REPUBLIC OF INDONESIA MINISTRY OF PUBLIC WORK AND HOUSING DIRECTORATE GENERAL OF HIGHWAY DIRECTORATE OF ROAD NETWORK DEVELOPMENT
QUARTERLY PROGRESS REPORT NO. 7 OCTOBER - DECEMBER 2015
TECHNICAL ASSISTANCE FOR SUPPORT OF PROJECT MANAGEMENT UNIT OF REGIONAL ROADS DEVELOPMENT PROJECT UNDER : ADB LOAN NUMBER 2817-INO IDB FINANCING NUMBER 0161 IND
RENARDET S.A. CONSULTING ENGINEERS
Joint Venture With : 1. PT. Multi Phi Beta 2. PT. Widya Graha Asana 3. PT. Disiplan Consult 4. PT. Anugerah Kridapradana
MINISTRY OF PUBLIC WORKS AND HOUSING DIRECTORATE GENERAL OF HIGHWAYS DIRECTORATE OF ROAD NETWORK DEVELOPMENT
Core Team Consultant (CTC)
for
Regional Roads Development Project (RRDP) ADB Loan No.2817{NO
i
Ref. : RRDP-3B9l2Bl7-INOl04_02_0Ufill6 Jakafta,4 February 2016 Encl : Reports Chief of Sub Directorate Planning & Programming Officer in Charge of PMU-RRDP Gedung Sapta Taruna, Lt.7 JL. Pattimura No. 20, Kebayoran Baru Jakarta :
. \r
For the attention by: Bapak DR.
Ir. Slamet Muljono, M.Eng.Sc
Subject: Loan No. 2817-INO (ADB) and Financing 0161-IND (IDB): Regional Roads Development Project (RRDP) Quarterly Progress Report No. 7, October - December 2015 Dear Bapak, Please find attached twenty (20) copies
in English of the
No. 7, October - December 2015 for your kind attention.
RRDP Quarterly Progress Repoft
We trust that this meets your satisfaction.
Yours fa
1.
2. 3.
4. 5. 6. 7. B.
9. 10.
Director of Road Network Development, DGH (as a report) Head of Sub Directorate of Integrated Planning and Road Network, DGH Head of Sub Directorate of Technical Environment and Road Safety, DGH Head of Sub Directorate Technical Reconstruction, DGH Head of Sub Directorate Monitoring and Evaluation, DGH Chief of Satker PAP2PHLN, DGH Section Head of Integrated and Planning, DGH Country Dlrector Indonesia Resident Mission of ADB, Jakafta Resident Representative Country Gateway Office Islamic Development Bank DSC-1, Kalimantan
1i. DSC-2, Central Java 72. DSC-3, East Java Renardet S.A & Associates 74. File
13.
aiointventureof RenardetS.A.PTMulti Phi Beta. PTWidvaGrahaAsana. PTDisiplanConsult. PTAnugerahKridapradana CTC-RRDP
Office: Wisma lskandarsyah, Jl. lskandarsyah Raya Kav. 12-14, Blok C-6, Kebayoran Baru - Jakarta Selatan 12160 Ph. (O21\ 127 89636; Fax. (0211 727 89538, Email:
[email protected]
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
TABLE OF CONTENTS
1.
Table of Contents
i
Executive Summary
1
1.1
Project Description
1
1.2
Current Implementation
1
1.2.1 Procurement
1
1.2.2 Civil Works
1
1.2.3 Consultancy Services
8
Current Status of Loan
8
1.3 2.
General
9
2.1
Reporting Requirements
9
2.2
Loan Status
10
2.3
Financial Management
11
2.4
Project Cost Monitoring
13
2.5
ADB Missions
14
2.6
Project Steering Committee Meeting
14
2.7
Loan Closing Date
14
3. Project Management and Implementation
14
3.1
Procurement Plan
14
3.2
Procurement Status
14
3.3
Implementation Status – Civil Works
15
3.4
Details of Variation Orders
15
3.5
Implementation of the Anti-Corruption Plan
23
3.5.1 Community Representative Observer (CRO)
23
3.5.2 Third Party Monitoring (TPM)
23
3.5.3 Complaint Handling System (CHS)
23
3.6
Implementation of the Environmental Management Plan
23
3.7
HIV-AIDS and Anti Human Trafficking Program
25
3.8
Monitoring of Health and Safety
42
3.9
Resettlement & Rehabilitation Activities
43
3.9.1 Preparation of LARP
43
3.9.2 LARP Implementation
43
Seminars, Workshops & Training
54
4.1 Estimated Funding Status for RRDP Civil Works and Consultant Services.
54
5.
RRDP Website
54
6.
Documentation Collection and Scanning
55
4.
i
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
Forms Form A
General
2 Sheets
Form B
Summary of Implementation
2 Sheets
Form C
Status of Problems
2 Sheets
Form D
Contract Package Status
Form E
Details of the Budget
17 Sheets 1 Sheets
ii
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
Appendices Appendix 1
Overall Financial Status
Appendix 2
Procurement Plan
Appendix 3
Project and Cost Monitoring
Appendix 4
Details Variation Orders Up to End June 2015
Appendix 5
Summary of Contract Data
Appendix 6
Unsettled Complains
Appendix 7a
CROs Activities on RRDP
Appendix 7b
Status of CRO Reports
Appendix 8
EMP Compliance ( Up to end June 2015 )
Appendix 9
Status of Social Safeguard Study.
Appendix 10
Status of Monitoring of Environmental Mitigation on RRDP
Appendix 11
Overall Land Acquisition Status End June 2015
Appendix 12
Environmental Safeguards
Appendix 13
Construction programme
Appendix 14a
Cost Estimated of Civil Works Packages
Appendix 14b
Cost Estimated of Consultant Sevices
Appendix 15
Monitoring Health and Safety During Construction
Appendix 16
.Abbreviation and Acronyms
iii
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
1.
Executive Summary 1.1 Project Description The RRDP project is an aided project from the Asian Development Bank (ADB) Loan No. 2817-INO and financing from the Islamic Development Bank (IDB) Agreement No.0161-IND. The RRDP Project will improve strategic National Road Corridors in North Kalimantan, Central and East Java to support economic growth in the developed and poorer areas of Indonesia. The National Road Network in southern Java is incomplete, with some road sections of the southern Trans Java Highway not yet constructed resulting in gaps in the network. Similarly, road network improvements are needed to support economic development in the less developed and remote districts in North Kalimantan and improve road connections from Kalimantan to the border. The project includes a component for the rehabilitation of 476 km of National Roads consisting of road new construction, resurfacing and widening and bridge rehabilitation and replacement. Total project length is 3,390 metres in two (2) provinces in Java and two (2) provinces in Kalimantan. 1.2 Current Implementation 1.2.1 Procurement All sub-projects have commenced with pre-qualification in 20 December 2011 through ICB procurement process. West Kalimantan The last package to commence 30RCP01 (CW-05) (Sosok – Tayan) commenced 15 June 2015, the Contract Agreement for this package having been signed on 15 January 2015. North Kalimantan Procurement of four (4) Civil Work package in North Kalimantan completed and all works commenced in 2014. Central Java Contracts for CW-1 was signed on 12 January 2015, for CW-2 13 January 2015 and CW-3 on 7 January 2015.. The Commencement of Works (COW) for Lots 1, 2 and 3 was 3 August, 2015, 23 July, 2015 and 5 June 2015 respectively. 1.2.2 Civil Works All of eleven (11) packages have been contracted through ICB tender process, and all eleven (11) packages have commenced as shown in the table below:
1
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
Ref
Package No
Package Name
Contract Sign
COW
Province
CW-04
28-RCP-01
Jolosutro – Sandang Biru
21 Aug 2013
18 Oct 2013
East Java
CW-06
30-RCP-02
Tebas – Singkawang (Sec 1) Tebas – Singkawang (Sec. 2) ByPasss Sambas Galing-Tanjung Harapan
14 Nov 2013
17 Dec 2013
West Kalimantan
CW-7
30-RCP-03
Sp.Tanjung – Galing Aruk(Bts.Serawak-Sp.Tanjung
27 Nov 2013
4 Dec 2013
West Kalimantan
CW-08
34-RCP01
Tanjung Selor-Sp.3 Tj. Palas – Sekatakbuji
3 Nov 2014
12 Dec 2014
CW-09
34-RCP02
Sp.3 Tanjung Palas –Sekatak Buji (Section 2)
25 Jun 2014
4 Sept 2014
CW-10
34-RCP-03
Sp. Tiga Apas – Simanggaris (Section 1)
11 Apr 2014
10 July 2014
CW-11
34-RCP-04
Sp. Tiga Apas – Simanggaris (Section 2); Simanggaris – Bts. Negara (Serudong)
11 April 2014
1 Oct 2014
CW-05
30-RCP01
Sosok – Tayan
15 Jan 2015
15 Jun 015
Tanjung – Bts Kota Sanggau CW-01
24-RCP01
Tambakmulyo - wawar
13 Jan 2015
3 Aug 2015
CW-02
24-RCP02
Giriwoyo - Duwet
12 Jan 2015
23 Jul 2015
CW-03
24-RCP03
Wawar - Congot
7 Jan 2015
5 June 2015
East Kalimantan
West Kalimantan
Central Java
The table below shows the actual physical progress at the end of this fourth quarter 2015: Package
JolosutrioSendangbiru (CW-04)
Sosok – Tayan (CW-05)
Tebas- Singkawang. Bypass Sambas Galing-Tj.harapan (CW-06)
Province
Contractor
East Java
Physical Progress % Sche d
Actual
Diff.
PT.Hutama Karya
79.87
76.41
-3.46
West Kalimantan
PT. Yasa Patria Perkasa; PT. Budi Bakti Prima -JO
1.42
8.71
7.29
West Kalimanatan
PT.Brantas Abipraya. Tri Citra Perdana Trifa Abadi -JO
58.24
58.26
0,02
2
Remarks
To Addendum No.3 signed 20 March 2015.
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
Package
Sp.Tanjung-Galing Sp.Tanjung –Aruk (CW-07)
Tanjung Selor – Sp.3 Tj.PalasSekatakbuji (Sect 1), (CW-08)
Sp.3 Tanjung Palas – Sekatak Buji (Section 2 ), (CW09).
Sp.Tiga Apas – Simanggaris (Section 1). (CW10) Sp.Tiga Apas – Simanggaris (Section 2). SimanggariBts.Negara (Serudong) (CW-11)
Province
Contractor
West Kalimantan
North Kalimantan
North Kalimantan
North Kalimantan
North Kalimantan
Wawar – Congot (CW-03)
Central Java
Giriwoyo – Duwet (CW-02)
Central Java
Tambakmulyo – Wawar (CW-01)
Central Java
Physical Progress %
Remarks
Sche d
Actual
PT.Waskita Karya PT.Yasa Patria Perkasa
39.27
37.12
-2.16
Technical Justification/ Add No.1 additional work submitted to ADB
PT. Waskita Karya
30.28
43.75
13.47
COW 12 Dec 2014
PT. Brantas Abipraya ; PT.Mahir Jaya Mahakam Raya – JO
52.69
38.99
-13.70
Behind Schedule
PT.Perdasa- JO
36.26
40.12
3.87
Behind Schedule
Halla Corporation
14.13
12.02
-2.11
Behind
17.52
14.41
-3.12
Behind
2.93
2.94
0.01
1.12
2.24
1.12
Diff.
PT Pem.Perumahan
PT.Jaya Konstruksi Manggala Pratama PT. Hutama Karya (Persero) PT. Pembangunan Perumahan (Persero)
The location of RRDP Packages is shown on the following Project Location Maps.
3
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
WEST KALIMANTAN
4
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
NORTH KALIMANTAN
5
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
EAST JAVA
6
PMU RRDP – Quarterly Progress Report No. 7, October – December 2015
CENTRAL JAVA
7
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
1.2.3
Consultancy Services
TA Consultant
Planned Mobilization from the Project Admin. Manual (PAM)
Contract Signed
Actual Mobilization
Responsible Agency
CTC (CSP-1)
April 2012
12 Feb 2014
3 Mar 2014
DGH
DSC-1 (CSP-2)
April 2012
21 Nov 2013
16 Dec 2013
DGH
DSC-2 (CSP-11)
Jan 2014
15 May 2015
DGH
18 Oct 2013
DGH
DSC-3 (CSP-3)
Sep 2013
14 Apr 2015 16 Oct 2013
Road Safety Support (CSP-4)
Jan 2013
6 Oct 2015
Institutional development for Road Network Management (CSP-5)
Jan 2013
Not yet
DGH
Road safety awareness Campaign and Training (CSP-6)
Jan 2013
Not yet
DGLT
Integrated Vehicle Overloading Control Strategy (CSP-7)
Jan 2013
Indonesia Transport Sector Dev. Strategy and Policy (CSP-8)
Jan 2013
Not yet
Bappenas
Overloading and Speed Enforcement (CSP-9)
Jan 2013
Not yet
DGLT
HIV/ AIDS anti Trafficking Program (CSP-10))
Jan 2013
Road Safety Equipment
Sept 2013
19 Nov 2015
6 Oct 2015
7 Oct 2015
DGH
January 2016
7 Oct 2015
Not yet
Remarks
Cancelled by DGLT
DGNTP
Cancelled by DGLT
DGH DGNTP
The appointment of some Consultancy Services has been delayed for reasons including the procurement process. There have been delays in appointments for Technical Assistant Consultant services CSP-4 to CSP-10. . For the CSP-6 and CSP-9 were cancelled by DGLT as they informed at the Wrap-up Meeting Project Review Mission ADB on 12 November, 2015 1.3 Current Status of Loan At the end of this Fourth Quarter 2015, December
2015, the progress in
disbursement is as shown. The disbursement of US $ 54,712.095.37 is only 22.33% of the available loan, has been disbursed against a scheduled 37.07% with Twenty Two (22) months of the loan period already elapsed..
8
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Loan Extension Proposal: Proposal for an Extension of the Loan Period were submitted to the ADB on 13 March 2015; and approval was given 5 June, 2015; reasons for extension of loan period were: a. The loan extension was based on the estimation for the completion of Civil Works activities where it is currently believed that seven (7) Packages would not be finished before the Loan Closing date of 31 August 2016. b. Documents/ Signing of Contract for Package CW-05 (Sosok-Tayan and Tanjung Bts. Kota Sanggau) was delayed and early 2015 with work anticipated to commence mid April 2015 with a Construction Period of thirty six (36) months, Civil works could be completed until April 2018. c. Considering a time for completion of the Civil Works at Package CW-05 of April 2018 and allowing three (3) months for Contingencies, the Loan Extension period proposed was twenty three (23) months i.e. to 31 July 2018. Details of the overall loan situation are presented in Forms A through to E after the text of this report. These Forms are an English translation of the quarterly report prepared by PMU for Bappenas. 2.
General 2.1 Reporting Requirements Quarterly Progress Reports: This is the sixth (6th) Quarterly Progress Report to be prepared and covers the Third (3rd) Quarter of 2015. Report
Period Covered
Final Version Issued
Quarterly Progress Report No.1
March 2014 – June 2014
May 2015
Quarterly Progress Report No.2
July – September 2014
May 2015
Quarterly Progress Report No.3
October – December 2014
May 2015
Quarterly Progress Report No.4
January – March 2015
June 2015
Quarterly Progress Report No.5
April- June 2015
July 2015
Quarterly Progress Report No. 6
July - Sept 2015
October 2015
Quarterly Progress Report No. 7
Oct – Dec 2015
January 2016
Financial Monitoring Reports: Reports have been prepared for each quarter since early 2014, the first and the second were issued in July 2014, covered the period January – June 2014. Since that date, reports have been prepared each quarter on schedule as shown in the table below.
9
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Report
Period Covered
Date Issued
Financial Monitoring Report No.1
January – March 2014
10 July 2009
Financial Monitoring Report No.2
April – June 2014
Financial Monitoring Report No.3
July – September 2014
5 November 2014
Financial Monitoring Report No.4
October - December 2014
January 2015
Financial Monitoring Report No.5
January – March 2015
April 2015
Financial Monitoring Report No.6
April – June 2015
July 2015
Financial Monitoring Report No. 7
July - Sept 2015
29 October 2015
Financial Monitoring Report No.8
October – December 2015
January 2016
CTC Monthly Progress Reports: These reports have been prepared covering each full month since CTC mobilized in March 2014 the first, covering the month of April 2014. Report
Period Covered
Final Version Issued
Monthly Progress Report No.10
January 2015
26 March 2015
Monthly Progress Report No.11
February 2015
27 March 2015
Monthly Progress Report No.12
March 2015
15 April 2015
Monthly Progress Report No.13
April 2015
9 June 2015
Monthly Progress Report No.14
May 2015
23 June 2015
Monthly Progress Report No.15
June 2015
July 2015
Monthly Progress Report No. 16
July 2015
August 2015
Monthly Progress Report No. 17
August 2015
September 2015
Monthly Progress Report No. 18
Sept 2015
Oct 2015
Monthly Progress Report No. 19
Oct 2015
Nov 2015
Monthly Progress Report No. 20
Nov. 2015
Dec 2015
Monthly Progress Report No.21
Dec 2015
Jan 2016
2.2 Loan Status The agreed allocation of loan funds from the original loan agreement together with the % disbursed to the end of the quarter is presented in the following table:
Categ ory
Description
Loan ADB Amount US$ Reallocation 5 June 2015
1
Civil Works
155,000,000
2
Road Safety Equipment
2,200.000
Financing IDB Amount US$
53,500,000
10
Totals Disbursed to End Dec 2015 in US$
% Disbursed
ADB
IDB
45,017.94
6,455.90
24.69
0
0
0
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
3
Consulting Services
20,200,000
3,000,000
2,935.00
303.26
21.30
4
Un allocated
2,600,000
8,500,000
0
0
0
180,000
65,000
47,952.93
6,759.16
22,33
Original Loan Amount
Details of the overall loan Status can be found in Appendix 1 2.3 Financial Management S-Curve for Financial Progress The following curve shows the financial disbursement progress up to the end of December 2015:
11
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Current Loan Allocation and Disbursement (%) to Date
% complete
100.00 95.00 90.00 85.00 80.00 75.00 70.00 65.00 60.00 55.00 50.00 45.00 40.00 35.00 30.00 25.00 20.00 15.00 10.00 5.00 -
22.33
Jul-18 Jun-18 May-18 Apr-18 Mar-18 Feb-18 Jan-18 Dec-17 Nov-17 Oct-17 Sep-17 Aug-17 Jul-17 Jun-17 May-17 Apr-17 Mar-17 Feb-17 Jan-17 Dec-16 Nov-16 Oct-16 Sep-16 Aug-16 Jul-16 Jun-16 May-16 Apr-16 Mar-16 Feb-16 Jan-16 Dec-15 Nov-15 Oct-15 Sep-15 Aug-15 Jul-15 Jun-15 May-15 Apr-15 Mar-15 Feb-15 Jan-15 Dec-14 Nov-14 Oct-14 Sep-14 Aug-14 Jul-14 Jun-14 May-14 Apr-14 Mar-14 Feb-14 Jan-14 Dec-13
Original based PAM
Planned Disbursement
L o a n Amo u n t (US$ 0 0 0 ) Ca te go ry
Civil Work
To ta l Disbu rse d to 3 1 De c 2 0 1 5
ADB O rigin a l
Actual Disbursement
IDB
Re a llo c a tio n 5 Ju n e 2 0 1 5
O rigin a l
IDB
155,000.00
155,000.00
1,300.00
2,200.00
12,200.00
12,200.00
Road Sector Dev. Program
5,600.00
5,600.00
-
-
-
-
Road Sector Program
3,300.00
2,400.00
-
-
-
-
Unallocated
2,600.00
2,600.00
8,500.00
-
-
-
1 8 0 ,0 0 0 .0 0
1 8 0 ,0 0 0 .0 0
6 5 ,0 0 0 .0 0
Road Safety Equipment Consultant Services
L o a n Amo u n t
53,500.00
ADB
% Disbu rse d
45,017.94 -
3,000.00
12
2,935.00
4 7 ,9 5 2 .9 3
6,455.90 303.26
6 ,7 5 9 .1 6
24.69% 21.30%
2 2 .3 3 %
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
2.4
Project Cost Monitoring A summary of the project cost monitoring in tabular format is presented as Appendix No. 3. Status:December 2015
Sub-Project Name / Package Contract Number NO. CENTRAL JAVA PROVINCE CW-01 Tambakmulya - Wawar 24-RCP-01 01/24-RCP-01/NR/IDB/0161/0115 CW-02 24-RCP-02
Giriwoyo - Duwet
Length (km)
38.46
23.75
Name of Contractor
Current Contract Value Including Amendments if any
PT. Pembangunan Perumahan (Persero) -
243,741,564,000.00
PT.Hutama Karya (Persero)
142,000,000,000.00
Originil
Originil
Contract Data Date of Date of Contract COW 12-Jan-15
13-Jan-15
3-Aug-15
23-Jul-15
Const. Period
Time Ellapse Days / %
Completion Date
1,095
143 Days 13.06 %
2-Aug-18
154 Days 21.10 %
22-Jul-17
202 Days 55.34 %
4-Jun-16
797 Days 88.07 %
10-Apr-16
192 Days 17.53 %
14-Jun-18
737 Days 67.31 %
15-Dec-16
750 Days 68.49 %
4-Jun-17
377 Days 51.64 %
11-Dec-16
476 Days 65.21 %
2-Sep-16
532 Days 59.11 %
25-Dec-16
730
hk.02.03/bjgd/24-RCP-02/I/2015/01 CW-03 24-RCP-03
Wawar - Congot
14.13
PT. Jaya Konstruksi Manggala Pratama, Tbk
58,253,088,000.00
Originil
7-Jan-15
5-Jun-15
365
02/24-RCP-03/NB/IDB/0161/0115 EAST JAVA PROVINCE CW-04 Jolosutro - Sendang biru 28-RCP-01A
21.3
PT. Hutama Karya (Persero)
93,350,000,000.00 93,350,000,000.00 98,889,601,000.00 112,823,335,000.00
Originil Add.1 Add.2 Add.3
PT. Yasa Patria Perkasa; PT. Budi Bakti Prima, JO
465,647,542,528.81
Originil
PT.Brantas Abipraya PT. Tri Citra Perdana PT.Trifa Abadi JO
292,603,385,000.00 407,294,892,000.00
Originil Add.1
14-Nov-13 28-Aug-15
17-Dec-13
PT. Waskita Karya PT. Yala Patria Perkasa
238,974,973,000.00 325,740,200,000.00
Originil Add.1
26-Nov-13 20-Oct-15
4-Dec-13
01/28-RCP-01A/RB/ADB/2817/0813
WEST KALIMANTAN PROVINCE CW-05 Sosok - Tayan 30-RCP-01 Tanjung - Bts.Kota Sanggau 02/30-RCP-01/RB/ADB/2817/2015 CW-06 30-RCP-02 CW-07 30-RCP-03
Tebas - Singkawang Sambas Bypass Galing - Tanjung Harapan 02/30-RCP-02/RB/ADB/2817/1113 Sp.Tanjung - Galing; Aruk (Bts Serawak)- Sp.Tanjung 03/30-RCP-03/RB/ADB/2817/1113
NORTH KALIMANTAN PROVINCE CW-08 Tj.Selor - Sp.3 Tanjung Palas 34-RCP-01 Sp.Tanjung - Sekatakbuji (Sect 1) 01-34/RCP/LOAN/PJN.III/11.14
CW-09 34-RCP-02
Sp.3 Tj.Palas - Sekatak Buji (Section 2) 02-34-RCP/LOAN/PJN.III/06.14
CW-10 34-RCP-03
SP.3 Apas - Simaranggis (Sect 1)
79.2
29.8 6.1 20 40.91 11.13
21-Aug-13 24-Dec-13 18-Dec-14 20-Mar-15 15-Jan-15
18-Oct-13
730
65.03
PT. Waskita Karya
PT.Brantas Abipraya
189,970,248,000.00
165,332,338,000.00
Originil
Originil
3-Nov-14
25-Jun-14
15-Jun-15
1,095
1,095
1,095
12-Dec-14
4-Sep-14
730
730
PT.Mahir Jaya Mahakam Raya
45.00
PT.Pemb. Perumahan PT.Perdasa JO
289,000,000,000.00 313,142,781,000.00
Originil Add.1
11-Apr-14
359,652,697,000.00
Originil
11-Apr-14
10-Jul-14
900
03-34-RCP/LOAN/PJN.III/04.14
CW-11 34-RCP-04
SP.3 Apas - Simaranggis (Sect 2) Simaranggis - Bts. Negara 04-34-RCP/LOAN/PJN.III/04.14
27.15 20.60
Halla Corporation
Disbursement (IDR) Loan Financing
Re ma rks
%
%
Schedule : 1.121 Actual : 2.239 Slippage : 1.118
50,161,413,699.00 20.58%
IDB : 100%
- Proposed of Variation Order process in BBPJN V
Schedule : 2.927 Actual : 2.935 Slippage : 0.008
30,250,000,000.00 21.30%
IDB : 100%
- Proposed of Variation Order process in BBPJN V
Schedule : 17.519 Actual : 14.412 Slippage : -3.107
13,507,537,381.00 23.19%
IDB : 100%
- Proposed of Variation Order process in BBPJN V
Schedule : 79.867 Actual : 76.408 Slippage : -3.459
70,702,881,379.00 62.67%
ADB : 70%
- Progress Slowly
Schedule : 1.422 Actual : 8.709 Slippage : 7.287
84,012,996,053.00 18.04%
ADB : 70%
- Proposed of Variation Order process in BBPJN VII
Schedule : 58.243 Actual : 58.259 Slippage : 0.016
199,856,880,711.00 49.07%
ADB : 70%
905
1,279
34.82
Physical Progress (%)
1-Oct-14
13
1,095
449 Days 41.00 %
29-Sep-17
- Proposed of additional length 12.3 Km in Sambas - Tanjung Harapan
Schedule : 39.268 Actual : 37.107 Slippage : -2.161
126,291,458,657.00 38.77%
ADB : 70%
- Proposed capacity expansion up to 4 lanes for 5.623 km length, need land acquisition requirement. - Need LARP implementation
Schedule : 30.280 Actual : 43.750 Slippage : 13.470
94,674,419,736 49.84%
ADB : 70%
Schedule : 52.689 Actual : 38.992 Slippage : -13.697
76,979,144,449 46.56%
ADB : 70%
Schedule : 36.255 Actual : 40.118 Slippage : 3.863
158,556,262,703 50.63%
ADB : 70%
- Need LARP Monitoring
Schedule : 14.125 Actual : 12.016 Slippage : -2.109
98,934,738,824 27.51%
ADB : 70%
- Revised of Variation Order process in BBPJN VII
- Need improvement for land slide locations, design process by DSC-1 - Revised of Variation Order process in BBPJN VII - Production stone crusher (blasting) waiting for permission of POLRI, BBPJN VII need support. - Need improvement for land slide locations, design process by DSC-1 - Proposed of Variation Order process in DGH
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
2.5 ADB Missions ADB Missions
The ADB with the IDB carried out Missions to East Java (ADB), Central Java (IDB) respectively commencing 15 September, 2015 finishing with West and North Kalimantan (ADB) on 12th November, 2015. IDB Missions
See the above 2.6 Project Steering Committee Meeting No Steering Committee meetings have been held to date. 2.7 Loan Closing Date The DGH submitted Explanatory Notes for proposed extension of loan proceeds end M a r c h 2015 to Bappenas, MOF and ADB and on 5 June 2015 the ADB
approved an extension of the Loan Period to July 31, 2018. 3.
Project Management and Implementation There were no major changes in project management during the quarter 3.1 Procurement Plan In Appendix No. 2 is presented a copy of the general Procurement Plan for all, Civil Works, Goods and Consulting Services of the project updated to the end of the third quarter of 2015. 3.2 Procurement Status Civil Works Procurement has been conducted under the Bank’s Procurement Procedures as described in the Loan Agreement. The International Competitive Bidding (ICB) will apply for packages with an estimated total cost of more than US$10 Million to comply with the Bank’s threshold. According to Government of Indonesia (GOI) regulation, prequalification shall be apply to all packages with construction estimated cost to be more than IDR 100 Billion. All Procurement is complete for eleven (11) packages with all construction is ongoing. Goods There were no for Goods procurement processed during the third quarter 2015. Services The status of Core Team (CTC), Supervision Teams (DSC-1, DSC2 and DSC-3), are discussed in Section 3.5 of this report. :
14
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
3.3 Implementation Status – Civil Works Construction commenced at Eleven (11) Packages as shown in the table below to end of December 2015. Contractor
Package CW-01 TambakMulyo Mawar CW-02 Giriwoyo - Duwet
PT. Pembangunan Perumahan – PT.Armada HG JO PT. HutamaKarya
CW-3 Wawar - Congot
PT.JayaManggala Konstruksi
CW-04JolosutroSendangbiru CW-05 Sosok – Tayan; Tanjung – Bts. Kota Sanggau CW-06 TebasSingkawang Bypass Sambas GalingTanjungHarapan CW-07 Galing – Sp.Tanjung Sp.Tanjung - Aruk CW-08 Tj.Selor – Sp.3 Tj. Palas Sp.3Tj.Palas Sekatakbuji CW-09 Sp.3 TanjungPalasSekatakbuji (Sect 2) CW-10 Sp.3 Apas – Simanggaris (Section 1) CW-11 Sp.3 Apas – Simanggaris (Section 2) SimanggarisBts.Negara (Serudong)
PT.HutamaKarya (Persero) PT.Yasa Patria Perkasa – PT.BudiBakti Prima -JO PT.BrantasAbipray a (Persero) PT.Tri Citra Perdana PT.TrifaAbadi –JO PT.WaskitaKarya. PT.Yasa Patria Perkasa
Contract Signed
Physical Progress (%) COW
Sched.
Actual
Slippage
12 Jan 15
3 Aug 15
1.12
2.24
1.12
13 Jan 15
23 Jul 15
2.97
2.94
0.01
7 Jan 15
5 June 15
17.52
14.41
-3.12
16 Oct 13
18 Oct 13
79.87
76.41
-3.46
15 Jan 15
15 Jun 15
1.42
8.71
+7.29
14 Nov 13
17 Dec 13
58.24
58.26
0.12
26 Nov 13
4 Dec 13
39.27
37.12
-2.16
3 Nov 14
12 Dec 14
30.28
43.75
13.47
25 Jun 14
4 Sept 14
52.69
38.99
- 13.70
11 Apr 14
10 July 14
36.26
40.12
3.86
11 Apr 14
01 Oct 14
14.13
12.02
-2.11
PT. WaskitaKarya (Persero)
PT.BrantasAbipray a (Persero), PT.Mahir Jaya Mahakam Raya PT.Pemb. Perumahan. PT.Perdasa
Halla Corporation
Below shows the progress to the 25th December 2015 and indicates any major issues and proposed solutions: East Java Packages 1. Package 28-RCP01A, Jolosutro – Sendangbiru. Activities: -Wonogoro Bridge casting concrete at Abutments and Backwall, treadplate, inlet/ outlet RCBC,
15
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
earthworks – placing of select embankment; work at Road Shoulders using Aggregate Class “S”, Drainage V- ditches and Mortared Stonework Retaining Wall; laying CTB & asphalt AC-WC. Work now progressing in accordance with Addendum No. 3 signed 20 March, 2015. Completion of drainage of Stone Mortared V-ditches, inlet and outlets to RCBC may not be completed in time due lack of material and Contractors implementation of the Works often slow due to lack of Shop Drawings and support. Some work items such as Road Shoulder Aggregate Class “S”, V-ditch Mortared Stone remain uncompleted. Materials such as Quarry Sand should be purchased at source; implementation Safety precautions should be carried out according to the Contract; V-ditch and Mortared Stonework should be implemented simultaneously to improve progress. Central Java Packages: 2. Package 24-RCP-01 Tambakmulyo - Wawar: Activities:- Clearing and Grubbing,
Common
Embankment,
Embankment Sta 0+500.
Common
Excavation;
placing
Select
Contractor late to anticipate rainy season and
determine alternative quarry which can be utilized. Another quarry to be located & accelerate process of permit. Draft Addendum No. 1 in process of approval. 3. Package 24-RCP-02 Giriwoyo – Duwet: Activities: - preparation r-bar and formwork, pouring concrete to Sasem Bridge Caisson and abutment/ wing wall Kalongan bridge; backfill to RCBC; Excavation for widening Pucang Anom Bridge; preparation r-bar RCBC Sta 13+700 and Tulakan Bridge. Ongoing excavation partly in rock but there is no rate in the BOQ. Several locations have poor site distances – to be covered in Review Design. Records kept regarding estimated quantities of Rock Excavation. Draft Addendum No. 1 in process of approval. 4. Package 24-RCP-03 Wawar – Congot. Activities: - Clearing and Grubbing, Placing Select Embankment, Grade preparation, Structural excavation for Box Culverts, installation Box Culverts (5No.), placing aggregate Class “B”, Stone Masonry for Retaining Wall; placing Lean Concrete. Contractor unable to start many items permanent work until design finalized and payment determined. Review Design to be finalized quickly by Balai V so that revised schedule can be drawn up and work commence. Draft Addendum No. 1 in process of approval. West Kalimantan Packages 5. Package 30-RCP-01, Sosok–Tayan; Tanjung – Sanggau border (CW-05) Activities: - Common excavation left and right sides in hilly terrain;
Grade
preparation, Traffic Management and Routine Maintenance, placing Aggregate
16
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Base Course Class A and hot mix Asphalt at Sosok-Tayan and Tanjung-Sanggau links; placing CTB and AC-BC (2) links. Progress has slowed with onset of rainy season. Contractor instructed to expedite erection and increase working hours in good weather. Draft Addendum No. 1 in process of approval. 6. Package
30-RCP-02,
Tebas-
Singkawang,
Bypass
Sambas,
Galing-
Tj.Harapan (CW-06) Activities: - excavation for widening, side ditch, placing Filter Fabric at widening segment 2; placing Granular Embankment for widening, placing Aggregate Class A and Class B at segment 4; laying AC-BC and AC-WC at segment 4, AC-BC segment 2. Missing link 12.4 km in length with severe road condition should be included in the Works by the issue of an Addendum to Contract. Accordingly Addendum No. 2 is in the process of approval. 7. Package 30-RCP03, Sp.Tanjung – Galling; Aruk- Bts. Serawak (CW-07) Activities:- Excavation and Grade preparation, Rock Excavation, placing Granular Select Embankment, installation of V-side ditch and Type DS-6 Drainage, placing Granular Select Embankment, placing Aggregate Class “A”, Structures – Box Culverts, Piling at Bridge Abutments and placing r-bar; installation of Temporary Bridge. December 2015: Contractor failed to bring crushed aggregates to the site so work at pavement almost stopped so incurring a negative slippage. Contractor proposes to bring crushed aggregates from Merak outside the project and build new jetty for barges; obtain permission from the Army for utilization of new quarry. Compaction equipment too few for the work. The last section to the border Aruk -Sp.Tanjung instructed by Government decree to widen last 11.00km to a 4-lane dual carriageway, with only 5.62 km included in RRDP Addendum No.1. Additional time required for completion required determined at 184 c. days. Completion of additional LARAP required for implementation. Packages in North Kalimantan 8. Package 34-RCP-01 Tj.Selor – SekatakBuji Section 1 (CW-08) Activities: Excavation and Embankment, Grade preparation, Pavement widening and shoulders, installation of Side Ditches, placing Granular Pavement, Box Culvert, Structural Concrete Class K 250, AC-BC placing. Work curtailed due to onset of rainy season and high rainfall. Contractor advised to accelerate excavation earthworks during drier weather. Protection required at landslide locations. Design and required draft Addendum No.1 in process.
17
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
9. Package 34-RCP-02 Sp.3 Tj.Palas – SekatakBuji, section 2 (CW-09) Activities: - Preparation & Concreting V-side Ditches, placing Aggregate Class A & Class B, placing Stone Masonry and Mortar Stone Masonry, installed AMP Ambalat now operational. Supply of raw materials/ aggregate not sufficient - lack of transportation of aggregates; RCP production too low and production of Concrete V-ditch requires increasing. Protection required at landslide locations. Design and required draft Addendum No.1 in process by DSC-1/ DGH. 10. Package 34-RCP03 Sp.3 Apas – Simanggaris (Section1) (CW-10) Activities: - Excavation and Embankment, Side Ditches and Grade preparation, Placing Granular Select Embankment, laying CTB and AC-BC. Procurement of materials, Cash Flow, production of aggregates, contract implementation/ supervision by Contractor inadequate. Contractor agreed to add Stone Crusher for CTB, AC-BC and AC-WC production. 11. Package 34-RCP04 (CW-11), Sp. 3 Apas – Simanggaris (Section 2) (CW-11) Activities: - Common excavation and Rock Excavation, Common Embankment, Granular Select Embankment, V-ditch Type DS-6 drainage, Concrete to Abutments, CTB, Concrete Class 250 and 175 in progress. Apparent lack of crushing plant and insufficient dump trucks for earthworks. Contractor instructed to expedite additional resources. Contractor claims Design Drawings don’t match actual site conditions. Approval of Design Review/ Addendum No.1 in process. 3.4 Details of Variation Orders See Appendix No.3 for Details of Variation Orders Consultancy Services: Core Team Consultant (CTC) Contract No.03-02/CTC/PM/LN/ADB/2817.0214 was signed on 12 February 2014, between the Ministry of Public Works, Directorate General of Highways and Lead Consultant Renardet S.A
in a Joint Venture with Local Consultants PT.Widya
Graha Asana; PT.Multi Phibeta; PT. Anugerah Krida Pratama; PT.Disiplan Consultant as the Core Team Consultant (CTC). CTC Personnel commenced mobilization in the project at end March 2014 The NOL for Addendum No.1 to the CTC Contract was issued by ADB on 19 March 2015, the final is currently in process for the signing.
18
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
The following table indicates the current status Contract/ Addendum for the CTC Contract: Contract
Dated
US$ (Ex.VAT)
IDR (Ex. VAT)
Original Contract
12 Feb 2014
1,192,400
19,472,500,000
Addendum No.1
19 March 2015
1,473,900
22,584,677,000
Addendum No. 2
Draft submitted 25 Nov 2015
Design Supervision Consultants (DSC) Under the Regional Roads Development Project (RRDP), three (3) Design and Supervision Consultants (DSC) are required with the Team Leader from each of the Design and Supervision Consultants to act as “The Engineer” as defined in the FIDIC Conditions of Contract. DSC are
responsible for checking
completed
designs, monitoring construction Quality and Progress, certifying of Monthly Interim Payment Certificates (IPCs) and preparing and submission of Monthly Progress Reports. Design and Supervision Consultants will be responsible for the Design and Construction Supervision of all Civil Works. The task includes the maintenance of a Quality Assurance Plan (QAP), Environmental Monitoring Plan (EMP), Health and Safety Plan and Traffic Safety Plan, and the validation/ updating of designs. The DSC1 and DSC3 Teams contracted and managed by DGH through the Bina Marga Regional Office (Balai) are based in Banjarmasin and Surabaya; with DSC-2 (Central Java) based in Yogyakarta. The DSC-2 Contract with Botek Bosphorous Technical Engineering (Turkey) was signed 14 April 2015. DSC-1 (Kalimantan Region) DSC-1 for West Kalimantan and East Kalimantan is China Engineering Consultants Incorporated (CECI), in Joint venture with PT.Wira Wydiatama; PT.Hasfarm Dian Konsultan; PT.Yodya Karya; PT.Seecons; PT.Pola Agung Consulting who were mobilized on January 2014 with the Team Leader Mr.Lin, Hung-Cheng acting as “the Engineer”. The original Contract for DSC-1 is US$ 936.570 and IDR 30.372.995.000 (excl VAT). DSC-1 has a total of seven (7) packages, six (6) packages are ongoing and one (1) package has been signed the Contract Agreement (30 - RCP01). The contractor awaits processing of Advance Payment as a condition for the commencement of work (GCC Cause 8.1). ADB has commented on the draft Addendum No.1 DSC-01 on 5 January 2015. The NOL for draft Addendum No.1 to the DSC-1 Contract was issued by ADB on 7 April 2015.
19
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
After approval of the draft addendum 1, the value of the Contract changed by US$589,920 plus IDR 36,353,305,000, (Excl VAT). Design Supervision Consultant (DSC-2), Central Java Province IDB issued NOL to the Bid Evaluation Report for Technical and Financial proposal for DSC-2 on 28 December 2014. The Consultant to act confirmed as DSC-2 is BOTEK BOSPHOROUS TECHNICAL ENGINEERING (Turkey) in association with five (5) local Consultants ACE (PVT) LTD, PT.Kwaesa Hexagon, PT.Binatama Wirawredha Konsultan, PT. Tata Guan Patria Copnsultant, PT.Caturbina Guna Persada.. The NOL for the draft Contract DSC-2 was issued by IDB 3 March 2015. The contract has been signed on 14 April 2015, between the Client with Turkish Consultant, Botek Bosphorous & Associates for the total amount of IDR 11,348,910,000 and US$725,740 (Exclude VAT). The mobilization of the Consultant commenced 11 May 2015 in Yogyakarta with the Team Leader Geoge W.Noble acting as the Engineer together with Co. Team Leader while Supervision Engineers (SE) for the three (3) packages mobilized in July, 2015. Design Supervision Consultant (DSC-3), East Java Province The DSC-3 for East Java is PT.PERENTJANA DJAYA mobilized on 20 January 2014 with the Chief Supervision Engineer Fajar Subianto acting as “the Engineer”. The Original Contract signed with DSC-3 is IDR 6.939.950.000 (Excl VAT), signed on 16 October 2013. Addendum No.1 submitted for DSC-3 was approved by the ADB on 29 October 2014. This Addendum No.1 increased the Contract Value to IDR 7.505.980.000, - (Excl VAT) signed 3 November 2014. The following table indicates the current status Contract/ Addendum for the DSC-3 Contract: Contract
Dated
IDR (Ex. VAT)
Original Contract
16 Oct 2013
6.939.950.000
Addendum No.1
3 Nov 2014
7.505.980.000
Addendum No.2
30 Nov 2015
8,830,085,000
Selection of Technical Assistant Consultant CSP- 4: Road Safety Engineering Support (DGH) EOI was submitted by Consultants on 20 September 2014 and the Evaluation Report for a Short List of Consultant was sent to ADB on 28 October 2014. “No Objection Letter” for short list of the consultant and draft of Request for Proposal (RFP) was issued by ADB on 9 December 2014. Invitations to the shortlisted Consultants was issued on 29 December 2014 and submission of proposals on 23 February 2015. Pokja evaluated the Technical proposal and this sent to ADB on 12 March 2015; ADB issued “No Objection Letter “ 20 March 2015. Financial Proposals
20
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
were opened on 31 March 2015. Pokja completed evaluating the combined Financial and Technical Proposals and Report sent to the ADB on 27 April 2015. ADB issued the No Objection Letter (NOL) on 18 May 2015 and Clarification and Negotiation with the highest rank was held on 10 June 2015. Clarification and negociation and drft Contracts have been completed by Pokja and documents sent toADB on 18 August, 2015. ADB issued NOL on 23 September. The contract has been signed on 6 October 2015.DGH submitted the signed contract to ADB on 3 November and ADB issued letter of No Objection on 13 November, 2015. CSP - 5: Capacity Development Program (DGH) A Coordination meeting was held between the relevant sections of DGH and CTC presided by Secretary General of BINA MARGA on the scope of work on 31 October 2014. According to the letter from Secretary General of Directorate General of Highways (DGH) dated 20 November, 2015 with the subject of Plan of Capacity Apparatus Civilian National Development within DGH, this package is expected will be started in January 2016. Currently, DGH staff and the POKJA prepare the Term of Reference (TOR), the Owner Cost Estimate and the draft of Request Expression of Interest (REOI) that will be sent to ADB. CSP - 6: Road Safety Awareness Campaign & Training (DGLT) A Meeting was held between DGLT and CTC on Terms of Reference (TOR). ADB already gave their comment for revision of the first submission. On 20 January 2015 another meeting between DGLT, ADB and CTC was held at ADB Office –IRM Jakarta regarding finalization/ preparation revised TOR and Owner Cost Estimate. DGLT was informed that they will submit to PMU/ADB two ( 2) weeks later, but up to the end of June 2015, such documents not yet received. According to the Coordination meeting held at Bappenas on 4 August 2015 and at the Wrap-up Meeting Project Review Mission ADB on 12 November, 2015, this package was cancelled by DGLT and the relocation activity is still waiting a decision from the Steering Committee. CSP - 7: Overloading and Speed Enforcement (DGNTP) ADB selected another institution to support INTPC to draft a short list of consultants due to conflict of interest. Short list of the consultants was completed including Request for Proposal (RFP) and Terms of Reference (TOR) sent to ADB 26 September 2014; concurred by the Bank on 19 November 2014. Invitation to shortlisted Consultant was made by POKJA of DGNTP on 4 December 2014. The submission of Technical and Financial proposals was made 26 January 2015. POKJA completed the Evaluation of Technical Proposals, and the result sent to the ADB on 19 May 2015. ADB issued a “No Objection Letter” on 5 June 2015. Opening of Financials Proposals was held on 18 June 2015. Thecombined evaluation of the Technical and Financial was completed by POKJA and the report 21
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
sent to the ADB on 12 August,2015. ADB issued a letter of no objection on 22 September, 2015. The results of negotiation and draft contract were sent to the ADB on 4 November and ADB issued a NOL on 13 November, 2015. The contract was signed on 19 November, 2015 and the mobilization expected will be on early of January 2016. CSP - 8: Indonesia Transport Sector Development Strategy and Policy Study (Bappenas) A Short list of Consultants including a Request for Proposal (RFP) and TOR was sent to the ADB on 10 July 2014; and was concurred by ADB on 24 September 2014. The result of the evaluation of the Technical proposal was sent to ADB on 26 January 2015. ADB commented on 6 February 2015 and issued a “No Objection Letter “on 29 April 2015. Opening of Financial Proposal was conducted on 7 May 2015. The Combined Evaluation (Technical and Financial) report was sent to ADB on 15 May 2015 and ADB issued NOL on 14 July, 2014. Currently POKJA are preparing a revised report, and are undertaking negotiation with the first ranked for the preparation of a draft Contract.. The result of negotiation with the first rank and the draft contract of this package has been sent to ADB on 19 October 2015. . ADB issued NOL on 10 November, 2015. Currently, the process of signing contract is still waiting approval from Minister of Bappenas. . CSP – 9: Integrated Vehicle Overloading Control Strategy A meeting was held between DGLT and CTC on Terms of Reference (TOR) for which ADB already gave comment to revise on the first submission. On 20 January 2015 another meeting between DGLT, ADB and CTC was held at ADB Office –IRM Jakarta regarding finalizing prepared revised TOR and Owner Cost Estimate. DGLT was informed that they will submit to PMU/ADB about two ( 2) weeks later.
Up to
the end of June 2015. According to the Coordination meeting held at Bappenas on 4 August 2015 and at the Wrap-up Meeting Project Review Mission ADB on 12 November, 2015, this package was cancelled by DGLT and the relocation activity is still waiting a decision from the Steering Committee. CSP – 10: Human Trafficking Prevention and HIV/AIDS Campaign Programs EOI was submitted by Consultants on 20 September 2014 and an Evaluation Report for a Short List of Consultant sent to ADB on 28 October 2014. “No Objection Letter” for the short list of Consultants and draft of Request for Proposal (RFP) was issued by ADB on 9 December 2014. An invitation to the shortlisted consultants was issued on 29 December 2014 and the submission of proposals made on 23 February 2015. POKJA evaluated the Technical proposal and this was sent to ADB on 12 March 2015; ADB issued “No Objection Letter “on 20 March 2015. The Financial Proposals were opened on 31 March 2015. The POKJA completed evaluating the combined Financial and Technical Proposals and report 22
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
sent to ADB on 27 April 2015. ADB issued No Objection Letter ( NOL) on 18 May 2015 . The Clarification and Negotiation with the highest rank has been held on 10 June 2015; draft Contracts have been prepared by POKJA and sent to the ADB on 18 August, 2015. ADB issued NOL on 23 September, 2015 . The contract has been signed on 6 October 2015.DGH submitted the signed contract to ADB on 3 November and ADB issued letter of No Objection on 13 November, 2015. 3.5 Implementation of the Anti-Corruption Plan 3.5.1 Community Representative Observer (CRO) The bid openings for three (3) packages in West Kalimantan, four (4) packages in East Kalimantan and three (3) packages in Central Java were attended by the selected CROs who were required to prepare a report with the results of their observations. A CRO was not present at the bid opening ceremony for one (1) Package in East Java Refer to Appendices No. 7 for a tabular summary of the CRO activities. 3.5.2 Third Party Monitoring (TPM) A TPM program was not included in the PAM (Project Administration Manual) of Regional Roads Development Project and at the PMM Socialization meeting in Bandung it was decided that the TPM is not required and implementation can be discontinued. 3.5.3 Complaint Handling System (CHS) Two (2) complaints were received in 2009 from Solidaritas Perempuan in Jogjakarta Branch and (3) three complaints in 2011 from Pengurus Wilayah Aliansi Masyarakat Adat Nusantara Kalimantan Barat ; Jaringan Advokasi Tambang Kalimantan Timur; Solidaritas Perempuan Wardarina. The above five (5) Complaints were received through the ADB. Two (2) complaints were received during the month of October 2014 dated O ctober 2 2 , 2014, and October 31, 2014. CTC received copies from PMU in December, 2014. Two (2) complains relate to the bid evaluation for the CW - 08 package. One ( 1 ) complaint received on 19 December 2014 relates to the S o s o k Tayan package, a n d one received on February 2015, r e l a t e s to the Tebas - Singkawang package relating the Condition of the road at the front of SMP No.4 Singkawang. The Complaints were responded to by POKJA and the Chief of Bina Marga Singkawang. 3.6 Implementation of the Environmental Management Plan All contractors have been informed that they must prepare an Environmental Management and Monitoring action plan RKPPL (Rencana Kerja Pengelolaan dan Pemantauan Lingkungan) prior to commencement of each construction package.
23
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
DSC will provide technical assistance to each contractor in order to prepare the necessary documents The detail status of plan preparation is as follows: Date
Pack. No.
Project Name
Safeguard Document
28-RCP 01A (CW-01)
Jolosutro Sendangbiru
AMDAL
2009
Will conduct briefing for Contractors
24-RCP 01 (CW-01) 24-RCP 03 (CW-01) 24-RCP 02 (CW-01)
Tambak Mulyo – Wawar AMDAL
5 Oktober 2005
Will conduct briefing for Contractors
Wawar - Congot
Draft
Final
Giri Woyo - Duwet
30-RCP 02(CW-06)
Sosok - Tayan
UKL-UPL
16 Februari 2011
30-RCP 02(CW-06)
Tanjung – Batas Kota Sanggau
UKL-UPL
16 Februari 2011
Tebas Singkawang (Section-1 & Section2)
AMDAL
18 Februari 2013
Bypass Sambas
UKL-UPL
Galing-Tj.Harapan
UKL-UPL
30-RCP 02(CW-06)
Sp.Tanjung-Galing (Section-1) 30-RCP 03 (CW-07)
Will conduct briefing to Contractors Will conduct briefing to Contractors Will conduct briefing to Contractors
13 Januari 2011
Will conduct briefing to Contractors
AMDAL
09-07-2015
Will conduct briefing to Contractors
UKL-UPL
20 December 2010
UKL-UPL
14 Agustus
UKL-UPL
13 Januari 2011
UKL-UPL
13 December 2010
Tanjung Selor - SP.3 Tanjung Palas SP.3 Tanjung Palas Sekatak Buji (Sect ion-1)
34-RCP02 (CW-09)
SP.3 Tanjung Palas Sekatak Buji (Sect ion-2)
34-RCP03 (CW-10)
SP.3 Apas Simaranggis (Section- 1) SP.3 Apas Simaranggis (Section- 2)
34-RCP03 (CW-11)
Will conduct briefing to Contractors Will conduct briefing to Contractors
UKL-UPL Sp.Tanjung-Galing (Section-2) Aruk-Sp.Tanjung 34-RCP02 (CW-08)
Status
Simaranggis (Section- 2) – Bts Negara (Serudong)
24
Will conduct briefing to Contractors
Will conduct briefing to Contractors Will conduct briefing to Contractors Will conduct briefing to Contractors
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
A summary of the monitoring of environmental mitigation conducted by CTC for all packages is presented in is as follows and a detailed record of the Status of environmental safeguard documentation in presented in Appendix No. 12. 1)
East Java Province Package 28-RCP 01: Jolosutro – Sendangbiru Environmental Monitoring Result
Type of work
New Road Construction, Widening road and Widening Bridge Construction
Length (Km)
21,3
Safeguard Document Required AMDAL
Activities Environmental Issues Pavement Work (widening etc.)
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project at the resident location
In Progress
Noise and Vibration
Good maintenance of the equipment on make with the equiment well
Along the Project at the resident location
In Progress
Embankment stabilitiy
Temporary Landslide protection and terasering
Along the embankment area and the location of road widening road and the potensial land slide
In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule. And direct as by engineer make terasering slege
Mobilization of Material
Air Quality
The use of terpaul in coverings on trucks
Along the Project from quarry are to project area
Has not been properly implemented
AMP and Stone Crusher operation
Air quality and noise pollution
AMP and Stone Crusse far from the residences
At the location of AMP and crusher operation in Sitiarjo village
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project esspecially at the Cutting and the embakment location
In Progress
Noise Pollution
Do not use high noise equipment and preferably do not carry out at noon time
Along the Project.
Completed
Earth Work (Cut and fill )
25
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities Environmental Issues
Storage materials (haardous and explosives)
2)
Mitigation Action
Location
Status
Landslide
Carry Out excavations at the cliffor hill with terrace system
At the cutting area esspecialy at STA 16+150 - 18+000
In progress according with work schedule
Permit of disposal area
Stockpile only on the location permitted
In the right or left side of road
In progress
Health and Safety Work
Place in the area indicated with warning signs and guard away from settlements Placement on the of flood level
Hilly area on the STA (07+00016+000)
In progress
Basecamp location
Has not been properly implemented
Mobilization of Labor
Social Jealousy
Involve local labour
Some labour is from local district
In progress
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged to existing roads
Access roads to the project site
In progress
Central Java Province Package 28-RCP 01: Tambak Mulyo – Wawar Environmental Monitoring Result
Type of work
Wedening Road and new road Construction and Widening Bridge Construction
Length (Km)
38,462
Safeguard Document Required UKL-UPL
Activities Environmental Issues Pavement Work (widening etc.)
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project.especially at embankment location
In Progress
Noise and Vibration
Good maintenance of the equipment
Working area far from resident
In Progress
Embankment stabilitiy
Temporary Landslide protection
Along the embankment area at the location of road widening
In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule. And direct as by engineer
26
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities Environmental Issues
Mitigation Action
Location
Status
Mobilization of Material
Air Quality
The use of tarpaulin coverings on trucks
Along the Project.
Has not been properly implemented
AMP and Stone Crusher operation
Air quality and noise pollution
Place equipment far from the residences
At the location of AMP and crusher operation village
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season
Earth Work (Cut and fill )
In Progress
Noise Pollution
Do not use high explosives and preferably do not carry out at noon time Stockpile only on the location permitted
Earth Work (Cut and fill )
Completed
In the right or left side of road
In progress
Place in the area indicated with warning signs and guard away from settlements
Storage materials location
In progress
Placement on the of flood level
Basecamp
Has not been properly implemented In progress
Earth Work (Cut and fill )
Permit of disposal area
Storage materials (haardous and explosives)
Health and Safety Work
Mobilization of Labor
Social Jealousy
Involve local labour
Some labour is from local district
Bridge Construction
Water flow disturbance
Water diversion
At Luk Ulo Bridge
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged at the existing roads
Access roads to the project site
27
In progress
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
3)
Central Java Province Package 28-RCP 02: Giriwoyo – Duwet Environmental Monitoring Result
Type of work
New Road Construction Widening Road and Widening Bridge Construction
Length (Km)
23,751
Safeguard Document Required
AMDAL
Activities Environmental Issues Pavement Work (widening etc.)
Mitigation Action
Location
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project especially at new road at STA 12+650 - 13+725, and STA 18+000 21+800
Noise and Vibration
Good maintenance of the equipment or make the equipment well Temporary Landslide protection
Working area far from resident
Embankment stabilitiy
Mobilization of Material
Air Quality
The use of tarpaulin coverings on trucks
Along the Project from the quarry are to the project are
In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule. And direct as by engineer Has not been properly implemented
AMP and Stone Crusher operation
Air quality and noise pollution
Place equipment far from the residences
At the location of AMP and crusher operation location
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season Do not use high explosives and preferably do not carry out at noon time Carry Out excavations at the cliffor hill with terrace system
Hilly area at the Erth Work location esspecially at the common ecavation or common embankment location
Stockpile only on the location permitted
Disposal area Location
Earth Work (Cut and fill with blasting)
Noise Pollution
Landslide
Permit of disposal area
28
Along the embankment area especially at new road at STA 12+650 13+725, and STA 18+000 - 21+800
Status
Hilly area at the earth work area
At the cutting area esspecialy at the hilly location
In progress according with work schedule
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities Environmental Issues Storage materials (haardous and explosives)
4)
Health and Safety Work
Mitigation Action
Location
Place in the area indicated with warning signs and guard away from settlements Placement on the of flood level
Hilly area on the erth work area
Status
Basecamp location
Mobilization of Labor
Social Jealousy
Involve local labour
Some labour is from local district
In progress
Bridge Construction
Water flow disturbance
Water diversion
At Bridge location
In progress
Material hauling and mobilization of heavy equipment
Crowded of traffict at eksisting road
Repair damaged to existing roads
Access roads to the project site
In progress
Construction Road
Crowded of traffict at eksisting road
Management traffict and rambu traffict at erth work location
At the cross with local road (eksisting road) esspecially at STA O+000, STA 5+150, 9+225, 12+650, 13+725,18+000,21+800, 21+375
In progress
Central Java Province Package 28-RCP 02: Wawar – Congot Environmental Monitoring Result
Type of work
Wedening Road and new road Construction and Widening Bridge Construction
Length (Km)
4,13
Safeguard Document Required
UKL-UPL
Activities Environmental Issues Pavement Work (widening etc.)
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project especially at embankment location
In Progress
Noise and Vibration
Make the equipment well or maintenance of the equipment routine
Working area esspecially at the resident area
In Progress
Embankment stabilitiy
Temporary Landslide protection
Along the embankment area or at the location of road widening
In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule and direct as by engineer
Mobilization of Material
Air Quality
29
The use of terpaulin coverings on trucks
Along the Project.
Has not been properly implemented
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities Environmental Issues AMP and Stone Crusher operation
Earth Work (Cut and fill )
Storage materials (haardous and explosives)
5)
Mitigation Action
Location
Status
Air quality and noise pollution
Place the equipment at far from the residences
At the location of AMP and crusher operation
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season
Earth Work (Cut and fill ) location
In Progress
Noise Pollution
Do not use high noise from equipment and preferably do not at noon time
Earth Work (Cut and fill ) location
Completed
Permit of disposal area
Stockpile only on the location permitted
Permit of disposal area at the rigt or left disposal area
In progress
Health and Safety Work
Place in the area indicated with warning signs and guard away from settlements Placement on the of flood level
Storage materials location
In progress
Basecamp location
Has not been properly implemented
Mobilization of Labor
Social Jealousy
Involve local labour
Some labour is from local district
In progress
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged to existing roads
Access roads to the project site
In progress
West Kalimantan Province Package 30-RCP 01: Sosok – Tayan. Environmental Monitoring Result
type of work
Widening Road Construction and Widening Bridge Construction
Length (Km)
41,60
Safeguard Document Required UKL-UPL
Activities
Pavement Work (widening etc.)
Environmental Issues
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project
In Progress
Noise and Vibration
Good maintenance of the equipment
Make equipment wih low noise
In Progress
30
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result type of work
Length (Km)
Safeguard Document Required
Activities
Environmental Issues Embankment stabilitiy
Mitigation Action Temporary Landslide protection
Location Along the embankment area at the location of road widening
Status In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule and direct as by engineer
Mobilizationof Material
Air Quality
The use of terpal in coverings on trucks
Along the Project
Has not been properly implemented
AMP and Stone Crusher operation
Air quality and noise pollution
Place equipment far from the residences
At the location of AMP and crusher operation
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season Do not use high explosives and preferably do not carry out at noon time
Earth Work (Cut and fill ) location
In Progress
Earth Work (Cut and fill ) location
In Progress
Landslide
Carry Out excavations at the cliffor hill with terrace system
Earth Work (Cut and fill ) location
In progress according with work schedule
Permit of disposal area
Stockpile only on the location permitted
In the right side of road at disposal area
In progress
Health and Safety Work
Place in the area indicated with traffik sighn and warning signs and guard away from settlements
Storage materials (haardous and explosives)
In progress
Placement on the of flood level
Basecamp location
Has not been properly implemented
Earth Work (Cut and fill)
Noise Pollution
Storage materials (haardous and explosives)
Mobilization of Labor
Social Jealousy
Involve local labour
Some labour is from local district
In progress
Bridge Construction
Water flow disturbance
Water diversion
Bridge Construction
In progress
31
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result type of work
Length (Km)
Safeguard Document Required
Activities
Material hauling and mobilization of heavy equipment
6)
Environmental Issues Damage of existing road
Mitigation Action Repair damaged to existing roads
Location Access roads to the project site
Status In progress
West Kalimantan Province Package 30-RCP 01: Tanjung – Bts Kota Sanggau Environmental Monitoring Result
Type of work
New Road Construction Widening Road and Widening Bridge Construction
Length (Km)
37,60
Safeguard Document Required UKL-UPL
Activities
Pavement Work (widening etc.)
Environmental Issues
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project
In Progress
Noise and Vibration
Good maintenance of the equipment
Make with the equipment wih low noise
In Progress
Embankment stabilitiy
Temporary Landslide protection
Along the embankment area at the location of road widening
In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule and direct as by engineer
Mobilizationof Material
Air Quality
The use of terpal in coverings on trucks
Along the Project
Has not been properly implemented
AMP and Stone Crusher operation
Air quality and noise pollution
Place equipment far from the residences
At the location of AMP and crusher operation
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season Do not use high explosives and preferably do not carry out at noon time Carry Out excavations at the cliffor hill with terrace system
Earth Work (Cut and fill ) location
In Progress
Earth Work (Cut and fill ) location
Completed
Earth Work (Cut and fill ) location
In progress according with work schedule
Earth Work (Cut and fill)
Noise Pollution
Landslide
32
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities
Storage materials (haardous and explosives)
7)
Environmental Issues
Mitigation Action
Location
Permit of disposal area
Stockpile only on the location permitted
In the right side of road at disposal area
In progress
Health and Safety Work
Place in the area indicated with warning signs and guard away from settlements Placement on the of flood level
Storage materials (haardous and explosives)
In progress
Basecamp location
Has not been properly implemented
Status
Mobilization of Labor
Social Jealousy
Involve local labour
Some labour is from local district
In progress
Bridge Construction
Water flow disturbance
Water diversion
Bridge Construction
In progress
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged to existing roads
Access roads to the project site
In progress
West Kalimantan Province Package 30-RCP 02: Tebas – Singkawang Section 1 Environmental Monitoring Result
Type of work
Wedening Road Construction
Length (Km)
3,6
Safeguard Document Required
AMDAL
Activities Environmental Issues Pavement Work (widening etc.)
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project esspecially at pavement work area
In Progress
Noise and Vibration
Good maintenance of the equipment
Pavement Work (widening etc.)
In Progress
Mobilizationof Material
Air Quality
The use of tarpaulin coverings on trucks
Along the Project and acces road to project esspecialy at the Basecamp until project area
Has not been properly implemented
AMP and Stone Crusher operation
Air quality and noise pollution
Place equipment far from the residences
At the location of AMP and crusher operation
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Permit of disposal area
Stockpile only on the location permitted
In the right or left side of eksisting road location
In progress
33
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
8)
Storage materials
Rambu of traffict sighn at the material storage
Mobilization of Labor
Social Jealousy
Material hauling and mobilization of heavy equipment
Damage of existing road
Place in the area indicated with warning signs and guard away from settlements Involve local labour
Storage material area location
In progress
Some labour is from local district
In progress
Repair damaged to existing roads
Alternative roads to the project site
In progress
West Kalimantan Province Package 30-RCP 02: Tebas – Singkawang Section 2 Environmental Monitoring Result
Type of work
Wedening Road Construction and new Bridge Construction
Length (Km)
26,3
Safeguard Document Required AMDAL
Activities
Pavement Work (widening etc.)
Environmental Issues
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project.especially at pavement work area
In Progress
Noise and Vibration
Good maintenance of the equipment
Along the Project.especially at pavement work area
In Progress
Embankment stabilitiy
Protection sludge flow at the eksisting road
Embankment stabilitiy location at the side drainage
Completed
Management traffict
Embankment stabilitiy location at the side drainage
Completed
The use of tarpaulin coverings on trucks Place equipment far from the residences
Along the Project and acces road to project.
Has not been properly implemented
At the location of AMP and crusher operation
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Rambu of traffict at the material storage
Place in the area indicated with warning signs and guard away from settlements Placement on the of flood level
Storage material area
In progress
Basecamp
Has not been properly implemented
Mobilizationof Material
Air Quality
AMP and Stone Crusher operation
Air quality and noise pollution
Storage materials
Mitigation Action
Mobilization of Labor
Social Jealousy
Involve local labour
Some labour is from local district
In progress
Bridge Construction
Water flow disturbance
Water diversion
At Bridge Location work
In progress
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged to existing roads
Alternative roads to the project site
In progress
34
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
9)
West Kalimantan Province Package 30-RCP 02: Galing – Tanjung Harapan Environmental Monitoring Result
Type of work
Widening Road Construction and Reconstruction Bridge Construction
Length (Km)
20
Safeguard Document Required AMDAL
Activities
Pavement Work (widening etc.)
Environmental Issues
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project especially at the resident area
In Progress
Noise and Vibration
Good maintenance of the equipment
Working with good equipment and maintance the equipment routine
In Progress
Mitigation of impact will be apply according the schedule and direct as by engineer Completed
Mobilizationof Material
Air Quality
The use of terpal in coverings on trucks
Along the Project.
AMP and Stone Crusher operation
Air quality and noise pollution
Place equipment far from the residences
At the location of AMP and crusher operation
The location protected from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season
Earth Work (Cut and fill )
In Progress
Noise Pollution
Do not use high explosives and preferably do not carry out at noon time Stockpile only on the location permitted and traffic sign
Earth Work (Cut and fill )
Completed
In the right or left side of the eksisting road
In progress
Place in the area indicated with warning signs and guard away from settlements Involve local labour
Storage materials location
In progress
Some labour is from local district Bridge Construction location
In progress
Bridge Construction location
In progress
Earth Work (Cut and fill )
Permit of disposal area
Storage materials
Health and Safety Work
Mobilization of Labor
Social Jealousy
Bridge Construction
Water flow disturbance
Water diversion
Damage of traffict existing road
Traffict management or traffict sid and alternatif road
35
In progress
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities
Material hauling and mobilization of heavy equipment
Environmental Issues Damage of existing road
Mitigation Action Repair damaged to existing roads
Location Access roads to the project site
Status In progress
10) West Kalimantan Province Package 30-RCP 03: Sp Tanjung – Galing Environmental Monitoring Result Type of work
Widening Road Construction and Reconstruction Bridge Construction
Length (Km)
20
Safeguard Document Required AMDAL
Activities
Pavement Work (widening etc.)
Environmental Issues
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Pavement Work (widening etc.) Location
In Progress
Noise and Vibration
Make the Good equipment and maintenance of the equipment routine
Pavement Work (widening etc.) Location
In Progress
Embankment stabilitiy
Temporary Landslide protection
Along the embankment area at the location of road widening
In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule. And direct as by engineer Has not been properly implemented
Mobilizationof Material
Air Quality
The use of tarpaulin coverings on trucks
Along the Project.
AMP and Stone Crusher operation
Air quality and noise pollution
AMP and Stone Crusher operation far from resident
At the location of AMP and crusher operation
In progress
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season Do not use high noise and preferably do not carry out at noon time
Earth Work (Cut and fill ) location
In Progress
Earth Work (Cut and fill ) location
Completed
Earth Work (Cut and fill )
Noise Pollution
36
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities
Storage materials (haardous and explosives)
Environmental Issues
Mitigation Action
Location
Status
Landslide
Carry Out excavations at the clif for hill with terrace system
Earth Work (Cut and fill ) location
In progress according with work schedule
Permit of disposal area
Stockpile only on the location permitted
Permit of disposal area location
In progress
Health and Safety Work
Place in the area indicated with warning signs and guard away from settlements
Hilly area
In progress
Placement on the of flood level
Basecamp
Has not been properly implemented
Mobilization of Labor
Social Jealousy
Involve local labour
Some labour is from local district
In progress
Bridge Construction
Water flow disturbance
Water diversion
At Bridge Worker
In progress
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged to existing roads
Access roads to the project site
In progress
11) North Kalimantan Province Package 34-RCP 01: Tj. Selor – Simpang
Tiga
Tanjung Palas – Sekatak Buji (Section 1) Environmental Monitoring Result Type of work
Widening Road Construction and Reconstruction Bridge Construction
Length (Km)
34,82
Safeguard Document Required AMDAL
Activities
Pavement Work (widening etc.)
Environmental Issues
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project
In Progress
Noise and Vibration
Good maintenance of the equipment Temporary landslide protection
Pavement Work loation
In Progress
Along the embankment area at the location of fill location
In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot)
Embankment stabilitiy
Mobilizationof Material
Mitigation Action
Air Quality
37
The use of terpal in coverings on trucks
Along the Project.
Mitigation of impact will be apply according the schedule and direct as by engineer Has not been properly implemented
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities
AMP and Stone Crusher operation
Earth Work (Cut and fill)
Environmental Issues
Location
Status
Air quality and noise pollution
Place equipment far from the residences
At the location of AMP and crusher operation
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season Do not use high noises equipment and preferably do not carry out at noon time
Earth Work (Cut and fill) location
In Progress
Earth Work (Cut and fill)
Completed
Landslide
Technial assistence
Earth Work (fill) location esspecialy at STA 16 + 000
In progress according with work schedule
Permit of disposal area
Stockpile only on the location permitted
In the right or left side of the eksisting road
In progress
Health and Safety Work
Place in the area indicated with warning signs and traffict sighn and guard away from settlements Placement on the of flood level
Storage materials location
In progress
Basecamp location
Has not been properly implemented
Noise Pollution
Storage materials (haardous and explosives)
Mitigation Action
Mobilization of Labor
Social Jealousy
Involve local labour
local district
In progress
Bridge Construction
Water flow disturbance
Water diversion
Bridge Construction
In progress
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged to existing roads
Access roads to the project site
In progress
12) North Kalimantan Province Package 34-RCP 02: Tj. Selor – Simpang Tiga Tanjung Palas – Sekatak Buji (Section 2) Environmental Monitoring Result Type of work
Widening Road Construction and Widening Bridge Construction
Length (Km)
65,03
Safeguard Document Required AMDAL
Activities
Pavement Work (widening etc.)
Environmental Issues Air quality pollution
Noise and Vibration
38
Mitigation Action Conduct regular watering specially during the dry season Good maintenance of the equipment
Location
Status
Along the Project
In Progress
Pavement Work
In Progress
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities
Environmental Issues
Mitigation Action
Location
Status In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule. And direct as by engineer Has not been properly implemented
Embankment stabilitiy
Temporary Landslide protection
Along the embankment area at the location of road widening esspecialy at Pimping Village
Mobilizationof Material
Air Quality
The use of terpal in coverings on trucks
Along the Project.
AMP and Stone Crusher operation
Air quality and noise pollution
Place equipment far from the residences
At the location of AMP and crusher operation in sitiarjo village
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters Conduct regular watering specially during the dry season Do not use high explosives and preferably do not carry out at noon time Carry Out excavations at the cliffor hill with terrace system Stockpile only on the location permitted
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Earth Work (Cut and fill ) location
In Progress
Earth Work (Cut and fill ) location
Completed
Earth Work (Cut and fill ) location
In progress according with work schedule
Earth Work (Cut and fill ) location esspecialy at disposal area Storage materials (haardous and explosives)
In progress
Basecamp location
Has not been properly implemented
Earth Work (Cut and fill)
Air quality pollution
Noise Pollution
Landslide
Permit of disposal area
Storage materials (haardous and explosives)
Health and Safety Work
Place in the area indicated with warning signs and guard away from settlements Placement on the of flood level
In progress
Mobilization of Labor
Social Jealousy
Involve local labour
local district
In progress
Bridge Construction
Water flow disturbance
Water diversion
Bridge Construction
In progress
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged to existing roads
Access roads to the project site
In progress
39
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
13) North Kalimantan Province Package 34-RCP 03: Simpang Tiga Apas Simanggaris (Section 1) Environmental Monitoring Result Type of work
New Road Construction Widening Road and Widening Bridge Construction
Length (Km)
45
Safeguard Document Required UKL-UPL
Activities
Pavement Work (widening etc.)
Environmental Issues
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project Esspecialy at near with residence location
In Progress
Noise and Vibration
Good maintenance of the equipment
Make with the equipment wih low noise
In Progress
Embankment stabilitiy
Temporary Landslide protection
Along the embankment area at the road widening location
Mobilizationof Material
Air Quality
Along the Project.
AMP and Stone Crusher operation
Air quality and noise pollution
The use of terpal in coverings on trucks Place equipment far from the residences
In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule and direct as by engineer Has not been properly implemented
At the location of AMP and crusher operation
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Air quality pollution
Conduct regular watering specially during the dry season Do not use
Earth Work (Cut and fill ) location
In Progress
Earth Work (Cut and fill ) location
Completed
Earth Work (Cut and fill ) location
In progress according with work schedule
Permit of disposal area location
In progress
Storage materials location
In progress
Basecamp location
Has not been properly implemented In progress
Earth Work (Cut and fill )
Noise Pollution
Landslide
Permit of disposal area Storage materials (haardous and explosives)
Mobilization of Labour
Health and Safety Work
Social Jealousy
40
high noises and preferably do not carry out at noon time Carry Out excavations at the cliff or hill with terrace system Stockpile only on the location permitted Place in the area indicated with warning signs and guard away from settlements Placement on the of flood level Involve local labour
Local district
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities
Environmental Issues
Mitigation Action
Location
Status
Bridge Construction
Water flow disturbance
Water diversion
Bridge Construction
In progress
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged to existing roads
Access roads to the project site
In progress
14) North Kalimantan Province Package 34-RCP 04: Simanggaris – Batas Negara (Serudong) Environmental Monitoring Result Type of work
New Road Construction Widening Road and Widening Bridge Construction
Length (Km)
47,04
Safeguard Document Required UKL-UPL
Activities
Pavement Work (widening etc.)
Environmental Issues
Mitigation Action
Location
Status
Air quality pollution
Conduct regular watering specially during the dry season
Along the Project
In Progress
Noise and Vibration
Good maintenance of the equipment
Make with the equipment wih low noise
In Progress
Embankment stabilitiy
Temporary Landslide protection
Along the embankment area at the location of road widening
In Progress but still need improvement with installment of temporary protection (such as embankment between land area and slopes foot) Mitigation of impact will be apply according the schedule and direct as by engineer Has not been properly implemented
Mobilizationof Material
Air Quality
The use of terpal in coverings on trucks
Along the Project
AMP and Stone Crusher operation
Air quality and noise pollution
Place equipment far from the residences
At the location of AMP and crusher operation
The location far from residences
Surface water pollution
Precautions to not throw directly into the channel by setting upshelters Conduct regular watering specially during the dry season Do not use high explosives and preferably do not carry out at noon time
At drainage channels near AMP and Stone Crusher
Has not been properly implemented
Earth Work (Cut and fill ) location
In Progress
Earth Work (Cut and fill ) location
Completed
Earth Work (Cut and fill)
Air quality pollution
Noise Pollution
41
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Environmental Monitoring Result Type of work
Length (Km)
Safeguard Document Required
Activities
Storage materials (haardous and explosives)
Environmental Issues
Mitigation Action
Location
Status
Landslide
Carry Out excavations at the cliffor hill with terrace system
Earth Work (Cut and fill ) location
In progress according with work schedule
Permit of disposal area
Stockpile only on the location permitted
In the right side of road at disposal area
In progress
Health and Safety Work
Place in the area indicated with warning signs and guard away from settlements Placement on the of flood level
Storage materials (haardous and explosives)
In progress
Basecamp location
Has not been properly implemented
Mobilization of Labor
Social Jealousy
Involve local labour
Some labour is from local district
In progress
Bridge Construction
Water flow disturbance
Water diversion
Bridge Construction
In progress
Material hauling and mobilization of heavy equipment
Damage of existing road
Repair damaged to existing roads
Access roads to the project site
In progress
3.7 HIV-AIDS and Anti Human Trafficking Program As described in clause Selection of Technical Assistant Consultant, for Program for HIV/AID and anti Human Trafficking expected will started in July 2015, still under process of evaluation by Committee procurement. October 2015, still under process of signing contract by Committee procurement. PT Hutama Karya, the contractor of Package 28-RCP-01A of Jolosutro Sendangbirum, Malang District, East Java, already done HIV socialization for the workers in June 2015, while the Specific TA Team of HIV/AIDS will give Socialization in March 2016 3.8 Monitoring of Health and Safety Each contractor must take reasonable precautions to maintain the health and safety of his employees including collaboration with local health authorities. The object of this program is to minimize any accident and health problems during construction work execution and is part of CTC monitoring activities. Health and Safety Monitoring for each package can be found in Appendix 15. From the details in this Appendix it can be seen that the minimum attainment is “mildly satisfactory” with “good” being attained for a number of factors. Each package is made aware of the results with encouragement to improve where necessary.
42
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
3.9 Resettlement & Rehabilitation Activities 3.9.1 Preparation of LARP This has been carried out in accordance with the requirements set out in the safeguard document from ADB that requires monitoring in LARAP preparation and implementation for each package in the RRDP program. Monitoring conducted by the CTC has been prepared in five (5) documents of LARP while LARP will be prepared for two (2) physical work packages i.e. packages 34-RCP-03 and 34-RCP04. 3.9.2 LARP Implementation Based on the results of monitoring, data collection and coordination with local government and projects, progress of the implementation of LARP can be grouped as follows: 1. East Java For Package 28-RCP 01A (CW-04): 50 Hectares production forest which is part of the 148.14 Hectares forestry land for all trace of the southern causeway of East Java still under process of obtaining land use permit issued by the Ministry of Forestry because of the long span of management between local government and Head of management of Perhutani (State-owned Enterprises of Ministry of Forestry) that has to be considered. In the meantime to commence work, Dispensation Permit which has just issued may be used. Determination and acquisition of land replacement located in Bondowoso District. The candidate of replacement land has been surveyed September 2013 and status of the land replacement for forestry permits in the form that is the recommendation from Bondowoso Regent issued February 2014. Extension of forestry permit from the Ministry of Forest and Environment already issued in August 2015. 2. Central Java
Package 24-RCP-01 (CW-01): Tambak Mulyo-Wawar. Package 24-RCP02: Giriwiryo - Duwet (CW-02) and Package 24-RCP 03 : Wawar-Congot CW-03) : Head of Tata Pemerintahan section of Kebumen local government 17 March, 2015 said that there is no more problem of compensation at the community level.
Statement is based on
Implementation Preparation Meeting RRDP Kebumen regency on January 27, 2015. a. All compensation already paid in August 2015. b. Because there are no people to be moved, there is no community empowerment
program
43
for
affected
people.
However
Badan
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Pemberdayaan Masyarakat Desa and Bappeda will try to propose Community Empowerment program for related people in 2016 3. West Kalimantan Package 30-RCP 01(CW-05): Sosok-Tayan; Tanjung-Sanggau City Border. and Acquisition Sosok - Tayan 100% completed, currently preparing the recapitulation. Estimated LARP 2011 (Rp)
Description Fiscal Year 2012 Sosok-Tayan Sp. Tanjung-Bts Kota Sanggau
Realization of Payment Compensation (Rp)
5.099.493.204 2.055.890.700
Fiscal Year 2013 Sosok-Tayan Sp. Tanjung-Bts Kota Sanggau
3.446.395.831
Fiscal Yeat 2014 Sosok-Tayan Sp. Tanjung-Bts Kota Sanggau
211.392.000
TOTAL
2.055.890.700
8.757.281.035
Package 30-RCP 02 (CW-06): Tebas-Singkawang (Section-1). For 3.6 KM road length is at Jalan Bambang Ismoyo Singkawang. CTC RRDP Safeguard team along with staff of the National Land Agency Singkawang,
Singkawang
City
Public
Works
Department
staff,
contractors, DSC and Chief Singkawang Village Central Java, together with administrative staff. National Land Agency staff Singkawang have made measurements by checking certificates to find out the parcel boundary APs invitation ROW. Results of measurement known that the APs are outside the fence of the building land owned by APs in the sense of a building located in the ROW. Proof of measurement. Package. 30RCP-02, Section 2, Tebas-Singkawang, Length 26.3 KM road. Monitoring results with Safeguard and Public Works Department Sambas district on roads Tebas-Singkawang stakes still visible for a distance ranging 1 KM, indicating the measured width of the ROW peg to the road. Results of measurement: width 20-25 meters. Thus all buildings (APs) fences, bridges, walls of buildings located in the ROW, concluding that there are no land APs affected by the widening.
44
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Sambas – Tanjung Harapan, 13 km long road, the results of a survey conducted by the Safeguard Team-CTC on roads Sambas -Tanjung Harapan as follows: Rumija varies between 15-17 meters - Near Sta 0 + 000 there are settlements - There is a traditional market present to the right side - There are oil palm plantations - Many have planted cane on the shoulder of the road - After the bridge from the direction of Sta 0 + 000 exposed wooden bridge access to homes - There are many passing vehicles trucks and buses Pakage 30-RCP 03 (CW-07): Simpang Tanjung-Galing (Section-1 dan Section-2), Aruk (Batas Serawak) - Simpang Tanjung. a. Singkawang City Based on the data obtained by the CTC , the citizens who will be affected by the project identified in Bambang Ismoyo Street in Tebas Singkawang (Part - 1) link which is part of Package 30 - RCP 02 ( CW - 06 ). Singkawang government has set aside funds for the purpose of land acquisition, identified PAPs (Project Affected Persons). It is planned to complete payment of compensation to the PAPs in November 2015. Results Coordination with Mr. Zukarnaein, Public Works Department Singkawang. (Head of the handle RRDP). Apparent that the original land acquisition affected by road widening, originally numbered (15) houses is reduced to four (4) homes, because of change in design. The results confirm the PPK package 30-RCP 02 (CW-06) Section 1 Tebas-Singkawang, the payment to PAPs previously will be paid in March 2015 is not yet liquid. Thus the delayed payment for WTP, prediction funds to be disbursed in November 2015. The regional government to soon pay compensation to the affected PAPs. ADB requires that for payment of compensation to the PAPs, related components: land, buildings and plant/plant details of the value of compensation so Consultants need to update the latest data. b. Sambas District According LARP documents there are still programs that to be completed on Tebas-Singkawang (Section-2) and
Galing-Tanjung
Harapan link as part of Package 30-RCP 02 (CW-06), and Aruk-Sp. Tanjung link as part of Package 30-RCP 03 (CW-07): 45
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Compensation value or the assets value of Project Affected Persons (PAPs) is determined by the Regent's Decision based on the assessment of the Data Collection and Negotiation Team for Awarding Compensation of Provincial and National Roads Improvement. Negotiation in section Singkawang – Tebas (Section 2) has been completed and the results reported in September 2011. Furthermore, the results of these negotiations will be set as the “santunan” by the Regent of Sambas. Clarification of data, the segment Section -2. Tebas - Singkawang (Section 2), 26.3 km long road The results of the observations made by the Safeguard Team, Department of Public Works and Contractor Sambas district are still many ROW boundary markers ; All buildings Affected widening project RRDP ( fences , bridges , walls of buildings , etc. ) located within the ROW ; The width of the ROW , the measurement results 20 to 25 meters . The cost of compensation for the affected PAPs building project , by decree of the Regent No.270.B in 2011 . Compensation for WTP building already paid , It has been done aspirations in the segment section- 2 ( Slash Singkawang ) of the 80 respondents responded well widen the road , and hope soon to be completed ; Directorate General of Highways, through the Balai Besar of the Region VII Kalimantan (BPPJN VII), has send a letter to Regent Sambas and Singkawang Concerning Implementation of Land Acquisition and Resettlement FOR RRDP in Sambas and Singkawang District of West Kalimantan Province. Recovery back to the communities affected by land acquisition, until now there has been no program of Sambas district government and Singkawang. However, the local government has planned an empowerment program for people whose land is affected by land acquisition. On 16 February 2015,
the coordination meetings have been
implemented Land Acquisition and Resettlement for RRDP Roads Sambas (Kartiasa) -Tanjung Harapan troughout the 13 KM, attended by : Head of Department of Public Works Binamarga, Water, Energy and Mineral Resources Sambas district. The meeting was attended by Core Team Consultant RRDP, Assistant 1, Assistant II, Assistant III, some SKPDs Sambas district, sub-
46
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
district of Sambas, Headman of some village
whose territory
included in the plan Roads Kartiasa–Tj.Harapan. As of April 2015, there has been no development of funding proposals related to land acquisition in Sambas-Tanjung Harapan package, the meeting with ADB there are several alternatives, among others: Its land communities affected by the widening of national roads, equivalent compensation payments, was replaced by entering in to local government programs, PPK package 30RCP-02, need to coordinate with the Head of Department of Public Works of West Kalimantan Province, to ensure road ROW in Tebas package- Singkawang (Section 2). When people are exposed to house entrance in the street ROW, paid only building sand plants. In the segment Aruk (Border) -Simpang Tanjung or package 30RCP 03 (CW-07), length of 11.1 km is to be made four-lane two lanes along the 6.1 km where the physical work will be built with funds from the state budget while the 5.14 km will be funded Loan (RRDP-ADB). 4. North Kalimantan Package 34-RCP 01 (CW-08): Tanjung Selor- SP. 3 Tanjung Palas and Sp. 3 Tanjung Palas Sekatak Buji (Section-1); Package 34-RCP 02 (CW09): Sp. 3 Tanjung Palas Sekatak Buji (Section-2); Package 34-RCP 03 (CW-10): SP.3 Apas - Simaranggis (Section- 1); Packages 34-RCP 04 (CW-11): SP.3 Apas - Simaranggis (Section-2) and Simanggaris-Bts Negara (Serudong). a)
Bulungan District Activities that have been carried out on 34-RCP Package 01 (CW-08) and Package 34-RCP 02 (CW-09) is land acquisition and Ressetlement pland of the building and crops affected by the project RRDP in July 2015. PPK have been measuring the buildings and the crops that have been affected by land acquisition. Data obtained from the PPK and Update data on 2 – 10 July 2015, the payment for the building and the crops have been olready paid by Bulungan Government up to 9 August 2014 until July 2015 list of the.data.as.follows.
47
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
INVENTORY ASSET HAS OCCUPATED BY RRDP PROJECT ROAD IN BULUNGAN DISTRICT, NORTH KALIMANTAN PRIVINCE
No
Subdistrict / Vilage
BuildIng has olready Paid
Jml
Nilai (Rp)
Plantation has olready Paid
Building Not yet Paid
Plantation Not yet Paid
Total WTP Occupated
Jml Phn
Nilai (Rp)
Jml
Nilai (Rp)
Jml Phn
Nilai (Rp)
Building has Olready Paid
Plantation has Olready Paid
Building not yet Paid
Plantation not yet Paid
0
0
0
0
0
0
0
0
0
0
0
0
10
2
0
0
0
0
0
Tj Selor – SP3.TJ Palas – Sekatak Buji (Section 1) 0
Jelorai Selor
0
0
0
1
Tanjung Palas/Pejalin
0
0
161
35,921,000
3
2,636,400
TJ Palas – Sekatak Buji (Section 2) 2
Tanjung Palas Utara/Pimping
14
68,864,800
178
9,765,000
0
0
0
0
12
14
3
Tanjung Palas Utara/Karang Agung
3
124,810,700
172
9,603,500
0
0
0
0
1
9
4
Tanjung Palas Utara/Panca Agung
11
42,905,500
106
21,014,000
3
2,458,900
56
7,979,000
10
17
3
6
5
Sekatak/Sekatak Benggara
11
231,052,000
3
135,000
2
21,686,450
1
30,000
9
1
2
1
Sekatak/Pentian
2
32,593,700
1
893,000
4
9,073,750
0
0
2
1
3
0
Sekatak/Bunau
2
6,569,250
0
0
0
0
0
0
2
0
0
0
Sekatak/Sekatak Buji
6
86,669,300
0
0
1
547,700
1
6
0
1
1
Sekatak/Maritam
0
51
627,800
0
0
0
0
1
0
0
672
77,959,300
13
42
53
11
8
6 7 8 9
TOTAL Nomber
49
0 593,465,250
36,403,200
48
58
210,000 0 8,219,000
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
a) Nunukan District In Nunukan District, for Package 34-RCP 03 (CW-10) and Package 34-RCP 04 (CW-11) have been carried out activities related to land acquisition for road construction is moving the building and the plantatation of WTP and the Company Plantation Owner. Based on the letter head of the working unit PJN North Kalimantan region III No.PW.04.01 / PJNAS.III-KT / 950, dated 6 January 2015 addressed to the Head of Balai Besar National Road VII, regarding plans for relocation package 34-RCP11, (according to the DED ), due to several considerations, realignment canceled and the relocation back to the existing road confirmed. As of 2 until 10 July 2015, activities are to LARP at the existing road at Package 34-RCP 04 (CW-11) to be completed so that the Contracktor can be construction. The detailed of the moving of building and the plantation occupated the poject RRDP Package CW 10 and CW 11 is below. A detailed summary of the land acquisition requirements for packages CW 11 the existing road on LARP studies are included in Appendix No. 11. Land Acquisition and Resettlement Plan (LARP) was prepared for sub-project in Nunukan District: SP.3 Apas – Simanggaris (Section 2). The LARP is based on preliminary design that use corridor of impact (COI) 16 -20 meters. Sp.3 Apas – Simanggaris link (Section 2) were at Km 00 + 000 – 26 + 900 within Tulin Onsoi Sub-district and Simanggaris Sub-district, that is passes through plantation, especially.pal.moil.
49
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
VERIFICATION / INVENTARISATION ASSET WTP AND THE COMPANY PLANTATION HAVE OCCUPATED OF RRDP PROJECT PACKAGE: SP. 3 APAS - SIMANGGARIS (SECTION I) Asset Have Occupated No.
1
Name Company/ WTP
STA
Name Villages
Land
Buildi ng
m2
m2
Apas, Kec. Sebuku
Nomber of Sawit Palntation Left
Remarked/ Status Of Land Acquisition
Right Sudah pindah ke STA 0+450. Kompensasi: menurut istri pemilik belum ada
Mustafa
0+375
2 (1)
PT. Karang Juang Hijau Lestari
0+000
To
09+000
Apas, Kec. Sebuku dan Semunat Kec. Tulin Onsoi
51
25
Sudah Land Clearing. Kompensasi: pemindahan pohon
2 (2)
PT. Karang Juang Hijau Lestari
09+000
To
15+000
Semunat Kec. Tulin Onsoi
64
1
Sebagian sudah Land Clearing. Kompensasi: pemindahan pohon
3 (1)
PT. Karang Juang Hijau Lestari 3
15+975
To
27+675
Sekikilan, Kec. Tulin Onsoi
316
218
Sebagian sudah Land Clearing. Kompensasi: pemindahan pohon
5
Basayul
21+275
To
21+375
Sekikilan, Kec. Tulin Onsoi
6
Kamal
27+850
To
28+025
Tinampak I
7
Sadat
28+000
To
28+100
Tinampak I
8
Milwan
28+025
To
28+175
Tinampak I
15
9
Yohanes
28+175
To
28+300
Tinampak I
8
10
Dinas
28+175
To
28+350
Tinampak I
20
PT. Tirta Madu Plasma
29+850
To
32+450
Tinampak I
101
Iding
32+850
To
33+000
Tinampak I
3 (2) 11
54
28
8
Pemindahan rumah dan pohon akan dilaksanakan pada bulan Agustus 2015; Kompensasi: Penimbunan dan perataan lahan untuk rumah seluas 600 m2 pada STA 21+250
15 1
21
50
Sudah di Sosialisasi. Belum terdapat kesepakatan mengenai kompensasi
Sudah Land Clearing. Kompensasi: pemindahan pohon Sudah di Sosialisasi. Belum terdapat kesepakatan
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
12
Janudin
33+100
To
33+380
Tinampak I
13
NN
33+200
To
33+400
Tinampak I
15
4
PT. Tirta Madu Sawit Jaya 2
35+150
To
39+175
Tinampak I
76
14
Paulus
40+550
To
40+750
Salang, RT-03
8
15
H. Lodeh
41+600
To
41+680
Salang, RT-03
16
Pabo
42+000
To
42+200
Salang, RT-03
11
17
Basir
42+200
To
42+400
Salang, RT-03
3
18
Pudding
42+530
To
42+650
Salang, RT-03
19
Sibuk
42+750
To
42+800
Salang, RT-03
5
20
Manuil
42+800
To
42+825
Salang, RT-03
3
21
Kasmawati
42+850
To
42+900
Salang, RT-03
22
Masunu
43+350
To
43+400
Salang, RT-03
11
23
Tahanan
43+600
To
43+650
Salang, RT-03
9
24
Matius
43+650
To
43+800
Salang, RT-03
4
25
Wandih
43+750
To
43+950
Salang, RT-03
26
Salamat
43+800
To
43+825
Salang, RT-03
27
Sahrudin
44+450
To
44+650
Salang, RT-03
28
Andi Apak
44+750
To
44+950
Salang, RT-03
29
Andi Zubair
44+750
To
44+950
Salang, RT-03
35
110
mengenai kompensasi
Sudah Sosialisasi. Belum Land Clearing. Kesepakatan kompensasi: pemindahan pohon
13
3
2
Belum Sosialisasi.
7 5 6 4 6 82
644
556
JUMLAH 1,200 Catatan: 1. Coridor of Impact (CoI) yang diperhitungkan untuk pendataan ini berdasarkan ROW Desain, kecuali STA 40+550 - STA 45+150 selebar 20 meter 2. Jarak dari saluran sebelah kiri luar sampai dengan saluran sebelah kanan luar jalan eksisting terukur rata-rata 16 meter 3. Patok Rumija hanya terdapat didepan Pospam Terpadu Perbatasan Indonesia-Malaysia, jarak antar patok 14 meter
51
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
VERIFICATION / INVENTARISASI ASSET WTP AND COMPANY PLANTATION HAVE OCCUPATED PROJECT RRDP PACKAGE: SP. 3 APAS - SIMANGGARIS (SECTION II); SIMANGGARIS – SERUDONG Asset Have Occupated No.
Nama Company/ WTP
STA
Name Villages
Land
Building
m2
m2
Nomber of Sawit Plantation Left
Remarked/ Status of Land Acquisition
Right
1
Daeng Tayang
0+000
0+500
Tabur Lestari, Kec. Simanggaris
-
Tidak terkena proyek
2
Andi Amir
2+000
2+025
Tabur Lestari, Kec. Simanggaris
-
Tidak terkena proyek
3
Yunus
3+100
3+150
Tabur Lestari, Kec. Simanggaris
4
Ngatijan
3+100
3+150
Tabur Lestari, Kec. Simanggaris
3
5
Simonpiak (Hj. Mina)
3+650
3+800
Tabur Lestari, Kec. Simanggaris
2
Tidak terkena proyek
6
Rahim (Ibrahim)
3+950
4+125
Tabur Lestari, Kec. Simanggaris
5
Kompensasi: Buatkan jalan kebun ± 200 m
7
Hj. Mina
4+050
4+215
Tabur Lestari, Kec. Simanggaris
6
Kompensasi: Memperbaiki jalan tanah yang becek
8
Lusan
4+425
4+750
Tabur Lestari, Kec. Simanggaris
15
Sudah Land Clearing
9
H. Pataruddin
4+850
4+900
Semaja, Kec. Simanggaris
3
10
Samsuddin
5+050
5+250
Semaja, Kec. Simanggaris
10
Kompensasi: Dibuatkan jalan kebun ± 500 m
8
Jika rumah/pondok terkena, proyek bantu untuk digeser dan dibuatkan tapak rumah.
-
Tidak terkena proyek
11
Bokir (Saenudin)
5+600
6+175
Semaja, Kec. Simanggaris
12
H. Nurdin
6+250
6+325
Semaja, Kec. Simanggaris
2
13
Made
7+675
7+725
Semaja, Kec. Simanggaris
3
14
Ruslan
9+800
9+875
Semaja, Kec. Simanggaris
15
Ruslan
10+025
10+100
Semaja, Kec. Simanggaris
16
H. Gatak
10+025
10+100
Semaja, Kec. Simanggaris
6
17
H. Gatak
10+700
10+875
Semaja, Kec. Simanggaris
25
12 6
52
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
18
19
Hj. Mina PT. Bumi Simanggaris Indah (BSI)
10+900
12+525
11+075
12+750
Semaja, Kec. Simanggaris
Kompensasi: Memperbaiki jalan tanah yang becek
18
Semaja, Kec. Simanggaris
17 -
-
50
91
JUMLAH 141 Catatan: 1. Coridor of Impact (CoI) yang diperhitungkan untuk pendataan ini selebar 20 meter 2. Jarak dari saluran sebelah kiri luar sampai dengan saluran sebelah kanan luar jalan eksisting terukur rata-rata 16 meter 3. Patok Rumija hanya terdapat didepan Pospam Terpadu Perbatasan Indonesia-Malaysia, jarak antar patok 14 meter 4. Status tanah, tanah negara. Surat tanah yang dimiliki warga paling tinggi Surat Pernyataan Penguasaan Tanah (SPPT).
53
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
4.
Seminars, Workshops & Training Practical Training on monitoring the implementation of Environmental Management and Quality Assurance / Management System was held 23 June, 2015 for DSC-1 Packages in Pontianak. The next Training/ Workshops are scheduled to be held are in Yogyakarta for Central Java and East Java Packages in February, 2016 followed by Balikpapan for North Kalimantan mid, 2016. Training aims to provide the basic information needed to support the implementation of monitoring implementation of environmental management so that all relevant provisions and procedures for environmental management and quality management system can be adhered to and implemented in accordance with the terms and conditions. Loan Utilization for Civil Works 4.1.
Estimated Funding Status for RRDP Civil Works and Consultant Services. The estimate for Civil Works Packages in RRDP can be seen in Appendix No.14, using the exchange rate of 1US$ = 13,500 IDR.
5.
RRDP Website The RRDP-CTC website has now been running on the fixed server site and can be found on http://www.pmu-rrdp.com . The RRDP-CTC website contains all of the following items: a) General RRDP information including copies of all reports i.e. Monthly Progress Reports and Quarterly Progress Reports with the latest uploaded reports being the MPR , QPR for 2014 and third quarter of 2015, Social and Environmental Status Reports, Quarterly LARP, LARP Implementation and the Road Safety Audit Reports. b) Project list and Project Progress Status including Procurement Plan and Bid Winners, and Copies of all Bid Documents although currently without drawings while waiting for the original CAD files to be converted to PDF files) c) ACAP and Complaint Handling System including contact points, list of Community Representation Observers, and list of Third Party Monitors who have already been appointed. d) Announcements (current and archived) e) Newsletter f) Documents, (including all reports and bidding documents) g) Package Location Map h) Responses from the CHU following contract signing. Members of the public will be able to submit a complaint via the website regarding the implementation of any RRDP package.
54
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
6.
Documentation Collection and Scanning CTC have set up a system whereby all RRDP documentation is being scanned and stored as soft copies with an appropriate well documented retrieval system. Scanning commenced includes design documents (drawings, Engineers Estimates & Special
Specifications),
contract
documentation
(originals
and
amendments),
procurement documentation, progress reports (weekly & monthly) and letters (correspondence,..ADB..comments.&..site..visit..reports). All of files store as electronic filing in external storage device.
55
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Form A : General FORMULIR A : UMUM LAPORAN PELAKSANAAN KEGIATAN YANG DIBIAYAI DARI PINJAMAN DAN/ ATAU HIBAH LUAR NEGERI TAHUN ANGGARAN 2015 NAMA KEMENTERIAN NEGARA/LEMBAGA : Kementrian Pekerjaan Umum dan Perumahan Rakyat NAMA PEMBERI PHLN A.
: Asian Development Bank (ADB) dan Islamic Development Bank (IDB)
DESKRIPSI I. NAMA PROYEK PINJAMAN/HIBAH
: Regional Roads Development Project (RRDP)
II. NOMOR NPPHLN DAN REGISTER
: ADB No.2817-INO, Register : 10846401
III. TANGGAL PENANDATANGANAN
: ADB : 7 Mei 2012
IDB No. 0161-IND, Register : 10848801 NPPHLN
IDB :17 April 2012
IV. TANGGAL EFEKTIF NPPHLN A. TANGGAL EFEKTIF TENTATIF
: -
B. TANGGAL EFEKTIF RIIL
: ADB : 3 Juli 2012 : IDB : 2 Mei 2012
V. TANGGAL PENUTUPAN NPPHLN A. ORIGINAL
: ADB : 31 Agustus 2016 IDB : 30 April 2016
ADDENDUM
: ADB : 31 Juli 2018 IDB : 9 Juni 2019
B. ACTUAL VI. JUMLAH PINJAMAN/HIBAH A. ORIGINAL
:: :ADB USD 180 billion : IDB : USD 65 billion
B. ACTUAL VII. TUJUAN
:: Untuk meningkatkan pertumbuhan ekonomi dan pengentasan kemiskinan di wilayah koridor utara Pulau Kalimantan melalui pembangunan dan peningkatan prasarana jalan regional strategi, dengan beberapa sasaran yang akan dicapai melalui proyek ini adalah: (i) Peningkatan/ pembangunan jalan sepanjang 476 km; (ii) Peningkatan tata kelola melalui dukungan kebijakan di sektor jalan serta (iv) Peningkatan kapasitas sumber daya manusia dalam pengelolaan jalan.
VIII. SASARAN
: Akses Lintas Selatan Jawa dana Akses Lintas Perbatasan Kalimantan
IX INSTANSI PENANGGUNG JAWAB (EXECUTING AGENCY) X. INSTANSI PELAKSANA (IMPLEMENTING AGENCY) NO. 1 2 3 4
INSTANSI PELAKSANA Ditjen Bina Marga Dijen Perhubungan Darat Ditjen Kepolisian Lalulintas Bappenas
Kategori Civil Works Goods Consulting Services Unallocated Total
ALOKASI DANA REVISI (JUTA VALAS ) REALOKASI 1 USD 208.50 USD 208.50 USD 1.30 USD 2.20 USD 24.10 USD 23.20 USD 11.10 USD 11.10 USD 245.00 USD 245.00
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
XI. KATEGORI PINJAMAN NO. 1 2 3 4
DANA ALOKASI DANA PENDAMPING (JUTA VALAS) (JUTA VALAS)
KATEGORI PINJAMAN Civil Works Goods Consulting Services & Training Unallocated Total
USD 208.50 USD 1.30 USD 24.10 USD 11.10 USD 245.00
USD 88.50 USD USD USD 47.00 USD 135.50
REVISI REALOKASI (5 Juni 2015) USD 208.50 USD 2.20 USD 23.20 USD 11.10 USD 245.00
XII. LINGKUP PEKERJAAN 1. Pekerjaan Jasa Konstruksi/Civil Works untuk 11 paket 2. Pekerjaan Jasa Konsultansi (civil works) yaitu CTC (Dit. Bina Program), DSC-1, DSC-2 dan DSC-3 (Dit. Bina Pelaksanaan Wilayah II) 3. Pekerjaan Jasa Konsultansi (roads sector developmet program) yaitu Road Safety Support, Institutional Development for Road Network Management, Road Safety Awareness Campaign and Training, Overloading and Speed Enforcement, Indonesia Transport Sector Development Strategy and Policy Study, Integrated Vehicle Overloading Control Strategy dan HIV/AIDS and Anti-Trafficking Program XIII. LOKASI (PROVINSI/KABUPATEN/KOTA) NO. 1 2 3 4
PROVINSI/KABUPATEN/KOTA Jawa Tengah Jawa Timur Kalimantan Barat Kalimantan Utara
ALOKASI DANA (JUTA VALAS ) USD 76.60 USD 21.30 USD 187.80 USD 191.40 USD 477.10
REVISI Non PPN Consultant Civil Work
6,563.36 100,634.36
0.000
XIV. DISBURSEMENT PLAN DAN REALISASI PHLN (Juta Rp) Tahun
Rp
a. b.
2013 2014
Triwulan I : 4,762.72
c.
2015
37,759.33
Rp Actual 1,345.26 -
Triwulan II 11,929.28 66,950.62
Rp Actual
Rp
3,090.24
Triwulan III 101,483.97
Actual 90,473.86
Triwulan IV 107,197.72 166,719.17
78,604.13
138,648.01
119,204.32
291,742.13
Total Disbursement Actual Plan (Rp) 107,197.72 107,197.72 92,637.82 284,895.14 252,441.74
535,100.09
Persentase Total Realisasi Penyerapan DIPA (Rp) (%) 374,930.79 107,197.72 28.59 441,338.27 187,547.18 42.50 535,100.09 450,250.19 84.14
Total DIPA (Rp)
B. PETUGAS YANG DAPAT DIHUBUNGI I. KETUA PELAKSANA HARIAN PMU RRDP Nama : DR.Ir. Slamet Mulyono M.Eng Alamat Kantor : Jl. Pattimura No. 20, Jaksel Nomor Telp : 021-7210218 Nomor Faksimili : 021-7210219 Alamat E-mail :
[email protected]
II. ESELON II PENANGGUNG JAWAB Nama : Ir. Soebagiono, M.Sc Jabatan : Direktur Pengembangan Jaringan Jalan Alamat Kantor : Jl. Patimura No.20 Jakarta Selatan Nomer Telp : 021- 7200281 Nomer Faksimili : 021- 7201760 Alamat E-mail :
[email protected]
III.A PROJECT IMPLEMENTING UNIT I #### Nama : DR. Ir.Triono Jundasmono, MT Jabatan : PPK Kegiatan Penyiapan Program dan Administrasi Pinjaman Luar Negeri Alamat Kantor : Jl. Pattimura No. 20, Jaksel Nomer Telp : 021-7248870 Nomer Faksimili : 021-7248870 Alamat E-mail :
[email protected]
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM B.1 : SUMMARY IMPLEMENTATION IN FISCAL YEAR 2015 A. FINANCE (in IDR) A. KEUANGAN (dalam Rp.)
No. Paket
0
PAKET KONTRAK
[a1]
I.
TATA CARA PENARIKAN (PP/PL/LC/RK) [a2]
NILAI KONTRAK DAN STATUSNYA PADA AKHIR TAHUN SEBELUMNYA
[b1]
(b2)
PENYERAPAN KUMULATIF SAMPAI DENGAN DESEMBER TAHUN SEBELUMNYA
REALISASI PENYERAPAN WITHDRAWAL APLICATION (WA) TH YL
[c]
[d]
PENYERAPAN PADA TAHUN ANGGARAN 2015 TRIWULAN I (1 Jan - 31 Maret)
TRIWULAN II (1 Apr - 30 Jun)
TRIWULAN III (1 Juli - 30 Sept)
TRIWULAN IV (1 Okt - 31 Des)
TOTAL TA 2015
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
[e]
[f]
[g]
[h]
[i]
[j]
[k]
[l]
[m]
[n]
IDB Financing No.IND-0161, Register : 10848804 Civil Works Jawa Tengah
24-RCP01 Tambakmulyo - Wawar
PL
243,741,564,000
-
-
-
3,602,739,238
-
6,387,975,695
24-RCP02 Giriwoyo - Duwet (Section 1)
PL
142,000,000,000
-
-
-
3,285,705,632
-
5,825,847,038
24-RCP03 Wawar - Congot
PL
58,253,088,000
-
-
-
883,115,663
-
1,565,842,271
10,591,470,545
3,478,873,693
443,994,652,000
-
-
-
7,771,560,533
13,779,665,004
10,591,470,545
30,614,650,642
20,057,790,000
-
-
-
195,639,803
20,057,790,000
-
-
-
195,639,803
464,052,442,000
-
-
-
Total Civil Works III.
14,192,336,618
44,316,648,000
23,346,553,448
1,284,637,181
47,529,605,000
45,601,285,181.0
-
12,943,440,331
25,818,181,818
21,292,105,000
1,681,818,182
43,347,098,000
27,500,000,000.0
19,469,884,374
1,688,108,893
25,397,716,000
12,279,579,438
64,108,542,821
4,654,564,256
116,274,419,000
85,380,864,619
3,367,787,150
4,145,024,850
4,681,000,000
4,145,024,850.00
70,134,829,818
Consulting Services & Training DSC-2 (Jawa Tengah - IDB)
PL
Total Consulting Services Total - IDB Financing No.IND-0161
I.
-
-
346,886,397
3,367,787,150
4,145,024,850
4,681,000,000
4,145,024,850.00
7,967,200,336
-
14,126,551,400
10,591,470,545
31,385,337,292
70,134,829,818
67,476,329,971
8,799,589,106
120,955,419,000
89,525,889,469
1,670,068,629
-
2,961,177,008
8,168,166,964
6,578,924,510
4,797,084,832
20,666,014,853
16,871,691,026
31,876,185,000
29,836,942,822
5,502,988,120
-
9,757,285,231
31,818,181,818
21,678,021,815
35,660,589,835
21,644,636,852
72,598,885,000
53,462,818,670
16,684,824,884
19,265,387,000
31,691,755,826
14,844,707,505
64,519,046,000
60,572,594,000
20,971,294,263
40,002,388,091
42,693,982,000
40,002,388,091.0
36,297,334,240
34,292,845,617
54,749,999,000
42,113,834,379.0
26,302,425,021
30,922,059,859
39,149,999,000
30,922,059,859.0
27,794,927,466
46,384,404,133
58,748,843,000
58,685,467,909
6,571,478,809
24,175,036,608
24,200,000,170
24,175,036,608.0
205,955,820,313
229,137,769,691
388,536,939,170
339,771,142,338
346,886,397
-
770,686,650 770,686,650
-
ADB Loan No.2817-INO, Register : 10846401 Civil Works
Jawa Timur 28-RCP01 Jolosutro - Sendangbiru
PL
112,823,335,000
23,011,025,595
23,011,025,595
3,173,866,120
PL
465,647,542,528
PL
407,294,892,000
43,890,507,750
43,890,507,750
38,679,370,633
4,890,543,605
-
8,671,359,569
PL
325,740,200,000
35,846,245,950
35,846,245,950
18,902,906,060
3,236,199,505
-
5,738,068,291
-
12,748,419,940
Kalimantan Barat 30-RCP01
Sosok - Tayan Tanjung - Bts. Kota Sanggau
-
Singkawang - Tebas (Section 1+2) 30-RCP02 Bypass Sambas
29,043,061,611
Tanjung Harapan - Galing Galing - Sp. Tanjung 30-RCP03
Sp. Tanjung - Aruk (Bts. Serawak)
-
Kalimantan Utara 34-RCP01
Tanjung Selor - Sp.3 Tanjung Palas
PL
189,970,248,000
-
-
18,133,523,673
2,749,038,484
-
4,874,288,662
-
10,829,337,614
34-RCP02 Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
PL
165,332,328,425
-
-
18,064,668,427
1,914,004,062
-
3,393,698,688
-
7,539,871,230
34-RCP03 Sp. Tiga Apas - Simanggaris (Section 1)
PL
289,000,000,000
-
-
42,213,971,993
4,611,448,056
-
8,176,505,751
PL
359,652,598,000
-
-
38,783,433,540
4,130,633,761
-
7,323,979,429
177,951,740,446
28,704,924,222
-
50,896,362,630
34-RCP04
Sp.3 Tanjung Palas-Sekatak Buji (Section 1)
Sp. Tiga Apas - Simanggaris (Section 2)
7,419,585,534 -
18,165,961,726 6,173,908,171
7,820,988,762 4,881,478,242 -
Simanggaris - Bts. Negara (Serudong) Total Civil Works II.
GOODS Road Saftey Enforcement
2,315,461,143,953
PL
Total Goods III.
Consulting Services & Training CTC RRDP
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
33,781,300,000 41,611,883,000
PL
8,256,578,000
Indonesia Transport Sector Development Strategy and Policy Study Integrated Vehicle Overloading Control Strategy HIV/AIDS and Anti-Trafficking Program
PL
6,074,599,000 -
5,207,337,131
429,311,676
-
761,207,617
6,074,599,000
2,565,772,206
498,712,623
-
884,261,641
-
1,964,587,761
1,040,992,500
1,865,182,640
159,179,787
-
282,239,858
-
627,059,848
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
83,649,761,000
6,074,599,000
7,115,591,500
9,638,291,977
1,087,204,085
Total - ADB Loan No.2817-INO
2,399,110,904,953
108,822,378,295
109,863,370,795
187,590,032,423
Total - IDB + ADB
2,863,163,346,953
108,822,378,295
109,863,370,795
187,590,032,423
Total Consulting Services
PL PL
46,542,613,447
-
PL
PL PL
102,979,832,006
-
PL
PL
64,090,759,200
-
DSC-3 (Jawa Timur - ADB) Road Safety Support
PL
102,747,779,295
-
DSC-1 (Kalimantan -ADB)
Institutional Development for Road Network Management Road Safety Awareness Campaign and Training Overloading and Speed Enforcement
102,747,779,295
-
-
3,921,898,000
-
1,691,195,341
-
-
1,927,709,116
3,921,898,000
4,282,842,950
29,792,128,307
-
52,824,071,746
68,012,657,200
37,759,328,643
-
66,950,623,146
78,604,127,745
1,332,733,500 1,194,140,000 -
12,282,035,367
5,505,418,800
15,163,750,000
10,760,050,300
3,231,768,975
6,360,727,200
6,579,331,000
6,360,727,200.00
2,796,171,507
2,638,238,625
3,864,651,000
3,832,378,625.00
-
-
-
-
-
-
-
-
-
-
2,526,873,500
18,309,975,849
14,504,384,625
25,607,732,000
20,953,156,125
107,262,674,956
49,069,486,947
224,265,796,162
243,642,154,316
414,144,671,170
360,724,298,463
138,648,012,248
119,204,316,765
291,742,126,133
252,441,743,422
535,100,090,170
450,250,187,932
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM B : SUMMARY OF IMPLEMENTATION FOR FISCAL YEAR 2015 B.
PHYSICAL IMPLMENTATION ( %)
No.
PAKET KONTRAK
[a]
TANGGAL PENANDATANGANAN KONTRAK
TANGGAL AKHIR KONTRAK (PHO)
[b]
[c]
KUMULATIF s.d TA.2014
PERKEMBANGAN FISIK TAHUN ANGGARAN 2015 Akhir Triwulan I Target Realisasi
Akhir Triwulan II Target Realisasi
Akhir Triwulan III Target Realisasi
Akhir Triwulan IV Target Realisasi
[d]
[e]
[f]
[g]
[h]
[i]
[j]
[k]
2.24%
Jawa Tengah 1
24-RCP-01 Tambakmulyo - Wawar
12-Jan-15
2-Aug-18
-
-
-
-
-
0.04%
0.36%
1.12%
2
24-RCP-02 Giriwoyo - Duwet (Section I)
13-Jan-15
22-Jul-17
-
-
-
-
-
0.60%
0.61%
2.93%
2.94%
3
24-RCP-03 Wawar -Congot
7-Jan-15
4-Jun-16
-
-
-
-
-
12.46%
2.97%
17.52%
14.41%
21-Aug-13
10-Apr-16
29.04%
34.49%
38.09%
48.44%
45.15%
60.13%
52.53%
79.87%
76.41%
15-Jan-15
14-Jun-18
-
0.00%
0.00%
0.028%
0.092%
0.59%
1.00%
1.42%
8.71%
14-Nov-13
15-Dec-16
25.76%
37.05%
37.02%
52.64%
52.67%
45.51%
45.66%
58.24%
58.26%
26-Nov-13
4-Jun-17
14.06%
30.90%
17.00%
39.50%
22.67%
49.47%
35.36%
39.27%
37.11%
3-Nov-14
11-Dec-16
0.10%
2.77%
2.79%
6.71%
14.02%
16.91%
30.28%
43.75%
Jawa Timur 4
28-RCP01A Jokosutro - Sendangbiru Kalimantan Barat
5
30-RCP01
6
30-RCP02
Sosok - Tayan; Tanjung- Bts. Kota Sanggau Tembas - SIingkawang Sec.1 + Sec.2 Bypass Sambas Galing - Tanjung Harapan
7
30-RCP03
Simpang Tanjung - Galing SP.3 Aruk /Bts. Serawak-Simpang. 3 Tanjung
Kalimantan Utara Tanjung Selor- SP.3 Tanjung Palas
8
34-RCP01
9
34-RCP02
Tanjung Palas -Sekatak Buji (Sec.2)
25-Jun-14
2-Sep-16
2.28%
5.01%
2.47%
16.58%
8.23%
32.70%
15.86%
52.69%
38.99%
10
34-RCP03
SP.Tiga Apas - Simanggaris (Section 1)
14-Apr-14
25-Dec-16
6.48%
11.80%
7.56%
24.01%
15.84%
34.78%
25.86%
36.26%
40.12%
11-Apr-14
29-Sep-17
0.52%
1.31%
1.41%
3.92%
7.42%
4.47%
14.13%
12.02%
11
34-RCP04
Sp.3 Tanjung Palas-Sekatak Buji (Section 1)
Sp. Tiga Apas - Simanggaris Simanggaris - Bts. Negara (Serudong)
6.81%
3.52%
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM C : STATUS / PROBLEM 2817-INO / IND-0161 Regional Roads Development Project (RRDP) - Jumlah Pinjaman 3-Jul-12 s/d 31-Dec-15 1276 hari
1 Loan
: USD
245,000,000.00
-
Tandatangan
Asian Development Bank
USD
180,000,000.00
-
Loan Efektif
Islamic Development Bank
USD
65,000,000.00
: USD
54,712,095.37
Penyerapan ADB : USD
47,952,934.41
Penyerapan IDB : USD
6,759,160.96
- Penyerapan Kumulatif
- Waktu Terpakai (bulan)
:
- Realisasi Penyerapan TA-2015 :
39.40 IDR 450,250,187,932
:
7 Mei 2012 (ADB) & 17 April 2012 (IDB) 3 Juli 2012 (ADB) & 2 Mei 2013 (IDB)
Loan Closing (addendum)
:
31 Juli 2018 (ADB) & 10 Juni 2019
2 Civil Works Jawa Tengah 1. 24 RCP-01 (CW-01) PT.
- Pengajuan Justifikasi teknis
Pembangunan
Perumahan (Persero)
- Justifikasi teknis dalam proses pembahasan di BBPJN V
Status LARP : - Program peningkatan pendapatan bagi warga terkena proyek belum dilakukan.
- Warga terkena proyek sebenarnya boleh memakai tanah yang sudah dikompensasi dan mereka sudah melakukannya, sebelum pekerjaan kontruksi masih ke tanah mereka - Bappeda sedang merancang kegiatan
- Santunan warga rentan terkena proyek belum dilakukan
/
program
untuk
peningkatan pendapatan bagi daerah yang terkena proyek. 2. 24 RCP-02 (CW-02) PT.
Hutama
- Pengajuan Justifikasi teknis Karya
(Persero)
- Justifikasi teknis dalam proses pembahasan di BBPJN V
Status LARP : - Ada 8 orang belum mengambil kompensasi tanah mereka dari kantor pengadilan setempat
3. 24 RCP-03 (CW-03) PT.
Jaya
- Pemeliharaan rutin perkerasan dan saluran Konstruksi - Pengajuan Justifikasi teknis
Masalah kompensasi sampai saat ini belum ada realisasi
- Memproduksi batu pecah, menunggu izin dari Pemda setempat - Justifikasi teknis sedang direvisi oleh BBPJN V
Manggala Pratama, Tbk
Jawa Timur
Status LARP :
1. 28 RCP-01A (CW-04) PT. Hutama (Persero)
- Proses pembayaran untuk pertukaran kawasan hutan dari kabupaten Malang ke kawasan hutan kabupaten Bondowoso, Karya untuk 148 ha, akan selesai pada tahun 2015
- Izin dari Mininstry Kehutanan menggunakan lahan hutan
dan
Lingkungan
- Sisa kawasan hutan yang harus dibayar adalah 1,267,245m2 atau 26,73 hektar. Pertengahan September 2015, Bappeda Kabupaten Malang mengatakan bahwa pembayaran akan dilaksanakan sesuai jadwal multiyears karena batas kapasitas APBD Malang.
untuk
- Perpanjangan izin dispensasi telah dikeluarkan dan diterima oleh Kabupaten Malang
- BPM (Badan Pemberdayaan Masyarakat ) telah menyiapkan Rencana Aksi untuk proyek terkait dengan menyiapkan beberapa anggaran APBDP 2015 sekitar Rp 200 juta untuk program ini. Pelaksanaan Program pemulihan pendapatan. Pada 5 Nopember 2015, BPM sudah melakukan pelatihan ekonomi produktif bagi 54 warga terkena proyek.
- BPM menjanjiukan masih akan memberi gerobak untuk jualan bagi 54 warga terkena proyek tahun 2016
- Menurut surat yang diterima dari Kepala Dinas Pekerjaan Umum Provinsi Kalimantan Barat kepada Direktur Pelaksana Wilayah II Ditjen Bina Marga pada tanggal 11 Februari 2014 - pembayaran kompensasi berdasarkan taksiran LARP-ADB di 2011 of Rp. 2.055.890.700, dan perkiraan ini telah direalisasikan oleh Dinas Pekerjaan Umum melalui Provinsi Kalimantan Barat Provinsi dana anggaran Rp.8.757.281.035 untuk tahun pajak melalui 2011-2014.
- Laporan Land Acquisation and Resettlementt Plan (LARP) telah selesai dibuat dan disampaikan ke Kementerian Pekerjaan Umum dan Perumahan Rakyat dan ADB
Kalimantan Barat 1. 30 RCP-01 (CW-05) PT. Yasa Patria Perkasa; PT.Budi Bakti Prima, JO
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
2. 30 RCP-02 (CW-06) PT. Brantas Abipraya ; PT. Status LARP Tri Citra Perdana; PT. - Telah dilakukan pengukuran di Jalan Bambang Ismoyo Trifa Abadi JO Singkawang sepanjang 3.6 km. Hasil pengukuran menunjukkan bahwa AP berada di luar pagar tanah bangunan milik AP meskipun bangunan yang direlokasi di ROW 13 m. Hasilnya adalah (i) proyek hanya mempengaruhi pagar populasi. Pemda Singkawang telah menganggarkan untuk kompensasi, nmun hingga akhir bulan Agustus 2015 pembayaran kompensasi belum dibayar; (ii) tidak ada dampak pada tanaman dan pohon; (iii) tidak ada rumah yang rentan terkena dampak . Jumlah kompensasi untuk pagar melibatkan penilaian konsultan. disamping itu pembebasan lahan asli yang terkena pelebaran jalan, awalnya berjumlah 15 rumah menjadi 4 rumah, karena perubahan desain.
- Pembayaran Kompensasi setelah SK selesai, belum ada realisasi
Walikota Singkawang
- Hasil pemantauan dan pengukuran Tim Safeguard bersama Kementerian PU Sambas bahwa pada RoW di sepanjang 1 km ada 20-25 meter terkena proyek pelebaran RRDP (pagar, jembatan dan dinding bangunan) 3. 30 RCP-03 (CW-07)
Kontrak Addendum I, 20 Oktober 2015
PT.Waskita Karya; Status LARP PT.Yala Patria Perkasa - Usulan kapasitas 4 jalur sepanjang 5,623 km, perlu pembebasan Lahan - Belum dilaksanakan pembayaran kepada 5 warga terkena dampak pekerjaan konstruksi pelebaran jalan.
- Nilai Addendum I Rp. 325,740,200,000 - LARP telah dilaksanakan CTC Akhir Oktober 2015 dan Laporan Draf LARP sudah disampaikan ke ADB, 16 Des 2015 Pembayaran kompensasi berdasarkan SK Bupati Kabupaten Sambas, hingga akhir Desember 2015 belum ada realisasi.
Kalimantan Utara 1. 34 RCP-01 (CW-08) PT. Waskita Karya
2, 34 RCP-02 (CW-09)
-
Diperlukan Perkuatan badan jalan pada lokasi longsoran
Usulan Justifikasi teknis dalam proses revisi oleh DSC -1 Kalimantan Status LARP - Lahan yang terkena proyek RRDP adalah tanah penduduk dan tanah negara luasnya seluas 31,67 Ha. Tanah penduduk berupa kebun, tegalan, dan permukiman, Untuk rumah dan tanam tumbuh penduduk yang terkena proyek mendapatkan penggantian, tetapi untuk tanah penduduk yang tidak memiliki surat bukti kepemilikan tidak mendapatkan ganti rugi tanah. Hal ini dikarenakan Pemda Kabupaten Bulungan khawatir jika lahan penduduk itu diganti rugi, maka untuk proyek lain di Kabupaten Bulungan akan meminta ganti rugi lahan juga, jadi kemungkinannya bisa digantikan oleh program-program Pemda Bulungan melalui SKPD-SKPD yang ada, sedangkan tanah negara perupa kawasan hutan yang termasuk Kawasan Hutan Produksi Terbatas tidak perlu mengurus Pinjam Pakai Kawasan Hutan tapi harus berkoordiasi dengan Dinas Kehutanan Kabupaten Bulungan. -
- Produksi batu pecah belum dapat dilaksanakan menunggu ijin blasting dari POLRI PT.Brantas Abipraya PT.Mahir Jaya Mahakam - Usulan justifikasi teknis sedang diproses di Ditjen Bina Marga Raya. JO
-
Proses Desain untuk perkuatan badan jalan akibat longsoran sedang dikerjakan DSC-1 Kalimantan
- Penggantian bangunan dan tanam tumbuh yang terkena proyek RRDP telah dianggarkan oleh Pemda Kabupaten Bulungan dan sebagian telah dibayarkan pada tahun 2014 sebesar Rp 117.187.200,- bagi sebanyak 17 bangunan dan sisanya sebanyak 95 bangunan akan dibayarkan pada tahun 2015, sedangkan untuk tanam tumbuh pada tahun 2014 telah dibayarkan sebesar Rp 45.686.000,- bagi 339 pohon dan selebih sebanyak 125 pohon akan dibayarkan pada tahun 2015
- Membeli Batu Pecah dari Pihak Ketiga
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Status LARP - Lahan yang terkena proyek RRDP adalah tanah penduduk yang tidak ada / bukti surat kepemilikan dan tanah negara seluas 27,72 Ha. Tanah penduduk berupa kebun, tegalan, dan permukiman, sedangkan tanah negara perupa kawasan hutan yang termasuk Kawasan Hutan Produksi Terbatas. Untuk tanah penduduk tidak ada penggantian tanah yang terkena proyek RRDP dikarenakan Pemda Kabupaten Bulungan khawatir untuk proyek lain di Kabupaten Bulungan akan meminta ganti rugi lahan, jadi kemungkinannya bisa digantikan oleh programprogram Pemda Bulungan melalui SKPD-SKPD yang ada Untuk rumah dan tanam tumbuh penduduk yang terkena proyek mendapatkan penggantian, tetapi untuk tanah penduduk yang tidak memiliki surat bukti kepemilikan tidak mendapatkan gantirugi tanah. Hal ini dikarenakan Pemda Kabupaten Bulungan khawatir jika lahan penduduk itu diganti rugi, maka untuk proyek lain di Kabupaten Bulungan akan meminta ganti rugi lahan juga, jadi kemungkinannya bisa digantikan oleh program-program Pemda Bulungan melalui SKPD-SKPD yang ada, sedangkan tanah negara perupa kawasan hutan yang termasuk Kawasan Hutan Produksi Terbatas tidak perlu mengurus Pinjam Pakai Kawasan Hutan tapi harus berkoordiasi dengan Dinas Kehutanan Kabupaten Bulungan. 3. 34 RCP-03 (CW-10)
- Pekerjaan saluran samping menunggu relokasi tanaman sawit
PT. PP - PT.Perdasa, JO
(saat ini proses alokasi) Status LARP - Lahan yang terkena proyek RRDP adalah tanah negara yang dikelola penduduk dan tanah yang dikuasai Perusahaan Perkebunan berupa HGU . Tanah negara yang dikuasai penduduk perupa kawasan perkebunan sawit, sedangkan tanah HGU yang dikuasai perusahaan berupa perkebunan sawit. Sehingga untuk tanah tersebut yang terkena proyek RRDP baik tanah HGU maupun yang dikelola penduduk tidak ada penggantian hanya kompensasi berupa pekerjaan untuk memindahkan bangunan dan tanaman kelapa sawit yang terkena proyek ke tempat yang telah ditentukan berdasarkan kesepakatan bersama dan pembuatan / perataan tapak rumah dan pembuatan jalan ke arah rumah atau ke kebun penduduk yang terkena proyek
4. 34 RCP04 (CW-11) But Halla Corporation
- Penggantian bangunan dan tanam tumbuh yang terkena proyek RRDP telah dianggarkan oleh Pemda Kabupaten Bulungan dan sebagian telah dibayarkan pada tahun 2014 sebesar Rp 656.160.600,- bagi sebanyak 46 bangunan dan sisanya sebanyak 53 bangunan akan dibayarkan pada tahun 2015 Dan tanam tumbuh sebesar Rp 40. 854.300,- bagi 439 pohon dan sisanya sebanyak 59 pohon akan dibayarkan pada tahun 2015
- Tidak ada penggantian untuk tanah, bangunan milik penduduk dan tanaman yang terkena proyek RRDP yang berada di tanah negara, kecuali penduduk atau perusahaan tersebut minta agar bangunan dan tanaman yang terkena proyek RRDP minta kompensasi berupa pemindahkan bangunan milik penduduk dan tanaman baik milik penduduk maupun milik perusahaan perkebunan ke lokasi yang disepakati bersama. Telah dipindahkan sebagian dari 238 pohon kelapa sawit milik penduduk dan 962 pohon kelapa sawit milik perusahaan perkebunan dan telah dipindahkan sebuah bangunan sesuai kesepakatan
- Usulan justifikasi teknis dalam proses revisi di DS-1 Kalimantn Status LARP - Diperlukan pelaksanaan LARP dan relokasi - Lahan yang terkena adalah tanah negara, tidak ada bangunan warga yang terkena proyek RRDP, tapi terdapat tanaman kelapa sawit dan kelapa milik warga yang terkena proyek RRDP
3 Konsultan a Core Team Consultant
Tidak ada penggantian untuk tanah, bangunan milik penduduk dan tanaman yang terkena proyek RRDP yang berada di tanah negara, kecuali penduduk tersebut minta agar bangunan dan tanaman yang terkena proyek RRDP minta kompensasi berupa pemindahan tanaman kelapa sawit yang terkenaa proyek RRDP. Terdapat 291 pohon kelapa sawit milik warga dan 17 pohon kelapa minta dipindahkan, terdapat 22 orang WTP
- Tagihan invoice 14 -18 (April 2015 - Agustus 2015) Status LFIS ADB Website : sudah terbayar 10 Desember 2015 - Proses Addendum 2
- Sampai Akhir Desember masih belum masuk ke rekening Renardet SA, dan sudah ditanyakan ke ADB menunggu proses pembayaran
b DSC -1 Kalimantan
-
-
c DSC -2 Jawa Tengah
- Proses Addendum I
-
- segera pergantian personal DSC
-
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
d DSC-3 Jawa Timur
- Persetujuan ADB atas Draft Kontrak Addendum No.2, 30 Nop 2015 - Perpanjangan Waktu dari 750 hari menjadi 925 hari - Nilai Addendum No.2. Rp. 9,713,093,500 (termasuk ppn)
e. Road Safety Support
- Tanda tangan Kontrak : 6 Oktober 2015 - Nilai kontrak : Rp.4,047,644,000
f. HIV Aids and Trafficking - Tanda tangan Kontrak : 6 Oktober 2015 program - Nilai kontrak : Rp.2,535,416,000
d Technical Assistance (TA) yang belum terkontrak
Status sampai 31 Desember 2015
CSP-5 : Institutional Devl for Road Network Management
Saat ini sedang disiapkan revisi TOR, Harga Perkiraan Sendiri (HPS) dan Draft Request for Expression of Interest (REOI)
CSP-6 : Road Safety Awareness Campaign and Training
Paket ini dapat pindah ke aktivitas lain, menunggu keputusan dari Komite Pengarah (Bappenas)
CSP-7 : Overloading and Speed Enforcement
Proses Pengiriman kontrak ke ADB (tanda tangan kontrak 19 November 2015)
CSP-8 : Indonesia Transport Sector Development Strategy and Policy
Proses Pengumuman Pemenang oleh Pokja, dilanjutkan proses penandatanganan kontrak
CSP-9 : Integrated Vehicle Overloading Control Strategy
Paket ini dapat pindahkan ke aktivitas lain, menunggu keputusan dari Komite Pengarah (Bappenas)
4 DIPA 2015 - Alokasi PHLN untuk Revisi DIPA 2015 sebesar Rp. 535,100,092,000
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP01 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 12 Januari 2015
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 1 Desember 2014
15-Juni-2012
- Periode Kontrak
: 1,095 hari kalender
25-Juni-2013
- Tanggal Akhir Kontrak
: 2 Agustus 2018
- Nama kontraktor/konsultan/suplayer
: PT. Pembangunan Perumahan
Oleh Penanggung Jawab Kegiatan
8-Apr-12
Persetujuan Pemberi Pinjaman
22-Apr-12
18-Sep-12 (Comment)
PT. Armada Hada Graha, JO Undangan Lelang
30-Apr-12
1-May-14
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan 5 Juli 2012-3 Sept 2012
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
17-Sep-12
21-Sep-14
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
7-Okt-2014
Status Kemajuan : Rencana : 1.121% ; Actual : 2.239% ; Deviasi : 1,118%
12-Jan-15
Status Penyerapan : Rp. 50,161,413,699 (20.58%)
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
Waktu Terpakai : 142 hari ( 12.97%)
1-Dec-14
Permintaan Uang Muka
12-May-15
Penarikan Uang Muka
10-Jul-15
Sisa waktu terpakai : 953 hari (87.03 %)
D5. STATUS PENYERAPAN
Dalam Rupiah
PENYERAPAN NILAI KONTRAK *) KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
(e) 243,741,564,000
(f) -
PENYERAPAN TA 2015 Triwulan 1
Triwulan 2
Triwulan 3
Triwulan 4
TOTAL TA 2015
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
3,602,739,238
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
6,387,975,695
-
14,192,336,618
44,316,648,000
23,346,553,448
1,284,637,181
47,529,605,000
Realisasi (p) 45,601,285,181
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP02 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 13 Januari 2015
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 1 Desember 2014
15-Juni-2012
- Periode Kontrak
: 730 hari kalender
25-Juni-2013
- Tanggal Akhir Kontrak
: 22 Juli 2017
- Nama kontraktor/konsultan/suplayer
: PT. Hutama Karya
8-Apr-12
Oleh Penanggung Jawab Kegiatan
22-Apr-12
Persetujuan Pemberi Pinjaman
18-Sep-12 (Comment)
Undangan Lelang
30-Apr-12
1-May-14
5 Juli 2012-3 Sept 2012
10 Juli 2014-24 Agustus 2014
17-Sep-12
21-Sep-14
26-Sep-12
7-Okt-2014
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
Status Kemajuan :
13-Jan-15
Rencana : 2.927% ; Actual : 2.239% ; Deviasi : 1,118%
Status Penyerapan : Rp. 30,250,000,000 (21.30%)
Persetujuan oleh Bappenas (bila diperlukan)
Waktu Terpakai : 153 hari ( 20.96%)
1-Dec-14
Persetujuan Pemberi Pinjaman Permintaan Uang Muka
13-May-15
Penarikan Uang Muka
9-Jul-15
Sisa waktu terpakai : 577 hari (73.04 %)
D5. STATUS PENYERAPAN
Dalam Rupiah
PENYERAPAN NILAI KONTRAK *) KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
(e) 142,000,000,000
(f) -
PENYERAPAN TA 2015 Triwulan 1
Triwulan 2
Triwulan 3
Triwulan 4
TOTAL TA 2015
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
3,285,705,632
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
5,825,847,038
-
12,943,440,331
25,818,181,818
21,292,105,000
1,681,818,182
43,347,098,000
Realisasi (p) 27,500,000,000
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP03 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 7 Januari 2015
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 1 Desember 2014
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 360 hari kalender
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
: 4 Juni 2016
- Nama kontraktor/konsultan/suplayer
: PT. Jaya Konstruksi Manggala Pratama
Pasca Kualifikasi 24-Jan-14
Undangan Lelang
1-May-14 25-Apr-14
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan
10 Juli 2014-24 Agustus 2014
Oleh Penanggung Jawab Kegiatan
21-Sep-14
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK 7-Okt-2014
Tandatangan Kontrak
Status Kemajuan :
7-Jan-15
Rencana : 17.519% ; Actual : 14.412% ; Deviasi : -3,107%
Status Penyerapan : Rp. 13,507,537,381 (23.19%)
Persetujuan oleh Bappenas (bila diperlukan)
Waktu Terpakai : 202 hari ( 55.34%)
1-Dec-14
Persetujuan Pemberi Pinjaman Permintaan Uang Muka
19-May-15
Penarikan Uang Muka
10-Jun-15
Slipage : 158 hari (43.89%)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 58,253,088,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
-
Triwulan 1
Triwulan 2
883,115,663
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
1,565,842,271
Triwulan 3
10,591,470,545
3,478,873,693
Triwulan 4
-
19,469,884,374
TOTAL TA 2015
1,688,108,893
25,397,716,000
Realisasi (p) 12,279,579,438
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 28-RCP01A (Jawa Timur)
D2. LANGKAH-LANGKAH KEGIATAN
TANGGAL
TANGGAL
RENCANA PERUBAHAN
(a)
(b)
TANGGAL
D3. STATUS KONTRAK
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(c)
(d)
PROSES PENGADAAN Prakualifikasi
- Tanggal Kontrak - Tanggal Addendum 1
: 21 Agustus 2013 : 24 Desember 2013
- Tanggal Addendum 2
: 18 Desember 2014
Oleh Penanggung Jawab Kegiatan
1-Mar-12
27-Jun-12
- Tanggal Addendum 3
: 20 Maret 2015
Persetujuan Pemberi Pinjaman
15-Mar-12
6-Feb-13
- Tanggal Persetujuan Peminjam
: 8 September 2013
- Periode Kontrak
: 730 hari Kalender
- Periode Kontrak Addendum
: 905 hari Kalender
- Tanggal Akhir Kontrak
: 17 Oktober 2015
- Tanggal Akhir Kontrak Addendum
: 10 April 2016
- Nama kontraktor/konsultan/suplayer
: PT.Hutama Karya
Pasca Kualifikasi Undangan Lelang
24-Mar-12
1-Mar-13
Persetujuan Pemberi Pinjaman
Evaluasi Pengadaan 30 Mei 201228Juni 2012
Oleh Penanggung Jawab Kegiatan
2 Mei 2013 4 Juni 2013
Persetujuan Pemberi Pinjaman
10-Jul-13
D4. STATUS TERAKHIR Status Kemajuan :
KONTRAK Tandatangan Kontrak
Rencana : 79.519 % ; Actual : 76.408 % ; Deviasi : -3.459 %
21-Aug-13
Status Penyerapan : Rp. 70,702,881,379 (62.67 %)
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
Waktu Terpakai : 796 hari (87.96 %)
9-Sep-13
Permintaan Uang Muka
18-Sep-13
Penarikan Uang Muka
Sisa waktu terpakai : 109 hari (12.04 %)
9-Oct-13
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 112,823,335,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
23,011,025,595
Triwulan 1
Triwulan 2
1,670,068,629
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
2,961,177,008
Triwulan 3
8,168,166,964
6,578,924,510
Triwulan 4
4,797,084,832
20,666,014,853
TOTAL TA 2015
16,871,691,026
31,876,185,000
Realisasi (p) 29,836,942,822
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP01 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 15 Januari 2015
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 4 Pebruary 2015
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 1,095 hari kalender
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
: PT. Yasa Patria Perkasa
14 Juni 2018
PT. Budi Bakti Prima, JO
Pasca Kualifikasi 23-Apr-12
Undangan Lelang
26-Feb-13
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan 29 Juni 2012 27 Agust 2012
Oleh Penanggung Jawab Kegiatan
21 Mei 2013 11 Sep 2013 11-Okt-2013
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
Catatan : Proses Usulan untuk Tender Ulang Status Kemajuan :
KONTRAK Tandatangan Kontrak
Rencana : 1.422% ; Actual : 8.709% ; Deviasi : 7.287%
15-Jan-15
Status Penyerapan : Rp. 84,012,996,053 (18.04%)
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
4-Feb-15
Permintaan Uang Muka
4-Jun-15
Penarikan Uang Muka
22-Jun-15
Waktu Terpakai : 191 hari (17.44 %) Sisa waktu terpakai : 904 hari (91.69 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 465,647,542,528
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
-
Triwulan 1
Triwulan 2
5,502,988,120
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
9,757,285,231
Triwulan 3
31,818,181,818
21,678,021,815
Triwulan 4
-
35,660,589,835
TOTAL TA 2015
21,644,636,852
72,598,885,000
Realisasi (p) 53,462,818,670
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP02 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 14 Nopember 2013
Prakualifikasi
- Tanggal Kontrak Addendum
: 28 Agustus 2015
Oleh Penanggung Jawab Kegiatan
31-Mar-12
27-Jun-12
- Tanggal Persetujuan Peminjam
: 28 November 2013
Persetujuan Pemberi Pinjaman
14-Apr-12
6-Feb-13
- Periode Kontrak
: 1.095 hari kalender
- Tanggal Akhir Kontrak
: 15 Desember 2016 : PT.Brantas Abipraya (persero)
Pasca Kualifikasi
- Nama kontraktor/konsultan/suplayer
Undangan Lelang
23-Apr-12
26-Feb-13
PT.Citra Persada
Persetujuan Pemberi Pinjaman
PT.Trifa Abadi, JO
Evaluasi Pengadaan 29 Juni 2012 27 Agust 2012
Oleh Penanggung Jawab Kegiatan
23 Mei 2013 28 Agust 2013
Persetujuan Pemberi Pinjaman
13-Sep-13
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
Status Kemajuan ::
14-Nov-13
Rencana : 58.243% ; Actual : 58.259% ; Deviasi : + 0.016%
Status Penyerapan : Rp. 199,856,880,711 (49.07%)
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
27-Nov-13
Waktu terpakai : 736 hari (67.21%)
Permintaan Uang Muka
28-Nov-13
Sisa waktu terpakai : 360 hari (37.69 %)
Penarikan Uang Muka
17-Dec-13
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 407,294,892,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
43,890,507,750
Triwulan 1
Triwulan 2
4,890,543,605
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
8,671,359,569
Triwulan 3
16,684,824,884
19,265,387,000
Triwulan 4
29,043,061,611
31,691,755,826
TOTAL TA 2015
14,844,707,505
64,519,046,000
Realisasi (p) 60,572,594,000
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP03 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 26 November 2013
Prakualifikasi
- Tanggal Kontrak Addendum
: 20 Oktober 2015
Oleh Penanggung Jawab Kegiatan
31-Mar-12
27-Jun-12
- Tanggal Persetujuan Peminjam
: 29 November 2013
Persetujuan Pemberi Pinjaman
14-Apr-12
6-Feb-13
- Periode Kontrak
: 1.095 hari kalender
- Tanggal Akhir Kontrak
: 2 Desember 2016
- Tanggal Akhir Addendum
: 4 Juni 2017 : PT.Waskita Karya (persero),
Pasca Kualifikasi Undangan Lelang
23-Apr-12
26-Feb-13
- Nama kontraktor/konsultan/suplayer
Persetujuan Pemberi Pinjaman
PT.Yasa Patria Perkasa, JO
Evaluasi Pengadaan 29 Juni 2012 27 Agust 2012
Oleh Penanggung Jawab Kegiatan
24 Mei 2013 -5 Sep 2013
Persetujuan Pemberi Pinjaman
12-Oct-13
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
Status Kemajuan :: Rencana : 39.268% ; Actual : 37.107% ; Deviasi : -2,161%
26-Nov-13
Status Penyerapan : Rp. 126,291,458,657 (38.77%)
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
28-Nov-13
Permintaan Uang Muka
29-Nov-13
Penarikan Uang Muka
17-Dec-13
Waktu terpakai : 759 hari (68.40%) Sisa waktu terpakai : 436 hari (39.82 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 325,740,200,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
35,846,245,950
Triwulan 1
Triwulan 2
3,236,199,505
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
5,738,068,291
Triwulan 3
-
12,748,419,940
Triwulan 4
-
20,971,294,263
TOTAL TA 2015
40,002,388,091
42,693,982,000
Realisasi (p) 40,002,388,091
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP01 (Kalimantan Utara)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 3 Nopember 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 19 Nopember 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 730 hari kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 11 Desember 2016
- Nama kontraktor/konsultan/suplayer
: PT. Waskita Karya (Persero)
Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
Comment ADB 4
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
Mar 2014, Klarifikasi -
4 -Okt-2012
KONTRAK Tandatangan Kontrak
Status Kemajuan Rencana : : 30.280 % ; Actual :43.750 % ; Deviasi : 13.470 %
3-Nov-14
Status Penyerapan : Rp. 94,674,419,736 (49,84 %)
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
19-Nov-14
Permintaan Uang Muka
24-Nov-14
Penarikan Uang Muka
8-Dec-14
Waktu terpakai
: 376 hari (51.51 %)
Sisa waktu terpakai : 354 hari (48.49 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 189,970,248,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
-
Triwulan 1
Triwulan 2
2,749,038,484
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
4,874,288,662
Triwulan 3
-
10,829,337,614
Triwulan 4
7,820,988,762
36,297,334,240
TOTAL TA 2015
34,292,845,617
54,749,999,000
Realisasi (p) 42,113,834,379
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP02 (Kalimantan Utara)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 25 Juni 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 Mei 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 730 Hari kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 2 September 2016
- Nama kontraktor/konsultan/suplayer
: PT.Brantas Abipraya PT.Mahir Jaya Mahakam Raya, J.O
Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013 9 Maret 2014, Proses persetujuan Mentri
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
4 -Okt-2012 Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
25-Jun-14
Status Kemajuan Rencana : : 52.698% ; Actual : 38.992% ; Deviasi : - 13.697%
Persetujuan oleh Bappenas (bila diperlukan)
Status Penyerapan : Rp. 76,979,144,449 (46.56%)
Persetujuan Pemberi Pinjaman
Waktu Terpakai
Permintaan Uang Muka
11-Aug-14
Penarikan Uang Muka
29-Aug-14
: 475 hari (65.07%)
Sisa waktu terpakai : 355 hari (48.63%)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 165,332,328,425
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
-
Triwulan 1
Triwulan 2
1,914,004,062
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
3,393,698,688
Triwulan 3
-
7,539,871,230
Triwulan 4
-
26,302,425,021
TOTAL TA 2015
30,922,059,859
39,149,999,000
Realisasi (p) 30,922,059,859
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP03 (Kalimantan Utara)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 11 April 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 Mei 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 900 Hari Kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 27 September 2015
- Tanggal Akhir Addendum
: 25 Desember 2016
- Nama kontraktor/konsultan/suplayer
: PT.Pembangunan Perumahan Tbk
Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
4 -Okt-2012
11-Des-2013
PT.Perdasa,JO
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR Persetujuan Pemberi Pinjaman KONTRAK Status Kemajuan Rencana : : 36.255 % ; Actual : 40.118% ; Deviasi : 3.863 %
11-Apr-14
Tandatangan Kontrak
Status Penyerapan : Rp. 158,556,262,703 (50.63%)
Persetujuan oleh Bappenas (bila diperlukan)
Waktu Terpakai
14-May-14
Persetujuan Pemberi Pinjaman Permintaan Uang Muka
3-Jul-14
Penarikan Uang Muka
4-Aug-14
: 531 hari (59.00 %)
Sisa waktu terpakai : 469 hari (52.11 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 289,000,000,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
-
Triwulan 1
Triwulan 2
4,611,448,056
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
8,176,505,751
Triwulan 3
7,419,585,534
18,165,961,726
Triwulan 4
4,881,478,242
27,794,927,466
TOTAL TA 2015
46,384,404,133
58,748,843,000
Realisasi (p) 58,685,467,909
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP04 (Kalimantan Utara)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 11 April 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 May 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 1095 Hari Kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 29 September 2017 : Butt Halla Corporation
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
4 -Okt-2012
11-Des-2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR Persetujuan Pemberi Pinjaman KONTRAK Tandatangan Kontrak
11-Apr-14
Status Kemajuan Rencana : : 14.125 % ; Actual :12.016% ; Deviasi : -2.109 %
Persetujuan oleh Bappenas (bila diperlukan)
Status Penyerapan : Rp. 98,934,738,824 (27.51%)
Persetujuan Pemberi Pinjaman
14-May-14
Permintaan Uang Muka
Waktu terpakai
23-Jul-14
Penarikan Uang Muka
: 448 hari (40.91 %)
Sisa waktu terpakai : 737 hari (67.31 %)
20-Aug-14
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 359,652,598,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
-
Triwulan 1
Triwulan 2
4,130,633,761
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
7,323,979,429
Triwulan 3
-
6,173,908,171
Triwulan 4
-
6,571,478,809
TOTAL TA 2015
24,175,036,608
24,200,000,170
Realisasi (p) 24,175,036,608
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Core Team Consultant (CTC)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 12 Februari 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 24 Februari 2014
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 46 bulan
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
: 31 Desember 2018 Renardet SA in JV with :
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi
PT. Widya Graha Asana
Undangan Lelang
PT. Multy Phibeta
Persetujuan Pemberi Pinjaman
PT.Anugerah Kridapradana PT. Disiplan Consult
Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK 12-Feb-14
Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan)
24-Feb-14
Persetujuan Pemberi Pinjaman
* Status Penyerapan
: IDR 5,573,622,393 dan USD 793,768.36
* Kontrak Awal
: USD 1,192,400 dan IDR 19,472,500,000
* Kontrak Addendum 1 : USD 1,473,900 dan IDR 22,584,677,000
2-Oct-14
Permintaan Uang Muka
Nol ADB : 19 Maret 2015
27-Oct-14
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 33,781,300,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
-
Triwulan 1
429,311,676
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
761,207,617
Triwulan 3
3,921,898,000
1,691,195,341
Triwulan 4
1,332,733,500
12,282,035,367
TOTAL TA 2015
5,505,418,800
15,163,750,000
Realisasi (p) 10,760,050,300
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Design and Supervision Consultant -1 Kalimantan
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
11 November 2013
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
37 bulan
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
Nopember 2016
- Nama kontraktor/konsultan/suplayer
:
CECI Engineriing Consultant in Ass
Pasca Kualifikasi
21 November 2013
PT. Wira Widyatama ; PT. Seecons 26-Feb-13
Undangan Lelang
PT. Hasfarm Dian Konsultan
0-Jan-00
Persetujuan Pemberi Pinjaman
PT. Yodya Karya, PT. Pola Agung Consulting
Evaluasi Pengadaan 24 Mei 2013 5 Sep 2013
Oleh Penanggung Jawab Kegiatan
12-Oct-13
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK 26-Nov-13
Tandatangan Kontrak
* Status Penyerapan : IDR 6,074,599,000 dan USD 217,049
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
28-Nov-13
Permintaan Uang Muka
9-Dec-13
Penarikan Uang Muka
28-Mar-14
* Kontrak Awal
: USD 936,574 dan IDR 30,372,995,000
* Addendum I
: USD 589,920 dan IDR 36,353,305,000
Addendum I , 7 April 2014
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 41,611,883,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
498,712,622.51
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
884,261,641.13
Triwulan 3
-
1,964,587,761
Triwulan 4
-
3,231,768,975
TOTAL TA 2015
-
6,579,331,000
-
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Design and Supervision Consultant -2 Jawa Tengah
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 14 April 2015
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 2040100/IND/0453 tanggal 3 Maret 2015
- Periode Kontrak
: 36 bulan
- Tanggal Akhir Kontrak
: 13 April 2018
- Nama kontraktor/konsultan/suplayer
: Botek Bosphorus Technical Engineering Corp JO
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
7-Jun-13
Pasca Kualifikasi
Associated Consulting Engineers-ACE,
Undangan Lelang
PT.Kwarsa Hexagon, PT.Binatama Wirawreda
Persetujuan Pemberi Pinjaman
Konsultan,PT.Tata Guna Patria,PT.Caturbina GP
Evaluasi Pengadaan
15 Nop 2013 Mei 2014 2013
Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK Tandatangan Kontrak Sudah mulai mobilisasi personil
Persetujuan oleh Bappenas (bila diperlukan)
Sudah mengajukan penarikan uang muka tgl 28 Agustus
Persetujuan Pemberi Pinjaman
2015 (masih
diproses)
Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
Dalam Rupiah PENYERAPAN TA 2015
NILAI KONTRAK *)
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
Triwulan 1
20,057,790,000 195,639,803 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
346,886,397
Triwulan 3
-
770,686,650
Triwulan 4
-
3,367,787,150
TOTAL TA 2015
4,145,024,850
4,681,000,000
Realisasi (p) 4,145,024,850
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Design and Supervision Consultant -3 Jawa Timur
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 6 Oktober 2013 : 11 Nopember 2013
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 25 bulan
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
: 16 Nopember 2015 : PT. Perentjana Djaja
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang
26-Feb-13
Persetujuan Pemberi Pinjaman
0-Jan-00
Evaluasi Pengadaan 24 Mei 2013 5 Sep 2013
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
12-Oct-13
D4. STATUS TERAKHIR
KONTRAK 26-Nov-13
Tandatangan Kontrak
* Status Penyerapan : IDR 1,040,992,500 untuk Uang Muka dan Invoice 1-14 : IDR 3,059,323,040
Persetujuan oleh Bappenas (bila diperlukan) 7-Nov-13
Persetujuan Pemberi Pinjaman
* Kontrak Awal
: IDR 6,939,950,000
Permintaan Uang Muka
26-Nov-13
* Kontrak Addendum I: IDR 7,505,980,000
Penarikan Uang Muka
9-Dec-13
* Nol ADB : 29 Oktober 2014
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 8,256,578,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
1,040,992,500
Triwulan 1
159,179,787
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
282,239,858
Triwulan 3
-
627,059,848
Triwulan 4
1,194,140,000
2,796,171,507
TOTAL TA 2015
2,638,238,625
3,864,651,000
Realisasi (p) 3,832,378,625
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Pre Contract, Contract, Amendment for additional works and other changes) D1. PAKET KONTRAK : Road Safety Support
D2. LANGKAH-LANGKAH KEGIATAN
(a) PROSES PENGADAAN Prakualifikasi Oleh Penanggung Jawab Kegiatan
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
21-Aug-14 11-Oct-14 21-Oct-14
Persetujuan Pemberi Pinjaman
- Tanggal Kontrak - Tanggal Persetujuan Peminjam - Periode Kontrak - Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
22-Aug-14 9-Dec-14 19-Dec-14
: : : : :
6 Oktober 2015 13 Nopember 2015 12 bulan 6 Oktober 2016 PT.Widya Graha Asana, PT.Barunadri
Pasca Kualifikasi Undangan Lelang Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
29-Dec-14 21-Mar-15
Persetujuan Pemberi Pinjaman KONTRAK Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
23-Feb-15 25-Mar-15 1-Apr-15
15-4-2015
D4. STATUS TERAKHIR
23-Feb-15 1-Apr-15 18-May-15
6-Oct-15 13-Nov-15 22-Dec-15
D5. STATUS PENYERAPAN
Dalam Rupiah PENYERAPAN TA 2015
NILAI KONTRAK *)
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
4,047,644,000
-
Triwulan 1
-
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
-
TOTAL TA 2015
-
Realisasi (p) -
-
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM D : CONTRACT PACKAGE STATUS (Pre Contract, Contract, Amendment for additional works and other changes) D1. PAKET KONTRAK : HIV/AIDS and Anti Trafficking Program
D2. LANGKAH-LANGKAH KEGIATAN
(a) PROSES PENGADAAN Prakualifikasi Oleh Penanggung Jawab Kegiatan
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2015
(b)
(c)
(d)
21-Aug-14 11-Oct-14 21-Oct-14
Persetujuan Pemberi Pinjaman
- Tanggal Kontrak - Tanggal Persetujuan Peminjam - Periode Kontrak - Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
22-Aug-14 9-Dec-14 19-Dec-14
: : : : :
6 Oktober 2015 13 Nopember 2015 12 bulan 6 Oktober 2016 PT.Intersys Kelola Maju, PT Dwikarsa
Pasca Kualifikasi Undangan Lelang Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
29-Dec-14 21-Mar-15
Persetujuan Pemberi Pinjaman KONTRAK Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
23-Feb-15 25-Mar-15 1-Apr-15
15-4-2015
D4. STATUS TERAKHIR
23-Feb-15 1-Apr-15 18-May-15
6-Oct-15 13-Nov-15
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 2,535,416,000
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
-
Triwulan 1
-
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
-
TOTAL TA 2015
-
Realisasi (p) -
-
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
FORM E : RINCIAN DOKUMEN ANGGARAN Nomer NPPHLN : ADB 2817-INO, Register : 10846401 IDB 0161-IND, Register : 10848804 PLN Nama Kegiatan dan Nomor Kode DIPA *
Valas
(a)
(b)
Rupiah (dalam juta)
Rupiah Ekivalen (juta)
Dana Pendamping Pagu
(c)
(d)
Rupiah Murni
Realisasi Pagu (e)
(f)
Rencana Penarikan PLN 2016
Realisasi
( Juta Rupiah )
(g)
(h)
1. Islamic Development Bank (IDB) Civil Works Jawa Tengah 1 2 3
24-RCP-01 24-RCP-02 24-RCP-03
Tambakmulyo - Wawar Giriwoyo - Duwet Wawar - Congot
Consultant Services 1 CSP-11 DSC-2 (IDB - Jawa Tengah) Total _IDB
USD
3,520.71
47,529.61
9,461.15
3,210.90
43,347.10
6,360.72
-
31,456.67
USD USD
1,881.31
25,397.72
2,143.35
-
58,497.98
-
61,229.16
USD
346.74
4,681.00
USD
8,959.66
120,955.42
17,965.21
-
1,596.20 152,780.00
USD
2,361.20
31,876.19
10,757.90
-
8,537.03
USD
5,377.70
72,598.89
35,000.00
USD
4,779.19
64,519.05
28,555.84
2. Asian Development Bank (ADB) Jawa Timur 4
5
6
7
28-RCP01A Jolosutro - Sendang biru Kalimantan Barat Sosok - Tayan 30-RCP01 Tanjung- Bts. Kota Sanggau Tebas - Singkawang Sec.1 + Sec.2 30-RCP02 Bypass Sambas Galing - Tanjung Harapan Simpang Tanjung - Galing 30-RCP03 Simpang Aruk /Bts. Serawak-Sp.3 Tanjung
-
20,636.08
33,000.00 -
USD
3,162.52
42,693.98
20,000.00
33,000.00 -
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Kalimantan Utara 8
34-RCP01
Tanjung Selor- SP.3 Tanjung Palas Sp.3 Tanjung Palas-Sekatak Buji (Section 1)
USD
4,055.56
54,750.00
25,805.52
-
60,475.92
9
34-RCP02
Tanjung Palas -Sekatak Buji (Sec.2)
USD
2,900.00
39,150.00
18,441.87
-
51,872.47
10
34-RCP03
SP.Tiga Apas - Simanggaris (Section 1)
USD
4,351.77
58,748.84
27,678.35
-
99,724.57
11
34-RCP04
USD
1,792.59
24,200.00
11,400.00
Sp. Tiga Apas - Simanggaris (Section 2) Simanggaris - Bts. Negara (Serudong)
87,927.26 -
Consultant Services DG Bina Marga , KemenPU 1 2 3 4 5 6
Core Team Consultant
USD
1,123.24
15,163.75
-
-
9,720.26
CSP-2
DSC-1 (ADB-Kalimantan)
USD
487.36
6,579.33
-
-
14,000.00
CSP-3
DSC-3 (ADB-Jawa Timur)
USD
286.27
3,864.65
-
-
343.60
CSP-4
Road Saftey Engineering Support
USD
-
-
-
-
2,643.86
CSP-10
HIV /AIDS and Anti Trafficking Program
USD
-
-
-
-
2,538.96
CSP- 5
Institutional Dev for Road Network Management
CSP-1
Total _ADB TOTAL (IDB+ADB)
USD
10,000.00
USD
30,677.38
414,144.67
177,639.48
-
434,420.00
USD
39,637.04
535,100.09
195,604.69
-
587,200.00
PMU RRDP – Quarterly Progress Report No.7, October - December 2015
Regional Roads Development Project (RRDP) Detail Contract, Allocation and Disbursement DIPA 2015 as of 30 September 2015 ADB Loan No.2817-INO & IDB Financing No. IND-0161 DIPA 2015
KONTRAK (termasuk PPN) NO
PAKET
PLN 10
Jawa Tengah
%
6
Eqv.USD 10
3
PPN -PLN 10
6
%
ALOKASI PDP 10
%
6
TOTAL 10
PLN
6
10
PDP
6
10
TOTAL
6
PENYERAPAN BERDASARKAN LFIS ADB SD saat ini TAHUN 2015
PENYERAPAN 10
6
PLN 10
6
Eqv.USD 10
3
PDP 10
TOTAL
6
10
6
PLN 10
Eqv. USD
6
10
3
PDP 10
TOTAL
6
10
6
31,048.58
40,363.15
403,631.50
116,274.42
1 24-RCP01 Tambakmulyo - Wawar
221,583.24
100
17,044.86
22,158.32
10
-
-
243,741.56
47,529.6
9,461.2
56,990.76
45,601.29
3,443.58
-
45,601.29
45,601.29
3,443.58
-
50,161.41
2 24-RCP02 Giriwoyo - Duwet (Section 1)
129,090.91
100
9,930.07
12,909.09
10
-
-
142,000.00
43,347.1
6,360.7
49,707.81
27,500.00
2,083.16
-
27,500.00
27,500.00
2,083.16
-
30,250.00
52,957.35
100
4,073.64
5,295.74
10
-
-
58,253.09
25,397.7
2,143.3
27,541.06
12,279.58
929.16
-
12,279.58
12,279.58
929.16
-
13,507.54
5,074.50
7,179.67
112,823.33
31,876.19
10,757.90
42,634.09
29,836.94
2,176.55
10,501.78
40,338.72
47,260.87
3,652.78
18,715.92
70
5,074.50
7,179.67
30
112,823.33
31,876.19
10,757.90
42,634.09
29,836.94
2,176.55
10,501.78
40,338.72
47,260.87
3,652.78
18,715.92
70,702.88
53,138.17
76,279.80
1,198,682.64
179,811.91
83,555.84
263,367.75
154,037.80
11,219.97
71,269.07
225,306.87
262,361.65
20,175.09
121,194.30
409,792.12
403,631.50
3 24-RCP03 Wawar - Congot Jawa Timur
71,796.67
4 28-RCP01 Jolosutro - Sendangbiru
71,796.67
Kalimantan Barat Sosok - Tayan 5 30-RCP01 Tanjung - Bts. Kota Sanggau Tebas - Singkawang (Section 1) Tebas - Singkawang (Section 2) 6 30-RCP02 Bypass Sambas Galing - Tanjung Harapan Sp. Tanjung - Galing 7 30-RCP03 Aruk (Bts. Serawak) - Sp. Tanjung
762,798.04
Kalimantan Timur Tanjung Selor - Sp.3 Tanjung Palas Sp.3 Tanjung Palas-Sekatak Buji (Section 1) 9 34-RCP02 Sp.3 Tanjung Palas - Sekatak Buji (Section 2) 10 34-RCP03 Sp. Tiga Apas - Simanggaris (Section 1) Sp. Tiga Apas - Simanggaris (Section 2) 11 34-RCP04 Simanggaris - Bts. Negara (Serudong)
654,244.22
8 34-RCP01
Pusat 1
33,847.00 10
33,847.00 359,604.79
134,239.63
85,380.86
6,455.90
-
85,380.86
85,380.86
6,455.90
-
93,918.95
70
22,220.42
29,632.12
10
139,694.26
30
465,647.54
72,598.89
35,000.00
107,598.89
53,462.82
3,945.44
24,834.68
78,297.50
53,462.82
3,945.44
24,834.68
83,643.78
259,187.66
70
19,199.09
25,918.77
10
122,188.47
30
407,294.89
64,519.05
28,555.84
93,074.89
60,572.59
4,438.90
28,554.65
89,127.25
127,182.29
9,951.38
59,956.36
199,856.88
207,289.22
70
11,718.67
20,728.92
10
97,722.06
30
325,740.20
42,693.98
20,000.00
62,693.98
40,002.39
2,835.63
17,879.74
57,882.13
81,716.54
6,278.27
36,403.26
126,291.46
50,129.46
65,424.42
1,028,098.05
176,848.84
83,325.74
260,174.58
155,896.40
11,320.55
73,494.02
229,390.42
273,092.00
21,190.07
128,743.37
429,144.57
120,890.16
70
9,178.02
12,089.02
10
56,991.07
30
189,970.25
54,750.00
25,805.52
80,555.52
42,113.83
3,039.26
19,853.66
61,967.50
60,247.36
4,511.50
28,402.33
94,674.42
105,211.48 199,272.68
70 70
8,068.31 15,328.67
10,521.15 19,927.27
10 10
49,599.70 93,942.83
30 30
165,332.33 313,142.78
39,150.00 58,748.84
18,441.87 27,678.35
57,591.87 86,427.19
30,922.06 58,685.47
2,243.62 4,274.22
14,577.54 27,666.01
45,499.60 86,351.47
48,986.73 100,899.44
3,776.74 7,838.63
23,093.74 47,566.88
76,979.14 158,556.26
228,869.90
70
17,554.46
22,886.99
10
107,895.81
30
359,652.70
24,200.00
11,400.00
35,600.00
24,175.04
1,763.44
11,396.80
35,571.84
62,958.47
5,063.20
29,680.42
98,934.74
8,978.88
11,645.59
128,101.46
30,288.73
-
30,288.73
3,146.84
3,953.45
43,487.98
15,163.75
-
15,163.75
25,059.49 2,652.75 8,063.36 5,083.01 1,282.97 2,981.68 1,163.34
1,852.27 200.66 604.16 367.35 94.65 217.72 85.54
-
20,914.46 2,652.75 8,063.36 5,083.01 1,282.97
41,813.37 5,573.62 10,349.82 11,157.61 3,848.74 2,981.68 1,163.34
3,238.26 443.66 793.77 865.06 311.70 217.72 85.54
3,832.38
282.20
-
3,832.38
6,738.55
520.81
39,534.53
100
308,429.42
10
-
-
2
DSC-1 Kalimantan (ADB)
43,137.39
100
3,121.33
4,313.74
10
-
-
47,451.12
6,579.33
-
6,579.33
3
DSC-2 Jawa Tengah (IDB)
19,694.92
100
1,715.96
1,969.49
10
-
-
21,664.41
4,681.00
-
4,681.00
4
DSC-3 Jawa Timur (ADB)
7,505.98
100
525.51
750.60
10
-
8,256.58
3,864.65
-
3,864.65
5 Road Safety Support
4,047.64
100
288.52
404.76
10
-
4,452.41
-
6 HIV/AIDS and Anti-Trafficking Program
2,535.42
100
180.73
253.54
10
-
2,788.96
-
$148,369.59
200,892.63
7 Institutional Development for Road Network Management TOTAL
70,702.88
296,321.16
116,455.87
CTC RRDP
-
17,965.21
2,008,926.30
701,881.21
2,871,336.99
535,100.09
-
-
-
-
-
-
-
44,715.03 17,515.79 16,506.98 3,279.85 7,412.41 -
195,604.69
730,704.78
450,211.50 $
33,025.23
155,264.87
601,331.34
709,908.76 $54,712.10
268,653.59
1,048,273.55
APPENDIX
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix 1
Regional Roads Development Project (RRDP) The Overall Financial Status as of 30 September 2015 ADB Loan No.2817-INO & IDB Financing No.IND-0161
1 USD = IDR 9,000
Loan Cat
Details of Category
1
2
1
Civil Works
2
Goods : Road Safety Equipment
Original Loan Allocation
Reallocation * dated 5 june 2015
ADB
IDB
ADB *
IDB
ADB
IDB
3a
3b
3c
3d
4a
4b
155,000.0 53,500.0 155,000.0
Awarded Contracts
Current Balance
53,500.0 110,089.0 31,048.6
44,911.0
IDB
ADB
IDB
6a
6b
7a
7b
22,451.4 16,579.41
ADB 8a
339.86 24,717.06 6,455.90 45,017.94
IDB
%=(8a/4a)
8b
40.89% 6,455.90
ADB
IDB
ADB
IDB
%=(8b/4b) 9a=(4a-8a) % =(9a/4a) 9b=(4b-8b) %=(9b/4b) 10a=(3c-4a) 10b=(3d-4b) 20.79% 65,071.08
59.11%
24,593
79.21%
22,451.4
-
-
0.0
-
1,300.0
1,300.0
1,300.0
-
Equipment for Institutional 2B Development for Road Network Management
0.0
-
900.0
900.0
900.0
-
0.0
-
-
6,000.0
-
6,000.0
3,195.5
-
2,804.5
-
407.81
804.82
1,237.43
38.72%
1,958.08
61.28%
5,300.0
-
5,300.0
3,191.4
-
2,108.6
-
461.99
461.99
1,176.76
36.87%
2,014.68
63.13%
-
3,000.0
-
-
1,284.0
900.0
-
900.0
629.9
270.1
-
400.0
-
400.0
292.5
107.5
-
900.0
-
-
-
3,000.0
-
3,000.0
2,200.0
-
1,300.0
3D Road Safety Support 3E 3F 3G 3H 3I 3J 4
Institutional Development for Road Network Management Road safety awareness campaign and training Overloading and Speed Enforcement Indonesia Transport Sector Development Strategy and Integrated Vehicle Overloading Control Strategy HIV/AiDS and Anti Trafficking Prevention Program Unallocated
-
3,000.0
1,715.96
303.26
-
-
3,000.0
-
3,000.0
-
2,200.0
2,200.0
-
2,200.0
-
-
1,300.0
1,300.0
-
1,300.0
-
800.0
-
800.0
800.0
-
800.0
-
300.0
-
300.0
116.6
-
116.6
-
180,000.0 65,000.0 180,000.0 65,000.0 117,581.7 32,764.5
62,418.3
-
17.31%
1,284.0
-
-
109.04
-
0.0
2,600.0
-
82.69%
82.3%
-
8,500.0
-
520.81
1,413
0.0
-
2,600.0
282.20
17.67%
2,108.6
107.5
183.4
192.46
303.26
-
0.0
-
8,500.0
-
303.26
-
2,804.5
270.1
2,600.0 TOTAL
-
44,911.0
2A Road Safety Equipment
Design and Supervision 3B Kalimantan Region Construction Supervision 3K Central Java Region Design and Supervision East 3C Java Region
-
ADB
Projected Loan Balance
Outstanding Value of Awarded Contract
Cummulative to Date
-
3A Core Team Consultant
-
IDB
5a = (3c-4a) 5b = (3d-4b)
Year to Date
-
Consultant Services
-
Current Quarter
1,300.0
3
-
ADB
in US$ 000's
Disbursement
-
-
8,500.0 32,235.5
2,600.0 17,641.67
643.12 26,266.07 6,759.16 47,952.93 40.78%
6,759.16
20.63%
69,152.88
58.81% 26,005.38
79.37% 62,418.35
8,500.0 32,235.46
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 2 Procurement Plan Of Implementation Support and Sector Institutional Development Regional Roads Development Project Status : Evaluation and Submission Result of Technical Submission Submissi shortlist (including Proposal Evaluation Review Invitation of RFP and TOR) Method of TOR , on of By Bank Plan/ NOL REOI Advert to Short- Technical of OE and EOI by (Prior/Po Actual dari Donor of REOI List and Selection Draft REOI Consulta Send to NOL by Send to NOL by Contract ( Excl.VAT ) st) Consultants Financial to the Bank nts the Bank Bank Bank Bank Proposals
Project Cost Ref. No
Name of Package Allocated (US$)
1
Implementation Support
a
CSP-1 : Core Team Consultant
b
CSP-2 : Design and Supervision Consultant (DSC-1 , Kalimantan)
6,000,000
EE/OE (US$)
3,914,374
5,300,000
5,827,926
900,000
777,754
US $
IDR ( mil )
1,192,400
19,472.50
936,574
QCBS
Plan
01-Jun-11
01-Jun-11 30-Jun-11
01-Jun-11
23-Feb-12
10-Jul-12
Actual
27-Oct-11
13-Dec-11 19-Dec-11
23-May-12
28-May-12
29-Jan-13
Plan
01-Jun-11
01-Jun-11 30-Jun-11
01-Jun-11
23-Feb-12
10-Jul-12
d
CSP-11 :Design and Supervision Consultant (DSC-2 (Central Java Province)
3,000,000
2,778,567
-
Actual
27-Oct-11
13-Dec-11 19-Dec-11
15-Jun-12
15-Jun-12
07-Dec-12
01-Jun-11
01-Jun-11 30-Jun-11
01-Jun-11
23-Feb-12
10-Jul-12
Actual
27-Oct-11
13-Dec-11 19-Dec-11
15-Jun-12
15-Jun-12
07-Dec-12
Plan
01-Jun-11
01-Jun-11 30-Jun-11
01-Jun-11
25-Mar-12
725,740
30,373.00
QCBS
Prior
6,939.95
QCBS
Prior
11,348.91
QCBS
20-Jun-12
31-Aug-12
30-Sep-12
07-Oct-12
11-Oct-12
Send to Bank
21-Oct-12
NOL by Bank
28-Oct-12
Negotiation ADB/IDB and Draft of Approval of Sign Contract Send to Draft Contract Send to Minister NOL by Contract of Public Minister ADB/IDB Works
28-Oct-12
29-Oct-12
11-Nov-12
Service Start Date
Period Completion (Month) Date
31 December 2015
Status
Action Plan
25-Nov-12
Prior
c
CSP-3 : Design and Supervision Consultant ( DSC-3 , East Java Province)
17-Jul-12
Opening of Financial Proposal
Result of Evaluation Combination (Technical and Financial Proposals)
18-Sep-13 17-Jul-12
31-Aug-12
30-Sep-12
07-Oct-12
17-Jul-12
31-Aug-12
30-Sep-12
07-Jun-13
15-Jul-12
22-Jul-12
05-Sep-12
05-Oct-12
07-Jun-13
16-Jul-13
15-Nov-13
18-Jun-14
13-Dec-13 11-Oct-12
21-Oct-12
28-Oct-12
28-Oct-12
29-Oct-12
11-Oct-12
21-Oct-12
28-Oct-12
28-Oct-12
29-Oct-12
12-Oct-12 20/12/2014
19-Dec-14
22-Dec-14
19-Dec-14
22-Dec-14
04-Dec-14
24-Dec-14
28-Dec-14
05-Mar-15
31-Mar-15
07-Jun-13
31-Oct-13
30-Sep-13
22-Jan-14
18-Nov-13
08-Oct-13
12-Feb-14
25-Feb-14
11-Nov-12
25-Nov-12
21-Nov-13
16-Dec-13
11-Nov-12
25-Nov-12
16-Oct-13
18-Oct-13
24-Nov-14
5-Jan-15
14-Apr-15
14-May-15
46
06-Dec-17
33
01-Sep-16
25
07-Nov-15
38
27-Jun-18
Prior Actual
5-Jun-12
04-Jan-12 20-Jan-12
20-Jun-12
Plan
01-Jan-12
23-Dec-11 01-Jan-12
01-Jan-12
12-Dec-14
17-Feb-15
03-Mar-15
The activity is move to back the original
e
CSP-5: Capacity Development Program
900,000
QCBS
, currently under process of prepare of TOR, Owner Estimate Cost and a Draft of
Prior
REOI
Actual Plan f
CSP-4: Road Safety Engineering Support
400,000
392,666
QCBS
01-Jan-12
CSP-10 :Human Trafficking Prevention and
Plan 300,000
262,402
QCBS
Road Sector Institutional Development CSP-6 :Road Safety Awareness Campaign & Trainning
3,000,000
CSP-7 : Overloading and Speed Enforcement
2,200,000
Plan QCBS
Actual
j
QCBS
07-Jan-15
23-Feb-15
04-Mar-15
11-Mar-15
18-Mar-15
25-Mar-15
01-Apr-15
08-Jul-14 12-Aug-14
20-Sep-14
28-Oct-14
09-Dec-14
29-Dec-14
23-Feb-15
12-Mar-15
20-Mar-15
31-Mar-15
27-Apr-15
18-May-15
23-Dec-11 01-Jan-12
01-Jan-12
09-Oct-14
23-Oct-14
07-Jan-15
23-Feb-15
04-Mar-15
11-Mar-15
18-Mar-15
25-Mar-15
01-Apr-15
08-Jul-14 12-Aug-14
20-Sep-14
28-Oct-14
09-Dec-14
29-Dec-14
23-Feb-15
12-Mar-15
20-Mar-15
31-Mar-15
27-Apr-15
18-May-15
23-Dec-11 01-Jan-12
01-Jan-12
01-Jan-12
CSP-8 : Indonesia Transport Sector Development Strategy and Policy Study
1,300,000
QCBS
18-Aug-15
-
23-Sep-15
-
18-Aug-15
23-Sep-15
22-Apr-15
06-Oct-15
07-Oct-15
15-Apr-15
22-Apr-15
06-Oct-15
07-Oct-15
12
06-Oct-16
12
06-Oct-16
This package may be move to another activity, waiting decision from the Steering Committee
01-Jan-12
23-Dec-11 01-Jan-12
01-Jan-12
19-Jan-15
01-Jun-14
01-Jan-12
23-Dec-11 01-Jan-12
26-Sep-14
19-Nov-14
04-Dec-14
26-Jan-15
19-May-15
05-Jun-15
18-Jun-15
12-Aug-15
22-Sep-15
04-Nov-15
13-Nov-15
19-Nov-15
01-Jan-12
This package may be move to another activity, waiting decision from the Steering Committee
01-Jan-12
Waiting consent from the Minister for the process of signing contract .
Prior Actual
QCBS
15-Apr-15
Mobilization is expected to be on early of January 2016.
Plan 800,000
-
Has not yet started
Actual
CSP-9 : Integrated Vehicle Overloading Control Strategy
-
Prior
Plan k
23-Oct-14
Prior
Plan
i
01-Jan-12
Actual
h
09-Oct-14
Prior
HIV/AIDS Campaign Programs
2
01-Jan-12
Prior Actual
g
23-Dec-11 01-Jan-12
Has not yet started 01-Jan-12
23-Dec-11 01-Jan-12
Prior Actual
10-Jul-14
24-Sep-14
26-Jan-15
29-Apr-15
07-May-15
15-May-15
14-Jul-15
19-Oct-15
10-Nov-15
TOTAL
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 3 Regional Road Development Project (RRDP) Progress and Cost Monitoring For Civil Works No.
Contract No.
Contract Description Type of Works
Contract Value
Contractor
IDR (x106)
Contract Sign Procurement Category Date Method
Contract Price (IDR 10⁶) Including Tax Original
Addendum
Status : December 2015 Cummulative Cost (IDR 10 6)
6
ADB /IDB Financing Ratio (%)
Cost During this Quarter (IDR 10 ) Actual
Planned
Actual as % ADB Share of Planned
Actual to date
To Last Quarter
Total
ADB / IDB Share
Physical Progress %
Planned to Actual as % Scheduled date of Planned
Actual
Difference
New Road, Widening, Resurfacing
278,810,582
PT. PP (Persero) - PT.Armada Hada Graha, JO
12-Jan-15
Civil Works
ICB
243,741.56
-
100
1,413.10
2,632.41
1,284.64
53.68
48,748.31
50,161.41
45,601.29
2,729.91
1,837.48
1.12
2.24
1.12
HK.02.03/BJGD/24-RCP-02/I/2015/01 Giriwoyo - Duwet
New Road, Widening, Resurfacing, Reconstruction
171,759,932
PT.Hutama Karya
13-Jan-15
Civil Works
ICB
142,000.00
-
100
1,850.00
3,308.60
1,681.82
55.91
28,400.00
30,250.00
27,500.00
4,160.60
727.06
2.93
2.94
0.01
3
02/24-RCP-03/NB/IDB/0161/0115
Widening; Reconstruction
71,444,835
PT.Jaya Konstruksi Manggala Pratama, Tbk
7-Jan-15
Civil Works
ICB
58,253.09
-
100
1,856.92
2,947.61
1,688.11
63.00
11,650.62
13,507.54
12,279.58
10,205.94
132.35
17.52
14.41
-3.11
4
01-28-RCP-01A/RB/ADB/2817/0813
New Road Jolosutro - Sendang biru Reconstruction Resurfacing
151,916,793
PT.Hutama Karya
21-Aug-13
Civil Works
ICB
93,350.00
70
22,948.45
22,271.33
16,871.69
103.04
47,754.43
70,702.88
47,260.87
90,112.00
78.46
79.87
76.41
-3.46
5
02/30-RCP-01/RB/ADB/2817/2015
Sosok - Tayan: Sp.Tanjung Reconstruction - Bts.Kota Sanggau Resurfacing
608,466,493
PT. Yasa Patria Perkasa ; PT. Budi Bakti Prima
15-Jan-15
Civil Works
ICB
465,647.54
70
47,859.41
3,864.87
21,644.63
1,238.32
35,000.00
82,859.41
53,462.81
53,176.95
155.82
1.42
8.71
7.29
6
02-30-RCP-02/RB/ADB/2817/1113
Tebas - Singkawang (Section 1); Tebas Singkawang (Section 2) Bypass Sambas
Reconstruction Resurfacing
430,578,648
PT.Brantas Abipraya-Tri Citra Perdana-Trifa Abadi, JO
14-Nov-13
Civil Works
ICB
292,603.39
407,294.89
70
23,327.40
51,848.64
14,844.71
44.99 176,530.48
199,857.88
127,182.29
277,938.03
71.91
58.24
58.28
0.04
7
03-30-RCP-02/RB/ADB/2817/1113
Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
Reconst + widening Reconstruction
333,214,553
PT Waskita Karya - Yasa Patria Perkasa, JO
27-Nov-13
Civil Works
ICB
238,974.97
325,740.20
70.00
64,002.62
(33,225.50)
40,002.39
(192.63)
64,409.09
128,411.71
81,716.54
160,492.20
80.01
39.27
37.11
-2.16
8
01-34-RCP/LOAN/PJN.III/11.14
Tanjung Selor- Sp.3 Tj.Palas - Sekatakbuji (section 1)
Reconstruction Resurfacing
333,214,553
PT.Waskita Karya (Persero)
3-Nov-14
Civil Works
ICB
189,970.25
-
70.00
53,888.76
30,889.16
34,292.85
174.46
40,785.66
94,674.42
60,247.36
86,018.53
110.06
30.28
43.75
13.47
9
02-34-RCP/LOAN/PJN.III/06.14
Sp.3 Tanjung Palas Sekatak Buji (Section 2)
Reconstruction Grade Improvement
215,483,495
PT.Brantas Abipraya -Mahir Jaya Mahakam Raya- JO
25-Jun-14
Civil Works
ICB
165,332.34
-
70.00
48,591.81
33,049.93
30,922.06
147.03
28,387.34
76,979.14
48,986.73
111,913.46
68.78
52.69
38.99
-13.70
10
03-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis (Sect 1)
Reconstruction Resurfacing
322,919,917
PT.Pemb. PerumahanPT.Perdasa JO
11-Apr-14
Civil Works
ICB
289,000.00
70.00
72,889.78
4,634.51
46,384.40
1,572.76
85,666.48
158,556.26
100,899.44
148,141.40
107.03
36.26
40.12
3.86
11
04-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis (Sect 2); Simanggaris Bts.Negara
Reconstruction Resurfacing
407,483,774
Halla Corporation
11-Apr-14
Civil Works
ICB
359,652.70
70.00
37,989.34
24,132.70
24,175.04
157.42
60,945.40
98,934.74
62,958.47
104,766.83
94.43
14.13
12.02
-2.11
3,325,293,575
TOTAL
376,617.58
146,354.26
233,792.32
1
01/24-RCP-01/NR/IDB/0161/0115
2
Tambakmulyo - Wawar
Wawar - Congot
2,783,598.69
112,823.34
-
313,142.78
-
551,129.50 1,004,895.39
668,095.37 1,049,655.84
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 4 Details of Variation Orders To End September 2015 No.
Package No.
Original Contract value (Rp.)
Tambakmulyo - Wawar
24-RCP-01
243,741,564,000
Not Yet
Giriwoyo - Duwet
24-RCP-02
142,000,000,000
Not Yet
Wawar - Congot
24-RCP-03
58,253,088,000
Not Yet
Sosok - Tayan Sp.Tanjung - Bts. Sanggau
30-RCP-01
465,647,542,528
Not Yet
Jolosutro - Bale kambang Sendang biru
28-RCP01A
Design Review (Rp.)
Design Review %
Price Escalation
Total Current Modified Contract Price (Rp.)
93,350,000,000
112,823,335,000.00 Add.3
20.86
Not Yet
112,823,335,000.00
407,294,893,000.00 Add.1
39.20
Not Yet
407,294,893,000.00
0.00
Not Yet
0.00
Tebas - Singkawang (Section 1); Tebas -Singkawang (Section 2) Bypass Sambas Galing - Tanjung Harapan
30-RCP02
292,603,385,000
Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
30-RCP03
238,974,973,000
Tanjung Selor -Sp.3 Tj Palas; Sp.3 Tj.Palas - Sekatakbuji
34-RCP01
189,970,248,000
Not Yet
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
34-RCP02
165,332,330,000
Not Yet
SP.3 Tj.Palas - Simaranggis (Sect 1)
34-RCP03
289,000,000,000
Not Yet
SP.3 Tj.Palas - Simaranggis (Sect 2)
34-RCP03
359,652,697,000
Not Yet
TOTAL
Escalation %
2,538,525,827,528
Total Current Modified %
520,118,228,000
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 5 Regional Roads Development Project (RRDP) Summary of Contract Data Up to December 2015 NO.
DESCRIPTION
a
b
1
Package No.
2
Name of Link
3
Length of Lingk (Km)
4
Contract Number
5
Contract Sign Dated
6
Contractor
7
Original Contract Amount (Rp.)
8
Commencement Date
9
Time for completion (Days) Addendum Cons.Period
WEST KALIMANTAN d
e
f
30 - RCP 01 (CW - 05)
30 - RCP 02 (CW - 06)
30 - RCP 03 (CW - 07)
28 - RCP 01 (CW - 04)
Sosok - Tayan Tanjung - Bts.Kota Sanggau 79.20 02/30-RCP-01/RB/ADB/2817/2015 15-Jan-15 PT. Yasa Patria Perkasa
Singkawang - Tebas (Section 1+2) Sambas Bypass Tanjung Harapan - Galing 55.97
Galing - Simpang tanjung Sp.Tanjung - Aruk (Bts.Serawak)
02/30-RCP-02/RB/ADB/2817/1113
03/30-RCP-03/RB/ADB/2817/1113
14-Nov-13 PT.Brantas Abipraya - PT.Citra Persada - PT.Trifa Abadi JO.
465,647,542,528.81
Status Progress
17-Dec-13
1.095
1.095
11
Status Disbursment (Rp)
12
Addendum Contract No.01 Addendum Contract No.02 Addendum Contract No.03
13
Completion Date
14
Remarks
Schedule : 1.422 % Actual : 8.709 % Deviation : +7.287 % 84,012,996,053.00 18.04%
Schedule : 58.243 % Actual : 58.259 % Deviation : 0.016 % 199,856,880,711.00 68.30% 407,294,892,000.00
14-Jun-18
21.20
15-Dec-16
01/28-RCP-01A/RB/ADB/2817/0813 21-Aug-13
PT.Waskita Karya PT.Yasa Patria Perkasa JO
292,603,385,000.00
15-Jun-15
Jolosutro - Sendangbiru
52.04
26-Nov-13
Time Ellapse : 191 Days ( 17.44 %) Time Ellapse : 736 Days ( 67.21 %) Remaining : 904 Days (82.56 %) Remaining : 359 Days (32.79 %) 10
EAST JAVA
c
PT. Hutama Karya
238,974,973,000.00 4-Dec-13 1.095 1.279 Time Ellapse : 749 Days (68.40 %) Remaining : 530 Days ( 31.60 %) Schedule : 39.268 % Actual : 37.107 % Deviation : -2.161 % 126,291,458,657.00 52.85% 325,740,200,000.00
4-Jun-17
93,350,000,000.00 18-Oct-13 730 905 Time Ellapse : 796 Days ( 87.96 %) Remaining : 109 Days ( 12.04 %) Schedule : 79.867 % Actual : 76.408 % Deviation : -3.459 % 70,702,881,379.00 62.67% 93,350,000,000.00 98,889,601,000.00 112,823,335,000.00 10-Apr-16
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Regional Roads Development Project (RRDP) Summary of Contract Data Up to December 2015
NO.
DESCRIPTION
a
b
1
Package No.
2
Name of Link
3
Length of Lingk (Km)
4
Contract Number
5
Contract Sign Dated
6
Contractor
7
Original Contract Amount (Rp.)
8
Commencement Date
EAS T KALI MANTAN c
d
e
f
34 - RCP 01 (CW - 08)
34 - RCP 02 (CW - 09)
34 - RCP 03 (CW - 10)
34 - RCP 04 (CW - 11)
Tanjung Selor - Sp3 Tanjung Palas Sp3 Tanjung Palas - Sekatak Buji (Section 1)
Sp3 Tanjung Palas - Sekatak Buji (Section 2)
Sp3 Ampas - Simanggaris (Section 1)
Sp3 Ampas - Simanggaris (Sec.2) Simanggaris - Bts.Negara (Serudong)
34.82
65.03
45.00
47.04
01-34/RCP/LOAN/PJN.III/11.14
02-34/RCP/LOAN/PJN.III/06.14
03-34/RCP/LOAN/PJN.III/04.14
04-34/RCP/LOAN/PJN.III/04.14
3-Nov-14
25-Jun-14
14-Apr-14
11-Apr-14
PT. WASKITA KARYA (Persero)
PT. Brantas Abipraya - PT. Mahir Jaya Mahakam Raya
189,970,248,000.00 12-Dec-14
PT.Pembangunan Perumahan (Persero)PT.Persada, JO
165,332,328,425.00 4-Sep-14
HALLA CORPORATION
289,000,000,000.00 10-Jul-14
359,652,698,000.00 1-Oct-14
52.11 9
Time for completion (Days)
730 Time Ellapse : 376 Days (51.51 %) Slipage : 354 Days ( 48.49 %)
10
Status Progress
Schedule : 30.280 % Actual : 43.750 % Deviation : 13.470 %
11
Status Disbursment
12
Addendum Contract No.01
13
Completion Date
15
Remarks
94,674,419,736.00 57.26%
11-Dec-16
730 Time Ellapse : 475 Days (66.07 %) Slipage : 255 Days ( 33.93 %) 255 Schedule : 52.689 % Actual : 38.992 % Deviation :-13.697 % 76,979,144,449.00 46.56%
2-Sep-16
67.31
900 Time Ellapse : 531 Days (59.00 %) Slipage : 369 Days ( 41.00 %)
1.095 Time Ellapse : 448 Days (40.91 %) Slipage : 647 Days ( 59.09 %)
Schedule : 36.255 % Actual : 40.118 % Deviation : 3.863 %
Schedule : 14.125 % Actual : 12.016 % Deviation : -2.109 %
158,556,262,703.00 54.86% 313,142,781,000.00 25-Dec-16
98,934,738,824.00 27.51%
30-Sep-17
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Regional Roads Development Project (RRDP) - IDB Financing Agreement IND-0161 Summary Status Of Contract Data For Civil Works Up To December 2015 NO.
DESCRIPTION
a
b
1
Package No.
2
Name of Link
3
Length of Lingk (Km)
4
Contract Number
5
Contract Sign Dated
6
Contractor
CENTRAL JAVA c
d
e
24 - RCP 01 (CW - 01)
24 - RCP 02 (CW - 02)
24 - RCP 03 (CW - 03)
LOT - 1
LOT - 2
Tambak Mulyo - Wawar Central Java
Giriwoyo - Duwet (Section-1) Central Java
38.46
23.75
01/24-RCP-01/NR/IDB/0161/0115
HK.02.03/BJGD/24-RCP-02/I/2015/01
12-Jan-15
13-Jan-15 PT. HUTAMA KARYA (PERSERO)
PT. PEMBANGUNAN PERUMAHAN -
LOT - 3
Wawar - Congot Central Java 14.13 02/24-RCP-03/NB/IDB/016/0115 7-Jan-15 PT. JAYA KONSTRUKSI
PT. ARMADA HADA GRAHA JO. 7
Original Contract Amount (Rp.)
8
Commencement Date
243,741,564,000.00 3-Aug-15
142,000,000,000.00 23-Jul-15
58,253,088,000.00 5-Jun-15
1053 9
Time for completion (Days)
10
Status Progress
11
Status Disbursment
12
Addendum Contract
13
Completion Date
14
Remarks
1.095 Time Ellapse : 142 Days (12.97 %) Slipage : 953 Days ( 87.03 %) Schedule : 1.121 % Actual : 2.239 % Deviation : +1.118 % 50,161,413,699.00 20.58%
2-Aug-18
730 Time Ellapse : 153 Days (20.96 %) Slipage : 577 Days ( 79.04 %) Schedule : 2.927 % Actual : 2.935 % Deviation : +0.008 % 30,250,000,000.00 21.30%
22-Jul-17
360 Time Ellapse : 202 Days (55.34 %) Slipage : 158 Days ( 44.66 %) Schedule : 17.519 % Actual : 14.412 % Deviation : -3.107 % 13,507,537,381.00 23.19%
30-May-16
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 6 Summary of Unsettled Complaints As of December 2015 Media of complaint
Category of complaint
Asian Development Bank (ADB)
Letter, October 2009
Refutations
Solidaritas Perempuan
Asian Development Bank (ADB)
Letter, October 2009
Refutations
Pengurus Wilayah Aliansi Masyarakat Adat Nusantara Kalimantan Barat
ADB Board of Directors
Letter No. 057/PW AMANKB/2011
Refutations
No.
Complainant
1
Hikmah Diniyah – Solidaritas Perempuan Yogyakarta Branch
2
3
Recipient of complaints
RRDP Package
Complaint Issue Many concerns raised during the meeting particulary due to many information inaccuracy and lack of significant social analyze. Even the head of the facilitation consultant group of the PPTA meeting stated that the PPTA study and report were not sufficient enough and therefore should be revised Some groups in Yogyakarta and west Kalimantan investigated the road-link as mentioned in the final draft PPTA. Their findings were submitted to ADB for considerations, particularly to the project officer Request to postpone the regional road development project particularly in west Kalimantan until there is an acknowledgement of rights and existence of the indigenous peoples along the road that will be developed.
Date of complaint
Date received by PMU/CTC
Date of response
Responded by
Proposed Response
October 2009
Asian Development Bank (ADB)and Indonesia government
Letter, October 2009
Asian Development Bank (ADB)
19 November 2011
ADB Board of Directors
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
No.
Complainant
Recipient of complaints
RRDP Package
Media of complaint
Category of complaint Refutations
4
Jaringan Advokasi Tambang Kalimantan Timur
ADB Board of Directors
Letter No. 008/eksternal/ XI/2011
5
Solidaritas Perempuan Wardarina
ADB Board of Directors
Letter, November 24, 2011
Complaint Issue We call the board of Directors of Asian Development Bank to not approve the proposed Regional Road Development Project. We would like to recommend the board of directors for not approving this proposed project yet due to the non-compliances with requirements of ADB safeguard policy statement and public communication policy
Date of complaint
Date received by PMU/CTC
Date of response
Responded by
Proposed Response
17 Juli 2011
ADB Board of Directors
Letter, November 24, 2011
ADB Board of Directors
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 7a Community Representative Observor (Cro) Actvities In RRDP December 2015 No
4
5
Province
Package Observed
EAST JAVA
Jolosutro-Sendangbiru 28-RCP01A
WEST Sosok - Tayan KALIMANTA N Tanjung- Bts.Kota Sanggau Tebas-Singkawang (Section1 &2)
6
Package Number
30-RCP01
30-RCP02
Date of Invitation to Bid
CROs Involvement in the Bidding Date of Bid Announcement Opening Date of Bid Winner
1-Mar-13
1-May-13
18-Aug-13
25-Jul-14
9-Sep-14
10-Dec-14
26-Feb-13
22-May-13
19-Oct-13
Bypass Sambas Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
7
8
EAST KALIMANTA Tj.Selor- Sp.3Tj. Palas N
30-RCP02
34-RCP01
26-Feb-13
11-Mar-13
23-May-13
13-Jun-13
12-Nov-13
16-Oct-14
Selected CRO Reports of CRO Activity · Process Verbal of the CRO selection for RRDP package of JolosutroSendangbiru, East Java SNVT of Roads and Bridge Development, May 2013 ·
Sp.3 Tanjung Palas Sekatak Buji (Sect 2)
Ir. Kinanti Kusumawati
Chandra Yuliana , ST,MT Process Verbal of the CRO selection for RRDP package of Sosok - Tayan, Ir.Retna Hapsari West Kalimantan SNVT of Roads and Bridge Development, June 2014 Kartadipura, MT · Process Verbal of the CRO selection for RRDP package of Tebas Singkawang, West Kalimantan SNVT of Roads and Bridge Development, February 2013 · · Process Verbal of the CRO selection for RRDP package of Sp.Tanjung Galing, West Kalimantan SNVT of Roads and Bridge Development, February 2013 · Process Verbal of the CRO selection for RRDP package of Tj.Selor - Sp.3 Tanjung Palas, East Kalimantan SNVT of Roads and Bridge Development, June 2013
Sp.3 Tanjung Palas Sekatak Buji (Sect 1) 9
Name
Ikrar Chandra Bachtiar, SKM
Address
SP.3 Apas Simaranggis (Sect 1) SP.3 Apas Simaranggis (Sect 2); Simanggaris Bts.Negara
11
1
CENTRAL JAVA
Email
Surabaya
Tanjungpura University Tanjungpura University
0812.50018822 0811.501.584
NA
NA
Lydia Gusti Resanika ,SE
NA
NA
Ikrar Chandra Bachtiar, SKM
NA
NA
NA
NA
Tanjung Pura University
Tanjung Pura University
Lydia Gusti Resanika ,SE Rahayu Widasari Mulawarman University Ulfatu Munawaroh
34-RCP02
11-Mar-13
13-Jun-13
4-May-14
· Process Verbal of the CRO selection for RRDP package of Sp.3 Tanjung Palas - sekatak buji (serction 2), East Kalimantan SNVT of Roads and Bridge Development, June 2013
Rahayu Widasari
Mulawarman University
Ulfatu Munawaroh 10
Telephone
34-RCP03
11-Mar-13
13-Jun-13
10-Feb-14
34-RCP04
11-Mar-13
13-Jun-13
6-Feb-14
Tambakmulyo - Wawar 24-RCP01
14-May-14
15-Jul-14
8-Dec-14
2
Giriwoyo - Duwet
24-RCP02
14-May-14
15-Jul-14
8-Dec-14
3
Wawar - Congot
24-RCP03
14-May-14
15-Jul-14
8-Dec-14
· Process Verbal of the CRO selection for RRDP package of Sp.3 Apas Simanggaris (serction 1), East Kalimantan SNVT of Roads and Bridge Rahayu Widasari Development, June 2013 · Ulfatu Munawaroh · Process Verbal of the CRO selection for RRDP package of Sp.3 Apas Simanggaris (serction 2) and Simanggaris - bts Negara, East Kalimantan Rahayu Widasari SNVT of Roads and Bridge Development, June 2013 · Ulfatu Munawaroh Process Verbal of the CRO selection for RRDP package of Tambakmulyo Wawar, Central Java SNVT of Roads and Bridge Development, June Ir.Yuniarto Adi, MT 2014 Process Verbal of the CRO selection for RRDP package of Giriwoyo Duwet, Central Java SNVT of Roads and Bridge Development, June 2014 Process Verbal of the CRO selection for RRDP package of Wawar Congot, Central Java SNVT of Roads and Bridge Development, June 2014
Mulawarman University NA
Mulawarman University
NA
NA
NA
Diponegoro University
Ir.Yuniarto Adi, MT
Diponegoro University
Ir.Yuniarto Adi, MT
Diponegoro University
NY = Not Yet
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 7b Status of CRO Reports December 2015 Status of Bidding Process RRDP Packages
Province
Bid Opening
Bid Winner (BW)
(BO)
Announcement
15-Jul-14
16-Dec-14
OK
Complete report of bid opening and bid winner announcement.
15-Jul-14
16-Dec-14
OK
Complete report of bid opening and bid winner announcement.
15-Jul-14
16-Dec-14
OK
Complete report of bid opening and bid winner announcement.
1-May-13
27-Jul-13
OK
Complete report of bid opening and bid winner announcement.
9-Sep-14
24-Dec-14
OK
Complete report of bid opening and bid winner announcement.
22-May-13
19-Oct-13
OK
Complete report of bid opening and bid winner announcement.
CW
Report Submission
Remarks
CW-01
Tambakmulyo - Wawar
CW-02
Giriwoyo - Duwet
CW-03
Wawar - Congot
CW-04
Jolosutro - Sendangbiru (East Java)
CW-05
Sosok - Tayan ; Tanjung - Batas Kota Sangga
CW-06
Tebas - Singkawang (Section 1 &2); Bypass Sambas ; Galing - Tanjung Harapan
CW-07
Sp.Tanjung - Galing ; Aruk - Batas Serawak
15-Jun-13
12-Nov-13
OK
Complete report of bid opening and bid winner announcement.
CW-08
Tj.Selor - Sp.3 Tanjung Palas (Section 1)
13-Jun-13
16-Oct-14
OK
Complete report of bid opening and bid winner announcement.
CW-09
Tj.Selor - Sp.3 Tanjung Palas (Section 2)
13-Jun-13
4-Jun-14
CW-10
Sp.3 Apas - Simaggaris (Section 1)
13-Jun-13
6-Feb-14
OK
Complete report of bid opening and bid winner announcement.
CW-11
Sp.3 Apas - Simaggaris (Section 2); Simanggaris - Bts Negara
13-Jun-13
6-Feb-14
OK
Complete report of bid opening and bid winner announcement.
Central Java
East Java
West Kalimantan
East Kalimantan
OK
Complete report of bid opening and bid winner announcement.
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 8 Environmental Management and Monitoring Plan (EMP) Compliance Regional Roads Development Project (RRDP) As December 2015 Contractor Performance on EMP No.
Package No.
Project Name
Length (Km)
Contractor
Contract Reference
Contract Description
Document Availability
Awareness & Readiness to EMP
Base Camp
Landscapi Waste Pollution Traffic Total Material ng/ Managem Control Managem Score Handling Reforestat ent Measures ent Obtained ion
Ranking (%)
Level
Remarks
EAST JAVA Being monitored during construction
1
28-RCP01A (CW-04) Jolosutro - Sendang biru
21.30
PT. Hutama Karya
01/28-RCP-01A/RB/ADB/2817/0813
New Road , Reconstruction incl. Resurfacing
v
v
v
v
v
v
v
v
100
100
CENTRAL JAVA Being monitored during construction 2
24-RCP01 (CW-01) Tambak Mulyo – Wawar
38.46
PT. Pembangunan Perumahan 01/24-RCP-01/NR/IDB/0161/0115 (Persero)
New Road, Widening, Resurfacing
v
v
v
v
v
v
v
v
100
100
3
24-RCP02 (CW-02) Giriwoyo - Duwet (Section-1)
23.75
PT. Hutama Karya
HK.02.03/BJGO/24-RCP-02/I/2015/01
New Road , Reconstruction, Widening and Resurfacing
v
v
v
v
v
v
v
v
100
100
4
24-RCP03 (CW-03) Wawar – Congot
14.13
PT. Jaya konstruksi,
02/24-RCP-03/NB/INB/0161/0115
Widening and Reconstruction
v
v
v
v
v
v
v
v
100
100
v
v
80
80
v
v
Being monitored during construction Being monitored during construction
PT. Manggala Pratama tdk, JO WEST KALIMANTAN 5
30-RCP01 (CW-05)
Sosok - Tayan; Tanjung-Batas Kota Sanggau
79.20
Tebas - Singkawang (Section-1); Tebas - Singkawang (Section-2); 6
30-RCP02 (CW-06) Bypass Sambas;
PT. Yasa Patria Perkasa PT. Budi Bakti Prima JO
02/30-RCP-01/RB/ADB/2817/2015
Reconstruction and Resurfacing (Direct Overlay)
v
v
55.97
PT. Tricitra Perdana, PT. Trifa Abadi JO
01/30-RCP-03/RB/ADB/2817/1113
Reconstruction, Resurfacing and Widening
v
v
v
v
v
Galing-Tanjung Harapan; Sambas-Tanjung Harapan 30-RCP03 (CW-07) Sp.Tanjung-Galing (Section-2);
100
100
100
100
100
100
13.00
Sp.Tanjung-Galing (Section-1); 7
Being monitored during construction Being monitored during construction
PT. Brantas Abipraya,
Being monitored during construction
PT. Waskita Karya (Persero), 52.04
PT. Yasa Patria Perkasa JO
02/30-RCP-03/RB/ADB/2817/1113
34.82
PT. Waskita Karya (Persero)
01-34/RCP/LOAN/PJN III/11.14
New Road , Resufacing and Reconstruction
v
v
v
v
v
v
v
v
v
v
v
v
v
v
v
v
v
v
v
v
Aruk (Bts.Serawak)-Sp. Tanjung NORTH KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08) SP. 3 Tanjung Palas - Sekatak Buji (Secton-1)
9
34-RCP02 (CW-09)
10
34-RCP03 (CW-10) SP.3 Apas - Simaranggis (Section- 1)
11
34-RCP04 (CW-11)
SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
SP.3 Apas - Simaranggis (Section-2) Simanggaris-Bts Negara (Serudong)
65.03
45.00
43.04
PT. Brantas Abipraya, PT. Mahir Jaya Mahakam Raya JO PT. Pembangunan Perumahan, PT. Persada JO Butt Halla Corporation
Reconstruction and Resurfacing
Being monitored during construction
Being monitored during construction 02-34/RCP/LOAN/PJN.III/06.14
Grade Improvement and Resurfacing
v
v
v
v
v
v
v
100
100
03-34/RCP/LOAN/PJN.III/04.14
New Road , Reconstruction and Reconstruction
v
v
v
v
v
v
v
100
100
04-34/RCP/LOAN/PJN III/04.14
New Road, Widening and Resurfacing
v v
v v
v v
v v
v v
v v
v v
100
100
Being monitored during construction
Being monitored during construction
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 9 Status of Social Safeguard Studies on Regional Roads Development Project (RRDP) As December 2015 No.
Length (Km)
District
Type of Works
Safeguard Document
Jolosutro - Sendang biru
21.30
Malang
New Road Construction incl. raising grade and New Bridge Construction
LARP
Package No.
Project Name
EAST JAVA 1
28-RCP01 (CW-01)
CENTRAL JAVA 2
24-RCP01 (CW-02)
Tambak Mulyo – Wawar
38.46
Kebumen
Widening, Resurfacing and New Bridge Construction
3
24-RCP02 (CW-03)
Giriwoyo - Duwet (Section-1)
23.75
Wonogiri
New Road Construction, Widening and New Bridge Construction
4
24-RCP03 (CW-04)
Wawar – Congot
14.13
Purworejo
Widening and Resurfacing
79.20
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
55.97
Singkawang & Sambas
Reconstruction, Resurfacing and Widening
LARP
WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05)
6
30-RCP02 (CW-06)
Tanjung-Batas Kota Sanggau
Tebas - Singkawang (Section-1); Tebas - Singkawang (Section-2); Bypass Sambas;
Sambas
LARP
LARP
Galing-Tanjung Harapan; Sp.Tanjung-Galing (Section-1); 7
30-RCP03 (CW-07)
Sp.Tanjung-Galing (Section-2);
52.04
Sambas
New Road Construction incl. raising grade and Reconstruction
34.82
Bulungan
New Road Construction incl. raising grade and Reconstruction
65.03
Bulungan
Grade Improvement and Resurfacing
Aruk (Bts.Serawak)-Sp. Tanjung EAST KALIMANTAN 8
34-RCP01 (CW-08)
Tanjung Selor - SP. 3 Tanjung Palas; SP. 3 Tanjung Palas - Sekatak Buji (Secton-1)
9
34-RCP02 (CW-09)
SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
LARP
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
No.
Package No.
10
34-RCP03 (CW-10)
Project Name
SP.3 Apas - Simaranggis (Section- 1)
Length (Km)
District
Type of Works
45.00
Nunukan
New Road Construction incl. raising grade and Reconstruction
43.04
Nunukan
Widening and Reconstruction
SP.3 Apas - Simaranggis (Section-2) 11
34-RCP04 (CW-11) Simanggaris-Bts Negara (Serudong
Safeguard Document
Possible for Updated LARP study related to relocation of road
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 10 Status of Monitoring of Environmental Mitigation on Regional Roads Development Project (RRDP) As December 2015 No.
Package No.
Project Nam e
Length (Km )
District
Type of Works
Construction Status
Contract Date
2014
2013
2015
2016
Remarks Start (COW)
Finish (PHO)
10
11
12
1
2
3
4
5
6
7
8
9-Apr-16
√
√
√
√
√
√
√
√X
√
√
√
9
10
11
12
1
2
3
4
5
6
7
8
9
10
11
12
√
√
√
√
√
√
√
√
√
√
X
√
√
√
1
2
3
4
5
6
7
8
9
10
11
12
EAST JAVA
1
28-RCP01 A(CW-04) Jolosutro - Sendang biru
21.30
Malang
New Road Construction incl. raising grade and New Bridge Construction
OC
21-Aug-13
√X √X
CENTRAL JAVA 2
24-RCP01 (CW-01) Tambak Mulyo – Waw ar
38.46
Kebumen
Widening, Resurfacing and New Bridge Construction
CS
12-Jan-15
-
√
√
X
√
√
√
3
24-RCP02 (CW-02) Giriw oyo - Duw et (Section-1)
23.75
Wonogiri
New Road Construction, Widening and New Bridge Construction
CS
13-Jan-15
-
√
√
X
√
√
√
4
24-RCP03 (CW-03) Waw ar – Congot
14.13
Purw orejo
Widening and Resurfacing
CS
7-Jan-15
-
√
√
X
√
√
√
79.20
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
OC
15-Jan-15
-
OC
14-Nov-13
15-Dec-16
√
√
√
√
√
√X
√
√
√
√
√
√
√X
√
WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05) Tanjung-Batas Kota Sanggau Tebas - Singkaw ang (Section-1);
55.97 30-RCP02 (CW-06) Bypass Sambas;
30-RCP03 (CW-07)
√
√
√X
√
√
√
√
√
√
√
√
√X
√
√X
√
√
√
√X
√
√
√
√
√
√
√
X
√
√
√X
√
√X
√
√
√
√X
√
√
√
√
√
√
X
√
X
√
√
√
√
√
√
√
√
√
√
X
√
√
√
√
√
√
√
√
√
Sambas 12.30
Sp.Tanjung-Galing; 7
√
Reconstruction, Resurfacing and Widening
Galing-Tanjung Harapan; Sambas-Tanjung Harapan
√
Singkaw ang & Sambas
Tebas - Singkaw ang (Section-2); 6
√X
52.04
Sambas
New Road Construction incl. raising grade and Reconstruction
OC
26-Nov-13
2-Dec-16
34.82
Bulungan
New Road Construction incl. raising grade and Reconstruction
OC
4-Nov-14
11-Dec-16
Aruk (Bts.Seraw ak)-Sp. Tanjung EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08) SP. 3 Tanjung Palas - Sekatak Buji (Secton-1)
√X
9
34-RCP02 (CW-09) SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
65.03
Bulungan
Grade Improvement and Resurfacing
OC
25-Jun-14
2-Sep-16
√
√
√
√
√
√X
√
√
√
√
√
√
√
10
34-RCP03 (CW-10) SP.3 Apas - Simaranggis (Section- 1)
45.00
Nunukan
New Road Construction incl. raising grade and Reconstruction
OC
14-Apr-14
28-Dec-16
√
√
√
√
√
√X
√
√
√
√
√
√
√
11
34-RCP04 (CW-11)
43.04
Nunukan
Widening and Reconstruction
OC
11-Apr-14
30-Sep-17
√
√
√
√
√
√X
√
√
√
√
√
√
√
X X
SP.3 Apas - Simaranggis (Section-2)
√
√
√
√
√
X
Simanggaris-Bts Negara (Serudong)
Note: OC
= Ongoing Construction
IFB
= Invitation For Bid
CS
= Contract Sign
BER
= Bid Evaluation Report
RT
= Retender
AMDAL
= Environmental Impact Assessment
NY
= Not yet
UKL/UPL
= Environmental Management & Monitoring Plans
NR
= Not required
SOP's
= Standard Operating Procedure
PHO
= Provisional Hand Over
√
= Monitored by DSC
COW
= Commencement of Work
X
= Monitored by CTC
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 11 Overall Land Acquisition Status on Regional Roads Development Project (RRDP) As December 2015
No.
Total To Be Acquired (m2)
Total Acquired (m2)
Progress In %
Remarks
Jolosutro - Sendang biru
1,481,400
1,481,400
100
Forest land affected is replaced by another with an area of land equivalent in the Bondowoso Regency
Package No.
Project Name
EAST JAVA 1
28-RCP01 (CW-01)
CENTRAL JAVA 2
24-RCP01 (CW-02)
Tambak Mulyo – Wawar
227,67
227,67
100
3
24-RCP02 (CW-03)
Giriwoyo - Duwet (Section-1)
No LA
NR
-
4
24-RCP03 (CW-04)
Wawar – Congot
No LA
NR
-
Sosok - Tayan;
No LA
NR
-
Tanjung-Batas Kota Sanggau
No LA
NR
-
Tebas - Singkawang (Section-1);
286
420
0
Not required land acquisition because for the design need is in accordance with the existing ROW Not required land acquisition because for the design need is in accordance with the existing ROW It has been verified against the land data and necessary to acquisition
Tebas - Singkawang (Section-2);
3,543
4,730
0
It has been verified against the land data and necessary to acquisition
Bypass Sambas;
No LA
NR
-
130
610
0
WEST KALIMANTAN
5
6
30-RCP01 (CW-05)
30-RCP02 (CW-06)
Galing-Tanjung Harapan;
It has been verified against the land data and necessary to acquisition
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
No.
7
Package No.
30-RCP03 (CW-07)
Total To Be Acquired (m2)
Total Acquired (m2)
Progress In %
Sp.Tanjung-Galing (Section-1);
No LA
NR
-
Sp.Tanjung-Galing (Section-2);
No LA
NR
-
Aruk (Bts.Serawak)-Sp. Tanjung
176
0
0
3,326
0
0
8,400
0
0
1.497.488,67
1,498,693,67
Project Name
Remarks
EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08) SP. 3 Tanjung Palas - Sekatak Buji (Secton1)
9
34-RCP02 (CW-09)
SP.3 Tanjung Palas - Sekatak Buji (Sect ion2)
10
34-RCP03 (CW-10)
SP.3 Apas - Simaranggis (Section- 1)
SP.3 Apas - Simaranggis (Section-2) 11
land area affected will be confirmed after preparation of the LARP document
34-RCP04 (CW-11) Simanggaris-Bts Negara (Serudong) GRAND TOTAL
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 12
Environmental Safeguard on Regional Roads Development Project (RRDP) As December 2015
No.
Package No.
Project Name
Length (Km)
District
Type of Works
Construc. Status
Intial Environmental Examination (IEE)
Environmental
Approval by BLHD
AMDAL (A)
2003
Safeguard Document
Environmental Management and Monitoring Plan (EMMP) or RKPPL
EAST JAVA
1
28-RCP01A (CW-04)
Jolosutro - Sendang biru
21.30
Malang
New Road , Reconstruction incl. Resurfacing
OC
October 2011
Doing at Contuction
CENTRAL JAVA 2
24-RCP01 (CW-02)
Tambak Mulyo – Wawar
38.46
Kebumen
New Road, Widening, Resurfacing
CS
October 2011
3
24-RCP02 (CW-03)
Giriwoyo - Duwet (Section-1)
23.75
Wonogiri
New Road , Reconstruction, Widening and Resurfacing
CS
October 2011
4
24-RCP03 (CW-04)
Wawar – Congot
14.13
Purworejo
Widening and Reconstruction
CS
October 2011
Doing at Contuction AMDAL (A)
5 October 2005
Doing at Contuction Doing at Contuction
WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05)
79.20
Sanggau
Tanjung-Batas Kota Sanggau Tebas - Singkawang (Section-1); 6
30-RCP02 (CW-06)
Tebas - Singkawang (Section-2); Bypass Sambas;
Reconstruction and Resurfacing (Direct Overlay)
October 2011
UKL/UPL (B)
16 February 2011
Doing at Contuction
October 2011
UKL/UPL (B)
16 February 2011
Doing at Contuction
OC
Doing at Contuction
October 2011 Singkawang & Sambas 55.97 Sambas
AMDAL (A) Reconstruction, Resurfacing and Widening
OC
18 February 2013 Doing at Contuction
October 2011 October 2011
UKL/UPL (B)
16 February 2011
Not Yet
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
No.
Package No.
Project Name
Length (Km)
District
Type of Works
Construc. Status
Galing-Tanjung Harapan;
Sambas-Tanjung Harapan
7
30-RCP03 (CW-07)
12.30
Sp.Tanjung-Galing; 52.04
Sambas
Aruk (Bts.Serawak)-Sp. Tanjung
New Road , Resufacing and Reconstruction
Intial Environmental Examination (IEE)
Environmental
Approval by BLHD
October 2011
UKL/UPL (B)
16 February 2011
-
will be prepared by DSC-1
-
October 2011
UKL/UPL (B)
13 January 2011
Doing at Contuction
October 2011
UKL/UPL (B)
13 January 2011
Not Yet
Safeguard Document
Environmental Management and Monitoring Plan (EMMP) or RKPPL
Doing at Contuction
OC
EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08)
34.82
Bulungan
SP. 3 Tanjung Palas Sekatak Buji (Secton-1)
Reconstruction and Resurfacing
OC October 2011
9
34-RCP02 (CW-09)
SP.3 Tanjung Palas Sekatak Buji (Sect ion-2)
65.03
Bulungan
Grade Improvement and Resurfacing
OC
October 2011
10
34-RCP03 (CW-10)
SP.3 Apas - Simaranggis (Section- 1)
45.00
Nunukan
New Road , Reconstruction and Reconstruction
OC
October 2011
SP.3 Apas - Simaranggis (Section-2) 11
21.1
34-RCP04 (CW-11)
Nunukan Simanggaris-Bts Negara (Serudong)
New Road, Widening and Resurfacing
Doing at Contuction
October 2011 UKL/UPL (B)
20 December 2010
Doing at Contuction UKL/UPL (B)
13 January 2011
Doing at Contuction
October 2011
-
-
The new environmental document will be prepared by DSC-1. AMDAL Team already mobilized.
October 2011
UKL/UPL (B)
13 December 2010
Doing at Contuction
OC
22.04
Doing at Contuction
Note : OC- Ongoing Construction; CS - Contract Signed; RT- Retender; NY- Not Yet ; IFB- Invitation For Bid; BER-Bid Evaluation Report
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 13 Regional Roads Development Project (RRDP) Construction Program Design :
Procurement:
NOL Docs/Award:
Invite Bids:
NOL Re-bid:
Re-bid Period:
Sign Contract:
Commencemen of Work
Ongoing Construction:
Completion Date :
Pack. No.
As of December 2015 Package Number
Location
Contract
Phase Code
Length, Kms
2012
2013
2014
2015
2016
2017
2018
REMARKS
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
EAST JAVA Add.3 4
Jolosutro- Sendangbiru
28-RCP01A
21.30 10-Apr-16
WEST KALIMANTAN 5
Sosok - Tayan Tanjung - Batas kota Sanggau
6
Singkawang - Tebas Sambas Bypass Tanjung Harapan -Galing
30-RCP02
7
Sp.Tanjung - Galing Sp.Tanjung Aruk (bts Serawak
30-RCP03
30-RCP01
79.20 14-Jun-18
55.97 15-Dec-16 52.04 4-Jun-17
CENTRAL JAVA 1
Tambak Mulyo - Wawar
24-RCP01
38.46 2-Aug-18
2
Giriwoyo - Duwet (Section 1)
24 - RCP02
23.75
3
Wawar - Congot
24-RCP03
14.13
22-Jul-17
30-May-16
EAST KALIMANTAN 8
Tanjung Selor - Sp.3 Tanjung Palas Sp.3 Tanjung Palas - Sekatak Buji
34-RCP01
34.82 11-Dec-16
9
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
34 - RCP02
65.03 2-Sep-16
SP.3 Apas - Simanggaris 10 (Section 1)
34-RCP03
45.00 25-Dec-16
SP.3 Apas - Simanggaris 11 (Section 2) Simanggaris - Bts.Negara
34-RCP04
47.04 30-Sep-17
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 14a Cost Estimate Of Civil Work Packages Regional Roads Development Project (RRDP) - ADB LOAN NO.2817-1NO Status : December 2015 No.
Package No.
Package Name
Length
Type of Works
(Km)
Original Contract Amount (Excl. Tax) (US$)
(IDR)
Variation Order (VO) Technical (IDR)
(%)
Escalation (IDR)
Total Contract Amount Excluding Tax Remarks (%)
(US$)
(IDR)
(%)
EAST JAVA PROVINCE 1
5
6
7
8
9
28-RCP 01A
Jolosutro - Sendang Biru
WEST KALIMANTAN PROVINCE Sosok - Tayan; 30-RCP01 Tanjung - Bts. Kota Sanggau Tebas - Singkawang (Section 1); Tebas - Singkawang (Section 2); 30-RCP02 Bypass Sambas; Galing - Tanjung Harapan Sambas - Tanjung Harapan* Sp. Tanjung - Galing; Aruk (Bts. Serawak) - Sp. Tanjung EAST KALIMANTAN PROVINCE Tanjung Selor - Sp.3 Tanjung Palas; 34-RCP01 Sp.3 Tanjung Palas-Sekatak Buji (Sec.1) Sp.3 Tanjung Palas - Sekatak Buji 34-RCP02 (Section 2) 30-RCP03
10
34-RCP03
11
34-RCP04
SHARING
Sp.Tiga Apas - Simanggaris (Sec. 1) Sp.Tiga Apas - Simanggaris (Sec. 2); Simanggaris - Bts.Negara (Serudong) Sub - Total ADB A D B (70 % ) G O I ( 30 % )
21.30
New Road Construction incl.raising grade and New Bridge Construction
6,333,107.19
84,863,636,363.64
17,703,032,000.00
20.86
8,486,363,636.36
10.00
8,287,539.70
111,053,032,000.00
79.20
Reconstruction and Resurfacing (Direct overlay)
31,590,742.37
423,315,947,753.64
63,497,392,163.05
15.00
42,331,594,775.36
10.00
39,488,427.96
529,144,934,692.05
55.97
Reconstruction, Resurfacing and Widening
19,850,975.92
266,003,077,272.73
116,938,006,364.00
43.96
26,600,307,727.27
10.00
30,562,790.40
409,541,391,364.00
13.20
Reconstruction
13,992,537.31
187,500,000,000.00
13,992,537.31
187,500,000,000.00
52.04
New Road Construction including raising grade and reconstruction
16,212,684.74
217,249,975,454.55
78,877,479,090.91
36.31
21,724,997,545.45
10.00
23,720,332.25
317,852,452,090.91
12,888,076.53
172,700,225,454.55
67,677,884,545.45
39.19
17,270,022,545.45
10.00
19,227,472.58
257,648,132,545.46
49.19
Proposed Addendum No.1
11,216,575.88
150,302,116,750.00
59,708,054,545.45
39.73
15,030,211,675.00
10.00
16,794,058.43
225,040,382,970.46
49.73
Proposed Addendum No.1
19,606,512.89
262,727,272,727.27
21,947,982,727.27
8.35
26,272,727,272.73
10.00
23,205,073.34
310,947,982,727.27
18.35 Addendum No.1
24,399,775.98
326,956,998,181.82
130,782,799,272.73
40.00
32,695,699,818.18
10.00
36,599,663.98
490,435,497,272.73
50.00
156,090,988.80
2,091,619,249,958.18
557,132,630,708.86
211,877,895.94
2,839,163,805,662.86
148,314,527.16 63,563,368.78
1,987,414,663,964.00 851,749,141,698.86
155,000,000.00 6,685,472.84
89,585,336,035.99
30.86 Addendum No.3
25.00
53.96
raising grade and reconstruction
Grade Improvement and Resurfacing New Road Construction including 45.00 raising grade and reconstruction Widening, Reconstruction and 43.04 New Road 409.60 65.03
Loan Portion GOI Portion Asumsi 1 US$ = 13,400 IDR
190,411,924,995.82
109,263,692.16 46,827,296.64 Allocated Loan ADB For Civil Works Packages Remaining Estimate Financing
Addendum No.1
Proposed New Link Addendum 46.31 No.1
New Road Construction including 34.82
Estimate VO
Proposed Addendum No.1
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix.14b Cost Estimate Of Consultant Sevices Regional Roads Development Project (RRDP) - ADB LOAN NO.2817-1NO No. Package No.
Package Name
Directorate of DGH BBPJN VII DGH BBPJN V DGH Subdit TLKJ DGH Sekditjen DGH Ministry of Finance Directorate of Traffic Police Bappenas
1
CSP-1
2
CSP-2
3
CSP-3
4
CSP-4
5
CSP-5
6
CSP-6
7
CSP-7
8
Indonesia Transport Sector Development Strategy and Policy Integrated Vehicle Overloading Ministry of CSP-9 Control Strategy Finance HIV/AIDs and Anti Trafficking Subdit TLKJ CSP-10 Prevention Program DGH S u b - T o t a l ADB
9 10
Core Team Consultant
Agency
Design Supervision for Kalimantan Region Design Supervision for East Java Region Road Safety Support Institutional Development for Road Network Management Road Safety Awareness Compaign and Training Overloading and Speed Enforcement
CSP-8
Combined A D B (100 % )
Allocated Amount (US$)
Estimate Contigency
Original Contract Amount (Excl. Tax) (US$)
(IDR)
Addendum (US$)
(IDR)
Price Escalation (US$) (IDR)
Estimate Total Contract Amount Excluding Tax (US$)
Total Contract Amount (Combined) (US$)
(IDR)
Remarks
6,000,000.00
1,192,400.00
19,472,500,000.00
609,449.00
9,952,611,112.00
180,184.90
2,942,511,111.20
1,982,033.90
32,367,622,223.20
4,397,528.10
5,300,000.00
936,570.00
30,372,995,000.00
458,692.00
14,123,975,223.00
139,526.20
4,449,697,022.30
1,534,788.20
48,946,667,245.30
5,187,524.56
971,309,350.00
-
10,684,402,850.00
797,343.50
4,857,172,800.00
362,475.58
900,000.00
6,939,950,000.00
400,000.00
4,047,644,000.00
-
900,000.00
12,000,000,000.00
-
3,500,000.00
2,773,143,500.00 809,528,800.00
-
12,000,000,000.00
895,522.39 Estimate
-
-
Cancelled
3,000,000.00
1,543,333.00
10,588,670,000.00
385,833.25
2,647,167,500.00
1,929,166.25
13,235,837,500.00
2,916,915.32
1,300,000.00
383,540.00
8,908,819,000.00
76,708.00
1,781,763,800.00
460,248.00
10,690,582,800.00
1,258,052.69
-
-
800,000.00
-
300,000.00 22,400,000.00
2,535,416,000.00 4,055,843.00 11,135,394.79
94,865,994,000.00
-
760,624,800.00
1,530,682.25
32,848,814,735.00
3,982,086.33
319,711.10
8,363,517,483.50
943,854.20
Allocated Loan ADB For Consultant Services Remaining Estimate
5,906,236.35
Cancelled
3,296,040,800.00
245,973.19
136,078,326,218.50
16,061,335.32
16,061,335.32
22,400,000.00 6,338,664.68
Appendix
PMU RRDP – Quarterly Progress Report No.7, October – December 2015
Appendix. 15 Monitoring Health And Safety During Construction (Keselamatan dan Kesehatan Kerja (K3) Konstruksi) December 2015 Pa cka ge No.
Contra ct No.
Contra ct Des cri pti on (Length)
Contra ctor
Worki ng Schedul e (RK3K)
Sa fety Meeti ng
Document Ava i l a bi l i ty (Da ta ,Pi cture, Intervi ew)
Pers onel Protecti on (APD)
La bour Ca mp
Roa d Sa fety duri ng Cons tructi on
Sys tem Ma na gemen K3 (SMK3)
Di s pos a l of Wa s te Ma teri a l
Tota l Score Obta i ned
Ra nki ng (%)
Level
Rema rks
EAST JAVA CW-04
01-28-RCP-01A/RB/ADB/2817/0813
Jol os utro - Ba l e ka mba ng - Senda ng bi ru (21,30 KM)
PT.Huta ma Ka rya (Pers ero)
WEST KALIMANTAN CW-05
01-30-RCP-01/RB/ADB/2817/0115
Sos ok - Ta ya n; Ta njung - Bts .Kota Sa ngga u
PT.Ya s a Pa tri a Perka s a ; PT. Budi Ba kti Pri ma JO
CW-06
02-30-RCP-02/RB/ADB/2817/1113
Teba s - Si ngka wa ng (Secti on 1); Teba s Si ngka wa ng (Secti on 2) Bypa s s Sa mba s Ga l i ng - Ta njung Ha ra pa n
PT.Bra nta s Abi pra ya -Tri Ci tra Perda na -Tri fa Aba di , JO
2
1
2
1
2
1
2
2
13
33
Sa ti s fa ctory
CW-07
03-30-RCP-02/RB/ADB/2817/1113
Sp. Ta njung - Ga l i ng; (bts .Sera wa k - Sp.Ta njung
PT Wa s ki ta Ka rya - Ya s a Pa tri a Perka s a , JO
-
-
-
-
-
-
-
-
-
-
Sa ti s fa ctory
Aruk
STARTED
EAST KALIMANTAN CW-08
01-34-RCP/LOAN/PJN.III/11.14
Ta njung Sel or-Seka ta k Buji -Ta njung Pa l a s Sec. 1 (34-RCP01)
PT. Wa s ki ta Ka rya (Pers ero)
4
2
3
3
3
3
3
2
23
58
Sa ti s fa ctory
CW-09
02-34-RCP/LOAN/PJN.III/06.14
Ta njung Sel or-Seka ta k Buji -Ta njung Pa l a s Sec. 2 (34-RCP02)
PT.Bra nta s Abi pra ya -Ma hi r Ja ya Ma ha ka m Ra ya - JO
4
2
3
3
3
2
3
2
22
55
Sa ti s fa ctory
CW-10
03-34-RCP/LOAN/PJN.III/04.14
SP.TIGA APAS - SIMANGGARIS (SECTION 1)
PT.Pemb. Peruma ha nPT.Perda s a JO
4
4
4
3
4
4
4
3
30
75
Good
CW-11
03-34-RCP/LOAN/PJN.III/04.14
SP. TIGA APAS - SIMANGGARIS - BTS. NEGARA Ha l l a Corpora ti on (SERUDONG)
2
2
2
3
3
2
3
3
20
50
Sa ti s fa ctory
CW-01
01/24-RCP-01/NR/IDB/0161/0115
-
-
-
-
-
-
-
-
-
-
JUST STARTED
CW-02'
HK.02.03/BJGD/24-RCP02/I/2015/01
CW-03
02/24-RCP-03/NB/IDB/016/0115
CENTRAL JAVA
Ra nki ng = (Tota l Score/40) * 100 %
Ta mba kmul yo - Wa wa r
PT.Pemba nguna n Peruma ha n ; PT.Arma da Ha da Gra ha
Gi ri woyo - Duwet
PT. Huta ma Ka rya (Pers ero)
JUST STARTED
Wa wa r - Congot
PT. Ja ya Kons truks i Ma ngga l a Pra ta ma Tbk
JUST STARTED
Score
0
1
2
3
4
5
% Compl i a nce
0-20
20-40
40-60
60-80
80-100
Sca l e
N.A.
Bel ow Pa r
Mi l dl y Sa ti s fa ctory
Sa ti s fa ctory
Good
Excel l ent
Ra nki ng
Bel ow Pa r
Mi l dl y Sa ti s fa ctory
Sa ti s fa ctory
Good
Excel l ent
Appendix
PMU RRDP – Quarterly Progress Report No. 7, October - December 2015
Appendix. 16 ABBREVIATIONS AND ACRONYMS ACAP ADB AMDAL ANDAS ATMS Bappedalda Bappenas BPK BPKP CTC CRO DSC-1 DSC-2 DSC-3 CW CHU DOP DGH DGLT DRBWR DTA DTP DFUR DGH EA EIA EIR EIRTP-2 ESAM EMP FMR FIDIC GOI HLRIP IA IDB IT ISEM IVP IG IRSMS KPKN LRAP LARF MOF MHA MPW MPR MOT NOL
Anti-Corruption Action Plan Asian Development Bank Environmental Management (Analysis Mengenai Dampak Lingkungan) Analysis Dampak Social Area Traffic Monitoring System Regional Environmental Impact Agencies Badan Perencanaan Pembangunan Nasional Badan Pemeriksaan Keuangan (Audit Board of the Government of Indonesia) Badan Pengawasan Keuangan dan Pembangunan (Development Finance Comptroller, internal auditor of the Government of Indonesia) Core Team Consultant Community Representative Observer Design and Supervision Consultant for Kalimantan Design and Supervision Consultant for Central Java Design and Supervision Consultant for East Java Civil Works Complaint Handling Unit Directorate of Planning Directorate General of Highways Directorate General of Land Transport Directorate Road and Bridge West Region Directorate of Technical Affairs Directorate of Traffic Police Directorate Freeway and Urban Road Directorate General of Highway Executing Agency Environmental Impact Assessment Eastern Indonesian Region Eastern Indonesia Regional Transport Project (Second Project) Environmental and Social Assessment Environmental Management Plan Financial Monitoring Report Federation Internationale des Ingenieur Conseils Government of Indonesia Heavy Loaded Road Improvement Project Implementation Agency Islamic Development Bank Information Technology Institutional Strengthening in Environmental Management Isolated Vulnerable People Inspectorate General Integrated Road Safety Management System Kantor Perbendaharaan Keuangan Negara Land Acquisition and Resettlement (Rencana Tindak Pengadaan Tanah dan Pemukiman Kembali) Land Acquisition Resettlement Frame Work Ministry of Finance Ministry of Home Affairs Ministry of Public Works Monthly Progress Report Ministry of Transportation No Objection Letter (from World Bank)
PMU RRDP – Quarterly Progress Report No. 7, October - December 2015
NRSC UKL/UPL OPRC PA PAS PMR PBCC PIP PIS PAD PMM PMU PPR PVD QPR RBRF RFP RRSP RS-SC SBD SIA SIPP SLKLL SOP SURIP SRRP SRIP SPI SC Sub Dit Lingkungan TKPM TOR TRACER WB WP-1 WPs WPM WTP
National Road Safety Council Upaya Pengelolaan Lingkungan dan Upaya Pemantauan Lingkungan (Site Specific Environmental and Monitoring Plans) Output and Performance Based Road Contract Procurement Agent Procurement Advisory Services Performance Monitoring Reporting Performance Based Contract Consultant Project Implementation Plan Project Implementation Schedule Project Appraisal Document Project Management Manual Project Management Unit (RRDP) Project Progress Report Pre fabricated Vertical Drainage Quarterly Progress Report Reforming Road Maintenance Management and Funding Request for Proposal Road Rehabilitation Sector Project Road Safety Steering Committee Standard Bidding Document Social Impact Assessment System Information Pemantauan Proyek Traffic Accident Reporting System Application Standard Operating Procedure Strategic Urban Road Infrastructure Project Sumatera Region Roads Project Strategic Road Infrastructure Project Support Project Implementation Steering Committee (Tim Pengarah) Sub Directorate of Environmental Tim Penanganan Komplain Masyarakat – a Complaints Investigation Unit within Inspectorate General Terms of Reference Study Penyelusuran Kembali World Bank Works Program – Year 1 Work Programs Wakil Pengamat Masyarakat Warga yang Terkena Proyek