papua 49 MW
Molluca 156,4 MW Java 4.594,5 MW
NTT 15 MW
PROMISING SCHEME TO BE DEVELOPED IN FIXED TIME HORIZON
ESDM untuk Kesejahteraan Rakyat
HYDROPOWER and MINI HYDROPOWER IN OPERATION
REGION
PLN PLANT CAP (kW)
West Indonesia
10
855,060
East Indonesia
7
IPP TOTAL PLANT CAP (kW)
11
1,035,060
217,380
7
217,380
Java - Bali
19 2,335,220
19
2,335,220
GRAND TOTAL
36 3,407,660
37
3,587,660
REGION
1
1
PLN
PLANT
180.000
TOTAL CAP (kW)
180.000
IPP
CAP (kW)
PLANT
CAP (kW)
TOTAL
TOTAL CAP (kW)
West Indonesia
34
15,582
7
21,095
41
36,677
East Indonesia
37
43,430
8
26,340
45
69,770
Java - Bali
36
72,768
8
2,055
44
74,823
107
131,780
23
49,490
130
181,270
GRAND TOTAL
ESDM untuk Kesejahteraan Rakyat
HYDROPOWER DEVELOPMENT PLAN ( 2011-2020 ) MW
1200
1102
West Indonesia
East Indonesia
Java - Bali 968
1000 800 600
493
450
405
400 257
254
200 0
0
29 9
2011
95 78 68
2012
235 145
77 93 18
4
0
296
252
2013
2014
62 43
2015
132 37
2016
119 0
2017
0
2018
0
2019
2020
COD / Capacity ( MW ) 2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
West Indonesia
0
0
95
77
62
493
405
132
0
0
GRAND TOTAL 1264
East Indonesia
29
254
78
93
43
252
145
235
296
119
1544
9
4
68
18
257
1102
37
0
450
968
2914
38
258
241
188
362
1847
587
367
746
1087
5722
REGION
Java - Bali GRAND TOTAL
ESDM untuk Kesejahteraan Rakyat
MINI HYDROPOWER DEVELOPMENT PLAN ( 2011-2016 ) MW 180.0
West Indonesia
East Indonesia
Java - Bali 152.7
160.0
151.8
140.0 120.0
104.8 93.4
100.0 80.0
57.6
60.0 40.0 20.0
59.0
47.7
55.4 43.1
41.1 28.6
26.9
17.1
12.0
9.2
7.7
3.6
0.0
0.0 2011
2012
2013
2014
2015
2016
COD / Capacity ( MW )
West Indonesia
7.7
9.2
47.7
152.7
151.8
28.6
GRAND TOTAL 397.6
East Indonesia
17.1
26.9
93.4
59.0
55.4
12.0
263.8
0
3.6
57.6
41.1
104.8
43.1
250.2
24.8
39.7
198.7
252.8
312.0
83.7
911.6
REGION
Java - Bali GRAND TOTAL
2011
2012
2013
ESDM untuk Kesejahteraan Rakyat
2014
2015
2016
HYDROPOWER DEVELOPMENT MASTERPLAN
– August 2011 – Masterplan Study of Hydropower Development in Indonesia (Nippon-Koei) : • Highly promising Hydropower schemes can be developed until 2027 is 12.319 MW (no scheme in protected forest, resettlement ± 2.500 hoseholds). – Promising Hydropower schemes which already had a Prefeasibility Study or pass through the social and environmental screening can be developed to replace fuel fossil power plant in the system, i.e : Hydropower with reservoir or “daily pondage” can replace peaking gaspower plant. – PLN will develop around 60%, the other 40% will be developed by IPP. ESDM untuk Kesejahteraan Rakyat
HYDROPOWER PUMP STORAGE POWER PLANT
To meet the electricity demand during the peak load in Java-Bali system, a total of 2,440 MW Pump Storage Power Plant has been planned for the next ten years, consist of: UPPER CISOKAN P/S : 1,040 MW (Pre-construction Stage, expected COD : 2016) MATENGGENG P/S : 900 MW (Design Stage, expected COD : 2019/2020) GRINDULU P/S : 500 MW (expected COD : 2020) 75,5 m height of Upper Dam and 98 m height of Lower Dam will be build using RCC for Upper Cisokan P/S. 4 units of adjustable speed pump turbine and generator will be install in the underground Power House. Pump Storage with capacity of 400 MW in Sumatera and 800 MW sea water Pump Storage in East Java has been identified for future study. ESDM untuk Kesejahteraan Rakyat
Resouces
PRIMERY INDUSTRY
FINAL UTILITY Product
Downstream (Energy Conversion)
Upstream (Utilize Energy Resources)
PRODUK ENERGI
PLTA
Turbine
Water flow and Waterfall Resources
Electricity
Power Plant
Household
PLTM/H Potention Survey
Transportation
Water flow and Waterfall Energy
Industry Commercial
Wheel Mechanical Equipment (rice grinder, water pump, small industry)
ESDM untuk Kesejahteraan Rakyat
Non Electricity
INSTITUTION RELATION TO UTILIZE WATER FLOW AND WATERFALL ENERGY LEMBAGA
Upstream
Downstream
•Water flow and water fall policy •Determination of WATA
•IUKU •Commissioning
Department of Public Works
•Irrigation and Dam Construction •Permission to Use Water Resources
•Operation and Maintenance
Ministry of Forestry
•Permission to Borrow and Use Land
MEMR
Ministry of Environment
•AMDAL (large scale)
Indonesia Investment Coordinating Board
•Permission of Investment
Local Government
PLN
•Permission of Location •AMDAL / UKL-UPL (small scale) •Permission to Build Power Plant •Establish the Management Institutions •Tender Process (large scale) •Evaluation of Bid Documents(large and small scale) •PPA
•Power Plant •Transmission/ Distribution •Operation and Maintenance
•Untuk Bantuan pemerintah diperlukan lembaga pengelola yang dibentuk dan ditunjuk oleh Pemda yang salah satu fungsinya untuk melakukan pengusahaan dalam rangka keberlanjutan operasi pembangkit.
ESDM untuk Kesejahteraan Rakyat
Total: 75.000 MW ESDM untuk Kesejahteraan Rakyat
ESDM untuk Kesejahteraan Rakyat
HYDRO POWER JENIS ENERGI
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Additional Capacity (MW)
1,8
3,0
213,0
1.260,0
909,0
342,0
488,2
536,3
2.348,1
1.141,4
800,0
424,5
1.136,8
330,0
Cumulative Installed Capacity (MW)
6.866,9
6.869,9
7.082,9
8.342,9
9.251,9
9.593,9
10.082, 1
10.618, 4
12.966, 5
14.107, 9
14.907, 9
15.332, 4
16.469, 2
16.799, 2
Million STM
6,27
6,27
6,47
7,62
8,45
8,76
9,21
9,70
11,84
2,88
13,62
14,00
15,04
15,34
REALIZATION (MW)
6,654
% Reelization
99%
ESDM untuk Kesejahteraan Rakyat
Law that Regulate Utilization of New and Renewable Energy (Hydro Power)
ESDM untuk Kesejahteraan Rakyat
Coordination and Synchronization Regulation about Utilization of Water Energy for Power Plant
ESDM untuk Kesejahteraan Rakyat
Law 30/2007 about Energy Law 7/2004 about Water Resources
Hydro Energy is energy contained in the water flow and waterfall (Law 7/2004 ) Based onLaw 30/2007 Article 1 point 6, water energy is classified as a renewable energy
ESDM untuk Kesejahteraan Rakyat
Potential Identification
Proposal
• Started from the acceptance of proposal from prospective developer to PLN Unit until approval of permission proposal of application for appointment of Direct Power Purchase by PLN Unit to PLN center • Started from the acceptance of permission proposal of application for appointment of Direct Power Purchase by PLN Unit until approval of Power Purchase Direct Appointment of the Director General of Electricity / Ministry of Energy and Mineral Resources
PPA Process
PPA
• Started from the acceptance of Power Purchase Direct Appointment of the Director General of Electricity / Ministry of Energy and Mineral Resources until PPA is signed by PLN • Started from signature for the PPA between PLN Unit and prospective developer until the financial closure date is agreed
Construction
• Started from agreement of the financial closure date between PLN unit and prospective developer until agreement of commercial operation date (COD)
Operation ESDM untuk Kesejahteraan Rakyat
• Started from the implementation of COD until the end of the contract
Studies, Budgeting & Procurement
• Started from Feasibility Study, design (basic design and detail design. Bid document, procurement process until preparation of the construction (design report, budgeting: government budget, assistance, loan, etc)
Construction
• Started from early stage of construction until COD
Operation
• Started from the implementation of COD until the end of the contract
ESDM untuk Kesejahteraan Rakyat
Terima Kasih
Go Green Indonesia ! KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN, DAN KONSERVASI ENERGI Jl. Pegangsaan Timur No. 1A, Cikini, Jakarta 10320 Tlp. (021) 39830077
www.ebtke.esdm.go.id
[email protected]