REPUBLIC OF INDONESIA MINISTRY OF PUBLIC WORKS DIRECTORATE GENERAL OF HIGHWAY DIRECTORATE OF PLANNING
QUARTERLY PROGRESS REPORT NO.1
APRIL - JUNE 2014
TECHNICAL ASSISTANCE FOR SUPPORT OF PROJECT MANAGEMENT UNIT OF REGIONAL ROADS DEVELOPMENT PROJECT UNDER : ADB LOAN NUMBER 2817-INO IDB FINANCING NUMBER 0161 IND
RENARDET S.A. CONSULTING ENGINEERS
Joint Venture With : 1. PT. Multi Phi Beta 2. PT. Widya Graha Asana 3. PT. Disiplan Consult 4. PT. Anugerah Kridapradana
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Table of Contents 1.
2.
3.
Executive Summary ..........................................................................................................................1 1.1
Project Description. ..................................................................................................................1
1.2
Current Implementation Situation .............................................................................................1 1.2.1
Procurement .............................................................................................................1
1.2.2
Civil Works ...............................................................................................................2
1.2.3
Consultancy Services ...............................................................................................7
1.3
Current Status of Loan .............................................................................................................7
1.4
Current Problems and Action Required at End of Second Quarter 2014 ................................8
General ...............................................................................................................................................8 2.1
Reporting Requirements...........................................................................................................8
2.2
Loan Status ..............................................................................................................................9
2.3
Financial Management ...........................................................................................................10
2.4
Project Cost Monitoring ..........................................................................................................10
2.5
ADB and IDB Missions ...........................................................................................................10
2.6
Project Steering Committee Meeting ......................................................................................11
2.7
Loan Closing Date ..................................................................................................................11
Project Management and Implementation ....................................................................................11 3.1
Procurement Plan ...................................................................................................................11
3.2
Procurement Status ................................................................................................................11
3.3
Implementation Status – Civil Works......................................................................................12
3.4
Variation Details .....................................................................................................................12
3.5
Ongoing Consultancy Services ..............................................................................................13
3.6
Implementation of the Anti-Corruption Plan ...........................................................................14
3.7
3.8
3.6.1
Community Representative Observer (CRO) ........................................................14
3.6.2
Third Party Monitoring (TPM) .................................................................................14
3.6.3
Complaint Handling System (CHS) ........................................................................15
Implementation of the Environmental Management Plan ......................................................15 3.7.1
HIV/AID and Anti Human Trafficking Program .......................................................15
3.7.2
Monitoring of Health and Safety .............................................................................15
Resettlement & Rehabilitation Activities .................................................................................16 3.8.1
Preparation of LARP ..............................................................................................16
3.8.2
LARP Implementation ............................................................................................16
4.
Seminars, Workshops & Training ..................................................................................................16
5.
RRDP Website................................................................................................................................17
i
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Forms Form A
General
2 Sheets
Form B
Summary of Implementation
2 Sheets
Form C
Status of Problems
2 Sheets
Form D
Contract Package Status
Form E
Details of the Budget
15 Sheets 1 Sheets
ii
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendices Appendix 1
The overall Financial Status
Appendix 2
Procurement Plan
Appendix 3
Project and Cost Monitoring
Appendix 4
Details Variation Orders Up to End June 2014
Appendix 5
Summary of Contract Data
Appendix 6
Unsettled Complains
Appendix 7a
CROs Activities on SRIP
Appendix 7b
Status of CRO Reports
Appendix 8
EMP Compliance ( Up to end June 2014)
Appendix 9
Status of Social Safeguard Study.
Appendix 10
Status of Monitoring of Environmental Mitigation on RRDP
Appendix 11
Overall Land Acquisition Status End June 2014
Appendix 12
Environmental Safeguards
Appendix 13
Construction programme
Appendix 14
Abbreviation and Acronyms
iii
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
1.
Executive Summary 1.1
Project Description. The RRDP project is aided project of ADB loans (No.2817-INO) and financing IDB (No.0161-IND). The proposed Project
will improve strategic national road
corridors in northern Kalimantan and southern Java to support economic growth in these two (2) less developed and poorer areas of Indonesia. The National Road Network in southern Java is incomplete, with some road sections of the southern Trans Java Highway not yet constructed resulting in gaps in the network. Similarly, road network improvements are needed to support economic development in the less developed and remote districts in northern Kalimantan and improve road connections to the Kalimantan border. The project includes a component for the rehabilitation of 476 km of national roads consisting of new construction, resurfacing and widening and bridge improvement/ replacement total length 3,390 meters in two (2) provinces in Java and two (2) provinces in Kalimantan. 1.2
Current Implementation Situation
1.2.1 Procurement All sub-projects started with pre-qualification 20 December 2011 through the ICB procurement process. West Kalimantan One (1) of the three (3) packages in West Kalimantan, CW-05 (Sosok-Tayan; Tanjung – Batas Kota Sanggau), Bidding Documents were submitted to ADB on 25 April 2014. After ADB comments on the draft Bidding Documents retendering carried out 23 June 2014 with agreement that DGH may apply the full eprocurement system for this Package as a pilot test. East Kalimantan One (1) Package in East Kalimantan CW-08, 34-RCP01, Tanjung Selor – Sp.3 Tanjung Palas & Sp.3 Tanjung Palas- Sekatak Biji (Section 1), Bid opening was held 13 June 2013, revision of the Bid Evaluation Report (BER) submitted to ADB on 25 April 2014; their comments were received on 19 May 2014. In response to the ADB comments POKJA commenced carrying out clarification with the public accountant. Central Java For three (3) packages in Central Java, financed by the IDB, Package CW-01 (Tambakulyo - Wawar), CW-02 (Giriwoyo – Duwet) ; CW-03 (Wawar – Congot) approved by IDB on 30 April 2014 the a Special Procurement Notice (SPN) was published in local and International Newspapers on 9 May 2014. Invitations to Qualified bidder were issued on 14 May 2014. Pre bid Meeting for 3 (three) packages was held on 18 June 2014. 1
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
1.2.2 Civil Works Six (6) out of eleven (11) packages have been contracted through ICB tender process as shown in the table below: Ref
Package No
CW-04
28-RCP01
CW-06
30-RCP02
Package Name
Contract Sign
COW
Province
Jolosutro – Sandang Biru
21 Aug 2013
18 Oct 2013
Tebas – Singkawang (Sec 1)
14 Nov 2013
17 Dec 2013
East Java
Tebas – Singkawang (Sec. 2) ByPasss Sambas Galing-Tanjung Harapan
CW-7
30-RCP03
West Kalimantan
Sp.Tanjung – Galing
27 Nov 2013
4 Dec 2013
Aruk(Bts.Serawak-Sp.Tanjung CW-09
34-RCP02
Sp.3 Tanjung Palas –Sekatak Buji (Section 2)
25 Jun 2014
Not Yet
CW-10
34-RCP03
Sp. Tiga Apas - Simanggaris (Section 1)
11 Apr 2014
Not yet
CW-11
34-RCP04
Sp. Tiga Apas – Simanggaris
11 April 2014
East Kalimantan
Not yet
(Section 2); Simanggaris - Bts. Negara (Serudong)
Three (3) packages out of the above eleven (11) packages are already ongoing. The table below shows the actual physical progress at the end of this second 2014 quarter: Package
JolosutrioSendangbiru TebasSingkawang. Bypass Sambas GalingTj.harapan Sp.TanjungGaling Sp.Tanjung Aruk
Province
Contractor
Physical Progress % Sche Actu Diff. d al
East java
Hutama Karya
13.37
23.81
10,44
West Kalimanatan
Brantas Abipraya. Tri Citra Perdana Trifa Abadi
2,371
3,898
1,527
Waskita Karya Yasa Patria Perkasa
4,206
4,016
-0,19
West Kalimantan
2
Remarks Since January 2014, work progress was very low.
Slightly behind Schedule
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
The location of all packages is shown on the following Project Location Map.
WEST KALIMANTAN
3
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
EAST KALIMANTAN
4
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
EAST JAVA
5
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
CENTRAL JAVA
6
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
1.2.3
Consultancy Services
TA Consultant
Planned Mobilization from the Project Administn Manual (PAM) up to June 2011
Contract Signed
Actual Responsible Mobilization Agency
CTC (CSP-1)
April 2012
12 Feb 2014
3 Mar 2014
DGH
DSC-1 (CSP-2)
April 2012
21 Nov 2013
16 Dec 2013
DGH
DSC-2
Not Yet
DSC-3 (CSP-3)
Not yet 16 Oct 2013
Road Safety Support (CSP-4) Institutional development for Road Network Management (CSP-5) Road safety awareness Campaign and Training (CSP-6) Integrated Vehicle overloading Control Strategy (CSP-7) Overloading and Speed Enforcement (CSP-8) Indonesia Transport Sector Dev. Strategy and Policy (CSP-9) HIV/AIDS anti Trafficking Program (CSP-10)) Road safety Equipment
18 Oct 2013
Remarks
DGH DGH
Jan 2013
Not yet
DGH
Jan 2013
Not yet
DGH
Jan 2013
Not yet
DGLT
Jan 2013
Not yet
DGLT
Jan 2013
Not yet
DGNTP
Jan 2013
Not yet
Bappenas
Jan 2013
Not yet
DGH
Sept 2013
Not yet
DGNTP
As can be seen from the above table all Consultancy service appointments were late for a number of reasons including delay of procurement process for the Consultant Services of DSC-2 and delay in the procurement process for civil works in Central Java. There were also delays in respect of Technical Assistant Consultant Services CSP-4 to CSP-10 1.3
Current Status of Loan At the end of this second quarter 2014, (June 2014) some US $ 6,372,268.55 representing 2.60% of the available loan has been disbursed. Disbursement is considerably behind schedule as 8.69% (4 month) of the loan availability period has already elapsed with the main reasons for delays being: a)
The long period waiting for the No Objection Letter (NOL) for tender documents packages in Central Java.
7
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
b)
Delay in disbursement of Advance Payment for package 34-RCP03 (Sp.3 Apas – Simanggaris, section 1) and 34-RCP04 Sp.3 Apas – Simanggaris – section 2; ; Simanggaris – bts. Negara).
c)
Late appointment of Technical Assistance (TA) Consultants for CSP 4 to CSP10 not yet contracted.
d)
CTC not yet received the Advance Payment.
Details of the overall loan situation are presented as a series in forms A through E found immediately after the main text in this report. These Forms are an English translation of the quarterly report prepared by PMU for Bappenas. 1.4
Current Problems and Action Required at End of Second Quarter 2014 Item
Loan Period Extension
Technical Assistant for Road Sector Development Program
2.
Problem Areas Three (3) to possibly five (5) packages will not be finished within the current loan period Until end June 2014 still not running.
Suggested Solution A proposed extension of time of the loan to be formulated and submitted to ADB for approval Accelerate the process of contracting
General 2.1
Reporting Requirements Quarterly Progress Reports: This is the first quarterly progress report to be prepared and covers the second quarter of 2014. Report
Period Covered
Final Version Issued
Quarterly Progress Report No.1
March 2014 – June 2014
November 2014
Financial Monitoring Reports: These reports have been prepared for each quarter since the beginning of 2014 although the first one, issued in May 2014, covered the period January – March 2014. The date, reports have been prepared each quarter on schedule as shown below: Report
Period Covered
Financial Monitoring Report
January – March 2014
Financial Monitoring Report
April – June 2014
Date Issued 10 July 2014
CTC Monthly Progress Reports: These reports have been prepared covering each full month since CTC mobilized at the beginning of March 2014. The first, covering the month of April 2014, was 8
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
issued in July 2014 however subsequent reports have been submitted within succeeding months. All reports are first vetted and edited when PMU feel it to be necessary. Report
2.2
Period Covered
Final Version Issued
Monthly Progress Report No. 1
April 2014
15 July 2014
Monthly Progress Report No. 2
May 2014
18 July 2014
Monthly Progress Report No. 3
June 2014
15 August 2014
Loan Status The agreed allocation of loan funds from the original loan agreement together with the % disbursed to the end of the quarter is presented below:
Category
Works
Works (Central Java)
Original Amount of loan Allocated in US$
Total Disbursed to 30 June 2014 in %
Distribution to 30 June 2014 in US$ 5,676,272.79
ADB
IDB
Percentage of Expenditure to be financed
155,000,000
-
70%
2.72%
-
53,500,000
100%
0
100%
0
0
Road Safety Equipment
1,300,000
Consultant’s services and training
12,200,000
3,000,000
100%
4.58%
695,995,76
4,300,000
-
100%
0
0
Over loading and speed Enforcement
2,200,000
-
100%
0
0
- Indonesia Transport Sector development Strategy and Policy study. - Integrated Vehicle Overloading Control Strategy - HIV/AID and anti Trafficking Prevention Program
2,400,000
-
100%
0
0
Unallocated
2,600,000
85,000,000
0
0
0
TOTAL AMOUNT
180,000,000
65,000,000
2.60
6,372,268.55
- Road Safety Support - Institutional Dev. for Road Network Management. - Road Safety awareness campaign and Training
Details of the overall loan status can be found in Appendix 1
9
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
2.3
Financial Management S-Curve for Financial Progress The following curve shows the financial disbursement progress up to the end of June 2014.
% complete
Current Loan Allocation and Disbursement (%) to Date 100.00 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 10.00 -
2.60 Dec-17
Sep-17
Jun-17
Mar-17
Dec-16
Planned Disbursment
Sep-16
Jun-16
Mar-16
Dec-15
Sep-15
Jun-15
2.4
Mar-15
Original based PAM
Dec-14
Sep-14
Jun-14
Mar-14
-
Dec-13
-
Sep-13
Jun-13
Mar-13
-
Actual Disbursement
Project Cost Monitoring A summary of the project cost monitoring in tabular format is presented in Appendix No. 3.
2.5
ADB and IDB Missions The following table summarizes Bank missions to RRDP Projects to date: Dates
Mission Team
From
To
ADB
15 Dec 13
20 Dec 13
Soewartono, HS
21 Apr 2014
24 April 2014
-
IDB
- Dr.Nizar Zaied - Murad Gurmeric
During this second quarter the Islamic Development Bank mission visited Indonesia commencing 21 April 2014. As can be seen from the table below the mission was mainly in connection with procurement process of RRDP and made one site visit to IDB RRDP projects in Central Java made with one meeting of RRDP attended by mission delegates, PMU and CTC. Date
Activity
21 April 2014
Introduction of CTC - RRDP staffs
22 April 2014
First Coordination meeting with PMU, Satker, PPK
23 April 2014
Site visit to three (3) packages in Central Java
24 April 2013
Second Coordination meeting with PMU, Satker, PPK
10
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
2.6
Project Steering Committee Meeting No Steering Committee meetings have been held to date.
2.7
Loan Closing Date There were no discussions had regarding the loan closing date.
3.
Project Management and Implementation There were no major changes in project management during the quarter 3.1
Procurement Plan Appendix No. 2 presents a copy of the general Procurement Plan for all Civil Works, Goods and Consulting Services of the project updated to the end of the second quarter 2014.
3.2
Procurement Status (A) Works Procurement is being conducted under the Bank’s Procurement Procedures as described in the Loan Agreement. The International Competitive Bidding (ICB) will apply for packages with the estimated total cost of more than US$10 Million to comply with the Bank’s threshold. According to Government of Indonesia (GOI) regulation, prequalification shall be apply to all packages with construction estimated cost to be more than IDR 100 Billion. All sub-projects started with pre-qualification in 20 December 2011 through the ICB process procurement. This advanced procurement action was agreed by both DGH and the Asian Development Bank (ADB) prior to the establishment of a CTC. The deadline of Qualification Document submission by the Applicants was 27 April 2012. Procurement is now complete for six (6) packages: two (2) packages in West Kalimantan, one (1) package in East Java and three (3) packages in East Kalimantan. For one (1) of the three (3) packages in West Kalimantan, CW-05 (Sosok-Tayan; Tanjung – Batas Kota Sanggau), the Bidding Document was sent to ADB on 25 April 2014; ADB commented on the draft Bidding Documents (retendering) on 23 June 2014 and agreed that DGH may apply the full e-procurement system for this package as a pilot test. For three (3) packages in Central Java, financed by IDB, package CW-01 ( Tambakulyo - Wawar), CW-02 (Giriwoyo – Duwet) ; CW-03 (Wawar – Congot) was approved
by IDB on 30 April 2014. The SPN was published in a local and
International Newspapers on 9 May 2014. Invitations to Qualified bidders were issued on 14 May 2014. 11
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
The Pre Bid Meeting was held on Semarang on 18 June 2014 and scheduled that bid submissions will be received on 15 July 2014. Revision of the Bid Evaluation Report (BER) for package CW-08 ,Tanjung Selor – Sp.3 Tanjung Palas & Sp.3 Tanjung Palas- Sekatak Biji (Section 1) in East Kalimantan was sent to ADB on 25 April 2014 and comments were received on 19 May 2014.
POKJA commenced carrying out clarification to public accountant in
response to the ADB comment. Letter of Acceptance for package CW-09 (Sp.Tiga Tanjung Palas – Sekatak Buji (Section 2), in East Kalimantan was issued on 4 June 2014. To complete Contract Documents the Contractor submitted the Performance Security to PPK on 24 June 2014; the Contract was signed 25 June 2014. (B) Goods There was no procurements in process during the second quarter 2014. (C) Services The Core Team (CTC), Supervision Teams (DSC-1 and DSC-3), status thereof are discussed in Section 3.5 of this report. :3.3
Implementation Status – Civil Works Contracts have been signed for three (3) packages; One (1) for East Java Province (CW-4), two (2) for West Kalimantan Province (CW-6 and CW-7) and construction commenced. Three (3) Packages in East Kalimantan signed contracts and ADB concurred with Contracts for three (3) packages (CW-9, CW-10 and CW-11). However, all of the three packages above (CW-9; CW-10 and CW-11) are facing delay due to not yet payment
of Advance Payment. Therefore the commencement of work for this
packages is delayed. 3.4
Variation Order Details No variations have yet to be made for three (3) packages.
12
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
3.5
Ongoing Consultancy Services a)
Technical Assistance for Core Team Consultants (CTC) to Support the Project Management Unit. Consultant: Renardet, S.A are in Joint Venture with Local Consultants PT.Widya Graha Asana; PT.Multi Phibeta; PT. Anugerah Krida Pratama; PT.Disiplan Consultant as the Core Team Consultant (CTC). Contract No.03-02/CTC/PM/LN/ADB/2817.0214 was signed on 12 February 2014, between the Ministry of Public Works, Directorate General of Highways and Lead Consultant Renardet S.A. Notice to Proceed (NTP) was issued on 25 February 2014 and Contract is scheduled to be completed by 29 February 2016. If the Loan period is extended it is likely that the CTC Contract will be likewise be amended accordingly. A Draft Addendum No.1 to the CTC Contract is currently being prepared to formalize a number of issues such as additional professional and sub professional personnel in the CTC Contract. Amended requirements to the CTC services are summarized as follows: a)
Additional TOR for Third Party Monitoring (TPM) activities
b)
Amendment of the CTC Team composition and staffing schedule
c)
Additional professional Staff for Traffic Engineer and Transport Economist.
d)
Replacement of Professional Staff for Environmental Specialist.
b) Technical Assistance for Construction Supervision Consultant (DSC-1) for packages in West and East Kalimantan. Lead Consultant: CECI (China Engineering Consultants Inc), Taiwan DSC-1 Contract No. 01/DSC-1/CS/ADB/2817/1113 was signed on 21 November 2013 between the Ministry of Public Works, Directorate of Western Region, DGH and CECI in Joint venture with PT.Wira Wydiatama; PT.Hasfarm Dian Konsultan; PT.Yodya Karya; PT.Seecons; PT.Pola Agung Consulting. The original Contract for DSC-1 is US$ 936.570 and IDR 30.372.995.000 (excl VAT). The mobilization of DSC-1 on 16th December 2013 was behind schedule as construction work had already started early December. c)
Technical Assistance for Construction Supervision Consultant (DSC-3) for Package in East Java. Consultant: PT.Perentjana Djaya. DSC-3 Contract No. 01/DSC-3/CS/ADB/2817/1013 was signed on 16 October 2013 between the Ministry of Public Works, Directorate of Western Region,
13
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
DGH and PT.Perentjana Djaya Notice to Proceed (NTP) was issued on 18th October 2013. d) Technical Assistance for Construction Supervision Consultant (DSC-2) for Package in Central Java. Procurement of Consultant Central Java, DSC-2 is still under evaluation by POKJA. e)
Other Consultants for Technical Assistant Road Sector Development Program and Road Sector Program, REOI, TOR, RFP and OE still under preparation and to be proposed to ADB.
3.6
Implementation of the Anti-Corruption Plan 3.6.1
Community Representative Observer (CRO) The bid openings for three (3) packages in West Kalimantan and four (4) packages in East Kalimantan were attended by the selected Community Representative Observers (CRO) who are required to prepare reports with the results of their observations. No CRO attended the bid opening at one (1)Package in East Java. See Appendix 7 for a tabular summary of CRO activities.
3.6.2
Third Party Monitoring (TPM) The Terms of Reference and budget for the TPM were contained in CTC draft Amendment No.1, which is still in process. Operational costs will be derived from the Technical Assistance component of the Loan for RRDP through the Core Team Consultant (CTC). It was decided that the best method of recruitment for Third Party Monitoring (TPM) was through the universities closest to each individual package and PMU mailed invitations asking them to express their interest in forming independent monitoring teams. Concept is based on the fact that Universities/Technical
Faculties
may
have
engineers
available
for
recruitment and Universities could use this opportunity to be involved in public service. It is hoped that this concept will be more effective and more efficient in getting legitimate, competent, independent TPM. The duties of a TPM include a) Reporting to the PPK for relevant package and obtain copies of all drawings and contract documentation. b) Make at least three (3) separate visits to site, with each visit up to four (4) days long, and ascertain that the works are being carried out in compliance with the drawings and documentation. c) Prepare and submit a report for the PMU following each visit with their last report post Project Hand Over (PHO). 14
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
3.6.3
Complaint Handling System (CHS) Up to June 2014, no complaints have been received.
3.7
Implementation of the Environmental Management Plan All contractors have been informed that they must prepare an Environmental Management and Monitoring action plan RKPPL (Rencana Kerja Pengelolaan dan Pemantauan Lingkungan) prior to commencement of each construction package. DSC will provide technical assistance to each contractor in the preparation of the documents The detail status of plan preparation is as follows: Pack. No.
Project Name
Safeguard Document
28-RCP 01A (CW01)
Jolosutro Sendangbiru
AMDAL
Tebas Singkawang (Section-1 & Section-2))
AMDAL
Bypass Sambas
UKL-UPL
30-RCP 02(CW-06)
30-RCP 03 (CW-07)
GalingTj.Harapan Sp.TanjungGaling (Section1) Sp.TanjungGaling (Section2) Aruk-Sp.Tanjung
Date Draft
Final
Status Will be conduct brief to Contractors
Will be conducting/ briefing of Contractors
UKL-UPL AMDAL
UKL-UPL
Will be conducting/ briefing of Contractors
UKL-UPL
A summary of the monitoring of environmental mitigation conducted by CTC for all packages is presented in Appendix No. 8 and a detailed record of the status of environmental safeguard documentation in presented in Appendix No. 12. 3.7.1 HIV/AID and Anti Human Trafficking Program Program for HIV/AID and anti Human Trafficking is not yet started, still in the process of procurement. The REOI, TOR, RFP and OE has been sent to ADB on 7 May 2014. 3.7.2 Monitoring of Health and Safety Each contractor must take reasonable precautions to maintain the health and safety of his employees including collaboration with local health authorities. The object of this program is to reduce accidents and health problems in the construction work sector and is part of the CTC monitoring activities.
15
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
3.8
Resettlement & Rehabilitation Activities 3.8.1 Preparation of LARP Being carried out In accordance with the requirements set forth in the ADB safeguard
document
where
monitoring
of
LARP
preparation
and
implementation is required for each package on the RRDP program. Monitoring of LARAP conducted by the CTC is prepared in five (5) documents; one (1) LARP will be prepared for two physical work packages of 34-RCP-03 and 34RCP04. 3.8.2 LARP Implementation Based on the results of monitoring, data collection and coordination with local government and projects, the progress of the implementation of LARP can be grouped as follows: 1. Land Acquisition Where land acquisition required land acquisition has been completed at: Package 28-RCP 01A (CW-01): Jolosutro-Sedangbiru and Package 24RCP-01 (CW-02): Tambak Mulyo-Wawar. While six (6) other packages are still in the process of land acquisition, and one (1) package does not require land acquisition. There are two (2) packages where implementation is waiting the completion of LARP preparation. 2. Compensation for buildings and plants Payments for compensation have to be made, with amounts set by the regulation set by the Department of Public Works, the Department of Agriculture or Regional Head Decision. 3. Rehabilitation Regarding livelihood recovery of the Affected Person (APs) in the form of allowance during the transition or assistance to vulnerable groups almost all the packages are still in the process of implementation. A detailed summary of the land acquisition requirements for packages based on LARP studies are included in Appendix No. 11. 4.
Seminars, Workshops & Training No seminars, workshops or training courses were held during the second quarter of 2014, due Training specialist personnel still not yet mobilized.
16
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
5.
RRDP Website The RRDP-CTC website is now running on the fixed server site and can be found on http://www.pmu-rrdp.com . The RRDP-CTC website contains all of the following items: a)
General RRDP information including copies of all reports i.e. Monthly Progress Reports and Quarterly Progress Reports with the latest uploaded reports being the MPR , QPR for the first quarter of 2014, Social and Environmental Status Reports and the Road Safety Audit Reports.
b)
Project list and Project Progress Status including Procurement Plan and Bid Winners, and Copies of all Bid Documents although currently without drawings while waiting for the original CAD files to be converted to PDF files)
c)
ACAP and Complaint Handling System including contact points, list of Community Representation Observers, and list of Third Party Monitors who have already been appointed.
d)
Announcements (current and archived)
e)
Newsletter
f)
Documents, (including all reports and bidding documents)
g)
Package Location Map
h)
Responses from the CHU following contract signing.
Via the website any member of the public can submit a complaint regarding the implementation of any RRDP package. Complaints can be submitted anonymously and they will be followed up by the person responsible from the relevant institution.
17
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM A : GENERAL
REPORT OF ACTIVITIES FINANCED BY LOAN AND OR GRANT OF FOREIGN FISCAL YEAR 2014
NAME OF MINISTRY/INSTITUTION
: Ministry of Public Works.
NAME OF LOAN AGENCY
: Asian Development Bank (ADB) dan Islamic Development Bank (IDB)
A.
DESRIPTION I. PROJECT NAME LOAN / GRANT
: Regional Roads Development Project (RRDP)
II. NPPHLN NUMBER AND REGISTER
: ADB No.2817-INO, Register : 10846401
III. DATE OF NPPHLN SIGNED
: ADB : 7 Mei 2012
IDB No. 0161-IND, Register : 10848804
IDB :17 April 2012 IV. EFFECTIVE DATE OF NPPHLN A. DATED OF EFFECTIVE TENTATIF
: -
B. DATED OF REAL EFFECTIVE
: ADB : 3 Juli 2012 : IDB : 2 Mei 2013
V. DATE OF CLOSING NPPHLN A. ORIGINAL
: ADB : 31 Agustus 2016
B. ACTUAL
:-
IDB : 30 April 2016
VI. AMOUNT OF LOAN / GRANT A. ORIGINAL
: :ADB USD 180 billion : IDB : USD 65 billion
B. ACTUAL VII. PURPOSE
:: To promote economic growth and poverty reduction in the region North of the island of Kalimantan corrodor through the construction and improvement of road and bridges, with some target to be achieve through this project are:: (i)improvement / construction of road along the 854 km; (ii) improvement / construction of bridges along the 3.860 m; (iii) improve governance policy support in the road sector and (iv) increasing the capacity of human resourcesin the management of the road.
: Southern Cross access Java and Kalimantan Border Crossing Access
VIII. TARGET
IX INSTANSI PENANGGUNG JAWAB (EXECUTING AGENCY) X. INSTANSI PELAKSANA (IMPLEMENTING AGENCY) NO. 1 2 3
INSTANSI PELAKSANA Ditjen Bina Marga (DGH) Dijen Perhubungan Darat (DGLT) Ditjen Kepolisian Lalulintas (DGNTP)
Kategori Civil Works Goods Consulting Services Unallocated Total
ALOKASI DANA (JUTA VALAS ) USD 208.50 USD 1.30 USD 24.10 USD 11.10 USD 245.00
REVISI -
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
XI. LOAN CATEGORY NO.
DANA ALOKASI DANA PENDAMPING (JUTA VALAS) (JUTA VALAS)
KATEGORI PINJAMAN
1 2 3
Civil Works Goods Consulting Services & Training
4
Unallocated Total
USD 208.50 1.30 USD USD 24.10 USD 11.10 USD 245.00
REVISI
USD 88.50 USD USD USD 47.00 USD 135.50
XII. SCOPE OF WORKS 1. Pekerjaan Jasa Konstruksi/Civil Works untuk 11 paket 2. Pekerjaan Jasa Konsultansi (civil works) yaitu CTC (Dit. Bina Program), DSC-1, DSC-2 dan DSC-3 (Dit. Bina Pelaksanaan Wilayah II) 3. Pekerjaan Jasa Konsultansi (roads sector developmet program) yaitu Road Safety Support, Institutional Development for Road Network Management, Road Safety Awareness Campaign and Training, Overloading and Speed Enforcement, Indonesia Transport Sector Development Strategy and Policy Study, Integrated Vehicle Overloading Control Strategy dan HIV/AIDS and Anti-Trafficking Program XIII. LOCATION (PROVINSI/KABUPATEN/KOTA) NO. 1 2 3 4
PROVINSI/KABUPATEN/KOTA Jawa Tengah Jawa Timur Kalimantan Barat Kalimantan Timur
ALOKASI DANA (JUTA VALAS ) USD 76.60 USD 21.30 USD 187.80 USD 191.40 USD 477.10
REVISI Non PPN Consultant Civil Work
6,563.36 100,634.36
0.000
XIV. DISBURSEMENT PLAN DAN REALISASI PHLN (Juta Rp) Rp
Tahun a. b.
2013 2014
Triwulan I : 4,762.72
Rp Actual 0.00 1,238.62
Triwulan II 0.00 11,929.28
Rp Actual 0.00 3,090.24
Triwulan III 0.00 101,483.97
Rp Actual 0.00 0.00
Triwulan IV 107,197.72 166,719.17
Actual 107,197.72 0.00
Total Disbursement Plan (Rp) 107,197.72 280,132.42
Total DIPA (Rp) 374,930.79 441,338.27
Total Realisasi DIPA (Rp) 107,197.72 1,238.62
Persentase Penyerapan (%) 28.59 0.28
B. CONTACT PERSON (PETUGAS YANG DAPAT DIHUBUNGI) I. KETUA PELAKSANA HARIAN PMU RRDP Nama : Ir. Slamet Mulyono M.Eng Alamat Kantor : Jl. Pattimura No. 20, Jaksel Nomor Telp : 021-7210218 Nomor Faksimili : 021-7210219 Alamat E-mail :
[email protected]
II. ESELON II PENANGGUNG JAWAB Nama : Ir. Harris H.Batubara, M.Eng.Sc Jabatan : Direktur Bina Program Ditjen Bina Marga Alamat Kantor : Jl. Patimura No.20 Jakarta Selatan Nomer Telp : 021- 7200281 Nomer Faksimili : 021- 7201760 Alamat E-mail :
[email protected]
III.A PROJECT IMPLEMENTING UNIT I #### Nama : DR. Ir.Didik Rudjito, MSc Jabatan : PPK Kegiatan Penyiapan Program dan Administrasi Pinjaman Luar Negeri Alamat Kantor : Jl. Pattimura No. 20, Jaksel Nomer Telp : 021-7248870 Nomer Faksimili : 021-7248870 Alamat E-mail :-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORMULIR B.1 : RINGKASAN PELAKSANAAN DALAM TAHUN ANGGARAN 2014 A. FINANCED (in IDR) No. Paket
CONTRACT PACKAGE
[a1] I.
TATA CARA PENARIKAN (PP/PL/LC/RK)
[a2]
CONTRACT VALUE AND STATUS AT THE END OF LAST YEAR
[b1]
(b2)
COMMULATIVE DISBURSEMENT UP TO DECEMBER LAST YEAR
REAL DISBURSEMENT WITHDRAWAL APLICATION (WA) TH YL
PENYERAPAN PADA TAHUN ANGGARAN 2014
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
[c]
[d]
[e]
[f]
[g]
[h]
[i]
[j]
[k]
[l]
[m]
TRIWULAN I (1 Jan - 31 Maret)
TRIWULAN II (1 Apr - 30 Jun)
TRIWULAN III (1 Juli - 30 Sept)
TRIWULAN IV (1 Okt - 31 Des)
TOTAL TA 2014 Realisasi [n]
Civil Works CENTRAL JAVA 0.00
-
-
-
0.00
0.00
0.00
41,821,587,300
0.00
41,821,587,300
0.00
0.00
-
-
-
0.00
0.00
0.00
25,717,998,895
0.00
25,717,998,895
0.00
0.00
-
-
-
0.00
0.00
0.00
10,716,725,250
0.00
10,716,725,250
0.00
1,164,447,900
0.00
2,355,687,250
0.00
7,162,465,450
-
11,229,538,250
0.00
-
26,135,334,348
3,090,244,128
19,672,419,777.4
-
24-RCP01
Tambakmulyo - Wawar
Pembayaran Langsung
0.00
0.00
0.00
24-RCP02
Giriwoyo - Duwet (Section 1)
Pembayaran Langsung
0.00
0.00
0.00
24-RCP03
Wawar - Congot
Pembayaran Langsung
0.00
0.00
0.00
Pembayaran Langsung
93,350,000,000.00
23,011,025,595.00
23,011,025,595.00
14,250,065,103.00
EAST JAVA 28-RCP01
Jolosutro - Sendangbiru
546,937,650
0.00
WEST KALIMANTAN 30-RCP01
Sosok - Tayan
Menunggu Persetujuan ADB untuk Re-Tender
Pembayaran Langsung
Tanjung - Bts. Kota Sanggau Tebas - Singkawang (Section 1)
30-RCP02
Tebas - Singkawang (Section 2) Bypass Sambas
Pembayaran Langsung
292,603,385,000.00
43,890,507,750.00
43,890,507,750.00
27,930,323,114.00
614,467,109
0.00
4,219,340,812
3,090,244,128
9,810,991,499
0.00
11,490,534,929
Pembayaran Langsung
238,974,973,000.00
35,846,245,950.00
35,846,245,950.00
22,811,247,423.00
501,847,443
0.00
3,446,019,111
0.00
8,012,830,845
0.00
7,711,722,379
0.00
Galing - Tanjung Harapan 30-RCP03
Sp. Tanjung - Galing Aruk (Bts. Serawak) - Sp. Tanjung
EAST KALIMANTAN 34-RCP01
Tanjung Selor - Sp.3 Tanjung Palas
Pembayaran Langsung
0.00
0.00
0.00
0.00
0.00
-
0.00
24,127,254,199
0.00
24,127,254,198.93
0.00
34-RCP02
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
Pembayaran Langsung
165,332,328,425.00
0.00
0.00
0.00
-
0.00
-
0.00
-
0.00
19,674,548,222
0.00
19,674,548,222.00
0.00
34-RCP03
Sp. Tiga Apas - Simanggaris (Section 1)
Pembayaran Langsung
289,000,000,000.00
0.00
0.00
0.00
-
0.00
-
0.00
32,185,930,000
0.00
10,115,000,000
0.00
42,300,930,000.00
0.00
Pembayaran Langsung
359,652,598,000.00
0.00
0.00
0.00
0.00
39,676,885,643
0.00
4,204,340,040
0.00
43,881,225,682.98
1,438,913,284,425.00
102,747,779,295.00
102,747,779,295.00
34-RCP04
Sp.3 Tanjung Palas-Sekatak Buji (Section 1)
Sp. Tiga Apas - Simanggaris (Section 2) Simanggaris - Bts. Negara (Serudong)
TOTAL CIVIL WORKS II.
Road Saftey Enforcment
Pembayaran Langsung
-
-
0.00
1,663,252,201.80
-
0.00
8,829,807,822.36
0.00
0.00
3,090,244,128.00
92,042,325,237.10
0.00
162,742,176,663.68
0.00
0.00
0.00
0.00
265,277,561,924.94
3,090,244,128.00
-
-
-
0.00
102,747,779,295.00
102,747,779,295.00
-
64,991,635,640.00
-
0.00
0.00
-
0.00 0.00
-
0.00
0.00
0.00
0.00
0.00
0.00 0.00
0.00
Consulting Services & Training 0.00
5,806,675,050.00
0.00
1,583,638,650.00
0.00
7,390,313,700.00
2,412,421,320
0.00
2,412,421,320.00
0.00
1,809,315,990.00
0.00
9,046,579,950.00
1,238,622,000.00
0.00
-
0.00
535,500,000.00
0.00
126,000,000.00
0.00
661,500,000.00
0.00
0.00
687,051,000
0.00
687,051,000.00
0.00
458,034,000.00
0.00
2,519,187,000.00
0.00
-
0.00
-
0.00
-
0.00
-
0.00
0.00
0.00
0.00
-
0.00
-
0.00
-
0.00
-
0.00
0.00
0.00
0.00
0.00
-
0.00
-
0.00
-
0.00
-
0.00
0.00
0.00
0.00
0.00
0.00
-
0.00
-
0.00
-
0.00
-
0.00
0.00
0.00
0.00
0.00
0.00
0.00
-
0.00
-
0.00
-
0.00
-
0.00
0.00
0.00
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
0.00
-
0.00
-
0.00
-
0.00
0.00
0.00
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
0.00
-
0.00
-
0.00
-
0.00
0.00
38,018,178,888.00
6,074,599,000.00
7,115,591,500.00
CTC RRDP
Pembayaran Langsung
0.00
0.00
0.00
0.00
DSC-1(ADB-KALIMANTAN)
Pembayaran Langsung
30,384,233,888.00
6,074,599,000.00
6,074,599,000.00
6,074,599,000.00
DSC-2(ISLAMIC - JATENG)
Pembayaran Langsung
0.00
0.00
0.00
0.00
DSC-3 (ADB-JATIM) Road Safety Support
Pembayaran Langsung
7,633,945,000.00
0.00
1,040,992,500.00
1,040,992,500.00
Pembayaran Langsung
0.00
0.00
0.00
0.00
Institutional Development for Road Network Management
Pembayaran Langsung
0.00
0.00
0.00
Road Safety Awareness Campaign and Training
Pembayaran Langsung
0.00
0.00
Overloading and Speed Enforcement
Pembayaran Langsung
0.00
Indonesia Transport Sector Development Strategy and Policy Study
Pembayaran Langsung
Integrated Vehicle Overloading Control Strategy HIV/AIDS and Anti-Trafficking Program
TOTAL Consulting Services IV.
0.00
GOODS TOTAL GOODS
III.
64,991,635,640.00
-
Unallocated TOTA L
7,115,591,500.00
2,412,421,320.00 687,051,000.00
3,099,472,320.00
0.00 1,238,622,000.00
1,238,622,000.00
-
3,099,472,320.00
0.00
9,441,647,370.00
0.00
3,976,988,640.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1,476,931,463,313.00
211,570,157,590.00
212,611,150,090.00
137,098,862,780.00
4,762,724,521.80
1,238,622,000.00
11,929,280,142.36
3,090,244,128.00
101,483,972,607.10
0.00
166,719,165,303.68
0.00
0.00
0.00
19,617,580,650.00 0 284,895,142,574.94
1,238,622,000.00 0 4,328,866,128.00
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORMULIR B : RINGKASAN PELAKSANAAN DALAM TAHUN ANGGARAN 2014 B. PHYSICAL IMPLMENTATION ( %) No.
PAKET KONTRAK
[a]
TANGGAL PENANDATANGANAN KONTRAK
TANGGAL AKHIR KONTRAK (PHO)
KUMULATIF s.d TA.2013
PERKEMBANGAN FISIK TAHUN ANGGARAN 2014 Akhir Triwulan I Target Realisasi
Akhir Triwulan II Target Realisasi
Akhir Triwulan III Target Realisasi
Akhir Triwulan IV Target Realisasi
[b]
[c]
[d]
[e]
[f]
[g]
[h]
[i]
[j]
[k]
1
24-RCP-01
Tambakmulyo - Wawar
-
-
-
-
-
-
-
-
-
-
-
2
24-RCP-02
Giriwoyo - Duwet (Section I)
-
-
-
-
-
-
-
-
-
-
-
3
24-RCP-03
Wawar -Congot
-
-
-
-
-
-
-
-
-
-
-
4
28-RCP01A
Jokosutro -Kedungsalam
21-Aug-13
13-Sep-15
14.65%
5.86%
22.88%
14.27%
23.03%
15.45%
-
22.0%
5
30-RCP01
Sosok - Tayan;
Menunggu Persetujuan ADB untuk Re-Tender Tanjung- Bts. Kota Sanggau Tembas - SIingkawang Sec.1 + Sec.2
6
30-RCP02
Bypass Sambas (Tanah Hitam /Tanjung Harapan - Sambas)
14-Nov-13
15-Dec-16
19.00%
1.07%
1.95%
2.37%
3.90%
5.49%
-
18.52%
-
26-Nov-13
2-Dec-16
19.00%
1.84%
0.47%
4.21%
4.02%
10.25%
-
14.54%
-
Galing - Tanjung Harapan Simpang Tanjung - Galing
7
30-RCP03 SP.3 Aruk /Bts. Serawak-Simpang. 3 Tanjung
8
34-RCP01
Tanjung Selor- SP.3 Tanjung Palas - Sekatak Buji (Sec.1)
-
-
-
-
-
-
-
-
-
9
34-RCP02
Tanjung Palas -Sekatak Buji (Sec.2)
25-Jun-14
-
-
-
-
-
-
-
-
-
10
34-RCP03
SP.Tiga Apas - Simanggaris (Section 1)
14-Apr-14
-
-
-
-
-
-
-
-
-
11
34-RCP04
Sp. Tiga Apas - Simanggaris - Bts. Negara (Serudong)
11-Apr-14
-
-
-
-
-
-
-
-
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM C : STATUS OF PROBLEMS 2817-INO / IND-0161
February 13, 2009 s/d August 13, 2016 (50.67 bulan)
Regional Road Development Project (RRDP)
- Jumlah Pinjaman (US$) : - Penyerapan Kumulatif (US$) Terpakai (bulan) - Waktu
:
- Realisasi PenyerapanTA-2014
:
:
245,000,000
1 Loan - Tandatangan Loan tanggal 7 Mei 2012(ADB), 17 April 2012 (IDB), Loan Efektif tanggal 3 Juli 2012 (ADB), 2 Mei 2013 (IDB). 2 Civil Works
6,373,940.92
24 RCP-01A - Progres sampai saat ini sudah 23 %
21.20
- Pekerjaan yang sedang berjalan cut and File
4,446,830,128.00
- Dalam Penawaran Galian Rock tidak terpakai
- Diusulkan segera melakukan evaluasi mengingat waktu yang ada dan kemajuan fisik dilapangan cenderung menurun - CTC akan membuat surat ke DSC
- Blowsting kenyataan dilapangan non blowsting - Quarry batu belum jelas dan belum disurvey - Stone Crusher belum dimobilisasi - AMP belum dimobilisasi - Kemajuan fisik perbulan kurang dari 1 % - Dengan sisa waktu kontrak yang ada sudah kritis - Agar segera dilaksanakan SCM - Review design belum diselesaikan - Info tambahan kontraktor menawar 68 % dari Owner Estimate, sehingga prediksi akan - merugi 30 RCP-03
- Mobilisasi AMP belum dilaksanakan - Survey Quarry batu baru dimulai
- CTC akan menyurati DSC untuk segera melakukan survey quarry dan koordinasi dengan Pihak Pemerintah setempat , perihal keberadaan
- Pekerjaan Box Cluvert sampai 20 titik belum dimulai
quarry di daerah hutan lindung dan mempercepat mobilisasi alat-alat
- Lokasi quarry batu di area hutan lindung sehingga dibutuhkan perizinana dengan pihak
yang dibutuhkan termasuk melaksanakan pekerjaan yang akan
terkait
memperlancar traffic seperti box culvert dan jembatan
- Tenaga Kerja dan bahan material masih sangat minim 34 RCP-03
- SPMK belum turun
- Kontraktor saat ini sedang memproses serta menyerahkan
- Uang Muka (Advance Payment) belum bisa ditagih
jaminan uang muka
- Pekerjaan dilapangan baru Field Engineering - Lokasi bekerja diatas existing - Permasalahan utama kontraktor belum menyerahkan Jaminan - Progres fisik masih nihil 34 RCP-04
- SPMK belum turun
- Kontraktor saat ini sedang memproses serta menyerahkan
- Uang Muka (Advance Payment) belum bisa ditagih
jaminan uang muka - Segera melaksanakan LARAP yang dilaksanakan oleh CTC khusus khusus didaerah relokasi. Kondisi sekarang sedang dilaksanakan pengukuran setelah itu CTC akan segera ke lapangan.
- Kontraktor belum menyerahkan Jaminan Uang Muka - Terjadi relokasi sepanjang 18 km - Kegiatan masih pengukuran terutama dilokasi relokasi - Progres fisik masih nihil - Mobilisasi belum berjalan 3 Konsultan - TA untuk konsultan CSP 4 sd CSP 10 belum ada terkontrak - CTC belum mengajukan penarikan uang muka - DSC 1 Kalimantan belum mengajukan MC 1 sd MC 6 - DSC 3 Jawa Timur belum mengajukan MC 1 sd MC 10
-
Mempercepat proses kontrak Segera memproses penagihan Segera memproses penagihan Segera memproses penagihan
4 DIPA 2014 -
Alokasi PHLN untuk RKAKL 2014 sebesar Rp.534.468.867.000,-
-
Penyerapan yang masih rendah
- Harus segera melakukan penarikan
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 28-RCP01A (Jawa Timur)
D2. ACTIVITY STEPS
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROCUREMENT PROCESS
- Tanggal Kontrak
: 21 Agustus 2013
Prequalification
- Tanggal Persetujuan Peminjam
: 8 September 2013
By Person Responsible
1-Mar-12
27-Jun-12
- Periode Kontrak
: 730 hari Kalender
Loan Lender 's Approval
15-Mar-12
6-Feb-13
- Tanggal Akhir Kontrak
: 11 September 2015
- Nama kontraktor/konsultan/suplayer
: PT.Hutama Karya
Post Qualification By Person Responsible
24-Mar-12
1-Mar-13
30 Mei 201228Juni 2012
2 Mei 2013 4 Juni 2013
Loan Lender 's Approval Procurement Evaluation By Person Responsible Loan Lender 's Approval
D4. STATUS TERAKHIR
10-Jul-13 Status Kemajuan :
CONTRACT Signed Contract
Rencana : 14,226 % ; Actual : 23.026 % ; Deviasi : + 8.800%
21-Aug-13
Status Penyerapan : Rp. 22,392,959,448 (23.99%)
Approval from Bappenas (if necessary) Lenders Approval
Time Ellapse : 255 hari (34.93 %)
8-Sep-13
Advance Payment request
Slipage : 475 hari (65.07 %)
18-Sep-13
Advance Payment withdrawal
D5. DISBURSEMENT STATUS
Dalam Rupiah PENYERAPAN TA 2014
NILAI KONTRAK *)
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
93,350,000,000.00 23,011,025,595 546,937,650 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
1,164,447,900
Triwulan 3
-
2,355,687,250
Triwulan 4
-
7,162,465,450
TOTAL TA 2014
-
11,229,538,250.00
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP01 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
15-Juni-2012
- Periode Kontrak
:
25-Juni-2013
- Tanggal Akhir Kontrak
:
Oleh Penanggung Jawab Kegiatan
8-Apr-12
Persetujuan Pemberi Pinjaman
22-Apr-12
18-Sep-12 (Comment)
Undangan Lelang
- Nama kontraktor/konsultan/suplayer
30-Apr-12
1-May-14
5 Juli 2012-3 Sept 2012
10 Juli 2014-24 Agustus 2014
17-Sep-12
21-Sep-14
:
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
41,821,587,300
TOTAL TA 2014
-
41,821,587,300.00
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP02 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
15-Juni-2012
- Periode Kontrak
:
25-Juni-2013
- Tanggal Akhir Kontrak
:
Oleh Penanggung Jawab Kegiatan
8-Apr-12
Persetujuan Pemberi Pinjaman
22-Apr-12
18-Sep-12 (Comment)
Undangan Lelang
- Nama kontraktor/konsultan/suplayer
30-Apr-12
1-May-14
5 Juli 2012-3 Sept 2012
10 Juli 2014-24 Agustus 2014
17-Sep-12
21-Sep-14
26-Sep-12
7-Okt-2014
:
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
Dalam Rupiah PENYERAPAN TA 2014
NILAI KONTRAK *)
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
25,717,998,895
TOTAL TA 2014
-
25,717,998,895.47
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP03(Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
:
Pasca Kualifikasi Undangan Lelang
24-Jan-14
Persetujuan Pemberi Pinjaman
1-May-14 25-Apr-14
Evaluasi Pengadaan 10 Juli 2014-24 Agustus 2014
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
21-Sep-14
KONTRAK Tandatangan Kontrak
7-Okt-2014
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
10,716,725,250
TOTAL TA 2014
-
10,716,725,250.00
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP01 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
:
Pasca Kualifikasi Undangan Lelang
23-Apr-12
26-Feb-13
29 Juni 2012 27 Agust 2012
21 Mei 2013 - 11 Sep 2013 11-Okt-2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
Catatan : Proses Usulan untuk Tender Ulang KONTRAK Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
Triwulan 1
Triwulan 2
Triwulan 3
Triwulan 4
TOTAL TA 2014 Realisasi (p) -
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP02 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 14 November 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 28 November 2013
Oleh Penanggung Jawab Kegiatan
31-Mar-12
27-Jun-12
- Periode Kontrak
: 1.095 hari kalender
Persetujuan Pemberi Pinjaman
14-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 29 November 2016
- Nama kontraktor/konsultan/suplayer
: PT.Brantas Abipraya (persero)- PT. Citra Persada PT. Trifa Abadi, JO
Pasca Kualifikasi Undangan Lelang
23-Apr-12
26-Feb-13
29 Juni 2012 27 Agust 2012
23 Mei 2013 - 28 Agust 2013 13-Sep-13
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
Status Kemajuan :
14-Nov-13
Rencana : 2.371 % ; Actual : 3.898 % ; Deviasi : + 1.527 %
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
28-Nov-13
Permintaan Uang Muka
28-Nov-13
Status Penyerapan : Rp. 48.746.605.665 (16.66%) Time Ellapse : 195 hari (17.8 %) Slipage : 900 hari (82.19 %)
Penarikan Uang Muka
D5. STATUS PENYERAPAN
Dalam Rupiah PENYERAPAN TA 2014
NILAI KONTRAK *)
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
292,603,385,000.00 43,890,507,750 614,467,109 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
4,219,340,812
Triwulan 3
3,090,244,128.00
9,810,991,499
Triwulan 4
-
11,490,534,929
TOTAL TA 2014
-
26,135,334,348.20
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP03 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 26 November 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 29 November 2013
Oleh Penanggung Jawab Kegiatan
31-Mar-12
27-Jun-12
- Periode Kontrak
: 1.095 hari kalender
Persetujuan Pemberi Pinjaman
14-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
: 2 Desember 2016 : PT.Waskita Karya (persero), - PT. Yasa Patria Perkasa, JO
23-Apr-12
26-Feb-13
29 Juni 2012 27 Agust 2012
24 Mei 2013 -5 Sep 2013 12-Oct-13
Pasca Kualifikasi Undangan Lelang Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
Status Kemajuan :
26-Nov-13
Rencana : 4,206 % ; Actual : 4,016 % ; Deviasi : - 0.190 %
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
29-Nov-13
Permintaan Uang Muka
29-Nov-13
Status Penyerapan : Rp. 35,846,245,950 (15%) Time Ellapse : 208 hari (18.99 %) Slipage : 917 hari (81 %)
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
(f)
(g)
Triwulan 1
238,974,973,000.00 35,846,245,950 501,847,443 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
Triwulan 3
Triwulan 4
TOTAL TA 2014
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
3,446,019,111
-
8,012,830,845
-
7,711,722,379
-
19,672,419,777.36
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes)
D1. PAKET KONTRAK : 34-RCP01 (Kalimantan Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
: :
Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
Comment ADB 4 Mar 2014,
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
Klarifikasi -
4 -Okt-2012
KONTRAK Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
24,127,254,199
TOTAL TA 2014
-
24,127,254,198.93
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP02 (Kalimantan Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 25 Juni 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 730 Hari
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
: 24 Juni 2014 : PT.Brantas Abipraya - PT.Mahir Jaya Mahakam Raya, J.O
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013 9 Maret 2014, Proses persetujuan Mentri
Pasca Kualifikasi Undangan Lelang Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
Persetujuan Pemberi Pinjaman
4 -Okt-2012
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
Periode Konstruksi : 730 hari
25-Jun-14
Status Penyerapan : belum menarik Uang Muka
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
165,332,328,425.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
19,674,548,222
TOTAL TA 2014
-
19,674,548,222.00
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP03 (Kalimantan Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 11 April 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 Mei 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 900 Hari Kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
: 27 September 2015 : PT.Pembangunan Perumahan (Persero) Tbk PT.Perdasa,JO
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
4 -Okt-2012
11-Des-2013
Pasca Kualifikasi Undangan Lelang Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK Periode Konstruksi : 900 hari Tandatangan Kontrak
11-Apr-14 Status Penyerapan : belum menarik Uang Muka
Persetujuan oleh Bappenas (bila diperlukan)
Proses Penerbitan Jaminan Uang Muka oleh Kontraktor
Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
289,000,000,000.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
32,185,930,000
Triwulan 4
-
-
TOTAL TA 2014
-
32,185,930,000.00
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP04 (Kalimantan Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 11 April 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 May 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 1095 Hari Kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 10 April 2017 : Halla Corporation
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
4 -Okt-2012
11-Des-2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK Periode Konstruksi : 1.095 hari Tandatangan Kontrak
11-Apr-14 Status Penyerapan : belum menarik Uang Muka
Persetujuan oleh Bappenas (bila diperlukan)
Proses Penerbitan Jaminan Uang Muka oleh Kontraktor
Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
359,652,598,000.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
39,676,885,643
Triwulan 4
-
4,204,340,040
TOTAL TA 2014
-
43,881,225,682.98
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Core Team Consultant (CTC)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 12 Februari 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 24 Februari 2014
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
: Renardet SA in JV with
Pasca Kualifikasi
PT. Widya Graha Asana
Undangan Lelang
PT. Multy Phibeta
Persetujuan Pemberi Pinjaman
PT.Anugerah Kridapradana PT. Disiplan Consult
Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
Belum melakukan penarikan Uang Muka dikarenakan belum siapnya garansi Bank
KONTRAK Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
5,806,675,050.00
Triwulan 4
-
1,583,638,650.00
TOTAL TA 2014
-
7,390,313,700.00
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : DSC-1 Kalimantan
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
16 Oktober 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
07 Nopember 2013
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
: CECI Engineriing
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang
26-Feb-13
Persetujuan Pemberi Pinjaman
0-Jan-00
Evaluasi Pengadaan 24 Mei 2013 5 Sep 2013
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
12-Oct-13
KONTRAK Tandatangan Kontrak
26-Nov-13
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
29-Nov-13
Permintaan Uang Muka
20-Jan-14
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
1,238,622,000.00
2,412,421,320.00
Triwulan 1
30,384,233,888.00 2,412,421,320.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
Triwulan 3
-
2,412,421,320.00
Triwulan 4
-
1,809,315,990.00
TOTAL TA 2014
-
9,046,579,950.00
Realisasi (p) 1,238,622,000.00
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : DSC-2 Jawa Tengah
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Juni 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
16 Oktober 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
07 Nopember 2013
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
: CECI Engineriing
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang
26-Feb-13
Persetujuan Pemberi Pinjaman
0-Jan-00
Evaluasi Pengadaan 24 Mei 2013 5 Sep 2013
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
12-Oct-13
Sudah dilakukan penarikan Uang Muka tanggal ..........2013
KONTRAK Tandatangan Kontrak
26-Nov-13
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
29-Nov-13
Permintaan Uang Muka
20-Jan-14
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
535,500,000.00
Triwulan 4
-
126,000,000.00
TOTAL TA 2014
-
661,500,000.00
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : DSC-3 Jawa Timur
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
Prakualifikasi
- Tanggal Persetujuan Peminjam
16 Oktober 2013 07 Nopember 2013
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
: : PT. Perentjana Djaya
Pasca Kualifikasi Undangan Lelang
26-Feb-13
Persetujuan Pemberi Pinjaman
0-Jan-00
Evaluasi Pengadaan 24 Mei 2013 5 Sep 2013
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
12-Oct-13
Sudah dilakukan penarikan Uang Muka tanggal ..........2013
KONTRAK Tandatangan Kontrak
26-Nov-13
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
29-Nov-13
Permintaan Uang Muka
9-Dec-13
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
7,633,945,000.00 1,040,992,500.00 687,051,000.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
687,051,000.00
Triwulan 3
-
687,051,000.00
Triwulan 4
-
458,034,000.00
TOTAL TA 2014
-
2,519,187,000.00
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
FORMULIR E : DETAILS OF THE BUDGET Nomer NPPHLN :
ADB 2817-INO, Register : 10846401 IDB 0161-IND, Register : 10848804 PLN
Rupiah ( dalam juta) Dana Pendamping
Nama Kegiatan dan Nomor Kode DIPA
Valas
(a)
Rupiah Murni
Rupiah Ekivalen (juta)
(b)
Rencana Penarikan PLN 2014
Pagu
Realisasi
Pagu
Realisasi
( Juta Rupiah )
(c)
(d)
(e)
(f)
(g)
(h)
Nomor DIPA : Kegiatan : Civil Works Jawa Tengah 1
24-RCP-01
Tambakmulyo - Wawar
USD
3,708.13
42,643.5
8,474.00
-
29,275.11
2
24-RCP-02
Giriwoyo - Duwet
USD
3,050.72
35,083.3
11,375.04
-
18,002.60
3
24-RCP-03
Wawar - Congot
USD
3,236.48
37,219.5
5,699.00
-
7,501.71
Jolosutro - Sendang biru
USD
2,244.66
25,813.6
21,000.00
-
7,860.68
Jawa Timur 4
28-RCP01A Kalimantan
5
30-RCP01
Sosok - Tayan Tanjung- Bts. Kota Sanggau
6
30-RCP02
USD
-
-
39,913.12
-
-
Bypass Sambas (TANAH HITAM /TANJUNG HARAPAN - SAMBAS)
USD
3,702.48
42,578.5
18,247.89
Galing - Tanjung Harapan 7
30-RCP03
34-RCP01
18,294.73 -
Simpang Tanjung - Galing Simpang Aruk /Bts. Serawak-Simpang 3 Tanjung
8
-
Tebas - Singkawang Sec.1 + Sec.2
USD
1,808.10
20,793.2
8,911.37
13,770.69 -
Tanjung Selor- SP.3 Tanjung Palas - Sekatak Buji (Sec.1) USD
5,018.39
57,711.5
39,155.94
-
16,889.08
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
PLN
Rupiah ( dalam juta) Dana Pendamping
Nama Kegiatan dan Nomor Kode DIPA
Rupiah Murni
Rupiah Ekivalen (juta)
Valas
Pagu
Realisasi
Pagu
Realisasi
Rencana Penarikan PLN 2014 ( Juta Rupiah )
9
34-RCP02
Tanjung Palas -Sekatak Buji (Sec.2)
USD
4,050.00
46,575.0
39,286.15
-
13,772.18
10
34-RCP03
SP.Tiga Apas - Simanggaris (Section 1)
USD
4,148.14
47,703.6
51,470.79
-
29,610.65
11
34-RCP04
SP. Tiga Apas - Simanggaris - Bts. Negara (Serudong)
USD
4,787.86
55,060.4
40,422.36
-
30,716.86
Consultant Services DG Bina Marga , KemenPU 1
CSP-1
Core Team Consultant
USD
495.65
5,700.00
-
-
7,390.31
2
CSP-2
DSC-1 (ADB-Kalimantan)
USD
1,120.00
12,880.00
-
-
9,046.58
3
CSP-11
DSC-2 (IDB - Jawa Tengah)
USD
620.11
7,131.25
-
-
661.50
4
CSP-3
DSC-3 (ADB-Jawa Timur)
USD
304.35
3,500.00
-
-
2,519.19
5
CSP-10
HIV /AIDS and Anti Trafficking Program
USD
16.96
195.00
-
-
-
6
CSP-4
Road Saftey Engineering Support
USD
65.22
750.00
-
-
-
USD
38,377.24
441,338.27
TOTAL Asumsi APBN 2014: 1 USD = Rp.10,500
283,955.65
205,311.87
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 1 Regional Roads Development Project (RRDP) The Overall Financial Status as of 30 June 2014 ADB Loan No.2817-INO & IDB Financing No.IND-0161 1 USD = IDR 9,000 Loan Cat
in US$ 000's
Details of Category
ADB
1
2
1
Civil Works
2
Goods : Road Safety Equipment
3
Consultant Services 3A 3B 3K
3C 3D 3E
3F 3G 3H 3I 3J 4
Original Loan Allocation IDB
3a
3b
155,000.0
Core Team Consultant Design and Supervision Kalimantan Region Construction Supervision - Central Java Region Design and Supervision East Java Region Road Safety Support Institutional Development for Road Network Management Road safety awareness campaign and training Overloading and Speed Enforcement Indonesia Transport Sector Development Strategy and Policy Study Integrated Vehicle Overloading Control Strategy HIV/AiDS and Anti Trafficking Prevention Program Unallocated
1 USD = IDR 11,500
IDB
4a
53,500.0
4b
76,769.6
0.00
ADB
Current Quarter IDB
ADB
5a = (3a-4a) 5b = (3b-4b)
78,230.4
53,500.0
IDB
6a
6b
266.98
Disbursement Year to Date ADB
7a
Cummulative to Date
IDB
ADB
7b
266.98
8a
-
Projected Loan Balance
5,676.27
IDB
%=(8a /4a) 7.39
%=(8b/ 4b)
8b
-
-
ADB
IDB
9a=(3a-4a)
9b=(3b-4b)
78,230.4
53,500.0
-
-
-
1,300.0
-
-
0.00
1,300.0
0.0
6,000.0
-
2,809.2
-
3,190.8
-
-
0.00
3,190.8
0.0
5,300.0
-
3,451.1
-
1,848.9
-
-
1,848.9
0.0
-
3,000.0
0.0
3,000.0
325.7
0.0
0.00
400.0
0.0
0.00
900.0
0.0
0.00
3,000.0
0.0
0.00
2,200.0
0.0
0.00
1,300.0
0.0
0.00
800.0
0.0
0.00
300.0
0.0
0.00
2,600.0
8,500.0
900.0
-
400.0
0.00 574.3
-
0.0
3,000.0
325.7
-
-
400.0
-
900.0
-
900.0
-
3,000.0
-
3,000.0
-
2,200.0
-
2,200.0
-
1,300.0
-
1,300.0
-
800.0
-
800.0
-
300.0
-
300.0
-
180,000.0
Assumption to Government Budget in FY 2014
ADB
Current Balance
1,300.0
2,600.0
TOTAL
Awarded Contracts
8,500.0
65,000.0
2,600.0
83,604.2
0.0
96,395.8
8,500.0
65,000.0
117.98
615.69
-
-
0.00
-
80.32
-
266.98
17.84
0.00
384.96
0.00
6,372.28
13.98
7.62
-
-
96,395.81
65,000.00
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 2 Procurement Plan Regional Roads Development Project ( RRDP ) as of June 2014 CIVIL WORKS No.
Sub - Project
Bidding Docum ents Province
Procurem ent Method
Prior/Post Review
Contracted Am ount (Including Tax) USD
Bidding Docum ent Package No.
IDR (x1000)
Subm itted Date
NOL Date
Bid Opening Date
01-Mar-13
15-Mar-13
29-May-13
Bid Evaluation Report Request Date
Appr'd /NOL Date
28-Jun-13
12-Jul-13
Contract Signature Date
CP / DP Supplier/ Contractor Nam e
Contract
No.
Com pletion Date (PHO)
(days)
Group - 1 4 5
6
7 8 9 10 11
Jolosutro - Sendangbiru Sosok -Tayan, Tanjung - Bts.kota Sanggau Tebas - Singkawang (Section 1); Tebas -Singkawang (Section 2) Bypass Sambas Galing Tanjung Harapan Sp. Tanjung - Galing; Aruk (bts.Serawak - Sp.Tanjung Tanjung Selor - Sp.3 Tanjung Palas; Sp.3 Tj.Palas - Sekatakbuji (section 1) Sp.3 Tanjung Palas - Sekatak Buji (Section 2) Sp. Tiga Apas - Simanggaris (Section 1) Sp. Tiga Apas - Simanggaris (Section 2); Simanggaris - bts.negara
1
Tambakmulyo - Wawar
2
Giriwoyo - Duwet (Section 1)
3
Wawar - Congot (post qualification)
East Java
ICB
Prior
West Kalimantan
ICB
Prior
ICB
Prior
292,603,385
30-RCP02
27-Jun-12
06-Feb-13
22-May-13
ICB
Prior
217,249,975
30-RCP03
27-Jun-12
06-Feb-13
ICB
Prior
34-RCP01
27-Jun-12
06-Feb-13
ICB
Prior
165,332,338
34-RCP02
27-Jun-12
ICB
Prior
238,974,973
34-RCP03
ICB
Prior
359,652,697
ICB ICB ICB
West Kalimantan
East Kalimantan
Central Java
93,350,000
28-RCP01A
21-Aug-13 PT Hutama Karya
01-28-RCP-01A/RB/ADB/2817/0813
Proposed for Retender
30-RCP01
730 1095
PT.Brantas Abipraya-Tri Citra Perdana-Trifa Abadi, JO
28-Aug-13
13-Sep-13
14-Nov-13
23-May-13
5-Sep-13
12-Oct-13
27-Nov-13 PT Waskita Karya - Yasa Patria Perkasa, JO
13-Jun-13
10-Sep-13
06-Feb-13
13-Jun-13
10-Sep-13
4-Mar-14
27-Jun-12
06-Feb-13
13-Jun-13
10-Sep-13
11-Dec-13
34-RCP04
27-Jun-12
06-Feb-13
13-Jun-13
10-Sep-13
11-Dec-13
Prior
24-RCP01
15-Jun-13
30-Apr-14
Prior
24-RCP02
15-Jun-13
30-Apr-14
Prior
24-RCP03
15-Jun-13
30-Apr-14
NOL DATE Short List
NOL for T ER
Prop.Negotiated Draft Contract
Contract Sign
Service Start Date
Time Elapsed
02-30-RCP-02/RB/ADB/2817/1113
1095
03-30-RCP-02/RB/ADB/2817/1113
1095
Revision Of BER PT.Brantas Abipraya -Mahir Jaya Mahakam Raya- JO PT.Pembangunan perumahan - Perdasa11-Apr-14 JO
25-Jun-14
730 02-34-RCP/LOAN/PJN.III/06.14
730
03-34-RCP/LOAN/PJN.III/04.14
900
04-34-RCP/LOAN/PJN.III/04.14
1095
Consultant Name
Contract No.
Period (Months)
11-Apr-14 Halla Corporation
1,367,163,368
CONSULTANT SERVICES NO
Sub - Project
Contract Value
Procurem ent Method
Prior/Post Review
Jakarta
QCBS
Prior
1,192,400
19,472,500
DGH
29-Jan-13
18-Sep-13
22-Jan-14
12-Feb-14
3-Mar-14
3.90
Renardet SA. With JV
03-02/CTC/PM/LN/ADB/2817/0214
46
South Kalimanatan
QCBS
Prior
936,570
30,372,995
DGH
7-Dec-13
20-Jun-13
7-Nov-13
21-Nov-13
16-Dec-13
6.60
CECI with JV
01/DSC-1/CS/ADB/2817/1113
33
East java
QCBS
Prior
0
6,939,959
DGH
7-Dec-13
29-May-13
8-Oct-13
16-Oct-13
20-Jan-14
8.30
PT. Perentjana Jaya
01/DSC-3/CS/ADB/2817/1013
25
Province
(Excluding Tax) USD
IDR (x1000)
Responsible Agency
1
Core Team Consultant
2
Design and Supervision Consultant 1 (DSC-1)
3
Design and Supervision Consultant (DSC-3)
4
Road Safety Support
QCBS
5
Institutional Development for Road Network Management
QCBS
DGH
6
Road Safety Awareness Campaign and Training
QCBS
DGLT
7
Overloading and Speed Enforcement
QCBS
DGNTP
8
Indonesia Transport Sector Development Strategy and Policy Study
QCBS
Bappenas
9
Integrated Vehicle Overloading Control Strategy
10
HIV/AIDS and Anti Trafficking Program
DGH
DGLT DGH
INDIVIDUAL CURRENCY TOTAL GRAND TOTAL in US$
2,128,970
56,785,454
Note: CP = Construction Period
2,128,970
1,423,948,822
DP = Delivery Period
$144,523,852 1US$ = 10,000 Rp.
On Going
N.A. = Not Applicable
Remarks
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 3 Regional Roads Development Project (RRDP) Progress And Cost Monitoring For Civil Works Status : June 2014 Estimated Cost Contract Description Type of Works IDR (x106)
No.
Contract No.
4
01-28-RCP01A/RB/ADB/2817/0813
Jolosutro - Bale kambang Reconstruction Sendang biru
6
02-30-RCP02/RB/ADB/2817/1113
Tebas - Singkawang (Section 1); Tebas Singkawang (Section 2) Bypass Sambas
7
03-30-RCP02/RB/ADB/2817/1113
9
Contractor
Contract Price (IDR 10⁶) ADB Including Tax Contract Sign Category Procurement Financing Date Method Original Addendum Ratio (%)
Cost During this Quarter (IDR) Actual
Planned
Cummulative Cost (IDR)
ADB Share Actual as % of Planned
To Last Quarter
Actual to date Total ADB Share
Physical Progress % Planned to date
Actual as % Scheduled of Planned
Actual
Difference
New Road
151,916.793
PT.Hutama Karya
21-Aug-13
Civil Works
ICB
93,350,000
70.00
0
-9,689,980,595
0
0.00
23,011,025,595
23,011,025,595
14,250,065,103
13,321,045,000
173
14.27
23.03
8.76
Reconstruction PT.Brantas Abipraya-Tri Citra Perdana430,578.648 Trifa Abadi, JO Resurfacing
14-Nov-13
Civil Works
ICB
292,603,385
70.00
10,809,016,100
6,934,700,224
7,566,311,270
155.87
43,890,507,750
54,699,523,851
34,808,787,905
50,825,207,975
108
2.37
3.90
1.53
Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
Reconst + PT Waskita Karya - Yasa Patria 333,214.553 widening Perkasa, JO Reconstruction
27-Nov-13
Civil Works
ICB
238,974,973
70.00
0
10,060,846,363
0
0.00
35,846,245,950
35,846,245,950
22,811,247,423
45,907,092,313
78
4.21
4.02
-0.19
02-34-RCP/LOAN/PJN.III/06.14
Sp.3 Tanjung Palas Sekatak Buji (Section 2)
Reconstruction PT.Brantas Abipraya -Mahir Jaya Grade 215,483.495 Mahakam Raya- JO Improvement
25-Jun-14
Civil Works
ICB
165,332,338
70.00
0
0
0
0.00
0
0
0
0
0
0.00
0.00
0.00
10
03-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis Reconstruction (Sect 1) Resurfacing
11-Apr-14
Civil Works
ICB
289,000,000
70.00
0
0
0
0.00
0
0
0
0
0
0.00
0.00
0.00
11
04-34-RCP/LOAN/PJN.III/04.14 (Sect 2); Simanggaris -
11-Apr-14
Civil Works
ICB
359,652,697
70.00
0
-
-
0
0
0
Resurfacing
SP.3 Apas - Simaranggis Bts.Negara
322,919.917 PT.Pemb. Perumahan- PT.Perdasa JO
Reconstruction 407,483.774 Halla Corporation Resurfacing
TOTAL
1,438,913,393
10,809,016,100 7,305,565,992 7,566,311,270
102,747,779,296 113,556,795,396
71,870,100,431
-
110,053,345,288
-
-
-
-
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 4 Details of Variation Orders To End June 2014 Package Name
Jolosutro - Bale kambang Sendang biru
Package Original Contract Design Review No. value (Rp.) (Rp.)
28-RCP01A
93,350,000,000.00
Tebas - Singkawang (Section 1); Tebas -Singkawang (Section 2) Bypass Sambas Galing - Tanjung Harapan
30-RCP02
292,603,385,000.00
Sp. Tanjung - Galing; Aruk (bts.Serawak - Sp.Tanjung
30-RCP03
217,249,975,454.55
Design Review %
Prie Escalation
Escalation %
Total Current Total Current Modified Contract Modified % Price (Rp.)
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 5 REGIONAL ROAD DEVELOPMENT PROJECT (RRDP) SUMMARY OF CONTRACT DATA
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix No. 6 Summary of Unsettled Complaints As of June 2014 No.
Complainant
Recipient of complaints
RRDP Package
Media of complaint
Category of complaint
Complaint Issue
Date of complaint
Date received by PMU/CTC
Date of response
Responded by
1.
Proposed Response
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 7a CROs Activities on RRDP June 2014 No
4
6
7
8
9
10
11
Province
EAST JAVA
Package Observed JolosutroSendangbiru
WEST Tebas-Singkawang KALIMANTA (Section1 &2) N Bypass Sambas Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
Package Number
SP.3 Apas Simaranggis (Sect 2); Simanggaris Bts.Negara
CROs Involvement in the Bidding Date of Bid Announcement Opening Date of Bid Winner
28-RCP01A
1-Mar-13
1-May-13
18-Aug-13
30-RCP02
26-Feb-13
22-May-13
19-Oct-13
30-RCP02
EAST KALIMANTA Tj.Selor- Sp.3Tj. Palas 34-RCP01 N Sp.3 Tanjung Palas Sekatak Buji (Section 1) Sp.3 Tanjung Palas Sekatak Buji (Section 34-RCP02 2)
SP.3 Apas Simaranggis (Sect 1)
Date of Invitation to Bid
34-RCP03
34-RCP04
26-Feb-13
11-Mar-13
11-Mar-13
11-Mar-13
11-Mar-13
23-May-13
13-Jun-13
13-Jun-13
13-Jun-13
13-Jun-13
12-Nov-13
Not Yet
4-May-14
10-Feb-14
6-Feb-14
Selected CRO Reports of CRO Activity · Process Verbal of the CRO selection for RRDP package of JolosutroSendangbiru, East Java SNVT of Roads and Bridge Development, May 2013 · · Process Verbal of the CRO selection for RRDP package of Tebas Singkawang, West Kalimantan SNVT of Roads and Bridge Development, February 2013 · · Process Verbal of the CRO selection for RRDP package of Sp.Tanjung Galing, West Kalimantan SNVT of Roads and Bridge Development, February 2013 · Process Verbal of the CRO selection for RRDP package of Tj.selor - Sp.3 Tanjung Palas, East Kalimantan SNVT of Roads and Bridge Development, June 2013
· Process Verbal of the CRO selection for RRDP package of Sp.3 Tanjung Palas - sekatak buji (serction 2), East Kalimantan SNVT of Roads and Bridge Development, June 2013 · Process Verbal of the CRO selection for RRDP package of Sp.3 Apas Simanggaris (serction 1), East Kalimantan SNVT of Roads and Bridge Development, June 2013 · · Process Verbal of the CRO selection for RRDP package of Sp.3 Apas Simanggaris (serction 2) and Simanggaris - bts Negara, East Kalimantan SNVT of Roads and Bridge Development, June 2013 ·
Name
Ikrar Chandra Bachtiar, SKM
Address
Tanjung Pura University
Lydia Gusti Resanika ,SE Ikrar Chandra Bachtiar, SKM
Tanjung Pura University
Telephone
Email
NA
NA
NA
NA
NA
NA
NA
NA
Lydia Gusti Resanika ,SE University Mulawarman Rahayu Widasari Ulfatu Munawaroh
Rahayu Widasari Ulfatu Munawaroh
Rahayu Widasari Ulfatu Munawaroh
University Mulawarman
University Mulawarman NA
Rahayu Widasari Ulfatu Munawaroh
University Mulawarman
NA
NA
NA NM/11-09-2010/CRO Activities on SRIP
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 7b Status of CRO Reports Status of Bidding Process No
RRDP Packages
4
Jolosutro - Sendangbiru (East Java)
5
Sosok - Tayan ; Tanjung - Batas Kota Sangga
6
Tebas - Singkawang (Section 1 &2); Bypass Sambas ; Galing - Tanjung Harapan
7
Province
East Java
(BO)
Bid Winner (BW) announcement
1-May-13
27-Jul-13
Bid Opening
June 2014 Report Submission Remarks
OK
Complete report of bid opening and bid winner announcement. Retender
22-May-13
19-Oct-13
OK
Complete report of bid opening and bid winner announcement.
Sp.Tanjung - Galing ; Aruk - Batas Serawak
15-Jun-13
12-Nov-13
OK
Complete report of bid opening and bid winner announcement.
8
Tj.Selor - Sp.3 Tanjung Palas (Section 1)
13-Jun-13
9
Tj.Selor - Sp.3 Tanjung Palas (Section 2)
13-Jun-13
4-Jun-14
OK
Complete report of bid opening and bid winner announcement.
West Kalimantan
Revision of BER
East Kalimantan 10
Sp.3 Apas - Simaggaris (Section 1)
22-Oct-07
6-Feb-14
OK
Complete report of bid opening and bid winner announcement.
11
Sp.3 Apas - Simaggaris (Section 2); Simanggaris - Bts Negara
13-Jun-13
6-Feb-14
OK
Complete report of bid opening and bid winner announcement.
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 8 Environmental Management and Monitoring Plan (EMP) Compliance on Regional Roads Development Project (RRDP) As June2014 Contractor Performance on EMP No.
Package No.
Project Name
Length (Km)
Contractor
Contract Reference
Contract Description
Document Availability
Awareness & Readiness to EMP
Base Camp
Waste Management
Material Handling
Pollution Control Measures
Traffic Management
Landscaping/ Reforestation
Total Score Obtained
Ranking (%)
Remarks Level
EAST JAVA
1
28-RCP01 (CW-01) Jolosutro - Sendang biru
21.30
PT. Hutama Karya
01/28-RCP-01A/RB/ADB/2817/0813
Being monitored during construction
New Road Construction incl. raising grade and New Bridge Construction
CENTRAL JAVA Widening, Resurfacing and New Bridge Construction New Road Construction, Widening and New Bridge Construction
2
24-RCP01 (CW-02) Tambak Mulyo – Wawar
38.46
-
-
3
24-RCP02 (CW-03) Giriwoyo - Duwet (Section-1)
23.75
-
-
4
24-RCP03 (CW-04) Wawar – Congot
14.13
-
-
Widening and Resurfacing
79.20
-
-
Reconstruction and Resurfacing (Direct Overlay)
01/30-RCP-03/RB/ADB/2817/1113
Reconstruction, Resurfacing and Widening
WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05) Tanjung-Batas Kota Sanggau
6
Tebas - Singkawang (Section-1);
PT. Brantas Abipraya
Tebas - Singkawang (Section-2);
PT. Tricitra Perdana
30-RCP02 (CW-06)
55.97 Bypass Sambas;
Being monitored during construction
PT. Trifa Abadi JO
Galing-Tanjung Harapan; Sp.Tanjung-Galing (Section-1); 7
30-RCP03 (CW-07) Sp.Tanjung-Galing (Section-2);
Being monitored during construction
PT. Waskita Karya (Persero) 52.04
PT. Yasa Patria Perkasa JO
02/30-RCP-03/RB/ADB/2817/1113
New Road Construction incl. raising grade and Reconstruction
34.82
-
-
New Road Construction incl. raising grade and Reconstruction
Aruk (Bts.Serawak)-Sp. Tanjung EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08) SP. 3 Tanjung Palas - Sekatak Buji (Secton-1) 34-RCP02 (CW-09) SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
65.03
-
-
Grade Improvement and Resurfacing
10
9
34-RCP03 (CW-10) SP.3 Apas - Simaranggis (Section- 1)
45.00
-
-
New Road Construction incl. raising grade and Reconstruction
11
34-RCP04 (CW-11)
43.04
-
-
Widening and Reconstruction
Being monitored during construction Being monitored during construction
Being monitored during construction
SP.3 Apas - Simaranggis (Section-2) Simanggaris-Bts Negara (Serudong)
Score
0
1
2
3
4
% Compliance
0-20
Scale
N.A.
Below Par
Mildly Satisfactory
Satisfactory
Good
Ranking
Below Par
20-40 Mildly Satisfactory
40-60
60-80
80-100
Satisfactory
Good
Excellent
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 9 Status of Social Safeguard Studies on Regional Roads Development Project (RRDP) As June 2014 No.
Package No.
Length (Km)
District
Type of Works
Safeguard Document
Jolosutro - Sendang biru
21.30
Malang
New Road Construction incl. raising grade and New Bridge Construction
LARP
LARP
LARP
Project Name
EAST JAVA 1
28-RCP01 (CW-01)
CENTRAL JAVA 2
24-RCP01 (CW-02)
Tambak Mulyo – Wawar
38.46
Kebumen
3
24-RCP02 (CW-03)
Giriwoyo - Duwet (Section-1)
23.75
Wonogiri
4
24-RCP03 (CW-04)
Wawar – Congot
14.13
Purworejo
Widening, Resurfacing and New Bridge Construction New Road Construction, Widening and New Bridge Construction Widening and Resurfacing
79.20
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
WEST KALIMANTAN 5
6
7
30-RCP01 (CW-05)
30-RCP02 (CW-06)
30-RCP03 (CW-07)
Sosok - Tayan; Tanjung-Batas Kota Sanggau Tebas - Singkawang (Section-1); Tebas - Singkawang (Section-2); Bypass Sambas; Galing-Tanjung Harapan; Sp.Tanjung-Galing (Section-1); Sp.Tanjung-Galing (Section-2);
55.97
Singkawang & Sambas
Reconstruction, Resurfacing and Widening
Sambas LARP 52.04
Sambas
New Road Construction incl. raising grade and Reconstruction
34.82
Bulungan
New Road Construction incl. raising grade and Reconstruction
65.03
Bulungan
Grade Improvement and Resurfacing
45.00
Nunukan
New Road Construction incl. raising grade and Reconstruction
43.04
Nunukan
Widening and Reconstruction
Aruk (Bts.Serawak)-Sp. Tanjung EAST KALIMANTAN 8
34-RCP01 (CW-08)
9
34-RCP02 (CW-09)
10
34-RCP03 (CW-10)
11
34-RCP04 (CW-11)
Tanjung Selor - SP. 3 Tanjung Palas; SP. 3 Tanjung Palas - Sekatak Buji (Secton-1) SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2) SP.3 Apas - Simaranggis (Section- 1) SP.3 Apas - Simaranggis (Section-2) Simanggaris-Bts Negara (Serudong)
LARP
Possible for Updated LARP study related to relocation of road
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 10 Status of Monitoring of Environmental Mitigation on Regional Roads Development Project (RRDP) As June2014 No.
Package No.
Project Nam e
Length (Km )
District
Type of Works
Construction Status
Contract Date
2014
2013
28-RCP01 (CW-01) Jolosutro - Sendang biru
21.30
Malang
New Road Construction incl. raising grade and New Bridge Construction
OC
Start (COW)
Finish (PHO)
10
11
12
1
2
3
4
5
6
18-Oct-13
17-Oct-14
√
√
√
√
√
√
√
√X
√
CENTRAL JAVA 2
24-RCP01 (CW-02) Tambak Mulyo – Waw ar
38.46
Kebumen
Widening, Resurfacing and New Bridge Construction
-
-
-
3
24-RCP02 (CW-03) Giriw oyo - Duw et (Section-1)
23.75
Wonogiri
New Road Construction, Widening and New Bridge Construction
-
-
-
4
24-RCP03 (CW-04) Waw ar – Congot
14.13
Purw orejo
Widening and Resurfacing
-
-
-
79.20
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
-
-
-
Reconstruction, Resurfacing and Widening
OC
17-Dec-13
15-Dec-14
√
√
√
√
√
√X
√
√
√
√
√
√X
WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05) Tanjung-Batas Kota Sanggau Tebas - Singkaw ang (Section-1);
Singkaw ang & Sambas
Tebas - Singkaw ang (Section-2); 6
30-RCP02 (CW-06)
55.97 Bypass Sambas; Sambas Galing-Tanjung Harapan; Sp.Tanjung-Galing (Section-1);
7
30-RCP03 (CW-07) Sp.Tanjung-Galing (Section-2);
52.04
Sambas
New Road Construction incl. raising grade and Reconstruction
OC
4-Dec-13
2-Dec-14
34.82
Bulungan
New Road Construction incl. raising grade and Reconstruction
-
-
-
Aruk (Bts.Seraw ak)-Sp. Tanjung EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08) SP. 3 Tanjung Palas - Sekatak Buji (Secton-1) 34-RCP02 (CW-09) SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
65.03
Bulungan
Grade Improvement and Resurfacing
-
-
-
√
10
34-RCP03 (CW-10) SP.3 Apas - Simaranggis (Section- 1)
45.00
Nunukan
New Road Construction incl. raising grade and Reconstruction
-
-
-
√
11
34-RCP04 (CW-11)
43.04
Nunukan
Widening and Reconstruction
-
-
-
9
SP.3 Apas - Simaranggis (Section-2) Simanggaris-Bts Negara (Serudong)
Note: OC
= Ongoing Construction
IFB
= Invitation For Bid
CS
= Contract Sign
BER
= Bid Evaluation Report
RT
= Retender
AMDAL
= Environmental Impact Assessment
NY
= Not yet
UKL/UPL
= Environmental Management & Monitoring Plans
NR
= Not required
SOP's
= Standard Operating Procedure
PHO
= Provisional Hand Over
√
= Monitored by DSC
COW
= Commencement of Work
X
= Monitored by CTC
2016
Remarks
EAST JAVA
1
2015
√
√
√
7
8
9
10
11
12
1
2
3
4
5
6
7
8
9
10
11
12
1
2
3
4
5
6
7
8
9
10
11
12
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 11 Overall Land Acquisition Status on Regional Roads Development Project (RRDP) As June2014 No.
Total To Be Acquired (m2)
Total Acquired (m2)
Progress In %
Jolosutro - Sendang biru
1,481,400
1,481,400
100
Tambak Mulyo – Wawar Giriwoyo - Duwet (Section-1) Wawar – Congot
1,192,988 No LA No LA
1,192,988 NR NR
100 -
Sosok - Tayan;
No LA
NR
-
Tanjung-Batas Kota Sanggau
No LA
NR
-
Tebas - Singkawang (Section-1); Tebas - Singkawang (Section-2); Bypass Sambas; Galing-Tanjung Harapan; Sp.Tanjung-Galing (Section-1); Sp.Tanjung-Galing (Section-2); Aruk (Bts.Serawak)-Sp. Tanjung
286 3,543 No LA 130 No LA No LA 176
0 0 NR 0 NR NR 0
0 0 0 0
3,326
0
0
8,400
0
0
2,690,249
2,674,388
Package No.
Project Name
Remarks
EAST JAVA 1
28-RCP01 (CW-01)
Forest land affected is replaced by another with an area of land equivalent and are in the Bondowoso Regency
CENTRAL JAVA 2 3 4
24-RCP01 (CW-02) 24-RCP02 (CW-03) 24-RCP03 (CW-04)
WEST KALIMANTAN 5
30-RCP01 (CW-05)
6
30-RCP02 (CW-06)
7
30-RCP03 (CW-07)
Not required land acquisition because for the design need is in accordance with the existing ROW Not required land acquisition because for the design need is in accordance with the existing ROW
EAST KALIMANTAN 8
34-RCP01 (CW-08)
9 10
34-RCP02 (CW-09) 34-RCP03 (CW-10)
11
34-RCP04 (CW-11)
Tanjung Selor - SP. 3 Tanjung Palas; SP. 3 Tanjung Palas - Sekatak Buji (Secton-1) SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2) SP.3 Apas - Simaranggis (Section- 1) SP.3 Apas - Simaranggis (Section-2) Simanggaris-Bts Negara (Serudong) GRAND TOTAL
land area affected will be confirmed after the preparation of LARP
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 12 Environmental Safeguard on Regional Roads Development Project (RRDP) No.
Package No.
Length (Km)
District
Jolosutro - Sendang biru
21.30
Malang
Project Name
Type of Works
Safeguard Document
Construc. Status
Intial Environmental Examination (IEE)
Environmental
Approval by BLHD
OC
October 2011
AMDAL (A)
2009
-
October 2011
-
October 2011
-
October 2011
Environmental Management and Monitoring Plan (EMMP) or RKPPL
EAST JAVA 1
28-RCP01 (CW-01)
New Road Construction incl. raising grade and New Bridge Construction
Not Yet
CENTRAL JAVA 2
24-RCP01 (CW-02)
Tambak Mulyo – Wawar
38.46
Kebumen
3
24-RCP02 (CW-03)
Giriwoyo - Duwet (Section-1)
23.75
Wonogiri
4
24-RCP03 (CW-04)
Wawar – Congot
14.13
Purworejo
79.20
Sanggau
Widening, Resurfacing and New Bridge Construction New Road Construction, Widening and New Bridge Construction Widening and Resurfacing
Not Yet AMDAL (A)
5 October 2005
Not Yet Not Yet
WEST KALIMANTAN 5
6
7
30-RCP01 (CW-05)
30-RCP02 (CW-06)
30-RCP03 (CW-07)
Sosok - Tayan; Tanjung-Batas Kota Sanggau Tebas - Singkawang (Section-1); Tebas - Singkawang (Section-2); Bypass Sambas; Galing-Tanjung Harapan; Sp.Tanjung-Galing (Section-1); Sp.Tanjung-Galing (Section-2); Aruk (Bts.Serawak)-Sp. Tanjung
Singkawang & Sambas 55.97
Reconstruction and Resurfacing (Direct Overlay)
-
Sambas
UKL/UPL (B)
16 February 2011
Not Yet
October 2011
UKL/UPL (B)
16 February 2011
Not Yet
AMDAL (A)
18 February 2013
October 2011 Reconstruction, Resurfacing and Widening
OC
Sambas
52.04
October 2011
New Road Construction incl. raising grade and Reconstruction
OC
Not Yet
October 2011
Not Yet
October 2011
UKL/UPL (B)
16 February 2011
Not Yet
October 2011
UKL/UPL (B)
16 February 2011
Not Yet
October 2011
UKL/UPL (B)
13 January 2011
Not Yet
October 2011
UKL/UPL (B)
13 January 2011
Not Yet
October 2011
UKL/UPL (B)
13 January 2011
Not Yet
UKL/UPL (B)
20 December 2010
EAST KALIMANTAN 8
34-RCP01 (CW-08)
Tanjung Selor - SP. 3 Tanjung Palas; SP. 3 Tanjung Palas -
34.82
Bulungan
New Road Construction incl. raising grade and Reconstruction
-
October 2011 October 2011
Not Yet Not Yet
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
No.
Package No.
Project Name
Safeguard Document
Environmental Management and Monitoring Plan (EMMP) or RKPPL
Construc. Status
Intial Environmental Examination (IEE)
Grade Improvement and Resurfacing
-
October 2011
Nunukan
New Road Construction incl. raising grade and Reconstruction
-
October 2011
UKL/UPL (B)
14 August 2013
Not Yet
Widening and Reconstruction
October 2011
UKL/UPL (B)
13 January 2011
Not Yet
Nunukan
October 2011
UKL/UPL (B)
13 December 2010
Not Yet
Length (Km)
District
65.03
Bulungan
45.00
43.04
Type of Works
Environmental
Approval by BLHD
Sekatak Buji (Secton-1) 9
34-RCP02 (CW-09)
10
34-RCP03 (CW-10)
11
34-RCP04 (CW-11)
SP.3 Tanjung Palas Sekatak Buji (Sect ion2) SP.3 Apas Simaranggis (Section1) SP.3 Apas Simaranggis (Section-2) Simanggaris-Bts Negara (Serudong)
Note : OC- Ongoing Construction; CS - Contract Signed; RT- Retender; NY- Not Yet ; IFBInvitation For Bid; BER-Bid Evaluation Report
Not Yet
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 13 Regional Roads Development Project (RRDP) Construction Program Design
Procurement:
NOL Docs/Award:
Invite Bids:
NOL Re-bid:
Re-bid Period:
Sign Contract:
Commencemen of work
Ongoing Construction:
Pack. No.
As of June 2014 Package Number Contract
Location Phase
Code
J
EAST JAVA 4
Jolosutro- Sendangbiru
28-RCP01A
21.30
30-RCP01
79.20
WEST KALIMANTAN Tanjung - Batas
2012
Length, Kms
5
Sosok - Tayan kota Sanggau
6
Singkawang - Tebas Sambas Bypass Tanjung Harapan -Galing
30-RCP02
55.97
7
Sp.Tanjung - Galing Sp.Tanjung Aruk (bts Serawak
30-RCP03
52.04
1
Tambak Mulyo - Wawar
24-RCP01
38.46
2
Giriwoyo - Duwet (Section 1)
24 - RCP02
23.75
3
Wawar - Congot
24-RCP03
14.13
CENTRAL JAVA
EAST KALIMANTAN 8
Tanjung Selor - Sp.3 Tanjung Palas Sp.3 Tanjung Palas - Sekatak Buji
34-RCP01
34.82
9
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
34 - RCP02
65.03
10
SP.3 Apas - Simanggaris (Section 1)
34-RCP03
45.00
11
SP.3 Apas - Simanggaris (Section 2) Simanggaris - Bts.Negara
34-RCP04
43.04
F
M
A
M
J
J
2013 A
S
O
N
D
J
F
M
A M
J
J
2014 A
S
O
N
D
J
F
M
A M
J
J
2015 A
S
O
N
D
J
F
M
A M J
J
2016 A
S
O
N
D
J
F
M
A M
J
J
2017 A
S
O
N
D
J
F
M
A M
J
J
A
S
O
N
D
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
Appendix 14 Abbreviation and Acronyms ACAP AMDAL ANDAS ATMS Bappedalda BPK BPKP
CTC CSC-1 CSC-2 CW CHU DOP DGH DGLT DRBWR DTA DTP DFUR DGH EA EIA EIR EIRTP-2 ESAM EMP FMR FIDIC GOI HLRIP IA IBRD IT ISEM IVP IG IRSMS KPKN LARAP LARF MOF MHA MPW
Anti-Corruption Action Plan Environmental Management (Analisis Mengenai Dampak Lingkungan) Analisis Dampak Sosial Area Traffic Monitoring System Regional Environmental Impact Agencies Badan Pemeriksaan Keuangan (Audit Board of the Government of Indonesia) Badan Pengawasan Keuangan dan Pembangunan (Development Finance Comptroller, internal auditor of the Government of Indonesia) Core Team Consultant Construction Supervision Consultant for Non-metropolitan Roads Construction Supervision Consultant for Metropolitan Roads Civil Works Complaint Handling Unit Directorate of Planning Directorate General of Highways Directorate General of Land Transport Directorate Road and Bridge West Region Directorate of Technical Affairs Directorate of Traffic Police Directorate Freeway and Urban Road Directorate General of Highway Executing Agency Environmental Impact Assessment Eastern Indonesian Region Eastern Indonesia Regional Transport Project (Second Project) Environmental and Social Assessment Environmental Management Plan Financial Monitoring Report Federation Internationale des Ingenieur Conseils Government of Indonesia Heavy Loaded Road Improvement Project Implementation Agency International Bank for Reconstruction and Development Information Technology Institutional Strengthening in Environmental Management Isolated Vulnerable People Inspectorate General Integrated Road Safety Management System Kantor Perbendaharaan Keuangan Negara Land Acquisition and Resettlement (Rencana Tindak Pengadaan Tanah dan Pemukiman Kembali) Land Acquisition Resettlement Frame Work Ministry of Finance Ministry of Home Affairs Ministry of Public Works
PMU RRDP – Quarterly Progress Report No. 1 April - June 2014
MPR MOT NOL NRSC UKL/UPL OPRC PA PAS PMU PMR PBCC PBC PIP PIS PBC PAD PMM PMU PPR PVD QPR RBRF RFP RRSP RS-SC SBD SIA SIPP SLKLL SOP SURIP SRRP SRIP SPI SC Sub Dit Lingkungan TKPM TOR TRACER WB WP-1 WPs WPM WTP
Monthly Progress Report Ministry of Transportation No Objection Letter (from World Bank) National Road Safety Council Upaya Pengelolaan Lingkungan dan Upaya Pemantauan Lingkungan (Site Specific Environmental and Monitoring Plans) Output and Performance Based Road Contract Procurement Agent Procurement Advisory Services Project Management Unit Performance Monitoring Reporting Performance Based Contract Consultant Performance Based Contract Project Implementation Plan Project Implementation Schedule Performance Based Contract Project Appraisal Document Project Management Manual Project Management Unit (SRIP) Project Progress Report Pre fabricated Vertical Drainage Quarterly Progress Report Reforming Road Maintenance Management and Funding Request for Proposal Road Rehabilitation Sector Project Road Safety Steering Committee Standard Bidding Document Social Impact Assessment Sistem Informasi Pemantauan Proyek Traffic Accident Reporting System Application Standard Operating Procedure Strategic Urban Road Infrastructure Project Sumatera Region Roads Project Strategic Road Infrastructure Project Support Project Implementation Steering Committee (Tim Pengarah) Sub Directorate of Environmental Tim Penanganan Komplain Masyarakat – a Complaints Investigation Unit within Inspectorate General Terms of Reference Studi Penyelusuran Kembali World Bank Works Program – Year 1 Work Programs Wakil Pengamat Masyarakat Warga yang Terkena Proyek