REPUBLIC OF INDONESIA MINISTRY OF PUBLIC WORKS DIRECTORATE GENERAL OF HIGHWAY DIRECTORATE OF PLANNING
QUARTERLY PROGRESS REPORT NO. 4
JANUARY - MARCH 2015
TECHNICAL ASSISTANCE FOR SUPPORT OF PROJECT MANAGEMENT UNIT OF REGIONAL ROADS DEVELOPMENT PROJECT UNDER : ADB LOAN NUMBER 2817-INO IDB FINANCING NUMBER 0161 IND
RENARDET S.A. CONSULTING ENGINEERS
Joint Venture With : 1. PT. Multi Phi Beta 2. PT. Widya Graha Asana 3. PT. Disiplan Consult 4. PT. Anugerah Kridapradana
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
TABLE OF CONTENTS
Table of Contents ..................................................................................................... i 1.
2.
3.
Executive Summary ................................................................................................................. 1 1.1
Project Description ........................................................................................................... 1
1.2
Current Implementation Situation .................................................................................... 1 1.2.1
Procurement ........................................................................................................ 1
1.2.2
Civil Works .......................................................................................................... 3
1.2.3
Consultancy Services .......................................................................................... 4
1.3
Current Status of Loan ...................................................................................................10
1.4
Current Problems and Action Required at End of first Quarter 2015 ............................10
General .................................................................................................................................... 11 2.1
Reporting Requirements ................................................................................................11
2.2
Loan Status ....................................................................................................................12
2.3
Financial Management ...................................................................................................13
2.4
Project Cost Monitoring ..................................................................................................14
2.5
ADB Missions .................................................................................................................15
2.6
Project Steering Committee Meeting .............................................................................15
2.7
Loan Closing Date .........................................................................................................15
Project Management and Implementation ........................................................................... 15 3.1
Procurement Plan ..........................................................................................................15
3.2
Procurement Status .......................................................................................................15
3.3
Implementation Status – Civil Works .............................................................................16
3.4
Variation Details .............................................................................................................17
3.5
Ongoing Consultancy Services ......................................................................................17
3.6
Implementation of the Anti-Corruption Plan ...................................................................20
3.7
3.8
3.6.1
Community Representative Observer (CRO) ................................................... 20
3.6.2
Third Party Monitoring (TPM) ............................................................................ 21
3.6.3
Complaint Handling System (CHS) ................................................................... 21
Implementation of the Environmental Management Plan ..............................................21 3.7.1
HIV-AIDS and Anti Human Trafficking Program ............................................... 22
3.7.2
Monitoring of Health and Safety ........................................................................ 22
Resettlement & Rehabilitation Activities ........................................................................23 3.8.1
Preparation of LARP ......................................................................................... 23
3.8.2
LARP Implementation ....................................................................................... 23
i
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
4.
Seminars, Workshops & Training ........................................................................................ 26
5.
Loan Utilization for Civil Works ............................................................................................ 26 5.1
Estimated Funding Status for RRDP Civil Works and Consultant Services. ..................26
6.
RRDP Website ...................................................................................................................... 26
7.
Documentation Collection and Scanning ............................................................................ 27
ii
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Forms Form A
General
2 Sheets
Form B
Summary of Implementation
2 Sheets
Form C
Status of Problems
2 Sheets
Form D
Contract Package Status
Form E
Details of the Budget
15 Sheets 1 Sheets
iii
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendices Appendix 1
The overall Financial Status
Appendix 2
Procurement Plan
Appendix 3
Project and Cost Monitoring
Appendix 4
Details Variation Orders Up to End March 2015
Appendix 5
Summary of Contract Data
Appendix 6
Unsettled Complains
Appendix 7a
CROs Activities on RRDP
Appendix 7b
Status of CRO Reports
Appendix 8
EMP Compliance ( Up to end March 2015 )
Appendix 9
Status of Social Safeguard Study.
Appendix 10
Status of Monitoring of Environmental Mitigation on RRDP
Appendix 11
Overall Land Acquisition Status End March 2015
Appendix 12
Environmental Safeguards
Appendix 13
Construction programme
Appendix 14
Cost Estimated of Civil Works Packages
Appendix 15
Monitoring Health and Safety During Construction.
Appendix 16
Abbreviation and Acronyms
iv
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
1.
Executive Summary 1.1
Project Description The RRDP project is an aided project with Asian Development Bank (ADB) loan No. 2817-INO and financing from the Islamic Development Bank (IDB) Agreement No.0161-IND. The proposed Project 1 will improve strategic national road corridors in northern Kalimantan and southern Java to support economic growth in these two ( 2 ) less developed and poorer areas of Indonesia. The National road network in southern Java is incomplete, with some road sections of the southern Trans Java Highway not yet constructed resulting in gaps in the network. Similarly, road network improvements are needed to support economic development in the less developed and remote districts in northern Kalimantan and improve road connections Kalimantan to the border. The project includes a component for the rehabilitation of 476 km of National roads consisting of new construction, resurfacing and widening and bridge rehabilitation and replacement 3.390 meters in length in two (2) provinces in Java and two (2) provinces in Kalimantan.
1.2
Current Implementation Situation 1.2.1 Procurement All sub-projects started with pre-qualification in 20 December 2011 through ICB procurement process. West Kalimantan At one (1) of the three (3) packages in West Kalimantan, CW-05 (SosokTayan; Tanjung – Batas Kota Sanggau), ADB agreed that DGH may apply the full e-procurement system for this package as a pilot test. Bid opening (Re-tender) for package 30RCP01 (CW-05) (Sosok – Tayan) was held on 9 September 2014. Bid Evaluation Report (BER) was sent to ADB on 3 October 2014. However, one (1) bid was not opened on 9 September, 2014 due to apparent missing with the bid documents.
bid security required in line
On investigation, the location of missing
documents was determined and eligibility of the bid was accepted. A second bid opening was held at DGH office, Jakarta on 16 October 2014 attended by POKJA members, Contractors, and CTC. ADB issued “No Objection Letter” on 9 December 2014 and Minister approval given on 11 December 2014. The Contract Agreement was signed on 15 January 2015. The Contract Document has sent to ADB on 3 February 2015 and the ADB issued “ No Objection Letter” on 4 February 2015.
1
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
East Kalimantan Procurement of four (4) Civil Work package in North Kalimantan has been completed. Central Java Bid opening for three (3) packages ; 24-RCP-01(CW-01) (Tambakmulyo – Wawar), 24-RCP-02(CW-02) (Giriwoyo - Duwet (Section 1)) and 24RCP-03(CW-03) (Wawar - Congot), was held on 15 July 2014 at Semarang, Central Java. Procurement team (POKJA) started the detailed bid evaluation including the clarification of three (3) lowest bids immediately after the bid opening; completed the Bid Evaluation Report and this was sent to IDB on 23 September 2014. After several clarifications made to IDB by POKJA, the “No Objection Letter” was issued for three (3) packages (CW-1, CW-2 and CW-3) on 1 December 2014. PPK commenced preparation of Contract Documents. Bid validity for CW 01, 02 and 03 was extended for a period of (40) days starting from 12 November 2014. The Letter of Acceptance of the above three packages was issued on 16 December 2014 and Draft contracts for these packages sent to IDB on 24 December 2014. IDB issued “ No Objection Letter “ of Draft Contract for the above three (3) packages on 5 January 2015. The Contracts for CW-1 was signed on 12 January 2015, for CW-2 signed on 13 January 2015 and for CW-3 signed on 7 January 2015. The Contract Documents for the above three (3) packages were sent to the IDB on 4 March 2015. To date DSC-2, Consultants who will cover the Central Java province, has not yet been mobilized. At the meeting held on 29 October 2014 among the related parties, IDB instructed DGH to expedite the process of selection. POKJA submitted a detailed analysis of Consultants Technical proposals and the IDB issued a “No Objection Letter” on 4 December 2014. The Consultant Financial proposals were consequently opened on 12 December 2014 and an evaluation of Financial proposals sent to he Bank on 28 December 2014. NOL was issued by the Bank on 28 December 2014. Draft contract sent to IDB on 17 February 2015. IDB approved the draft contract on 3 March 2015.
2
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
1.2.2 Civil Works Seven (7) out of eleven (11) packages have been contracted through ICB tender process as shown in the table below: Ref
Package No
Package Name
Contract Sign
COW
Province
CW-04
28-RCP-01
Jolosutro – Sandang Biru
21 Aug 2013
18 Oct 2013
East Java
CW-06
30-RCP-02
Tebas – Singkawang (Sec 1) Tebas – Singkawang (Sec. 2) ByPasss Sambas Galing-Tanjung Harapan
14 Nov 2013
17 Dec 2013
West Kalimantan
CW-7
30-RCP-03
27 Nov 2013
4 Dec 2013
West Kalimantan
CW-08
34-RCP01
Tanjung Selor-Sp.3 Tj. Palas Sekatakbuji
3 Nov 2014
12 Dec 2014
East Kalimantan
CW-09
34-RCP02
Sp.3 Tanjung Palas –Sekatak Buji (Section 2)
25 Jun 2014
4 Sept 2014
East Kalimantan
CW-10
34-RCP-03
Sp. Tiga Apas - Simanggaris (Section 1)
11 Apr 2014
10 July 2014
East Kalimantan
CW-11
34-RCP-04
Sp. Tiga Apas – Simanggaris (Section 2); Simanggaris - Bts. Negara (Serudong)
11 April 2014
1 Oct 2014
East Kalimantan
Sp.Tanjung – Galing Aruk(Bts.Serawak-Sp.Tanjung
Seven (7) packages out of eleven (11) packages above are already ongoing. The table below shows the actual physical progress at the end of this first quarter 2015: Package
JolosutrioSendangbiru
Tebas- Singkawang. Bypass Sambas Galing-Tj.harapan
Physical Progress % Sche Actual Diff. d
Province
Contractor
East java
PT.Hutama Karya
34,49
38.09
+3,60
PT.Brantas Abipraya. Tri Citra Perdana Trifa Abadi -JO
37,05
37,02
0,03
West Kalimanatan
3
Remarks
Addendum No.3 was signed 20 March 2015.
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Package
Sp.Tanjung-Galing Sp.Tanjung -Aruk
Physical Progress % Sche Actual Diff. d
Province
Contractor
West Kalimantan
PT.Waskita Karya PT.Yasa Patria Perkasa
31,46
17,00
-14,46
Seriously behind schedule
PT. Waskita Karya
2.76
2,785
0,025
COW 12 Dec 2014
PT. Brantas Abipraya ; PT.Mahir Jaya Mahakam Raya – JO
5,01
2,47
-2,54
Behind Schedule
PT.Perdasa- JO
11,80
7.56
-4,24
Behind Schedule
Halla Corporation
1,31
1,41
0,10
Tanjung Selor – Sp.3 Tj.Palas- Sekatakbuji (Sect 1)
East Kalimantan
Sp.3 Tanjung Palas – Sekatak Buji (Section 2 ).
East Kalimantan
Sp.Tiga Apas – Simanggaris (Section 1).
East Kalimantan
Sp.Tiga Apas – Simanggaris (Section 2). SimanggariBts.Negara (Serudong)
East Kalimantan
Remarks
PT Pem.Perumahan
The location of all Packages is shown on the following Project Location Maps. 1.2.3 Consultancy Services
TA Consultant
Planned Mobilization from the Project Admin. Manual up to date
Contract Signed
Actual Mobilization
Responsible Agency
CTC (CSP-1)
April 2012
12 Feb 2014
3 Mar 2014
DGH
DSC-1 (CSP-2)
April 2012
21 Nov 2013
16 Dec 2013
DGH
DSC-2
Not Yet
DSC-3 (CSP-3)
Not yet 16 Oct 2013
18 Oct 2013
DGH DGH
Road Safety Support (CSP-4)
Jan 2013
Not yet
DGH
Institutional development for Road Network Management (CSP-5)
Jan 2013
Not yet
DGH
Road safety awareness Campaign and Training
Jan 2013
Not yet
DGLT
4
Remarks
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
(CSP-6) Integrated Vehicle overloading Control Strategy (CSP-7)
Jan 2013
Not yet
DGLT
Overloading and Speed Enforcement (CSP-8)
Jan 2013
Not yet
DGNTP
Indonesia Transport Sector Dev. Strategy and Policy (CSP-9)
Jan 2013
Not yet
Bappenas
HIV/AIDS anti Trafficking Program (CSP-10))
Jan 2013
Not yet
DGH
Road safety Equipment
Sept 2013
Not yet
DGNTP
As can be seen from the above table the appointment of all Consultancy Services have been late for a number of reasons including delay in the procurement process for Consultant Services DSC-2 and delay in the procurement process for Civil Works in Central Java. Also there have been delays in appointments for Technical Assistant Consultant services CSP-4 to CSP-10.
5
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
WEST KALIMANTAN
6
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
EAST KALIMANTAN
7
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
EAST JAVA
8
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
CENTRAL JAVA
9
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
1.3
Current Status of Loan At the end of this first quarter 2015 March 2015, there was no progress in disbursement for this quarterly. The disbursement remains at US $ 21,686.86 representing 8.85% of the available loan, has been disbursed. Disbursement is considerably behind schedule at 28.26% (13 months) of the loan period has already elapsed with the main reasons for the delay being: Loan Extension Proposal Proposal for an Extension of the Loan Period has been submitted to the Secretary of Ministry of Public Works
on 13 February 2015; reasons for
extension of loan peiod are: a. The loan extension proposed is based on the estimation for the completion of Civil Works activities where it is currently believed that seven (7) Packages will not finish before the Loan Closing date of 31 August 2016. b. Documents/ Signing of Contract for Package CW-05 (Sosok-Tayan and Tanjung Bts. Kota Sanggau) is still in process. Work commencement estimated to be mid- April 2015, and with a Construction Period of thirty six (36) months, Civil works should be completed by Apil 2018. c. Considering a time for completion of the Civil Works at Package CW-05 of April 2018 including three (3) months for Contingencies, the proposed Loan Extension period is twenty three (23) months i.e. to 31 July 2018. Details of the overall loan situation are presented in Forms A through to and are found immediately after the main text in this report. These Forms are an English translation of the quarterly report prepared by PMU for Bappenas. 1.4
Current Problems and Action Required at End of first Quarter 2015 Item
Problem Areas
Suggested Solution
Seven packages will not be finished inside the current loan period
There is a need for an extension of time of loan.
Technical Assistant for Road Sector Development Program
Until end of March 2015 still not running smoothly.
Accelerate the process of contract
Package Jolosutro Sendangbiru
This package has fallen behind schedule, looks like contractor has a cash flow problem
PPK invited contractor for a third Show cause meeting held on 28 Jan-15. Outcome: Contractor should achieve catch up targets/ revised schedule to complete their Contract
LRAP Issues
Many problem with land Acquisition and Compensation process in Kalimantan.
Balai to organize meeting with ADB, Local Government, Satker, PPK, CTC to find solutions with problems in LARAP.
Loan Period Extension
10
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
2
General 2.1
Reporting Requirements Quarterly Progress Reports: This is the fourth (4th) quarterly progress report to be prepared and covers the first quarter of 2015. Report
Period Covered
Final Version Issued
Quarterly Progress Report No.1
March 2014 – June 2014
May 2015
Quarterly Progress Report No.2
July – September 2014
May 2015
Quarterly Progress Report No.3
October – December 2014
May 2015
Quarterly Progress Report No.4
January – March 2015
June 2015
Financial Monitoring Reports: These reports have been prepared for each quarter since the beginning of 2014, the first and the second one, issued in July 2014, covered the period January – June 2014. Since that date, reports have been prepared each quarter on schedule as shown in the table below. Report
Period Covered
Date Issued
Financial Monitoring Report No.1
January – March 2014
10 July 2009
Financial Monitoring Report No.2
April – June 2014
Financial Monitoring Report No.3
July – September 2014
5 November 2014
Financial Monitoring Report No.4
October - December 2014
January 2015
Financial Monitoring Report No.5
January – March 2015
April 2015
CTC Monthly Progress Reports: These reports have been prepared covering each full month since CTC were mobilized at the March 2014 the first, covering the month of April 2014, was issued in July 2014. Subsequent reports have been submitted more timely. All reports are first vetted and edited where PMU feel necessary which can cause some delays: Report
Period Covered
Final Version Issued
Monthly Progress Report No. 1
April 2014
15 July 2014
Monthly Progress Report No. 2
May 2014
18 July 2014
Monthly Progress Report No. 3
June 2014
15 August 2014
Monthly Progress Report No.4
July 2014
15 September 2014
Monthly Progress Report No.5
August 2014
26 September 2014
Monthly Progress Report No.6
September 2014
6 November 2014
Monthly Progress Report No.7
October 2014
27 November 2014
Monthly Progress Report No.8
November 2014
15 January 2015
Monthly Progress Report No.9
December 2014
23 February 2015
Monthly Progress Report No.10
January 2015
26 March 2015
11
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Report
2.2
Period Covered
Final Version Issued
Monthly Progress Report No.11
February 2015
27 March 2015
Monthly Progress Report No.12
March 2015
15 April 2015
Loan Status The agreed allocation of loan funds from the original loan agreement together with the % disbursed to the end of the quarter is presented in the following table:
Category
Works Works (Central Java)
Original Amount of loan Allocated in US$
Total Disbursed to 31 Mar 2015 in %
Distribution to 31 Mar 2015 in US$
ADB
IDB
Percentage of Expenditure to be financed
155,000,000
-
70%
9.74%
20.300.87
-
53,500,000
100%
0
0
100%
0
0
Road Safety Equipment
1,300,000
Consultant’s services and training
12,200,000
3,000,000
100%
9.12%
1,385.99
- Road Safety Support - Institutional Dev. for Road Network Management. - Road Safety awareness campaign and Training
4,300,000
-
100%
0
0
Over loading and speed Enforcement
2,200,000
-
100%
0
0
- Indonesia Transport Sector development Strategy and Policy study. - Integrated Vehicle Overloading Control Strategy - HIV/AID and anti Trafficking Prevention Program
2,400,000
-
100%
0
0
Unallocated
2,600,000
8,500,0000
0
0
0
TOTAL AMOUNT
180,000,000
65,000,000
8,85
21.686.86
Details of the overall loan Status can be found in Appendices 1
12
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
2.3
Financial Management S-Curve for Financial Progress The following curve shows the financial disbursement progress up to the end of March 2015 with the loan scheduling.
13
PMU RRDP – Quarterly Progress Report No. 4,January - March 2015
2.4
Project Cost Monitoring A summary of the project cost monitoring in tabular format is presented as Appendix No. 3. Status March 2015
No.
Contract No.
Contract Description
Type of Works
Estimated Cost
Contractor
IDR (x106)
1
2
3
01/24-RCP-01/NR/IDB/0161/0115 Tambakmulyo - Wawar
HK.02.03/BJGD/24-RCP02/I/2015/01
Giriwoyo - Duwet
02/24-RCP-03/NB/IDB/0161/0115 Wawar - Congot
New Road, Widening, Resurfacing New Road, Widening, Resurfacing, Reconstruction
Widening; Reconstruction
Contract Sign Category Procurement Date Method
Contract Price (IDR 10⁶) Including Tax Original Addendum
ADB/IDB Financing Ratio (%)
278,810,582
PT. PP (Persero)-PT.Armada Hada Graha, JO
12-Jan-15
Civil Works
ICB
243,741,564
100
171,759,932
PT.Hutama Karya
13-Jan-15
Civil Works
ICB
142,000,000
100
71,444,835
PT.Manggala Konstruksi Manggala Pratama, Tbk
7-Jan-15
Civil Works
ICB
58,253,088
100
151,916,793
PT.Hutama Karya
21-Aug-13
Civil Works
ICB
93,350,000
608,466,493
PT. Yasa Patria Perkasa ; PT. Budi Bakti Prima
15-Jan-15
Civil Works
ICB
465,647,542
70.00
Cost During this Quarter (IDR)
Cummulative Cost (IDR)
Actual
Planned
ADB Share
Actual as % of Planned
To Last Quarter
Actual to date Total ADB Share
0
11,528,920,191
0
0.00
27,380,463,350
27,380,463,350
Physical Progress % Planned to date
Actual as % of Planned
Scheduled
Actual
Difference
17,423,931,223
38,909,383,541
70
34.49
38.09
3.60
New Road
01-28-RCP01A/RB/ADB/2817/0813
Jolosutro - Bale kambang Reconstruction Sendang biru
5
02/30-RCP01/RB/ADB/2817/2015
Sosok - Tayan: Sp.Tanjung Reconstruction - Bts.Kota Sanggau
6
02-30-RCP02/RB/ADB/2817/1113
Tebas - Singkawang (Section 1); Tebas Singkawang (Section 2) Bypass Sambas
Reconstruction Resurfacing
430,578,648
PT.Brantas Abipraya-Tri Citra Perdana-Trifa Abadi, JO
14-Nov-13
Civil Works
ICB
292,603,385
70.00
0
3,731,326,220
0
0.00
104,672,375,855
104,672,375,855
66,609,693,726
108,403,702,075
97
37.048
37.017
-0.03
7
03-30-RCP02/RB/ADB/2817/1113
Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
Reconst + widening Reconstruction
333,214,553
PT Waskita Karya - Yasa Patria Perkasa, JO
27-Nov-13
Civil Works
ICB
238,974,973
70.00
0
10,772,434,704
0
0.00
64,409,091,802
64,409,091,802
41,714,153,483
75,181,526,506
86
31.460
17.00
-14.46
8
01-34-RCP/LOAN/PJN.III/11.14
333,214,553
PT.Waskita Karya (Persero)
3-Nov-14
Civil Works
ICB
189,970,248
70.00
0
5,248,877,952
0
0.00
28,495,537,200
28,495,537,200
18,133,523,673
33,744,415,152
84
2.763
2.785
0.02
9
02-34-RCP/LOAN/PJN.III/06.14
Sp.3 Tanjung Palas Sekatak Buji (Section 2)
Reconstruction Grade Improvement
215,483,495
PT.Brantas Abipraya -Mahir Jaya Mahakam Raya- JO
25-Jun-14
Civil Works
ICB
165,332,338
70.00
0
4,700,624,704
0
0.00
28,387,336,100
28,387,336,100
18,064,668,427
33,087,960,804
86
5.013
2.471
-2.54
10
03-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis (Sect 1)
Reconstruction Resurfacing
322,919,917
PT.Pemb. Perumahan- PT.Perdasa JO
11-Apr-14
Civil Works
ICB
289,000,000
70.00
0
11,112,868,296
0
0.00
66,336,241,704
66,336,241,704
42,213,971,993
77,449,110,000
86
11.799
7.561
-4.24
11
04-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis (Sect 2); Simanggaris Bts.Negara
Reconstruction Resurfacing
407,483,774
Halla Corporation
11-Apr-14
Civil Works
ICB
359,652,697
70.00
0
-2,293,233,737
0
0.00
60,945,395,564
60,945,395,564
38,783,433,520
58,652,161,827
104
1.308
1.407
0.10
0
44,801,818,330
0
242,943,376,045
425,428,259,905
4
112,823,335
70.00
Resurfacing
Resurfacing
Tanjung Selor- Sp.3 Tj.Palas - Sekatakbuji (section 1)
3,325,293,575
TOTAL
2,557,999,170
14
380,626,441,575 380,626,441,575
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
2.5
ADB Missions There were no RRDP Asian Development Bank missions during this first quarter 2015 with the last being held 23 September 2014 and 14 November 2014.
2.6
Project Steering Committee Meeting No Steering Committee meetings have been held to date.
2.7
Loan Closing Date During the ADB Midterm Review mission, informal discussions were held relating to the completion date for the packages in Kalimantan and three packages in Central Java. It was the consensus that packages may not be completed before the Loan closing date.
3
Project Management and Implementation There were no major changes in project management during the quarter 3.1
Procurement Plan In Appendix No. 2 is presented a copy of the general Procurement Plan for all, Civil Works, Goods and Consulting Services of the project updated to the end of the first quarter 2015.
3.2
Procurement Status (A)
Civil Works Procurement has been conducted under the Bank’s Procurement Procedures as described in the Loan Agreement. The International Competitive Bidding (ICB) will apply for packages with an estimated total cost of more than US$10 Million to comply with the Bank’s threshold. According to Government of Indonesia (GOI) regulation, prequalification shall be apply to all packages with construction estimated cost to be more than IDR 100 Billion. All Procurement is complete for eleven (11) packages although only seven (7) packages ongoing. One package CW-05, 30-RCP01, Sosok – Tayan; Tanjung – Batas Kota Sanggau, the contract has been signed on 15 January 2015, now waiting date of commencement of work when the Advance payment has been received by the contractor. Three (3) Packages in Central Java Province, CW-01, 24-RCP01, Tambakmulyo - Wawar ; CW-02, 24-RCP02 Giriwoyo – Duwet and CW03,24-RCP03, Wawar – Congot, signed contract 13 January 2015; now awaiting the Notice to Proceed for the DSC-2 contract for supervision Consultants. 15
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
(B)
Goods There were no for Goods procurement processed during the first quarter 2015.
(C)
Services The status of Core Team (CTC), Supervision Teams (DSC-1 and DSC-3), are discussed in Section 3.5 of this report. :
3.3
Implementation Status – Civil Works The seven (7) Packages are now under Construction, and the table below shows the progress at the end of March 2015. Package 28-RCP01A, Jolosutro – Sendangbiru. NOL for draft Addendum Contract No.3 was issued by ADB on 12 March 2015. Addendum No.3 is to accommodate the (i) the change of unit price of additional work for rock excavation ,(ii) relocation of electrical poles, (iii) additional tack coat for Asphaltic Cement Base Course leveling, additional pavement Marking, road signing, caisson work and other additional minor works, (iv) reduction of Cement Treated Base (CTB) quantity, stone masonry and drainage works. The Contract price under Addendum No.3 increased to IDR 112.823.335.000 including taxes, from the existing contract Addendum No.2 of IDR 98.889.601.000. As a consequence of additional works. the Contract period is proposed to be extend (175) days. According to DSC-3 progress report, the contractor progress up to end of March 15 was ahead schedule 3.60% against to schedule 34,49% (rescheduled). The contractor needs to increase progress with the supply of aggregates for asphalt work with material from the outside project area to achieve an average progress of 7% per month. Package 30-RCP03, Sp.Tanjung – Galling; Aruk- Bts Serawak, the
behind
schedule increased to -14,46%, This month contractor only produce 1,6%, but for target month should be more than 3% per month. Packages in East Kalimantan, Tj.Selor – Sekatakbuji Section 1 (34-RCP01). This package has running since 12 December 2014 and with achieved progress at 2.78% is above that scheduled by 0.01%. Sp.3 Tj.Palas – Sekatakbuji, section 2 (34-RCP02) now behind schedule increased to - 2,54% and the slippage from that scheduled is increasing. Activities in this package are relatively low since November 2014 and until now only increased by 0.19%. This situation should be countered and the Contractor given a warning by the DSC-1 and briefed on how to improve progress. At package 34-RCP03 (CW-10), Simpang 3 Apas – Simanggaris (section1), progress just reached 7.56% and behind schedule has increased to -4,24%. In
16
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
the month contractor only produced 0.60% compared to the scheduled of 3% per month. For package 34-RCP04 (CW-11), Simpang 3 Apas – Simanggaris (Section 2), the situation is still at preparation / mobilization stage, progress reach 1.41%, against to the schedule 1.31%, ahead schedule 0,10%. Conclusions, among seven (7) seven ongoing packages that are currently ongoing there are four (4) packages in delay and one (1) package in the category of critical i.e. package CW-07 The summary of Implementation Status and Cost Monitoring of RRDP project is shown on Appendix 3. 3.4
Variation Details Among seven (7) ongoing packages, only at package CW-04 Jolosutro – Sendangbiru,
Variations Orders have been made. NOL for draft Addendum
Contract No.3 was issued by ADB on 12 March 2015. Addendum No.3 is to accommodate the (i) the change of unit price of additional work for rock excavation ,(ii) electrical pole relocation, (iii) additional tack coat for Asphalt Cement Base Course leveling, pavement Marking, road signing, caisson work and other minor work, (iv) reduction of Cement Treated Base (CTB) quantity, stone masonry and drainage works. The Contract price under Addendum No.3 increased to IDR 112.823.335.000 including taxes, from the existing contract Addendum Contract No.2 of IDR 98.889.601.000. Because of additional works the contract period is proposed to be extended by 175 c days. For packages CW-06 and CW-07, several meetings/ discussion has been had between Contractor, PPK, Satker and Balai. The last discussion was had in the ADB office on 16 March 2015. 3.5
Ongoing Consultancy Services Core Team Consultant (CTC) Contract No.03-02/CTC/PM/LN/ADB/2817.0214 was signed on 12 February 2014, between the Ministry of Public Works, Directorate General of Highways and Lead Consultant Renardet S.A in a Joint Venture with Local Consultants PT.Widya Graha Asana; PT.Multi Phibeta; PT. Anugerah Krida Pratama; PT.Disiplan Consultant as the Core Team Consultant (CTC). CTC Personnel started to be involved in the project at end March 2014
The NOL for Addendum No.1 to the CTC Contract was issued by ADB on 19 March 2015, final is currently being prepared for the signing.
17
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
The following table indicates the current status Contract/ Addendum for the CTC Contract: Contract Original Contract
Dated
US$ (Ex.VAT)
12 Feb 2014
Addendum No.1
1.192.400
IDR (Ex. VAT) 19.472.500.000
1.473.900
22.584.677.000
Design Supervision Consultants (DSC) Under RRDP, three (3) Design and Supervision Consultants (DSC) were required with the Team Leader from each of the Design and Supervision Consultants to act as “The Engineer” as defined in the FIDIC Conditions of Contract and responsible for checking
completed designs, monitor construction Quality and Progress, certify
Monthly Interim Payment Certificates (IPCs) and prepare and submit Monthly Progress Reports. Design and Supervision Consultants will be responsible for the Design and Construction Supervision of all Civil Works. The task includes the maintenance of a Quality Assurance Plan (QAP), Environmental Monitoring Plan (EMP), Health and Safety Plan and Traffic Safety Plan, and the validation/ updating of designs. The DSC1 and DSC3 Teams contracted and managed by DGH through the Bina Marga Regional Office (Balai) are based in Banjarmasin and Surabaya; with DSC-2 (Central Java) will also be based in Surabaya. The contract not yet signed. DSC-1 (Kalimantan Region) The DSC-1 for West Kalimantan and East Kalimantan is China Engineering Consultants Incorporated (CECI), in Joint venture with PT.Wira Wydiatama; PT.Hasfarm
Dian Konsultan; PT.Yodya Karya; PT.Seecons; PT.Pola Agung
Consulting who were mobilized on January 2014 with the Team Leader Mr.Lin, HungCheng acting as “the Engineer”. The original Contract for DSC-1 is US$ 936.570 and IDR 30.372.995.000 (excl VAT). DSC-1 has a total of seven (7) packages, six (6) packages are ongoing and one (1) package has been signed the Contract Agreement (30 - RCP01). The contractor awaits processing of Advance Payment as a condition for the commencement of work (GCC Cause 8.1). ADB has commented on the draft Addendum No.1 DSC-01 on 5 January 2015. Up to March 2015, the draft Addendum No.1 to the DSC-1 contract still being finalized by Core Team DSC-1. Design Supervision Consultant (DSC-2), Central Java Province IDB issued NOL to the Bid Evaluation Report for Technical and Financial proposal for DSC-2 on 28 December 2014. The Consultant to act confirmed as DSC-2 is Botek
18
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Bosphorous in association with five (5) local Consultants (Contract not yet signed). The NOL for the draft Contract DSC-2 was issued by IDB 3 March 2015. Design Supervision Consultant (DSC-3), East Java Province The DSC-3 for East Java is PT.PERENTJANA DJAYA mobilized on 20 January 2014 with the Chief Supervision Engineer Fajar Subianto acting as “the Engineer” The original Contract for DSC-3 is IDR 6.939.950.000 (Excl VAT), was signed on 16 October 2013. ADB was approved draft Addendum No.1 for DSC-3 on 29 October 2014 The Contract for Addendum No.1 increased to IDR 7.505.980.000, - (Excl VAT) and has been signed 3 November 2014. The following table indicates the current status Contract/ Addendum for the DSC-3 Contract: Contract
Dated
IDR (Ex. VAT)
Original Contract
16 Oct 2013
6.939.950.000
Addendum No.1
3 Nov 2014
7.505.980.000
Selection of Technical Assistant Consultant CSP- 4: Road Safety Engineering Support (DGH) EOI was submitted by the consultants on 20 September 2014 and Evaluation Report for Short List of Consultant was sent to ADB on 28 October 2014. “No Objection Letter” for short list of the consultant and draft of Request for Proposal (RFP) was issued by ADB on 9 December 2014. The invitation to the shortlisted consultants was issued on 29 December 2014 and the submission of proposals on 23 February 2015. The Pokja has evaluated the Technical proposal and sent to ADB on 12 March 2015, ADB issued “No Objection Letter “ on 20 March 2015. Financial Proposals were opened on 31 March 2015. CSP - 5: Capacity Development Program (DGH) Coordination meeting was held among the related sections of DGH and CTC presided by Secretary General of BINA MARGA on the scope of works on 31 October 2014, but the program has just started to move and TOR and Cost estimate are still under discussion. CSP - 6 : Road Safety Awareness Campaign & Training (DGLT) A Meeting was held between DGLT and CTC on Terms of Reference (TOR) for which ADB already gave the comment for revise on the first submission. On 20 January 2015 another meeting between DGLT, ADB and CTC was held at ADB Office –IRM Jakarta regarding finalization/ preparation revised TOR and Owner Cost Estimate, and DGLT
19
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
was informed that they will submit to PMU/ADB two ( 2) weeks later. But up to the end of March 2015, documents have not yet been sent to ADB. CSP - 7: Overloading and Speed Enforcement (DGNTP) ADB selected another institution to support INTPC to draft a short list of consultants due to conflict of interest. Short list of the consultants was completed including Request for Proposal (RFP) and Terms of Reference (TOR), sent to ADB 26 September 2014 and was concurred by the Bank on 19 November 2014. Invitation to shortlisted Consultant was conducted by POKJA of DGNTP on 4 December 2014. The submission of Technical and Financial proposals was conducted 26 January 2015. Pokja completed conducting an Evaluation of Technical Proposals, and the result of the evaluation sent to ADB. CSP - 8: Indonesia Transport Sector Development Strategy and Policy Study (Bappenas) Short list of consultants including Request for Proposal (RFP) and TOR was sent to ADB on 10 July 2014 and was concurred by ADB on 24 September 2014. Result of evaluation of Technical proposal has been sent to ADB on 26 January 2015. ADB has commented on 6 February 2015, and now the Pokja is preparing a response to ADB. CSP – 9: Integrated Vehicle Overloading Control Strategy Meeting was held between DGLT and CTC on Terms of Reference (TOR) for which ADB already gave the comment to revise on the first submission. On 20 January 2015 another meeting between DGLT, ADB and CTC was held at ADB Office –IRM Jakarta regarding finalization revised TOR and Owner Cost Estimate. DGLT was informed that they will submit to PMU/ADB in two ( 2) week after that meeting, but up to the end of March 2015, such documents not yet received by ADB. CSP – 10: Human Trafficking Prevention and HIV/AIDS Campaign Programs EOI was submitted by the consultants on 20 September 2014. Evaluation Report for Short List of Consultant was sent to ADB on 28 October 2014. “No Objection Letter” for short list of the consultant and draft of Request for Proposal (RFP) was issued by ADB on 9 December 2014. The invitation to the shortlisted consultants was issued on 29 December 2014 and the submission of proposals on 23 February 2015. Pokja evaluated the Technical proposal and this sent to ADB on 12
March 2015; ADB
issued “ No Objection Letter “ on 20 March 2015. The Financial Proposals were opened on 31 March 2015. 3.6
Implementation of the Anti-Corruption Plan 3.6.1 Community Representative Observer (CRO) The bid openings for three (3) packages in West Kalimantan, four (4) packages in East Kalimantan and three (3) packages in Central Java were attended by the selected CROs who are required to prepare a 20
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
report with the results of their observations. For one (1) Package in East Java, a CRO was not present at the bid opening ceremony. Refer to Appendices No. 7 for a tabular summary of CRO activities. 3.6.2 Third Party Monitoring (TPM) Because of the TPM program is not included in the PAM (Project Administration Manual) of Regional Roads Development Project, in the PMM Socialization meeting in Bandung it was decided that the TPM is not required and the program can be discontinued. 3.6.3 Complaint Handling System (CHS) Two (2) complaints were received during the month of October. One c o m p l a i n t was dated O ctober 2 2 , 2014, and the other dated October 31, 2014. CTC only received copies from PMU in December, 2014. Two (2) com pla int s relate to the bid evaluation for the CW - 08 package. One ( 1 ) complaint received on 19 December 2014 relates to the S o s o k -Tayan package, one complaint received on February 2015, r e l a t e s to the Tebas - Singkawang package related the Condition of the road at the front of SMP No.4 Singkawang. The Complaints were responded to by Pokja and the Chief of Bina Marga Singkawang. 3.7
Implementation of the Environmental Management Plan All contractors have been informed that they must prepare an Environmental Management and Monitoring action plan (Rencana Kerja Pengelolaan dan Pemantauan Lingkungan) prior to commencement of each construction package. DSC will provide technical assistance to each contractor in order to prepare the necessary documents
21
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
The detail status of plan preparation is as follows: Safeguard Document
Pack. No.
Project Name
28-RCP 01A (CW-01)
Jolosutro Sendangbiru
AMDAL
Tebas Singkawang (Section-1 & Section2)
AMDAL
Bypass Sambas
UKL-UPL
Galing-Tj.Harapan
UKL-UPL
30-RCP 02(CW-06)
Date Draft
Final
Status Will conduct briefing for Contractors Will conduct briefing to Contractors
Sp.Tanjung-Galing (Section-1)
AMDAL
Sp.Tanjung-Galing (Section-2)
UKL-UPL
Aruk-Sp.Tanjung
UKL-UPL
34-RCP02 (CW-09)
SP.3 Tanjung Palas Sekatak Buji (Sect ion-2)
UKL-UPL
Contractors will be briefed
34-RCP03 (CW-10)
SP.3 Apas Simaranggis (Section- 1)
UKL-UPL
Contractors will be briefed
30-RCP 03 (CW-07)
Contractors will be briefed
A summary of the monitoring of environmental mitigation conducted by CTC for all packages is presented in Appendix No. 8 and a detailed record of the Status of environmental safeguard documentation in presented in Appendix No. 12. 3.7.1 HIV-AIDS and Anti Human Trafficking Program Program for HIV/AID and anti Human Trafficking expected will started in May 2015, still under process of evaluation by Committee procurement. 3.7.2 Monitoring of Health and Safety Each contractor must take reasonable precautions to maintain the health and safety of his employees including collaboration with local health authorities. The object of this program is to minimize any accident and health problems during construction work execution; is part of CTC monitoring activities. Health and Safety Monitoring for each package can be found in Appendix 15. From the details in this Appendix it can be seen that the minimum attainment is “mildly satisfactory” with “good” being attained for a number of factors. Each package is made aware of the results with encouragement to improve where necessary.
22
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
3.8
Resettlement & Rehabilitation Activities 3.8.1 Preparation of LARP This has been carried out in accordance with the requirements set out in the safeguard document from ADB that requires monitoring in LARAP preparation and implementation for each package in the RRDP program. Monitoring conducted by the CTC has been prepared in five (5) documents of LARP while one LARP will be prepared for two (2) physical work packages i.e. packages 34-RCP-03 and 34-RCP04. 3.8.2 LARP Implementation Based on the results of monitoring, data collection and coordination with local government and projects, progress of the implementation of LARP can be grouped as follows: 1.
East Java For Package 28-RCP 01A (CW-04): 50 Hectares production forest which is part of the 148.14 Hectares forestry land for all trace of the southern causeway of East Java still under process of getting land use permit issued by the Ministry of Forestry. This is because of the long span of management between local government and Head of management of Perhutani (State-owned Enterprises of Ministry of Forestry) that has to be considered. In the meantime to commence work, Dispensation Permit which has just issued may be used. Determination and acquisition of land replacement located in Bondowoso District. The candidate of replacement land has been surveyed on September 2013 and status of the land replacement for forestry permits in form that is the recommendation from Bondowoso Regent issued February 2014. Up to March 2015, the process is still in the hands of National Land Bureu of Malang Regency.
2.
Central Java Package 24-RCP-01 (CW-01): Tambak Mulyo-Wawar. Package 24RCP-02: Giriwiryo - Duwet (CW-02) and Package 24-RCP 03 : Wawar-Congot CW-03) : Head of Tata Pemerintahan section of Kebumen local government 17 March, 2015 said that there is no more problem of compensation at the community level. Statement is based on Implementation Preparation Meeting RRDP Kebumen regency on January 27, 2015.
23
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
a.
There are four villages of Puring sub district still not yet paid, for Village-owned land, these are villages of Tambakmulyo, Surorejan, Waluhrejo dan Sidoharjo.
b.
Village-owned land of Sidoharjo will be paid by APBD budget (District Budget Planning) in this first semester of 2015, and the rest of three villages will be paid by APBDP (Addendum of District Budget Planning)
c.
Because there are no people to be moved, there is no community empowerment program for affected people.
3.
West Kalimantan Package 30-RCP 01(CW-05): Sosok-Tayan; Tanjung-Sanggau City Border. and Acquisition Sosok - Tayan completed 100 %, currently preparing a recapitulation. Package 30-RCP 02 (CW-06): Tebas-Singkawang (Section-1 and Section-2) , Bypass Sambas, Galing-Tanjung Harapan. Pakage 30-RCP 03 (CW-07): Simpang Tanjung-Galing (Section-1 dan Section-2), Aruk (Batas Serawak) - Simpang Tanjung. a.
Singkawang City Based on data obtained by CTC, those residents were identified who will be affected by the project in the Bambang Ismoyo Street on Tebas-Singkawang (Section-1) link part of Package 30-RCP 02 (CW-06). Singkawang government has set aside for the purpose of land acquisition, but up to now still to be identified are PAPs (Project Affected Persons). It was planned that land acquisition process will be completed by October, 2014 However, apparent that these activities have not yet been completed with the process currently still in the stage of consultation with PAPs. Results of a Coordination with Mrs. Dwi, Public Works Department Singkawang. (Head of the handle RRDP): Presented that the original land acquisition affected by road widening, originally numbered (15) houses reduced to four (4) homes, because of change in design. The results confirm the PPK package 30-RCP 02 (CW-06) section 1 Tebas-Singkawang, payment to PAPs previously made will be paid in March 2015 as not yet liquid. Thus the delayed payment for WTP, predicted funds will be disbursed in June 2015.
24
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
b.
Sambas District Directorate General of Highways, through the Balai Besar of the Region VII Kalimantan, sent a letter No: PR.01.02 - Bz / 481, Banjarmasin, December 24, 2014 to LG Regent Sambas and Singkawang Concerning Implementation of Land Acquisition and Resettlement for RRDP in Sambas and Singkawang District of West Kalimantan Province. Recovery back to the communities is affected by land acquisition, until now there has been no program of Sambas district government and Singkawang. However, the local government has planned an empowerment program for people whose land is affected by land acquisition. As of March 2015, there has been no development of funding proposals related to land acquisition in the package SambasTanjung Harapan, the results of the meeting with ADB there were some options, among others: his land communities affected by the widening of national roads, the payment of compensation should be equivalent, replaced by entering into programs in local government, a more detailed discussion will be held a meeting on April 27, 2015 in Jakarta with local governments.
c.
Sanggau District. Land Acquisition Sosok - Tayan 100 % completed and currently preparing a recapitulation.
4.
North Kalimantan Package 34-RCP 01 (CW-08): Tanjung Selor- SP. 3 Tanjung Palas and Sp. 3 Tanjung Palas Sekatak Buji (Section-1); Package 34-RCP 02 (CW-09): Sp. 3 Tanjung Palas Sekatak Buji (Section-2); Package 34-RCP 03 (CW-10): SP.3 Apas - Simaranggis (Section- 1); Packages 34-RCP 04 (CW-11): SP.3 Apas - Simaranggis (Section-2) and Simanggaris-Bts Negara (Serudong). a)
Bulungan District Activities that have been carried out on 34-RCP Package 01 (CW-08) and Package 34-RCP 02 (CW-09) is a form of socialization and data collection of the residents who have the building and crops affected by the project in August 2014. Contractors have not been measuring the community lands that have been identified affected by land acquisition.
25
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
b) Nunukan District Until now for Package 34-RCP 03 (CW-10) and Package 34RCP 04 (CW-11) have not been carried out activities related to land acquisition for road construction. Based on the letter head of the working unit PJN East Kalimantan region III No.PW.04.01 / PJNAS.III-KT / 950, dated 6 January 2015 addressed to the Head of Balai Besar National Road VII, regarding plans for relocation package 34-RCP04, (according to the DED ), due to several
considerations,
realignment canceled and the relocation back to the existing road confirmed. As of March measurement activities are yet to be completed so that the preparation of LARP document cannot be started A detailed summary of the land acquisition requirements for all packages based on LARP studies are included in Appendix No. 11. 4.
Seminars, Workshops & Training No seminars, workshops or training courses were held during this first quarter 2015, due to personnel for the Training specialist still not yet mobilized.
5.
Loan Utilization for Civil Works 5.1
Estimated Funding Status for RRDP Civil Works and Consultant Services. The estimate for Civil Works Packages in RRDP can be seen in Appendix No.14, using the exchange rate of 1US$ = 12,500 IDR for future payments.
6.
RRDP Website The RRDP-CTC website has now been running on the fixed server site and can be found on http://www.pmu-rrdp.com . The RRDP-CTC website contains all of the following items: a)
General RRDP information including copies of all reports i.e. Monthly Progress Reports and Quarterly Progress Reports with the latest uploaded reports being the MPR , QPR for the first quarter of 2014, Social and Environmental Status Reports and the Road Safety Audit Reports.
b)
Project list and Project Progress Status including Procurement Plan and Bid Winners, and Copies of all Bid Documents although currently without drawings while waiting for the original CAD files to be converted to PDF files)
c)
ACAP and Complaint Handling System including contact points, list of Community Representation Observers, and list of Third Party Monitors who have already been appointed.
26
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
d)
Announcements (current and archived)
e)
Newsletter
f)
Documents, (including all reports and bidding documents)
g)
Package Location Map
h)
Responses from the CHU following contract signing.
Any member of the public can submit a complaint via the website regarding the implementation of any RRDP package. Complaints can be submitted anonymously and they will be followed up by a responsible person from a related institution. 7.
Documentation Collection and Scanning CTC have set up a system whereby all RRDP documentation is being scanned and stored as soft copies with an appropriate well documented retrieval system. Scanning commenced includes design documents (drawings, Engineers Estimates & Special Specifications), contract documentation (originals and amendments), procurement documentation,
progress
reports
(weekly
&
(correspondence,..ADB..comments.&..site..visit..reports).
27
monthly)
and
letters
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Form A : General LAPORAN PELAKSANAAN KEGIATAN YANG DIBIAYAI DARI PINJAMAN DAN/ ATAU HIBAH LUAR NEGERI TAHUN ANGGARAN 2014 NAMA KEMENTERIAN NEGARA/LEMBAGA : Kementrian Pekerjaan Umum NAMA PEMBERI PHLN A.
: Asian Development Bank (ADB) dan Islamic Development Bank (IDB)
DESKRIPSI I. NAMA PROYEK PINJAMAN/HIBAH
: Regional Roads Development Project (RRDP)
II. NOMOR NPPHLN DAN REGISTER
: ADB No.2817-INO, Register : 10846401
III. TANGGAL PENANDATANGANAN
: ADB : 7 Mei 2012
IDB No. 0161-IND, Register : 10848804 NPPHLN
IDB :17 April 2012
IV. TANGGAL EFEKTIF NPPHLN A. TANGGAL EFEKTIF TENTATIF
: -
B. TANGGAL EFEKTIF RIIL
: ADB : 3 Juli 2012 : IDB : 2 Mei 2013
V. TANGGAL PENUTUPAN NPPHLN A. ORIGINAL
: ADB : 31 Agustus 2016
B. ACTUAL
:-
IDB : 30 April 2016
VI. JUMLAH PINJAMAN/HIBAH A. ORIGINAL
: :ADB USD 180 billion : IDB : USD 65 billion
B. ACTUAL VII. TUJUAN
:-
VIII. SASARAN
: Akses Lintas Selatan Jawa dana Akses Lintas Perbatasan Kalimantan
: Untuk meningkatkan pertumbuhan ekonomi dan pengentasan kemiskinan di wilayah koridor utara Pulau Kalimantan melalui pembangunan dan peningkatan prasarana jalan dan jembatan, dengan beberapa sasaran yang akan dicapai melalui proyek ini adalah: (i) Peningkatan/ pembangunan jalan sepanjang 854 km; (ii) Peningkatan/ pembangunan jembatan sepanjang 3.860 m; (iii) Peningkatan tata kelola melalui dukungan kebijakan di sektor jalan serta (iv) Peningkatan kapasitas sumber daya manusia dalam pengelolaan jalan.
IX INSTANSI PENANGGUNG JAWAB (EXECUTING AGENCY) X. INSTANSI PELAKSANA (IMPLEMENTING AGENCY) NO. 1 2 3
INSTANSI PELAKSANA Ditjen Bina Marga Dijen Perhubungan Darat Ditjen Kepolisian Lalulintas
Kategori Civil Works Goods Consulting Services Unallocated Total
ALOKASI DANA (JUTA VALAS ) USD 208.50 USD 1.30 USD 24.10 USD 11.10 USD 245.00
REVISI -
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
XI. KATEGORI PINJAMAN NO.
DANA ALOKASI DANA PENDAMPING (JUTA VALAS) (JUTA VALAS)
KATEGORI PINJAMAN
1 2 3
Civil Works Goods Consulting Services & Training
4
Unallocated Total
USD 208.50 1.30 USD USD 24.10 USD 11.10 USD 245.00
REVISI
USD 88.50 USD USD USD 47.00 USD 135.50
XII. LINGKUP PEKERJAAN 1. Pekerjaan Jasa Konstruksi/Civil Works untuk 11 paket 2. Pekerjaan Jasa Konsultansi (civil works) yaitu CTC (Dit. Bina Program), DSC-1, DSC-2 dan DSC-3 (Dit. Bina Pelaksanaan Wilayah II) 3. Pekerjaan Jasa Konsultansi (roads sector developmet program) yaitu Road Safety Support, Institutional Development for Road Network Management, Road Safety Awareness Campaign and Training, Overloading and Speed Enforcement, Indonesia Transport Sector Development Strategy and Policy Study, Integrated Vehicle Overloading Control Strategy dan HIV/AIDS and Anti-Trafficking Program XIII. LOKASI (PROVINSI/KABUPATEN/KOTA) NO. 1 2 3 4
PROVINSI/KABUPATEN/KOTA Jawa Tengah Jawa Timur Kalimantan Barat Kalimantan Utara
ALOKASI DANA (JUTA VALAS ) USD 76.60 USD 21.30 USD 187.80 USD 191.40 USD 477.10
REVISI Non PPN Consultant Civil Work
6,563.36 100,634.36
0.000
XIV. DISBURSEMENT PLAN DAN REALISASI PHLN (Juta Rp) Tahun
Rp
a. b.
2013 2014
Triwulan I : 4,762.72
c.
2015
36,464.89
Rp Actual 1,345.26 -
Triwulan II 11,929.28 64,655.46
Rp Actual 3,090.24 -
Triwulan III 101,483.97 143,646.77
Rp Actual 90,473.86 -
Triwulan IV 107,197.72 166,719.17 236,300.51
Actual 107,197.72 92,637.82 -
Total Disbursement Plan (Rp) 107,197.72 284,895.14 481,067.63
Total DIPA (Rp) 374,930.79 441,338.27 481,067.63
Total Realisasi DIPA (Rp) 107,197.72 187,547.18
Persentase Penyerapan (%) 28.59 42.50
-
B. PETUGAS YANG DAPAT DIHUBUNGI I. KETUA PELAKSANA HARIAN PMU RRDP Nama : DR.Ir. Slamet Mulyono M.Eng Alamat Kantor : Jl. Pattimura No. 20, Jaksel Nomor Telp : 021-7210218 Nomor Faksimili : 021-7210219 Alamat E-mail :
[email protected]
II. ESELON II PENANGGUNG JAWAB Nama : Ir. Harris H.Batubara, M.Eng.Sc Jabatan : Direktur Bina Program Ditjen Bina Marga Alamat Kantor : Jl. Patimura No.20 Jakarta Selatan Nomer Telp : 021- 7200281 Nomer Faksimili : 021- 7201760 Alamat E-mail :
[email protected]
III.A PROJECT IMPLEMENTING UNIT I #### Nama : DR. Ir.Didik Rudjito, MSc Jabatan : PPK Kegiatan Penyiapan Program dan Administrasi Pinjaman Luar Negeri Alamat Kantor : Jl. Pattimura No. 20, Jaksel Nomer Telp : 021-7248870 Nomer Faksimili : 021-7248870 Alamat E-mail :-
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM B.1 : SUMMARY IMPLEMENTATION IN FISCAL YEAR 2015 A. FINANCE (in IDR) No. Paket
PAKET KONTRAK
[a1]
I.
TATA CARA PENARIKAN (PP/PL/LC/RK) [a2]
NILAI KONTRAK DAN STATUSNYA PADA AKHIR TAHUN SEBELUMNYA
[b1]
(b2)
PENYERAPAN KUMULATIF SAMPAI DENGAN DESEMBER TAHUN SEBELUMNYA
REALISASI PENYERAPAN WITHDRAWAL APLICATION (WA) TH YL
[c]
[d]
PENYERAPAN PADA TAHUN ANGGARAN 2015 TRIWULAN I (1 Jan - 31 Maret)
TRIWULAN II (1 Apr - 30 Jun)
TRIWULAN III (1 Juli - 30 Sept)
TRIWULAN IV (1 Okt - 31 Des)
TOTAL TA 2015
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
[e]
[f]
[g]
[h]
[i]
[j]
[k]
[l]
[m]
[n]
IDB Financing No.IND-0161, Register : 10848804 Civil Works Jawa Tengah
24-RCP01
Tambakmulyo - Wawar
PL
243,741,564,000
-
-
-
3,602,739,238
-
6,387,975,695
-
14,192,336,618
-
23,346,553,448
-
47,529,605,000
-
24-RCP02
Giriwoyo - Duwet (Section 1)
PL
142,000,000,000
-
-
-
1,991,263,336
-
3,530,686,222
-
7,844,220,102
-
12,903,830,341
-
26,270,000,000
-
24-RCP03
Wawar - Congot
-
1,565,842,271
-
3,478,873,693
-
5,722,786,374
-
11,650,618,000
-
-
11,484,504,188
-
25,515,430,413
-
41,973,170,162
-
85,450,223,000
-
PL
Total Civil Works III.
-
-
-
443,994,652,000
-
-
-
6,477,118,237
-
-
-
-
195,639,803
-
346,886,397
-
770,686,650
-
1,267,787,150
-
2,581,000,000
-
-
-
-
-
195,639,803
-
346,886,397
-
770,686,650
-
1,267,787,150
-
2,581,000,000
-
-
-
-
6,672,758,040
-
11,831,390,585
-
26,286,117,063
-
43,240,957,312
-
88,031,223,000
-
Consulting Services & Training DSC-2 (Jawa Tengah - IDB)
PL
Total Consulting Services Total - IDB Financing No.IND-0161
I.
58,253,088,000
883,115,663
443,994,652,000
ADB Loan No.2817-INO, Register : 10846401 Civil Works
Jawa Timur 28-RCP01
Jolosutro - Sendangbiru
23,011,025,595
23,011,025,595
3,173,866,120
1,670,068,629
-
2,961,177,008
-
6,578,924,510
-
10,822,396,853
-
22,032,567,000
-
5,502,988,120
-
9,757,285,231
-
21,678,021,815
-
35,660,589,835
-
72,598,885,000
-
-
8,671,359,569
-
19,265,387,000
-
31,691,755,826
-
64,519,046,000
-
3,236,199,505
-
5,738,068,291
-
12,748,419,940
-
20,971,294,263
-
42,693,982,000
-
PL
112,823,335,000
PL
465,647,542,528
PL
292,603,385,000
43,890,507,750
43,890,507,750
38,679,370,633
4,890,543,605
PL
238,974,973,000
35,846,245,950
35,846,245,950
18,902,906,060
Kalimantan Barat 30-RCP01
Sosok - Tayan Tanjung - Bts. Kota Sanggau Singkawang - Tebas (Section 1+2)
30-RCP02
Bypass Sambas Tanjung Harapan - Galing
30-RCP03
Galing - Sp. Tanjung Sp. Tanjung - Aruk (Bts. Serawak)
Kalimantan Utara Tanjung Selor - Sp.3 Tanjung Palas 34-RCP01
PL
189,970,248,000
-
-
18,133,523,673
2,749,038,484
-
4,874,288,662
-
10,829,337,614
-
17,814,382,240
-
36,267,047,000
-
34-RCP02
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
PL
165,332,328,425
-
-
18,064,668,427
1,914,004,062
-
3,393,698,688
-
7,539,871,230
-
12,403,173,021
-
25,250,747,000
-
34-RCP03
Sp. Tiga Apas - Simanggaris (Section 1)
PL
289,000,000,000
-
-
42,213,971,993
4,611,448,056
-
8,176,505,751
-
18,165,961,726
-
29,883,211,466
-
60,837,127,000
-
PL
359,652,598,000
-
-
38,783,433,540
4,130,633,761
-
7,323,979,429
-
16,271,881,171
-
26,767,427,639
-
54,493,922,000
-
177,951,740,446
28,704,924,222
50,896,362,630
-
113,077,805,006
-
186,014,231,143
-
378,693,323,000
-
Sp.3 Tanjung Palas-Sekatak Buji (Section 1)
Sp. Tiga Apas - Simanggaris (Section 2) 34-RCP04
Simanggaris - Bts. Negara (Serudong) Total Civil Works
II.
GOODS Road Saftey Enforcement
2,114,004,409,953
PL
Total Goods III.
Consulting Services & Training CTC RRDP
-
-
-
-
-
-
-
PL
33,781,300,000
PL
41,611,883,000
DSC-3 (Jawa Timur - ADB) Road Safety Support
PL
8,256,578,000
Institutional Development for Road Network Management Road Safety Awareness Campaign and Training Overloading and Speed Enforcement Indonesia Transport Sector Development Strategy and Policy Study Integrated Vehicle Overloading Control Strategy HIV/AIDS and Anti-Trafficking Program
PL PL PL PL PL
6,074,599,000 -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
5,207,337,131
429,311,676
-
761,207,617
-
1,691,195,341
-
2,782,035,367
-
5,663,750,000
-
2,565,772,206
498,712,623
-
884,261,641
-
1,964,587,761
-
3,231,768,975
-
6,579,331,000
-
1,040,992,500
1,865,182,640
159,179,787
-
282,239,858
-
627,059,848
-
1,031,520,507
-
2,100,000,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
6,074,599,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
83,649,761,000
6,074,599,000
7,115,591,500
9,638,291,977
1,087,204,085
-
1,927,709,116
-
4,282,842,950
-
7,045,324,849
-
14,343,081,000
-
Total - ADB Loan No.2817-INO
2,197,654,170,953
108,822,378,295
109,863,370,795
187,590,032,423
29,792,128,307
-
52,824,071,746
-
117,360,647,956
-
193,059,555,992
-
393,036,404,000
-
Total - IDB + ADB
2,641,648,822,953
109,863,370,795
187,590,032,423
36,464,886,347
-
64,655,462,331
-
143,646,765,019
-
236,300,513,304
-
481,067,627,000
-
Total Consulting Services
PL
102,747,779,295
-
DSC-1 (Kalimantan -ADB)
PL
102,747,779,295
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM B : SUMMARY OF IMPLEMENTATION FOR FISCAL YEAR 2015 B. PHYSICAL IMPLMENTATION ( %)
No.
PAKET KONTRAK
[a]
TANGGAL PENANDATANGANAN KONTRAK
TANGGAL AKHIR KONTRAK (PHO)
[b]
[c]
KUMULATIF s.d TA.2014
PERKEMBANGAN FISIK TAHUN ANGGARAN 2015 Akhir Triwulan I Target Realisasi
Akhir Triwulan II Target Realisasi
Akhir Triwulan III Target Realisasi
Akhir Triwulan IV Target Realisasi
[d]
[e]
[f]
[g]
[h]
[i]
[j]
[k]
Jawa Tengah 1
24-RCP-01 Tambakmulyo - Wawar
13-Jan-15
-
-
-
-
-
-
-
-
-
-
2
24-RCP-02 Giriwoyo - Duwet (Section I)
13-Jan-15
-
-
-
-
-
-
-
-
-
-
3
24-RCP-03 Wawar -Congot
7-Jan-15
-
-
-
-
-
-
-
-
-
-
21-Aug-13
17-Oct-15
29.04%
Jawa Timur 4
28-RCP01A Jokosutro - Sendangbiru
34.49%
38.09%
56.50%
75.57%
87.45%
Kalimantan Barat 5
30-RCP01
6
30-RCP02
Sosok - Tayan; Tanjung- Bts. Kota Sanggau
-
15-Jan-15
Tembas - SIingkawang Sec.1 + Sec.2 Bypass Sambas
14-Nov-13
15-Dec-16
25.76%
37.05%
37.02%
48.13%
61.86%
69.32%
26-Nov-13
2-Dec-16
14.06%
30.90%
17.00%
40.56%
48.69%
67.56%
3-Nov-14
2-Nov-16
0.10%
2.77%
2.79%
6.71%
14.02%
30.18%
Galing - Tanjung Harapan 7
30-RCP03
Simpang Tanjung - Galing SP.3 Aruk /Bts. Serawak-Simpang. 3 Tanjung
Kalimantan Utara Tanjung Selor- SP.3 Tanjung Palas
8
34-RCP01
9
34-RCP02
Tanjung Palas -Sekatak Buji (Sec.2)
25-Jun-14
2-Sep-16
2.28%
5.01%
2.47%
16.56%
32.70%
52.69%
10
34-RCP03
SP.Tiga Apas - Simanggaris (Section 1)
14-Apr-14
25-Dec-16
6.48%
11.80%
7.56%
24.01%
42.75%
62.07%
11-Apr-14
30-Sep-17
0.52%
1.31%
1.41%
3.92%
8.09%
14.13%
11
34-RCP04
Sp.3 Tanjung Palas-Sekatak Buji (Section 1)
Sp. Tiga Apas - Simanggaris Simanggaris - Bts. Negara (Serudong)
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM C : STATUS / PROBLEM 2817-INO / IND-0161 Regional Roads Development Project (RRDP) - Jumlah Pinjaman 13-Feb-09 s/d
-
Tandatangan
:
7 Mei 2012 (ADB) & 17 April 2012 (IDB)
USD 180,000,000.00
-
Loan Efektif
:
3 Juli 2012 (ADB) & 2 Mei 2013 (IDB)
Asian Development Bank Islamic Development Bank
USD
85,000,000.00 21,686,601.05
31-Mar-15
- Penyerapan Kumulatif
: USD
2237 hari
- Waktu Terpakai (bulan)
:
`
1 Loan
: USD 245,000,000.00
- Realisasi Penyerapan TA-2015 :
74.57 IDR 0
2 Civil Works Jawa Tengah 1. 24 RCP-01 (CW-01)
2. 24 RCP-02 (CW-02)
3. 24 RCP-03 (CW-03)
- Kontrak sudah ditandatangani 12 Januari 2015 - Kontrak sudah dikirimkan ke IDB tamggal 4 Maret 2015 untuk mendapatkan persetujuan IDB
- Mempersiapkan Commencement Date
- Commencement Date menunggu pembayaran uang muka dan mobilisasi DSC-2 sebagai Enjinir
ULP agar mobilisasi Enjinir lebih cepat
- Kontrak sudah ditandatangani 12 Januari 2015 - Kontrak sudah dikirimkan ke IDB tamggal 4 Maret 2015 untuk mendapatkan persetujuan IDB
- Mempersiapkan Commencement Date
- Commencement Date menunggu pembayaran uang muka dan mobilisasi DSC-2 sebagai Enjinir
ULP agar mobilisasi Enjinir lebih cepat
- Kontrak sudah ditandatangani 7 Januari 2015 - Kontrak sudah dikirimkan ke IDB tamggal 4 Maret 2015 untuk mendapatkan persetujuan IDB
- Mempersiapkan Commencement Date
- Commencement Date menunggu pembayaran uang muka dan mobilisasi DSC-2 sebagai Enjinir
ULP agar mobilisasi Enjinir lebih cepat
- Mempersiapkan dokumen penagihan uang muka - Segera memperbaiki Draft Kontrak DSC-2 dalam proses Pokja
- Mempersiapkan dokumen penagihan uang muka - Segera memperbaiki Draft Kontrak DSC-2 dalam proses Pokja
- Mempersiapkan dokumen penagihan uang muka - Segera memperbaiki Draft Kontrak DSC-2 dalam proses Pokja
Jawa Timur 1. 28 RCP-01A (CW-04)
- SCM ke 3 sudah dilakukan tanggal 29 Januari 2015
- Addendum III sudah disetujui oleh ADB
- Addendum No.3 sudah diproses, ada penyesuaian harga satuan galian batu dimana quantitynya meningkat 300% agar dapat meningkatkan kemajuan dilapangan
- Balai V Jawa Timur meminta arus kas (Cash flow) harus dilakukan
- Di lapangan sering tidak bekerja diakibatkan cash flow (kas keuangan) tidak sehat perlu dukungan dari management kontraktor - Cashflow dan terbatasnya quarry material CTB
oleh Kontraktor PT. Hutama Karya di Jawa Timur seperti pembayaran dan tagihan
Kalimantan Barat 1. 30 RCP-01 (CW-05)
2. 30 RCP-02 (CW-06)
- Penandatanganan kontrak sudah dilakukan 15 Januari 2015 dan mengajukan uang muka
- Segera mengajukan uang muka
- Proses uang muka menunggu perpanjangan Loan Agreement
- Menunggu persetujuan ADB
- Masa pelaksanaan adalah 1095 hari kalender melampau jauh dari closing date
- Sedang diajukan proses perpanjangan loan
- Implemantasi LARP sudah selesai, laporan sedang disiapkan
- Penyusunan Laporan Pelaksanaan LARP untuk dikirim ke ADB
- Justifikasi Teknis sudah dibahas dan menunggu persetujuan
- sedang diproses oleh Pemkot Singkawang namun untuk wilayah Sambas perlu didiskusikan dengan Pihak terkait perihal
Addendum dari ADB - Implemantasi LARP belum selesai - Terdapat tambahan ruas jalan yang ditangani dan memerlukan
pendanaan kompensasi
update LARP 3. 30 RCP-03 (CW-07)
- Justifikasi Teknis Addendum No. 1 masih diproses - Implemantasi LARP belum selesai
- menunggu persetujuan ADB - sedang diproses oleh Pemkot Sambas
Kalimantan Utara 1. 34 RCP-01 (CW-08)
- Proses Justifikasi Teknik pada Enjinir dan Kontraktor - Akibat hujan yang terjadi dilapangan mengakibatkan longsoran dibeberapa lokasi (5 lokasi)
- Justifikasi Teknik sedang diproses di Bina Teknik
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
2, 34 RCP-02 (CW-09)
- Akibat hujan yang terjadi dilapangan mengakibatkan longsoran
- Justifikasi Teknik sedang diproses di Bina Teknik
dibeberapa lokasi (7 lokasi) - Proses Draft Justifikasi Teknik antara Enjinir dan Kontraktor sudah selesai di Balai dan sudah disampaikan ke Bina Teknik 3. 34 RCP-03 (CW-10)
4. 34 RCP04 (CW-11)
- LARAP (Land Acquisition Resettlement Plan) - Proses Justifikasi Teknik pada Enjinir dan Kontraktor
- Justifikasi Teknik sedang diproses
- Proses Justifikasi Teknik pada Enjinir dan Kontraktor - Desain awal proyek ini adalah relokasi dan tidak jadi dilakukan dan akan kembali ke jalan eksisting
- Perubahan lokasi ke jalan lama sepanjang + 17 km karena untuk relokasi perijinan lahan memerlukan waktu lama -
- Karena pekerjaan konstruksi akan mengikuti jalan eksisting kontraktor minta pembayaran untuk biaya desain -
3 Konsultan a Core Team Consultant
- Addendum I sudah disetujui ADB 19 Maret 2015
- Dapat menarik Invoice
b DSC -1 Kalimantan
- Draft Addendum I masih mengalami perbaikan
- segera memperbaiki untuk mendapatkan persetujuan ADB - Agar dapat segera menarik Invoice
c DSC-3 Jawa Timur
-
d Technical Assistance (TA) yang belum terkontrak CSP-4 : Road Safety Support
Status sampai 31 Maret 2014 Sedang evaluasi kombinasi teknis dan biaya, hasilnya segera dikirim ke ADB
CSP-5 : Institutional Devl for Road Network Management
Belum dimulai
CSP-6 : Road Safety Awareness Campaign and Training
Belum dimulai komentar atas Kerangka Acuan Kerja, belum ada tindak lanjut dari Kemenhub
CSP-7 : Overloading and Speed Enforcement
Penyampaian Usulan teknis dan Keuangan
CSP-8 : Indonesia Transport Sector Development Strategy and Policy
Hasil dari Evaluasi Usulan Teknis telah disampaikan ke Bank
CSP-9 : Integrated Vehicle Overloading Control Strategy
Belum dimulai
CSP-10 : HIV Aids and Trafficking program
Sedang evaluasi kombinasi teknis dan biaya, hasilnya segera dikirim ke ADB
CSP-11 : Design and Supervision Consultant -DSC-2 Central Java (IDB)
Sudah disetujui Draft Kontrak oleh IDB 3 Maret 2015
4 DIPA 2015 - Alokasi PHLN untuk DIPA 2015 sebesar Rp. 481,067,627,000
Pada Triwulan I TA mengajukan tagihan
2015 paket pekerjaan belum ada yang
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 28-RCP01A (Jawa Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 21 Agustus 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 8 September 2013
Oleh Penanggung Jawab Kegiatan
1-Mar-12
27-Jun-12
- Periode Kontrak
: 730 hari Kalender
Persetujuan Pemberi Pinjaman
15-Mar-12
6-Feb-13
- Tanggal Akhir Kontrak
: 17 Oktober 2015
- Nama kontraktor/konsultan/suplayer
: PT.Hutama Karya
Pasca Kualifikasi Undangan Lelang
24-Mar-12
1-Mar-13
30 Mei 201228Juni 2012
2 Mei 2013 4 Juni 2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
10-Jul-13
D4. STATUS TERAKHIR Status Kemajuan :
KONTRAK Tandatangan Kontrak
Rencana : 34.49 % ; Actual : 38.09 % ; Deviasi : +3.60 %
21-Aug-13
Status Penyerapan : Rp. 27,998,529,498 (29.99.%)
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
Waktu Terpakai : 523 hari (57.79 %)
9-Sep-13
Permintaan Uang Muka
Slipage : 382 hari (42.21 %)
18-Sep-13
Penarikan Uang Muka
Nilai Addendum 3. -untuk variasi order, tambahan waktu dan tambahan nilai kontrak
9-Oct-13
D5. STATUS PENYERAPAN
Dalam Rupiah PENYERAPAN TA 2015
NILAI KONTRAK *)
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
112,823,335,000.00
23,011,025,595
Triwulan 1
Triwulan 2
1,670,068,629
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
2,961,177,008
Triwulan 3
-
6,578,924,510
Triwulan 4
-
############
TOTAL TA 2015
-
22,032,567,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP01 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 12 Januari 2015
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 1 Desember 2014
15-Juni-2012
- Periode Kontrak
: 1,095 hari kalender
25-Juni-2013
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
: PT. Pembangunan Perumahan - PT. Armada Hada Graha, JO
Oleh Penanggung Jawab Kegiatan
8-Apr-12
Persetujuan Pemberi Pinjaman
22-Apr-12
18-Sep-12 (Comment)
Undangan Lelang
30-Apr-12
1-May-14
5 Juli 2012-3 Sept 2012
10 Juli 2014-24 Agustus 2014
17-Sep-12
21-Sep-14
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
7-Okt-2014
12-Jan-15
* Commencement Date menunggu pembayaran uang muka dan mobilisasi Enjinir
Persetujuan oleh Bappenas (bila diperlukan)
* Nilai Kontrak : Rp. 243,741,564,000
Persetujuan Pemberi Pinjaman
1-Dec-14
* No, Kontrak : 01/24-RCP-01/NR/IDB/0161/0115
Permintaan Uang Muka
* Dokumen Kontrak sudah dikirim ke PMU tanggal 27 Pebruari 2015
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 243,741,564,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
3,602,739,238
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
6,387,975,695
Triwulan 3
-
14,192,336,618
Triwulan 4
-
23,346,553,448
TOTAL TA 2015
-
47,529,605,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP02 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 13 Januari 2015
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 1 Desember 2014
15-Juni-2012
- Periode Kontrak
: 730 hari kalender
25-Juni-2013
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
: PT. Hutama Karya
8-Apr-12
Oleh Penanggung Jawab Kegiatan
22-Apr-12
Persetujuan Pemberi Pinjaman
18-Sep-12 (Comment)
Undangan Lelang
30-Apr-12
1-May-14
5 Juli 2012-3 Sept 2012
10 Juli 2014-24 Agustus 2014
17-Sep-12
21-Sep-14
26-Sep-12
7-Okt-2014
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
* Commencement Date menunggu pembayaran uang muka dan mobilisasi Enjinir
13-Jan-15
* Nilai Kontrak : Rp. 142,000,000,000
Persetujuan oleh Bappenas (bila diperlukan)
* No, Kontrak : HK.02.03/BJGD/24-RCP-02/2015/01
1-Dec-14
Persetujuan Pemberi Pinjaman
* Dokumen Kontrak sudah dikirim ke PMU tanggal 27 Pebruari 2015
Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 142,000,000,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
1,991,263,336
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
3,530,686,222
Triwulan 3
-
7,844,220,102
Triwulan 4
-
12,903,830,341
TOTAL TA 2015
-
26,270,000,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP03 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 7 Januari 2015
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 1 Desember 2014
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 360 hari kalender
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
: PT. Jaya Konstruksi
Pasca Kualifikasi 24-Jan-14
Undangan Lelang
1-May-14 25-Apr-14
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan
10 Juli 2014-24 Agustus 2014
Oleh Penanggung Jawab Kegiatan
21-Sep-14
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK 7-Okt-2014
Tandatangan Kontrak
* Commencement Date menunggu pembayaran uang muka dan mobilisasi Enjinir
7-Jan-15
* Nilai Kontrak : Rp. 58,253,088,000
Persetujuan oleh Bappenas (bila diperlukan)
* No, Kontrak : 02/24-RCP-03/NR/IDB/0161/0115
1-Dec-14
Persetujuan Pemberi Pinjaman
* Dokumen Kontrak sudah dikirim ke PMU tanggal 27 Pebruari 2015
Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 58,253,088,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
883,115,663
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
1,565,842,271
Triwulan 3
-
3,478,873,693
Triwulan 4
-
5,722,786,374
TOTAL TA 2015
-
11,650,618,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP01 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 15 Januari 2015
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 1,095 hari kalender
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
: PT. Yasa Patria Perkasa
Pasca Kualifikasi 23-Apr-12
Undangan Lelang
26-Feb-13
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan 21 Mei 2013 - 11 Sep 2013 11-Okt-2013
29 Juni 2012 27 Agust 2012
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
Catatan : Proses Usulan untuk Tender Ulang KONTRAK Tandatangan Kontrak
* Commencement Date menunggu pembayaran uang muka
15-Jan-15
Persetujuan oleh Bappenas (bila diperlukan)
* Nilai Kontrak : Rp. 465,647,542,528.81
Persetujuan Pemberi Pinjaman
* No, Kontrak : 02/30-RCP-01/RB/ADB/2817/2015
Permintaan Uang Muka
* Pre Construction Meeting (PCM) tanggal 11 Pebruari 2015
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 465,647,542,528.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
5,502,988,120
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
9,757,285,231
Triwulan 3
-
21,678,021,815
Triwulan 4
-
35,660,589,835
TOTAL TA 2015
-
72,598,885,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP02 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 14 Nopember 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 28 November 2013
Oleh Penanggung Jawab Kegiatan
31-Mar-12
27-Jun-12
- Periode Kontrak
: 1.095 hari kalender
Persetujuan Pemberi Pinjaman
14-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 15 Desember 2016
- Nama kontraktor/konsultan/suplayer
: PT.Brantas Abipraya (persero)
Pasca Kualifikasi
PT.Citra Persada
Undangan Lelang
23-Apr-12
26-Feb-13
PT.Trifa Abadi, JO
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan 23 Mei 2013 - 28 Agust 2013 13-Sep-13
29 Juni 2012 27 Agust 2012
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK 14-Nov-13
Status Kemajuan :
27-Nov-13
Status Penyerapan : Rp. 104,672,375,854 (35.77%)
Permintaan Uang Muka
28-Nov-13
Waktu terpakai : 464 hari (42.37 %)
Penarikan Uang Muka
17-Dec-13
Slipage : 631 hari (57.63 %)
Tandatangan Kontrak
Rencana : 37.05 % ; Actual : 32.02 % ; Deviasi : - 0.03 %
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 292,603,385,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
43,890,507,750
Triwulan 1
4,890,543,605
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
8,671,359,569
Triwulan 3
-
19,265,387,000
Triwulan 4
-
31,691,755,826
TOTAL TA 2015
-
64,519,046,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP03 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 26 November 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 29 November 2013
Oleh Penanggung Jawab Kegiatan
31-Mar-12
27-Jun-12
- Periode Kontrak
: 1.095 hari kalender
Persetujuan Pemberi Pinjaman
14-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 2 Desember 2016
- Nama kontraktor/konsultan/suplayer
: PT.Waskita Karya (persero),
Pasca Kualifikasi
PT.Yasa Patria Perkasa, JO
Undangan Lelang
23-Apr-12
26-Feb-13
29 Juni 2012 27 Agust 2012
24 Mei 2013 -5 Sep 2013 12-Oct-13
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK 26-Nov-13
Status Kemajuan :
28-Nov-13
Status Penyerapan : Rp. 28,494,960,706 (11.92 %)
Permintaan Uang Muka
29-Nov-13
Waktu Terpakai : 477 hari (56.44 %)
Penarikan Uang Muka
17-Dec-13
Slipage : 618 hari (43.56 %)
Tandatangan Kontrak
Rencana : 30.90 % ; Actual : 17.003 % ; Deviasi : -13.897 %
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 238,974,973,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
35,846,245,950
Triwulan 1
3,236,199,505
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
5,738,068,291
Triwulan 3
-
12,748,419,940
Triwulan 4
-
20,971,294,263
TOTAL TA 2015
-
42,693,982,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP01 (Kalimantan Utara)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 3 Nopember 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 730 hari kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 11 Desember 2016
- Nama kontraktor/konsultan/suplayer
: PT. Waskita Karya (Persero)
Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
Comment ADB 4
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
Mar 2014,
4 -Okt-2012
Klarifikasi -
KONTRAK Tandatangan Kontrak
Status Kemajuan :
3-Nov-14
Rencana : 2.760 % ; Actual : 2.785 % ; Deviasi : 0.025 %
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
Status Penyerapan : Rp. 28,495,537,199 (15 %)
Permintaan Uang Muka
Waktu terpakai : 103 hari (14.11 %)
Penarikan Uang Muka
Slipage : 627 hari (85.89 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 189,970,248,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
2,749,038,484
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
4,874,288,662
Triwulan 3
-
10,829,337,614
Triwulan 4
-
17,814,382,240
TOTAL TA 2015
-
36,267,047,000
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP02 (Kalimantan Utara)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 25 Juni 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 Mei 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 730 Hari kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 2 September 2016
- Nama kontraktor/konsultan/suplayer
: PT.Brantas Abipraya PT.Mahir Jaya Mahakam Raya, J.O
Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013 9 Maret 2014, Proses persetujuan Mentri
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
4 -Okt-2012 Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
25-Jun-14
Status Kemajuan :
Persetujuan oleh Bappenas (bila diperlukan)
Rencana : 5.013 % ; Actual : 2.471 % ; Deviasi : - 2.542 %
Persetujuan Pemberi Pinjaman
Status Penyerapan : Rp. 28,494,960,706 (17.23%)
Permintaan Uang Muka
11-Aug-14
Waktu Terpakai : 203 hari (27.81 %)
Penarikan Uang Muka
29-Aug-14
Slipage : 527 hari (72.319 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 165,332,328,425.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
1,914,004,062
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
3,393,698,688
Triwulan 3
-
7,539,871,230
Triwulan 4
-
12,403,173,021
TOTAL TA 2015
-
25,250,747,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP03 (Kalimantan Utara)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 14 April 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 Mei 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 900 Hari Kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 27 September 2015
- Nama kontraktor/konsultan/suplayer
: PT.Pembangunan Perumahan (Persero) Tbk PT.Perdasa,JO
Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
4 -Okt-2012
11-Des-2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK Tandatangan Kontrak
11-Apr-14
Status Kemajuan :
14-May-14
Status Penyerapan : Rp. 66,336,241,703 (22.95%)
Rencana : 11.799 % ; Actual : 7.561 % ; Deviasi : -4.238 %
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka
3-Jul-14
Waktu Terpakai : 259 hari (28.78 %)
Penarikan Uang Muka
4-Aug-14
Slipage : 641 hari (71.22 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 289,000,000,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
(f)
(g) -
Triwulan 1
Triwulan 2
Triwulan 3
Triwulan 4
TOTAL TA 2015
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
4,611,448,056
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
8,176,505,751
-
18,165,961,726
-
29,883,211,466
-
60,837,127,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP04 (Kalimantan Utara)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 11 April 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 May 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 1095 Hari Kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 10 April 2017 : Butt Halla Corporation
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
4 -Okt-2012
11-Des-2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR KONTRAK Tandatangan Kontrak
11-Apr-14
Status Kemajuan :
14-May-14
Status Penyerapan : Rp. 60,945,395,586 (16.95%)
Persetujuan oleh Bappenas (bila diperlukan)
Rencana : 1.31 % ; Actual : 1.41 % ; Deviasi : +0.10 %
Persetujuan Pemberi Pinjaman Permintaan Uang Muka
23-Jul-14
Penarikan Uang Muka
Waktu terpakai : 176 hari (16.07 %)
20-Aug-14
Slipage : 919 hari (83.93 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 359,652,598,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
4,130,633,761
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
7,323,979,429
Triwulan 3
-
16,271,881,171
Triwulan 4
-
26,767,427,639
TOTAL TA 2015
-
54,493,922,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Core Team Consultant (CTC)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 12 Februari 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 24 Februari 2014
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 42 bulan
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
: 31 Desember 2016
- Nama kontraktor/konsultan/suplayer
: Renardet SA in JV with
Pasca Kualifikasi
PT. Widya Graha Asana
Undangan Lelang
PT. Multy Phibeta
Persetujuan Pemberi Pinjaman
PT.Anugerah Kridapradana PT. Disiplan Consult
Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK Tandatangan Kontrak
12-Feb-14
* Status Penyerapan : IDR 2,920,875,000 dan USD 178,860 untuk Uang Muka
24-Feb-14
* Kontrak Awal
dan Invoice 1 USD 10,751.46
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
2-Oct-14
Permintaan Uang Muka
27-Oct-14
Penarikan Uang Muka
: USD 1,192,400 dan IDR 19,472,500,000
* Kontrak Addendum 1 : USD 1,473,900 dan IDR 22,584,677,000 Nol ADB : 19 Maret 2015
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 33,781,300,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
429,311,675.57
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
761,207,616.69
Triwulan 3
-
1,691,195,340.73
Triwulan 4
-
2,782,035,367.01
TOTAL TA 2015
-
5,663,750,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Design and Supervision Consultant -1 Kalimantan
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
37 bulan
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
Nopember 2016
- Nama kontraktor/konsultan/suplayer
:
CECI Engineriing Consultant in Ass
Pasca Kualifikasi
21 November 2013 11 November 2013
PT. Wira Widyatama ; PT. Seecons 26-Feb-13
Undangan Lelang
PT. Hasfarm Dian Konsultan
0-Jan-00
Persetujuan Pemberi Pinjaman
PT. Yodya Karya, PT. Pola Agung Consulting
Evaluasi Pengadaan 24 Mei 2013 5 Sep 2013
Oleh Penanggung Jawab Kegiatan
12-Oct-13
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK 26-Nov-13
* Status Penyerapan : IDR 6,074,599,000 dan USD 117,984 untuk Uang Muka
28-Nov-13
* Kontrak Awal
: USD 936,574 dan IDR 30,372,995,000
Permintaan Uang Muka
9-Dec-13
* Addendum I
: USD 589,920 dan IDR 36,353,305,000
Penarikan Uang Muka
28-Mar-14
Tandatangan Kontrak
dan Invoice 1-10 : USD 99,065
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
belum disetujui ADB masih perlu perbaikan atas usulan addendum I
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 41,611,883,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
-
Triwulan 1
498,712,622.51
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
884,261,641.13
Triwulan 3
-
1,964,587,761.17
Triwulan 4
-
3,231,768,975.19
TOTAL TA 2015
-
6,579,331,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Design and Supervision Consulant -2 Jawa Tengah
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
- Periode Kontrak
:
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
: Botek Bosphorus Technical Engineering Corp JO
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
7-Jun-13
Pasca Kualifikasi
Associated Consulting Engineers-ACE,
Undangan Lelang
PT.Kwarsa Hexagon, PT.Binatama Wirawreda
Persetujuan Pemberi Pinjaman
Konsultan, PT.Tata Guna Patria, PT. Caturbina GP
Evaluasi Pengadaan
15 Nop 2013 Mei 2014 2013
Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK Tandatangan Kontrak Draft Kontrak sudah disetujui Islamic Development Bank tanggal 3 Maret 2015
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
195,639,803.07 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
346,886,396.89
Triwulan 3
-
770,686,650.04
Triwulan 4
-
1,267,787,150.01
TOTAL TA 2015
-
2,581,000,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Design and Supervision Consultant -3 Jawa Timur
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Maret 2015
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 6 Oktober 2013 : 11 Nopember 2013
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 25 bulan
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
: 16 Nopember 2015 : PT. Perentjana Djaja
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang
26-Feb-13
Persetujuan Pemberi Pinjaman
0-Jan-00
Evaluasi Pengadaan 24 Mei 2013 5 Sep 2013
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
12-Oct-13
D4. STATUS TERAKHIR
KONTRAK 26-Nov-13
Tandatangan Kontrak
* Status Penyerapan : IDR 1,040,992,500 untuk Uang Muka dan Invoice 1-13 : IDR 1,865,182,640
Persetujuan oleh Bappenas (bila diperlukan) 7-Nov-13
Persetujuan Pemberi Pinjaman
* Kontrak Awal
: IDR 6,939,950,000
Permintaan Uang Muka
26-Nov-13
* Kontrak Addendum I: IDR 7,505,980,000
Penarikan Uang Muka
9-Dec-13
* Nol ADB : 29 Oktober 2014
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e) 8,256,578,000.00
Dalam Rupiah PENYERAPAN TA 2015
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
1,040,992,500.00
Triwulan 1
159,179,787.01
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
282,239,857.88
Triwulan 3
-
627,059,848.25
Triwulan 4
-
1,031,520,506.86
TOTAL TA 2015
-
2,100,000,000.00
-
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
FORMULIR E : RINCIAN DOKUMEN ANGGARAN Nomer NPPHLN : ADB 2817-INO, Register : 10846401 IDB 0161-IND, Register : 10848804 PLN Nama Kegiatan dan Nomor Kode DIPA *
Dana Pendamping
Rupiah Ekivalen (juta)
Valas
(a)
Rupiah (dalam juta)
(b)
(c)
Rupiah Murni
Rencana Penarikan PLN 2015
Pagu
Realisasi
Pagu
Realisasi
( Juta Rupiah )
(d)
(e)
(f)
(g)
(h)
1. Islamic Development Bank (IDB) Civil Works Jawa Tengah 1
24-RCP-01
Tambakmulyo - Wawar
USD
2
24-RCP-02
Giriwoyo - Duwet
USD
3
24-RCP-03
Wawar - Congot
USD
DSC-2 (IDB - Jawa Tengah)
USD
-
47,529.61
-
26,270.00
3,802.37
47,529.61
9,461.15
2,101.60
26,270.00
6,360.72
932.05
11,650.62
2,143.35
-
206.48
2,581.00
-
-
17,965.21
-
7,257.90
-
11,650.62
Consultant Services 1
CSP-11 Total _IDB
USD
7,042.50
88,031.22
2,581.00 88,031.22
2. Asian Development Bank (ADB)
Jawa Timur 4
28-RCP01A
Jolosutro - Sendang biru
USD
1,762.61
22,032.57
22,032.57
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
PLN Nama Kegiatan dan Nomor Kode DIPA * Valas
Rupiah (dalam juta)
Rupiah Ekivalen (juta)
Dana Pendamping Pagu
Realisasi
Rupiah Murni Pagu
Realisasi
Rencana Penarikan PLN 2015 ( Juta Rupiah )
Kalimantan Barat 5
Sosok - Tayan 30-RCP01
USD Tanjung- Bts. Kota Sanggau
5,807.91
72,598.89
35,000.00
5,161.52
64,519.05
25,000.00
72,598.89 -
Tebas - Singkawang Sec.1 + Sec.2 6
30-RCP02
Bypass Sambas
USD
Galing - Tanjung Harapan
64,519.05 -
Simpang Tanjung - Galing 7
30-RCP03
Simpang Aruk /Bts. SerawakSp.3 Tanjung
USD
3,415.52
42,693.98
42,693.98
20,000.00 -
Kalimantan Utara 8
34-RCP01
9
34-RCP02
10
34-RCP03
11
34-RCP04
Consultant Services
Tanjung Selor- SP.3 Tanjung Palas Sp.3 Tanjung Palas-Sekatak Buji (Section 1) Tanjung Palas -Sekatak Buji (Sec.2) SP.Tiga Apas - Simanggaris (Section 1) Sp. Tiga Apas - Simanggaris (Section 2) Simanggaris - Bts. Negara (Serudong)
USD
USD USD
USD
2,901.36
2,020.06 4,866.97
4,359.51
36,267.05
25,250.75 60,837.13
54,493.92
33,415.77
-
36,694.60
-
19,310.46
-
36,267.05
25,250.75 60,837.13
54,493.92
20,580.99 -
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
PLN Nama Kegiatan dan Nomor Kode DIPA *
Rupiah (dalam juta) Dana Pendamping
Rupiah Ekivalen (juta)
Valas
Pagu
Realisasi
Rupiah Murni Pagu
Realisasi
Rencana Penarikan PLN 2015 ( Juta Rupiah )
DG Bina Marga , KemenPU 1
CSP-1
Core Team Consultant
USD
2
CSP-2
DSC-1 (ADB-Kalimantan)
USD
3
CSP-3
DSC-3 (ADB-Jawa Timur)
USD
4
CSP-4
5
CSP-10
Road Saftey Engineering Support HIV /AIDS and Anti Trafficking Program
Total _ADB
TOTAL (IDB+ADB) Asumsi APBN 2015: 1 USD = Rp.12,500 * DIPA 2015 Revisi -1
453.10
5,663.75
-
-
526.35
6,579.33
-
-
168.00
2,100.00
-
-
-
-
-
-
197,259.72
-
USD
-
-
USD
-
-
31,442.91
393,036.40
USD
USD
38,485.41
481,067.63
215,224.93
-
5,663.75 6,579.33 2,100.00 393,036.40
481,067.63
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Regional Roads Development Project (RRDP) Detail Contract, Allocation and Disbursement DIPA 2014 as of 31 March 2015 ADB Loan No.2817-INO & IDB Financing No.IND-0161 Current ADB Loan No. 2817-IND and IDB Financing No. IND-0161 Total Disbursed to end of Dec (US$)
Loan Amount (US$) Category
ADB
Civil Work Road Safety Equipment
Consultant Services
IDB
% Disbursed
155,000.00
53,500.00
20,300.87
9.74
12,200.00
3,000.00
1,385.99
9.12
Road Sector Development Program
6,900.00
-
-
-
Road Sector Program
3,300.00
-
-
-
Unallocated
2,600.00
8,500.00
180,000.00
65,000.00
Loan Amount
-
-
21,686.86
8.85
Current Loan Allocation and Disbursement (%) to Date 100 90
% complete
80 70 60 50 40 30 20 10
Actual Disbursement
43311
43281
0
43190
0
43100
0
43008
0
42916
0
42825
Planned Disbursment
0
42735
0
42643
0
42551
0
42460
42369
42277
42185
Original based PAM
42094
42004
41912
41820
8.85178002 5.770582959 2.600906139 0 0 0 2.491936343 2.443779608 41729
0
41639
0
41547
0
41455
41364
0
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix 1 Regional Roads Development Project (RRDP)
The Overall Financial Status as of 30 March 2015 ADB Loan No.2817-INO & IDB Financing No.IND-0161 in US$ 000's
1 USD = IDR 9,000
Loan Cat
Details of Category
1
2
1
Civil Works
2
Goods : Road Safety Equipment
3
Consultant Services
3A
Core Team Consultant
3E 3F 3G 3H 3I 3J 4
Road Safety Support Institutional Development for Road Network Management Road safety awareness campaign and training Overloading and Speed Enforcement Indonesia Transport Sector Development Strategy and Integrated Vehicle Overloading Control Strategy HIV/AiDS and Anti Trafficking Prevention Program Unallocated TOTAL 1 USD = IDR 11,500
Current Balance
IDB
ADB
IDB
3a
3b
4a
4b
53,500.0 104,683.7
IDB
Year to Date
ADB IDB ADB IDB
5a = (3a-4a) 5b = (3b-4b)
6a
6b
7a
-
-
-
7b
ADB 8a
IDB
ADB
IDB
50,316.3
21,209.5
-
1,300.0
-
6,000.0
-
3,280.7
-
2,719.3
-
-
-
432.61
13.19%
2,848.06
86.81%
5,300.0
-
3,305.3
-
1,994.7
-
-
-
714.76
21.62%
2,590.50
78.38%
-
3,000.0
-
0.0
-
-
19.39% -
-
-
84,382.80
80.61%
32,291
-
-
-
-
3,000.0
350.8
0.0
-
400.0
0.0
900.0
-
900.0
-
900.0
0.0
3,000.0
-
3,000.0
-
3,000.0
0.0
2,200.0
-
2,200.0
-
2,200.0
0.0
1,300.0
-
1,300.0
-
1,300.0
0.0
800.0
-
800.0
-
800.0
0.0
300.0
-
300.0
-
300.0
0.0
2,600.0
8,500.0
32,709.5
0.00
0.00
21,686.86
19.39%
90,131.97
80.61%
-
0.0
-
8,500.0
-
0.0
400.0
68,181.2
56.55%
1,994.7
350.8
32,290.5
310.60
0.0
-
111,818.8
43.45%
21,209.5
1,300.0
-
180,000.0 65,000.0
238.61
50,316.3
400.0
2,600.0
-
IDB
900.0
8,500.0
-
ADB
%=(8a/4a) 8b %=(8b/4b) 9a=(4a-8a) % =(9a/4a) 9b=(4b-8b) %=(9b/4b) 10a=(3a-4a) 10b=(3b-4b)
-
3,000.0
- 20,300.87
Projected Loan Balance
Outstanding Value of Awarded Contract
Cummulative to Date
-
549.2
32,290.5
ADB
Current Quarter
1,300.0
2,600.0
Assumption to Government Budget in FY 2015
Awarded Contracts
ADB
155,000.0
Design and Supervision 3B Kalimantan Region Construction Supervision 3K Central Java Region Design and Supervision East 3C Java Region 3D
Original Loan Allocation
Disbursement
65,461.85
32,709.48
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix 2 PROCUREMENT PLAN OF IMPLEMENTATION SUPPORT AND SECTOR INSTITUTIONAL DEVELOPMENT REGIONAL ROADS DEVELOPMENT PROJECT Status : Project Cost Ref. No
Name of Package Allocated (US$)
1
Implementation Support
a
CSP-1 : Core Team Consultant
b
CSP-2 : Design and Supervision Consultant (DSC-1 , Kalimantan)
6,000,000
EE/OE (US$)
3,914,374
5,300,000
5,827,926
900,000
777,754
Contract ( Excl.VAT ) US $
IDR ( mil )
1,192,400
19,472.50
Evaluation and Submission Result of Technical Submission Submissi shortlist (including Proposal Evaluation Review Invitation of RFP and TOR) of TOR , on of Metoda By Bank Plan/ NOL REOI Advert to Short- Technical OE and EOI by Seleksi (Prior/Po Actual dari Donor of REOI List and Draft REOI Consulta Send to NOL by Send to NOL by st) Consultants Financial to the Bank nts the Bank Bank Bank Bank Proposals
QCBS
Plan
01-Jun-11
01-Jun-11 30-Jun-11
01-Jun-11
23-Feb-12
10-Jul-12
Actual
27-Oct-11
13-Dec-11 19-Dec-11
23-May-12
28-May-12
29-Jan-13
Plan
01-Jun-11
01-Jun-11 30-Jun-11
01-Jun-11
23-Feb-12
10-Jul-12
Actual
27-Oct-11
13-Dec-11 19-Dec-11
15-Jun-12
15-Jun-12
07-Dec-12
01-Jun-11
01-Jun-11 30-Jun-11
01-Jun-11
23-Feb-12
10-Jul-12
d
e
CSP-11 :Design and Supervision Consultant (DSC-2 (Central Java Province)
CSP-5: Capacity Development Program
3,000,000
2,778,567
936,574
30,373.00
QCBS
Prior
-
6,939.95
QCBS
Prior
900,000
QCBS
QCBS
400,000
392,666
QCBS
g
262,402
QCBS
h
CSP-6 :Road Safety Awareness Campaign & Trainning
3,000,000
CSP-7 : Overloading and Speed Enforcement
2,200,000
k
800,000
CSP-8 : Indonesia Transport Sector Development Strategy and Policy Study
1,300,000
TOTAL
QCBS
17-Jul-12
31-Aug-12
30-Sep-12
07-Jun-13
11-Oct-12
21-Oct-12
28-Oct-12
28-Oct-12
29-Oct-12
11-Oct-12
21-Oct-12
28-Oct-12
28-Oct-12
29-Oct-12
22-Dec-14
07-Jun-13
11-Nov-12
31-Oct-13
15-Jul-12
22-Jul-12
05-Sep-12
05-Oct-12
12-Oct-12 20/12/2014
19-Dec-14
22-Dec-14
19-Dec-14
Actual
5-Jun-12
04-Jan-12 20-Jan-12
20-Jun-12
20-Jun-12
07-Jun-13
16-Jul-13
15-Nov-13
18-Jun-14
04-Dec-14
24-Dec-14
28-Dec-14
01-Apr-15
30-Sep-13
Plan
01-Jan-12
23-Dec-11 01-Jan-12
01-Jan-12
22-Jan-14
Status
Action Plan
25-Nov-12
18-Nov-13
08-Oct-13
12-Feb-14
25-Feb-14
11-Nov-12
25-Nov-12
21-Nov-13
16-Dec-13
11-Nov-12
25-Nov-12
16-Oct-13
18-Oct-13
24-Nov-14
5-Jan-15
12-Dec-14
17-Feb-15
03-Mar-15
Has not yet started 01-Jan-12
23-Dec-11 01-Jan-12
01-Jan-12
09-Oct-14
23-Oct-14
07-Jan-15
23-Feb-15
04-Mar-15
11-Mar-15
08-Jul-14 12-Aug-14
20-Sep-14
28-Oct-14
09-Dec-14
29-Dec-14
23-Feb-15
12-Mar-15
20-Mar-15
23-Dec-11 01-Jan-12
01-Jan-12
09-Oct-14
23-Oct-14
07-Jan-15
23-Feb-15
04-Mar-15
11-Mar-15
08-Jul-14 12-Aug-14
20-Sep-14
28-Oct-14
09-Dec-14
29-Dec-14
23-Feb-15
12-Mar-15
20-Mar-15
23-Dec-11 01-Jan-12
01-Jan-12
18-Mar-15
25-Mar-15
01-Apr-15
-
-
15-Apr-15
Prior
01-Jan-12
Has not yet started
23-Dec-11 01-Jan-12
01-Jan-12
01-Jan-12
23-Dec-11 01-Jan-12
26-Sep-14
19-Nov-14
04-Dec-14
Plan
23-Dec-11 01-Jan-12
07-Nov-15 The Evaluation Combination and Result of Negotiation and Draft Contract send by BAPEKON to Minister on 1 April 2015.
Waiting Approval from Minister
Technical Evaluation is being conducted by POKJA 18-Mar-15
25-Mar-15
01-Apr-15
-
-
15-Apr-15
22-Apr-15
Technical Evaluation is being conducted by POKJA
ADB will confirm again to DGLT in On Meeting on 20 Januari at ADB the event of Bappenas Meeting Office, DGLT was informed that they on April 2015 will submitt the TOR and cost Estimates in two weks after meeting, but untill now such document have not submitted yet.
01-Jan-12
Has not yet started
01-Jan-12
25
Technical Evaluation has been finished by the Pokja, the report will be send to PMU.
26-Jan-15
Prior
01-Jan-12
Prior Actual
01-Sep-16
19-Jan-15
Prior 01-Jun-14
33
ADB will confirm again to DGLT in On Meeting on 20 Januari at ADB the event of Bappenas Meeting Office, DGLT was informed that they on April 2015 will submitt the TOR and cost Estimates in two weks after meeting, but untill now such document have not submitted yet.
Prior
01-Jan-12
06-Dec-17
22-Apr-15
Prior
01-Jan-12
46
Need further discussion with 3 The activity is propose to change for th Floor- Bina Marga to speed up Purchasing of Equipment for Road the process Routine Maintenance
Prior
Actual
QCBS
07-Oct-12
07-Dec-12
Plan j
30-Sep-12
15-Jun-12
Actual
CSP-9 : Integrated Vehicle Overloading Control Strategy
31-Aug-12
25-Mar-12
Actual
QCBS
17-Jul-12
01-Jun-11
Plan i
29-Oct-12 13-Dec-13
15-Jun-12
Plan QCBS
28-Oct-12
01-Jun-11 30-Jun-11
Actual
Road Sector Institutional Development
28-Oct-12
Prior
HIV/AIDS Campaign Programs 2
21-Oct-12
13-Dec-11 19-Dec-11
Plan 300,000
11-Oct-12
01-Jun-11
Actual CSP-10 :Human Trafficking Prevention and
07-Oct-12 18-Sep-13
27-Oct-11
Plan CSP-4: Road Safety Engineering Support
30-Sep-12
Plan
Actual
f
31-Aug-12
Result of Evaluation Combination (Technical Negotiatio and Financial Proposals) n and ADB/IDB Service Draft of Approval Sign Period Completion Start Send to Contract of Draft Contract (Month) Date Date Send to NOL by Minister NOL by Send to Contract Bank Bank of Public Minister ADB/IDB Works
Prior
c
CSP-3 : Design and Supervision Consultant ( DSC-3 , East Java Province)
17-Jul-12
Opening of Financial Proposal
31- March -2015
10-Jul-14
24-Sep-14
26-Jan-15
Waiting Approval from ADB for ADB have Comment on 6 February 2015, the response has the Technical Evaluation been sent to ADB 30 March 2015
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 3 Regional Road Development Project (RRDP) Progress and Cost Monitoring For Civil Works Status March 2015 No.
Contract No.
Contract Description
Type of Works
Estimated Cost
Contractor
IDR (x106)
1
2
3
01/24-RCP-01/NR/IDB/0161/0115 Tambakmulyo - Wawar
HK.02.03/BJGD/24-RCP02/I/2015/01
Giriwoyo - Duwet
02/24-RCP-03/NB/IDB/0161/0115 Wawar - Congot
New Road, Widening, Resurfacing New Road, Widening, Resurfacing, Reconstruction
Widening; Reconstruction
Contract Sign Category Procurement Date Method
Contract Price (IDR 10⁶) Including Tax Original Addendum
ADB/IDB Financing Ratio (%)
PT. PP (Persero)-PT.Armada Hada 278,810,582 Graha, JO
12-Jan-15
Civil Works
ICB
243,741,564
100
171,759,932 PT.Hutama Karya
13-Jan-15
Civil Works
ICB
142,000,000
100
7-Jan-15
Civil Works
ICB
58,253,088
100
71,444,835
PT.Manggala Konstruksi Manggala Pratama, Tbk
Cost During this Quarter (IDR)
Cummulative Cost (IDR)
Actual
Planned
ADB Share
Actual as % of Planned
To Last Quarter
0
11,528,920,191
0
0.00
27,380,463,350
Physical Progress % Planned to date
Actual as % Scheduled of Planned
Actual
Difference
New Road
01-28-RCP01A/RB/ADB/2817/0813
Jolosutro - Bale kambang Reconstruction Sendang biru
151,916,793 PT.Hutama Karya
21-Aug-13
Civil Works
ICB
93,350,000
5
02/30-RCP01/RB/ADB/2817/2015
Sosok - Tayan: Sp.Tanjung Reconstruction - Bts.Kota Sanggau
PT. Yasa Patria Perkasa ; PT. Budi 608,466,493 Bakti Prima
15-Jan-15
Civil Works
ICB
465,647,542
70.00
6
02-30-RCP02/RB/ADB/2817/1113
Tebas - Singkawang (Section 1); Tebas Singkawang (Section 2) Bypass Sambas
Reconstruction Resurfacing
430,578,648
PT.Brantas Abipraya-Tri Citra Perdana-Trifa Abadi, JO
14-Nov-13
Civil Works
ICB
292,603,385
70.00
0
3,731,326,220
0
0.00
7
03-30-RCP02/RB/ADB/2817/1113
Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
Reconst + widening Reconstruction
333,214,553
PT Waskita Karya - Yasa Patria Perkasa, JO
27-Nov-13
Civil Works
ICB
238,974,973
70.00
0
10,772,434,704
0
0.00
64,409,091,802
8
01-34-RCP/LOAN/PJN.III/11.14
3-Nov-14
Civil Works
ICB
189,970,248
70.00
0
5,248,877,952
0
0.00
9
02-34-RCP/LOAN/PJN.III/06.14
Sp.3 Tanjung Palas Sekatak Buji (Section 2)
Reconstruction Grade Improvement
215,483,495
25-Jun-14
Civil Works
ICB
165,332,338
70.00
0
4,700,624,704
0
10
03-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis (Sect 1)
Reconstruction Resurfacing
322,919,917 PT.Pemb. Perumahan- PT.Perdasa JO
11-Apr-14
Civil Works
ICB
289,000,000
70.00
0
11,112,868,296
11
04-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis (Sect 2); Simanggaris Bts.Negara
Reconstruction Resurfacing
407,483,774 Halla Corporation
11-Apr-14
Civil Works
ICB
359,652,697
70.00
0
0
4
Actual to date Total ADB Share
112,823,335
70.00
27,380,463,350
17,423,931,223
38,909,383,541
70
34.49
38.09
3.60
104,672,375,855 104,672,375,855
66,609,693,726
108,403,702,075
97
37.048
37.017
-0.03
64,409,091,802
41,714,153,483
75,181,526,506
86
31.460
17.00
-14.46
28,495,537,200
28,495,537,200
18,133,523,673
33,744,415,152
84
2.763
2.785
0.02
0.00
28,387,336,100
28,387,336,100
18,064,668,427
33,087,960,804
86
5.013
2.471
-2.54
0
0.00
66,336,241,704
66,336,241,704
42,213,971,993
77,449,110,000
86
11.799
7.561
-4.24
-2,293,233,737
0
0.00
60,945,395,564
60,945,395,564
38,783,433,520
58,652,161,827
104
1.308
1.407
0.10
44,801,818,330
0
242,943,376,045
425,428,259,905
Resurfacing
Resurfacing
Tanjung Selor- Sp.3 Tj.Palas - Sekatakbuji (section 1)
333,214,553 PT.Waskita Karya (Persero)
3,325,293,575
PT.Brantas Abipraya -Mahir Jaya Mahakam Raya- JO
TOTAL
2,557,999,170
380,626,441,575 380,626,441,575
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 4 Details of Variation Orders To End March 2014 Design Review %
Package No.
Original Contract value (Rp.)
Design Review (Rp.)
28-RCP01A
93,350,000,000.00
112.8.335.000,00
Sosok – Tayan; Tanjung – Bts.Kota Sanggau
30-RCP01
465.647.542.528,00
Not yet
Tebas - Singkawang (Section 1); Tebas Singkawang (Section 2) Bypass Sambas Galing - Tanjung Harapan
30-RCP02
292,603,385,000.00
Not yet
Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
30-RCP03
217,249,975,454.55
Not yet
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
34-RCP02
165,332,338,000.00
Not yet
SP.3 Tj.Palas - Simaranggis (Sect 1)
34-RCP03
289,000,000,000.00
SP.3 Tj.Palas - Simaranggis (Sect 2)
34-RCP04
359,652,697,000
No.
Jolosutro - Bale kambang - Sendang biru
Price Escalation
Not yet
Not yet
Not yet
Escalation %
Total Current Modified Contract Price (Rp.)
Total Current Modified %
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 5 Regional Road Development Project (RRDP) Summary Of Contract Data Up to March 2015
NO.
DESCRIPTION
Jolosutro-BalekambangSendangbiru
a
b
c
Tebas - Singkawang (Section 1); Tebas Singkawang (Section 2) Bypass Sambas Galing - Tanjung Harapan
Sp. Tanjung Galing; Aruk (bts.Serawak Sp.Tanjung
Sp.3 Tanjung Palas Sekatak Buji (Section 2)
SP.3 Apas - Simaranggis (Sect 1)
SP.3 Apas Simaranggis (Sect 2); Simanggaris Bts.Negara
e
f
g
h
d
1
Package No.
28-RCP01A
30-RCP02
30-RCP03
34-RCP02
34-RCP-3
34-RCP04
2
Contract No.
01-28-RCP01A/RB/ADB/2817/0813
02-30-RCP02/RB/ADB/2817/1113
03-30-RCP02/RB/ADB/2817/1113
02-34RCP/LOAN/PJN.III/06.14
03-34-RCP/LOAN/PJN.III/04.14
04-34RCP/LOAN/PJN.III/04.14
3
Contract Sign Dated
21 August 2013.
14 November 2013.
27 November 2013.
25 June 2014.
11 April 2014.
11 April 2014.
4
Contractor
PT.HUTAMA KARYA
PT. Brantas Abipraya ; Tri Citra Perdana; Trifa Abadi- JO
PT. Waskita Karya ; PT.Yasa Patria Perkasa
PT.Brantas Abipraya Mahir Jaya Mahakam Raya- JO
PT.Pemb. Perumahan; PT.PerdasaJO
Halla Corporation
5
Original Contract Amount (Rp.)
93,350,000,000.00
292,603,385,000.00
238,974,973,000.00
165,332,338,000.00
289,000,000,000.00
359,652,697,000.00
6
Construction Period (Days)
730 Days
1095 Days
1095 Days
730 Days
900 Days
1095 Days
7
Commencement of Work
18-Oct-13
17-Dec-13
4-Dec-13
4-Sep-14
10-Jul-14
1 Oct 14
8
Addendum Contract
98.889.601.000,- (Add.2)
Not yet
Not yet
Not yet
Not yet
Not yet
905 Days (Add.3)
112.823.335.000,- (Add.3)
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
NO.
DESCRIPTION
Tj Selor-S.3 Tj.Palas Sp.3 Tj.Palas-Sekatakbuji
Sosok – Tayan Tanjung – batas\Kota Sanggau
Tambakmulyo Wawar
Giriwoyo - Duwet
Wawar - Congot
a
b
c
d
e
f
g
1
Package No.
34-RCP01
30-RCP01
24-RCP01
24-RCP02
24-RCP03
2
Contract No.
01-34-RCP/LOAN/PJN.III/11.14
02/30-RCP01/RB/ADB/2817/2015
01/24-RCP01/NR/IDB/0161/011 5
HK.02.03/BJGD/24RCP-02/I/2015/01
02/24-RCP03/NB/IDB/0161/0115
3
Contract Sign Dated
3 November 2014.
15 January 2015
12 January 2015
13 January 2015
7 January 2015
4
Contractor
PT.WASKITA KARYA
PT.Yasa Patria Perkasa; PT. Budi Bakti Prima JO
PT. PP (Persero)PT.Armada Hada Graha, JO
PT.HUTAMA KARYA (Persero)
PT.Manggala Konstruksi Manggala Pratama, Tbk
5
Original Contract Amount (Rp.)
189,970,248,000.00
243,741,564,000,00
142,000,000,000.00
58,253,088,000.00
6
Construction Period (Days)
730 Days
1095 Days
1095 Days
730 Days
365 Days
7
Commencement of Work
12 December 2014
Not yet
Not yet
Not yet
Not yet
8
Addendum Contract No.01
Not yet
Not yet
Not yet
Not yet
Not yet
465,647,542,528.81
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix . 6 Summary of Unsettled Complaints As of March 2015 No.
Complainant
1.
Budi Sarwono, Pemimpin JO PT. Bumi Rejo-PT. Sujainco,JO
2
Budi Sarwono, Pemimpin JO PT. Bumi Rejo-PT. Sujainco,JO
Recipient of complaints
RRDP Package
Media of complaint
Category of complaint
Complaint Issue
Date of complaint
Minister of Public Works of the Republic of Indonesia
No :34-RCP-01, Letter Tanjung SelorNo.050/BRDTanjung Palas, SJ/X/2014 Tanjung PalasSekatak (Section 1)
Refutations
Complaints differences morbidities Auction Process Package no: 34 - RCP - 01 , Tanjung Selor -Tanjung Palas , Tanjung Palas Sekatak ( section 1 ) Loan RRDP no. 2817 INO , East Kalimantan
31 October 2014
Procurement Committee
No :34-RCP-01, Tanjung SelorTanjung Palas, Tanjung PalasSekatak (Section 1)
Refutations
Disclaimer the announcement of the winner of the tender package no.34-RCP01, Tanjung SelorTanjung Palas-Sekatak (section 1) RRDP ADB Loan No. 2817-INO, East Kalimantan
22 October 2014
Letter No. 048/BRDSJ/X/2014
Date received by PMU/CTC
Date of response
24 October 2014
Responded by
Pokja RRDP East Kalimantan Chairman
Proposed Response
Announcement of the winner determination based on the evaluation procurement team that submitted trough bid evaluations report (BER) was revised on 1 september 2014 and according to no objection letter (NOL) from ADB date 25 September 2014 and based on a determination of the winner by minister of public works in 16 october 2014, so the announcement of the winner determination not associate with extention of period for bid validity and bid security. The procurement team take time to clarify the updating data of bidder’s Qualification especially
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
No.
Complainant
Recipient of complaints
RRDP Package
Media of complaint
Category of complaint
Complaint Issue
Date of complaint
Date received by PMU/CTC
Date of response
Responded by
Proposed Response
consistency with the prequalification data given to the procurement team. There is inconsistent data on the experience of the PT. Sujainco with PT. AngkasaPura 1 (Pesero), it is not appropriate with the financial report you gave to the procurement team ( the data has been clarified to PT. Angkasa Pura 1 (Pesero) and the public Accountants Achmad, Rasyid, Hisbullah & Jerry. Reprimand letter from Word Bank about sanction case no. 193 – letter reprimand dated 16 June 2014 3.
Kukuh Bandiono Kuasa JO PT. Multi StrukturePT.Brantas Abipraya
Working Group ( WG ) RRDP ADB Loan No.2017 INO In West Kalimantan .
Package 30 RCP01, Sosok Tayan - Bts . Sanggau City West Kalimantan.
Letter No. 225/MSMKT/KP/XII/2 014
Specific
Rebuttal to the Tender 19 December winner Package 30 2014 RCP01, Sosok - Tayan - Bts . Sanggau City West Kalimantan.
19 December 2014
Procurement Team Pokja
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 7a CROs ACTVITIES ON RRDP March 2015
No
Province
Package Observed
Package Number
Date of Invitation to Bid
CROs Involvement in the Bidding Process Date of Bid Opening
Announcement Date of Bid Winner
1
EAST JAVA
JolosutroSendangbiru
28RCP01A
1-Mar-13
1-May-13
18-Aug-13
1
WEST KALIMANTAN
Sosok - Tayan
30-RCP01
25-Jul-14
9-Sep-14
NY
TanjungBts.Kota Sanggau TebasSingkawang (Section1 &2)
2
Bypass Sambas Sp. Tanjung Galing; Aruk (bts.Serawak - Sp.Tanjung
3
30-RCP02
26-Feb-13
22-May-13
19-Oct-13
Selected CRO Reports of CRO Activity Name ·
Process Verbal of the CRO selection for RRDP package of Tebas - Singkawang, West Kalimantan SNVT of Roads and Bridge Development, February 2013
· 30-RCP02
26-Feb-13
23-May-13
12-Nov-13
·
Process Verbal of the CRO selection for RRDP package of Sp.Tanjung - Galing, West Kalimantan SNVT of Roads and Bridge Development, February 2013
· 1
EAST KALIMANTAN
Tj.SelorSp.3Tj. Palas
Sp.3 Tanjung Palas Sekatak Buji (Sect 1)
34-RCP01
11-Mar-13
13-Jun-13
Not Yet
Telephone
Email
Process Verbal of the CRO selection for RRDP package of Jolosutro- Sendangbiru, East Java SNVT of Roads and Bridge Development, May 2013 Process Verbal of the CRO selection for RRDP package of Sosok - Tayan, West Kalimantan SNVT of Roads and Bridge Development, June 2014
·
Address
Process Verbal of the CRO selection for RRDP package of Tj.Selor - Sp.3 Tanjung Palas, East Kalimantan SNVT of Roads and Bridge Development, June 2013
Chandra Yuliana , ST,MT Ir.Retna Hapsari Kartadipura, MT Ikrar Chandra Bachtiar, SKM
0812.50018822 Tanjungpura University
0811.501.584
NA
NA
NA
NA
NA
NA
Tanjung Pura University Lydia Gusti Resanika ,SE Ikrar Chandra Bachtiar, SKM Tanjung Pura University Lydia Gusti Resanika ,SE Rahayu Widasari
Ulfatu Munawaroh
Mulawarman University
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
No
Province
2
Package Observed
Package Number
Date of Invitation to Bid
Sp.3 Tanjung Palas Sekatak Buji (Sect 2)
34-RCP02
11-Mar-13
CROs Involvement in the Bidding Process Date of Bid Opening
Announcement Date of Bid Winner
13-Jun-13
4-May-14
Selected CRO Reports of CRO Activity Name ·
Process Verbal of the CRO selection for RRDP package of Sp.3 Tanjung Palas sekatak buji (serction 2), East Kalimantan SNVT of Roads and Bridge Development, June 2013
Rahayu Widasari
Address
3
34-RCP03
11-Mar-13
13-Jun-13
10-Feb-14
·
Process Verbal of the CRO selection for RRDP package of Sp.3 Apas - Simanggaris (serction 1), East Kalimantan SNVT of Roads and Bridge Development, June 2013
· SP.3 Apas Simaranggis (Sect 2); Simanggaris Bts.Negara
4
34-RCP04
11-Mar-13
13-Jun-13
6-Feb-14
·
CENTRAL JAVA
Tambakmulyo - Wawar
24-RCP01
14-May-14
15-Jul-14
2
Giriwoyo Duwet
24-RCP02
14-May-14
15-Jul-14
3
Wawar Congot
24-RCP03
14-May-14
15-Jul-14
NY
= Not Yet
NA
Process Verbal of the CRO selection for RRDP package of Sp.3 Apas - Simanggaris (serction 2) and Simanggaris - bts Negara, East Kalimantan SNVT of Roads and Bridge Development, June 2013
Process Verbal of the CRO selection for RRDP package of Tambakmulyo - Wawar, Central Java SNVT of Roads and Bridge Development, June 2014 Process Verbal of the CRO selection for RRDP package of Giriwoyo - Duwet, Central Java SNVT of Roads and Bridge Development, June 2014 Process Verbal of the CRO selection for RRDP package of Wawar - Congot, Central Java SNVT of Roads and Bridge Development, June 2014
Rahayu Widasari
NA
Mulawarman University
Ulfatu Munawaroh
· 1
Rahayu Widasari
Email
Mulawarman University
Ulfatu Munawaroh SP.3 Apas Simaranggis (Sect 1)
Telephone
NA
Mulawarman University
Ulfatu Munawaroh Ir.Yuniarto Adi, MT
Diponegoro University
Ir.Yuniarto Adi, MT
Diponegoro University
Ir.Yuniarto Adi, MT
Diponegoro University
NA
NA
NA
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 7b Status of CRO Reports March 2015
CW
RRDP Packages
Province
Status of Bidding Process Bid Winner Report Bid Opening (BW) Submission (BO) Announcement
Remarks
15-Jul-14
16-Dec-14
OK
Complete report of bid opening and bid winner announcement.
15-Jul-14
16-Dec-14
OK
Complete report of bid opening and bid winner announcement.
15-Jul-14
16-Dec-14
OK
Complete report of bid opening and bid winner announcement.
1-May-13
27-Jul-13
OK
Complete report of bid opening and bid winner announcement.
9-Sep-14
24-Dec-14
OK
Complete report of bid opening and bid winner announcement.
22-May-13
19-Oct-13
OK
Complete report of bid opening and bid winner announcement.
15-Jun-13
12-Nov-13
OK
Complete report of bid opening and bid winner announcement.
CW-08 Tj.Selor - Sp.3 Tanjung Palas (Section 1)
13-Jun-13
16-Oct-14
OK
Complete report of bid opening and bid winner announcement.
CW-09 Tj.Selor - Sp.3 Tanjung Palas (Section 2)
13-Jun-13
4-Jun-14
13-Jun-13
6-Feb-14
OK
Complete report of bid opening and bid winner announcement.
13-Jun-13
6-Feb-14
OK
Complete report of bid opening and bid winner announcement.
CW-01 Tambakmulyo - Wawar CW-02 Giriwoyo - Duwet
Central Java
CW-03 Wawar - Congot CW-04 Jolosutro - Sendangbiru (East Java)
CW-05
Sosok - Tayan ; Tanjung - Batas Kota Sangga
Tebas - Singkawang (Section 1 &2); CW-06 Bypass Sambas ; Galing - Tanjung Harapan CW-07
East Java
West Kalimantan
Sp.Tanjung - Galing ; Aruk - Batas Serawak
OK
Complete report of bid opening and bid winner announcement.
East Kalimantan CW-10 Sp.3 Apas - Simaggaris (Section 1)
CW-11
Sp.3 Apas - Simaggaris (Section 2); Simanggaris - Bts Negara
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 8 Environmental Management and Monitoring Plan (EMP) Compliance on Regional Roads Development Project (RRDP) As March 2015 Contractor Performance on EMP No.
Package No.
Project Name
Length (Km)
Contractor
Contract Reference
Contract Description
Document Availability
Awareness & Readiness to EMP
Base Camp
Waste Management
Material Handling
Pollution Control Measures
Traffic Landscaping/ Management Reforestation
Total Score Obtained
Ranking (%)
Remarks Level
EAST JAVA
1
28-RCP01A (CW-04) Jolosutro - Sendang biru
21.30
PT. Hutama Karya
01/28-RCP-01A/RB/ADB/2817/0813
New Road , Reconstruction incl. Resurfacing
38.46
PT. Pembangunan Perumahan (Persero)
01/24-RCP-01/NR/IDB/0161/0115
New Road, Widening, Resurfacing
Being monitored during construction
CENTRAL JAVA 2
24-RCP01 (CW-01) Tambak Mulyo – Wawar
3
24-RCP02 (CW-02) Giriwoyo - Duwet (Section-1)
23.75
PT. Hutama Karya
4
24-RCP03 (CW-03) Wawar – Congot
14.13
PT. Jaya konstruksi,
The construction not yet started The construction not yet started The construction not yet started
New Road , Reconstruction, Widening HK.02.03/BJGO/24-RCP-02/I/2015/01 and Resurfacing 02/24-RCP-03/NB/INB/0161/0115
Widening and Reconstruction
02/30-RCP-01/RB/ADB/2817/2015
Reconstruction and Resurfacing (Direct Overlay)
PT. Manggala Pratama tdk, JO WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05)
PT. Yasa Patria Perkasa 79.20
Tanjung-Batas Kota Sanggau
PT. Budi Bakti Prima JO
Tebas - Singkawang (Section-1);
Being monitored during construction
PT. Brantas Abipraya,
Tebas - Singkawang (Section-2);
PT. Tricitra Perdana, 55.97
6
The construction not yet started
30-RCP02 (CW-06) Bypass Sambas;
01/30-RCP-03/RB/ADB/2817/1113 PT. Trifa Abadi JO
Reconstruction, Resurfacing and Widening
Galing-Tanjung Harapan; Sambas-Tanjung Harapan
13.00
Sp.Tanjung-Galing (Section-1); 7
30-RCP03 (CW-07) Sp.Tanjung-Galing (Section-2);
Being monitored during construction
PT. Waskita Karya (Persero), 52.04
PT. Yasa Patria Perkasa JO
02/30-RCP-03/RB/ADB/2817/1113
New Road , Resufacing and Reconstruction
34.82
PT. Waskita Karya (Persero)
01-34/RCP/LOAN/PJN III/11.14
Reconstruction and Resurfacing
Aruk (Bts.Serawak)-Sp. Tanjung EAST KALIMANTAN Being monitored during construction
Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08) SP. 3 Tanjung Palas - Sekatak Buji (Secton-1)
9
34-RCP02 (CW-09) SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
65.03
PT. Brantas Abipraya, PT. Mahir Jaya Mahakam Raya JO
02-34/RCP/LOAN/PJN.III/06.14
Grade Improvement and Resurfacing
10
34-RCP03 (CW-10) SP.3 Apas - Simaranggis (Section- 1)
45.00
PT. Pembangunan Perumahan, PT. Persada JO
03-34/RCP/LOAN/PJN.III/04.14
New Road , Reconstruction and Reconstruction
11
34-RCP04 (CW-11)
43.04
Butt Halla Corporation
04-34/RCP/LOAN/PJN III/04.14
New Road, Widening and Resurfacing
Being monitored during construction Being monitored during construction
Being monitored during construction
SP.3 Apas - Simaranggis (Section-2) Simanggaris-Bts Negara (Serudong)
Score
0
1
2
3
4
% Compliance
0-20
Scale
N.A.
Below Par
Mildly Satisfactory
Satisfactory
Good
Ranking
Below Par
20-40 Mildly Satisfactory
40-60
60-80
80-100
Satisfactory
Good
Excellent
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 9 Status of Social Safeguard Studies on Regional Roads Development Project (RRDP) As March 2015
No.
Package No.
Project Name
Length (Km)
District
Type of Works
Safeguard Document
Jolosutro - Sendang biru
21.30
Malang
New Road Construction incl. raising grade and New Bridge Construction
LARP
EAST JAVA
1
28-RCP01 (CW01)
CENTRAL JAVA 2
24-RCP01 (CW02)
Tambak Mulyo – Wawar
38.46
Kebumen
Widening, Resurfacing and New Bridge Construction
3
24-RCP02 (CW03)
Giriwoyo - Duwet (Section-1)
23.75
Wonogiri
New Road Construction, Widening and New Bridge Construction
4
24-RCP03 (CW04)
Wawar – Congot
14.13
Purworejo
Widening and Resurfacing
79.20
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
LARP
Reconstruction, Resurfacing and Widening
LARP
LARP
WEST KALIMANTAN
Sosok - Tayan; 5
30-RCP01 (CW05) Tanjung-Batas Kota Sanggau
6
30-RCP02 (CW06)
55.97 Singkawang &
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Tebas - Singkawang (Section-1); Tebas – Singkawang (section 2)
Sambas
Bypass Sambas; Galing-Tanjung Harapan; Sp.Tanjung-Galing (Section-1); 7
30-RCP03 (CW07)
Sp.Tanjung-Galing (Section-2);
52.04
Sambas
New Road Construction incl. raising grade and Reconstruction
34.82
Bulungan
New Road Construction incl. raising grade and Reconstruction
Aruk (Bts.Serawak)-Sp. Tanjung
EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW08) SP. 3 Tanjung Palas - Sekatak Buji (Secton-1)
LARP
9
34-RCP02 (CW09)
SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
65.03
Bulungan
Grade Improvement and Resurfacing
10
34-RCP03 (CW10)
SP.3 Apas - Simaranggis (Section- 1)
45.00
Nunukan
New Road Construction incl. raising grade and Reconstruction Possible for Updated LARP study related to relocation of road
SP.3 Apas - Simaranggis (Section-2) 11
34-RCP04 (CW11)
Simanggaris-Bts Negara (Serudong) 43.04
Nunukan
Widening and Reconstruction
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 10 Status of Monitoring of Environmental Mitigation on Regional Roads Development Project (RRDP) As March 2015 No.
Package No.
Project Nam e
Length (Km )
District
Type of Works
Construction Status
Contract Date
2014
2013
2015
Remarks Start (COW)
Finish (PHO)
10
11
12
1
2
3
4
5
6
7
8
9-Apr-16
√
√
√
√
√
√
√
√X
√
√
√
9
10
11
12
1
2
3
√
√
√
√
√
√
√
√
EAST JAVA
1
28-RCP01 A(CW-04) Jolosutro - Sendang biru
21.30
Malang
New Road Construction incl. raising grade and New Bridge Construction
OC
21-Aug-13
√X √X
CENTRAL JAVA 2
24-RCP01 (CW-01) Tambak Mulyo – Waw ar
38.46
Kebumen
Widening, Resurfacing and New Bridge Construction
CS
12-Jan-15
-
3
24-RCP02 (CW-02) Giriw oyo - Duw et (Section-1)
23.75
Wonogiri
New Road Construction, Widening and New Bridge Construction
CS
13-Jan-15
-
4
24-RCP03 (CW-03) Waw ar – Congot
14.13
Purw orejo
Widening and Resurfacing
CS
7-Jan-15
-
79.20
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
CS
15-Jan-15
-
OC
14-Nov-13
15-Dec-16
√
√
√
√
√
√X
√
√
√
√
√
√
√X
√
WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05)
√X
Tanjung-Batas Kota Sanggau Tebas - Singkaw ang (Section-1);
Singkaw ang & Sambas
Tebas - Singkaw ang (Section-2); 55.97 6
30-RCP02 (CW-06) Bypass Sambas;
Sambas-Tanjung Harapan
√
√X
√
√X
√
√
√
√X
√
√X
√
√X
√
√
√
√X
√
√
√
√
Reconstruction, Resurfacing and Widening
Galing-Tanjung Harapan;
Sambas 13.00
Sp.Tanjung-Galing (Section-1); 7
30-RCP03 (CW-07) Sp.Tanjung-Galing (Section-2);
52.04
Sambas
New Road Construction incl. raising grade and Reconstruction
OC
26-Nov-13
2-Dec-16
34.82
Bulungan
New Road Construction incl. raising grade and Reconstruction
OC
4-Nov-14
11-Dec-16
65.03
Bulungan
Grade Improvement and Resurfacing
OC
25-Jun-14
2-Sep-16
√
√
√
√
√
√X
√
√
√
√
45.00
Nunukan
New Road Construction incl. raising grade and Reconstruction
OC
14-Apr-14
28-Dec-16
√
√
√
√
√
√X
√
√
√
√
43.04
Nunukan
Widening and Reconstruction
OC
11-Apr-14
30-Sep-17
√
√
√
√
√
√X
√
√
√
√
Aruk (Bts.Seraw ak)-Sp. Tanjung EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08)
√X
SP. 3 Tanjung Palas - Sekatak Buji (Secton-1) 9
10
34-RCP02 (CW-09) SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
34-RCP03 (CW-10) SP.3 Apas - Simaranggis (Section- 1)
SP.3 Apas - Simaranggis (Section-2) 11
34-RCP04 (CW-11) Simanggaris-Bts Negara (Serudong)
Note: OC
= Ongoing Construction
IFB
= Invitation For Bid
CS
= Contract Sign
BER
= Bid Evaluation Report
RT
= Retender
AMDAL
= Environmental Impact Assessment
NY
= Not yet
UKL/UPL
= Environmental Management & Monitoring Plans
NR
= Not required
SOP's
= Standard Operating Procedure
PHO
= Provisional Hand Over
√
= Monitored by DSC
COW
= Commencement of Work
X
= Monitored by CTC
2016
√
√
4
5
6
7
8
9
10
11
12
1
2
3
4
5
6
7
8
9
10
11
12
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 11 Overall Land Acquisition Status on Regional Roads Development Project (RRDP) As March 2015
No.
Project Name
Total To Be Acquired (m2)
Total Acquired (m2)
Progress In %
Remarks
Jolosutro - Sendang biru
1,481,400
1,481,400
100
Forest land affected is replaced by another with an area of land equivalent and are in the Bondowoso Regency
1,192,988
1,192,988
100
Private land and state land
Package No.
EAST JAVA
1
28-RCP01 (CW04)
CENTRAL JAVA 2 3 4
24-RCP01 (CW01) 24-RCP02 (CW02)
Tambak Mulyo – Wawar Giriwoyo - Duwet (Section-1)
No LA
NR
-
24-RCP03 (CW03)
Wawar – Congot
No LA
NR
-
Sosok - Tayan;
No LA
NR
-
Tanjung-Batas Kota Sanggau
No LA
NR
-
Tebas - Singkawang (Section-1);
286
420
0
Tebas - Singkawang (Section-2);
3,543
4,730
0
Bypass Sambas;
No LA
NR
-
130
610
0
WEST KALIMANTAN
5
6
30-RCP01 (CW05)
30-RCP02 (CW06)
Galing-Tanjung Harapan;
Not required land acquisition because for the design need is in accordance with the existing ROW Not required land acquisition because for the design need is in accordance with the existing ROW It has been verified against the land data and necessary to acquisition It has been verified against the land data and necessary to acquisition
It has been verified against the land data and necessary to acquisition
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
No.
Package No.
7
30-RCP03 (CW07)
Total To Be Acquired (m2)
Total Acquired (m2)
Progress In %
Sp.Tanjung-Galing (Section-1);
No LA
NR
-
Sp.Tanjung-Galing (Section-2);
No LA
NR
-
Aruk (Bts.Serawak)-Sp. Tanjung
176
0
0
3,326
0
0
Project Name
Remarks
EAST KALIMANTAN
Tanjung Selor - SP. 3 Tanjung Palas; (87 APs) 8
34-RCP01 (CW08)
SP. 3 Tanjung Palas - Sekatak Buji (Sec-1)
9
34-RCP02 (CW09)
SP.3 Tanjung Palas - Sekatak Buji (Sec-2)
10
34-RCP03 (CW10)
SP.3 Apas - Simaranggis (Section- 1): 1 AP, 3 Corporates)
11
34-RCP04 (CW11)
SP.3 Apas - Simaranggis (Section-2): No LARP
3 Corporate: 2 PT have been moved the Palm oil, 1 no responce yet 8,400
0
2,690,249
2,680,148
Simanggaris-Bts Negara (Serudong) GRAND TOTAL
0
land area affected will be confirmed after preparation of the LARP document
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 12 Environmental Safeguard on Regional Roads Development Project (RRDP) As March 2015 No.
Package No.
Project Nam e
Length (Km )
District
Type of Works
Construc. Status
Intial Environm ental Exam ination (IEE)
Environm ental
Approval by BLHD
Environm ental Managem ent and Monitoring Plan (EMMP) or RKPPL
AMDAL (A)
2009
Not Yet
Safeguard Docum ent
EAST JAVA
1
28-RCP01A (CW-04) Jolosutro - Sendang biru
21.30
Malang
New Road , Reconstruction incl. Resurfacing
OC
October 2011
38.46
Kebumen
New Road, Widening, Resurfacing
CS
October 2011
CS
October 2011 October 2011
CENTRAL JAVA 2
24-RCP01 (CW-02) Tambak Mulyo – Waw ar
3
24-RCP02 (CW-03) Giriw oyo - Duw et (Section-1)
23.75
Wonogiri
New Road , Reconstruction, Widening and Resurfacing
4
24-RCP03 (CW-04) Waw ar – Congot
14.13
Purw orejo
Widening and Reconstruction
CS
79.20
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
CS
Not Yet AMDAL (A)
5 October 2005
Not Yet Not Yet
WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05) Tanjung-Batas Kota Sanggau Tebas - Singkaw ang (Section-1);
16 February 2011
Not Yet
October 2011
UKL/UPL (B)
16 February 2011
Not Yet
AMDAL (A)
18 February 2013
Not Yet
October 2011 55.97 Reconstruction, Resurfacing and Widening
Galing-Tanjung Harapan;
Not Yet
OC
30-RCP02 (CW-06) Bypass Sambas;
Sambas-Tanjung Harapan
UKL/UPL (B)
October 2011
Singkaw ang & Sambas
Tebas - Singkaw ang (Section-2); 6
October 2011
October 2011
Sambas 13.00
Sp.Tanjung-Galing (Section-1);
UKL/UPL (B)
16 February 2011
Not Yet
October 2011
UKL/UPL (B)
16 February 2011
-
w ill be prepared by DSC-1
-
October 2011
UKL/UPL (B)
13 January 2011
Not Yet
October 2011
UKL/UPL (B)
13 January 2011
Not Yet
October 2011
UKL/UPL (B)
13 January 2011
Not Yet
Not Yet
OC 7
30-RCP03 (CW-07) Sp.Tanjung-Galing (Section-2);
52.04
Sambas
New Road , Resufacing and Reconstruction
Aruk (Bts.Seraw ak)-Sp. Tanjung EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08)
October 2011 34.82
Bulungan
Reconstruction and Resurfacing
SP. 3 Tanjung Palas - Sekatak Buji (Secton-1) 9
Not Yet
OC October 2011
UKL/UPL (B)
20 December 2010
Not Yet
34-RCP02 (CW-09) SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
65.03
Bulungan
Grade Improvement and Resurfacing
OC
October 2011
10
34-RCP03 (CW-10) SP.3 Apas - Simaranggis (Section- 1)
45.00
Nunukan
New Road , Reconstruction and Reconstruction
OC
October 2011
UKL/UPL (B)
14 August 2013
Not Yet
October 2011
UKL/UPL (B)
13 January 2011
Not Yet
11
34-RCP04 (CW-11)
43.04
Nunukan
New Road, Widening and Resurfacing
OC October 2011
UKL/UPL (B)
13 December 2010
Not Yet
SP.3 Apas - Simaranggis (Section-2) Simanggaris-Bts Negara (Serudong)
Note : OC- Ongoing Construction; CS - Contract Signed; RT- Retender; NY- Not Yet ; IFB- Invitation For Bid; BER-Bid Evaluation Report
Not Yet
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 13 Regional Roads Development Projecr (RRDP) Construction Program Design
Procurement:
NOL Docs/Award:
Invite Bids:
NOL Re-bid:
Re-bid Period:
Sign Contract:
Commencemen of work
Ongoing Construction:
Pack. No.
As of March 2015 Package Number Contract
Location Phase
2012
Length, Kms
Code
J
F
M
A M
J
J
2013 A S O N D
J
F M A M
J
J
2014 A S O N D
J
F M A M
J
J
2015 A S O N D
J
18 Oct 13
EAST JAVA 4
Jolosutro- Sendangbiru
28-RCP01A
21.30
5
Sosok - Tayan kota Sanggau
30-RCP01
79.20
6
Singkawang - Tebas Sambas Bypass Tanjung Harapan -Galing
30-RCP02
Sp.Tanjung - Galing Sp.Tanjung Aruk (bts Serawak
30-RCP03
52.04
WEST KALIMANTAN
7
Tanjung - Batas
17 Dec 13
55.97 4 Dec 13
CENTRAL JAVA 1
Tambak Mulyo - Wawar
24-RCP01
38.46
2
Giriwoyo - Duwet (Section 1)
24 - RCP02
23.75
3
Wawar - Congot
24-RCP03
14.13
EAST KALIMANTAN 8
Tanjung Selor - Sp.3 Tanjung Palas Sp.3 Tanjung Palas - Sekatak Buji
9
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
12 Dec 14
34-RCP01
34.82 4 Sep 14
34 - RCP02
65.03 10 Jul 14
10
SP.3 Apas - Simanggaris (Section 1)
11
SP.3 Apas - Simanggaris (Section 2) Simanggaris - Bts.Negara
34-RCP03
45.00 1 Oct 14
34-RCP04
43.04
F M A M J
J
2016 A S O N D
J
F M A M
J
J
2017 A S O N D
J
F M A M
J
J
A S O N D
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 14 Cost Estimate Of Civil Work Packages Regional Roads Development Project (RRDP) - ADB LOAN NO.2817-1NO Status : March 2015 No.
Package No.
Package Name
Length
Type of Works
(Km)
Allocated Amount (Excluding Tax) (US$)
(IDR)
Original Contract Amount (Excl. Tax) (US$)
(IDR)
Contigency Technical (IDR)
(%)
Total Contract Amount Excluding Tax Price Escalation (IDR) (%)
Remarks (US$)
(IDR)
(%)
EAST JAVA PROVINCE 1
5
6
7
8 9
28-RCP 01A
Jolosutro - Sendang Biru
WEST KALIMANTAN PROVINCE Sosok - Tayan; 30-RCP01 Tanjung - Bts. Kota Sanggau Tebas - Singkawang (Section 1); Tebas - Singkawang (Section 2); 30-RCP02 Bypass Sambas; Galing - Tanjung Harapan Sp. Tanjung - Galing; 30-RCP03 Aruk (Bts. Serawak) - Sp. Tanjung EAST KALIMANTAN PROVINCE Tanjung Selor - Sp.3 Tanjung Palas; 34-RCP01 Sp.3 Tanjung Palas-Sekatak Buji Sp.3 Tanjung Palas - Sekatak Buji 34-RCP02 (Section 2)
10
34-RCP03
11
34-RCP04
SHARING
Sp.Tiga Apas - Simanggaris (Sec. 1) Sp.Tiga Apas - Simanggaris (Sec. 2); Simanggaris - Bts.Negara Sub - Total ADB
21.30
New Road Construction incl.raising grade and New Bridge Construction
15,229,753.78
151,916,793,955.50
6,527,972.03
84,863,636,363.64
17,703,031,818.18 20.86
8,486,363,636.36 10.00
8,542,540.91
111,053,031,818.18 30.86
79.20
Reconstruction and Resurfacing (Direct overlay)
52,681,081.67
553,151,357,483.64
32,562,765.28
423,315,948,661.82
63,497,392,299.27 15.00
42,331,594,866.18 10.00
40,703,456.60
529,144,935,827.27 25.00
55.97
Reconstruction, Resurfacing and Widening
45,324,068.22
430,578,648,090.00
20,461,775.17
266,003,077,272.73 104,265,006,363.64 39.20
26,600,307,727.27 10.00
40,703,456.60
529,144,935,827.27 98.92
52.04
New Road Construction including raising grade and reconstruction
35,075,216.11
333,214,553,045.00
16,711,536.57
217,249,975,454.55
75,717,212,727.27 34.85
21,724,997,545.45 10.00
24,207,091.21
314,692,185,727.27 44.85
22,531,932.26
214,053,356,470.00
13,284,632.73
172,700,225,454.55
25,905,033,818.18 15.00
17,270,022,545.45 10.00
16,605,790.91
215,875,281,818.18 25.00
22,682,473.16
215,483,495,020.00
11,561,701.29
150,302,116,750.00
22,545,317,512.50 15.00
15,030,211,675.00 10.00
14,452,126.61
187,877,645,937.50 25.00
33,991,570.30
322,919,917,850.00
20,209,790.21
262,727,272,727.27
39,409,090,909.09 15.00
26,272,727,272.73 10.00
25,262,237.76
328,409,090,909.09 25.00
42,893,028.94
407,483,774,930.00
25,150,538.32
326,956,998,181.82
81,739,249,545.45 25.00
32,695,699,818.18 10.00
33,953,226.73
441,391,947,545.46 35.00
270,409,124.44
2,628,801,896,844.14
New Road Construction including raising grade and reconstruction Grade Improvement and 65.03 Resurfacing New Road Construction including 45.00 raising grade and reconstruction Widening, Reconstruction and 47.04 New Road 400.40 34.82
A D B (70 % ) G O I ( 30 % )
189,286,387.10 81,122,737.33
146,470,711.61 1,904,119,250,866.36 430,781,334,993.59
190,411,925,086.64
204,429,927.34 2,657,589,055,410.23 148,824,987.10 1,860,312,338,787.16 63,782,137.33 797,276,716,623.07
102,529,498.12 43,941,213.48
Asumsi 1 US$ = 12.500 IDR Allocated Loan ADB For Civil Works Packages Remaining Estimate
155,000,000.00 6,175,012.90
80,275,167,661.35
PMU RRDP – Quarterly Progress Report No. 4, January - March 2015
Appendix. 15 Monitoring Health And Safety During Construction ( Keselamatan Dan Kesehatan Kerja(K3) Konstruksi ) March 2015 Contractor Performance on Health and Safety (K3 Konstruksi) Package No.
Contract No.
CW-04
01-28-RCP01A/RB/ADB/2817/0813
Working Schedule (RK3K)
Safety Meeting
Document Availability (Data,Picture, Interview)
Personel Protection (APD)
Labour Camp
Road Safety during Construction
System Managemen K3 (SMK3)
Disposal of Waste Material
Total Score Obtained
Ranking (%)
PT.Brantas Abipraya-Tri Citra Perdana-Trifa Abadi, JO
4
2
4
2
4
4
2
2
24
60
Aruk PT Waskita Karya - Yasa Patria Perkasa, JO
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Contract Description (Length)
Contractor
Jolosutro - Bale kambang - Sendang biru (21,30 KM)
PT.Hutama Karya (Persero)
Level
Remarks
EAST JAVA
WEST KALIMANTAN CW-05
01-30-RCP01/RB/ADB/2817/0115
Sosok - Tayan; Tanjung - Bts.Kota PT.Yasa Patria Perkasa; Sanggau PT. Budi Bakti Prima JO
CW-06
02-30-RCP02/RB/ADB/2817/1113
Tebas - Singkawang (Section 1); Tebas -Singkawang (Section 2) Bypass Sambas Galing - Tanjung Harapan
CW-07
03-30-RCP02/RB/ADB/2817/1113
Sp. Tanjung - Galing; (bts.Serawak - Sp.Tanjung
Satisfactory
EAST KALIMANTAN CW-08
01-34RCP/LOAN/PJN.III/11.14
Tanjung Selor-Sekatak Buji-Tanjung Palas Sec. 1 (34-RCP01)
PT. Waskita Karya (Persero)
CW-09
02-34RCP/LOAN/PJN.III/06.14
Tanjung Selor-Sekatak Buji-Tanjung Palas Sec. 2 (34-RCP02)
PT.Brantas Abipraya Mahir Jaya Mahakam Raya- JO
CW-10
03-34RCP/LOAN/PJN.III/04.14
SP.TIGA APAS - SIMANGGARIS (SECTION 1)
PT.Pemb. PerumahanPT.Perdasa JO
-
-
-
-
-
-
-
-
-
-
CW-11
03-34RCP/LOAN/PJN.III/04.14
SP. TIGA APAS - SIMANGGARIS - BTS. NEGARA (SERUDONG)
Halla Corporation
-
-
-
-
-
-
-
-
-
-
Tambakmulyo - Wawar
PT.Pembangunan Perumahan ; PT.Armada Hada Graha
-
-
-
-
-
-
-
-
-
-
1
2
3
4
5
% Compliance
0-20
20-40
40-60
60-80
80-100
Below Par
Mildly Satisfactory
Satisfactory
Good
Excellent
Ranking
Below Par
Mildly Satisfactory
Satisfactory
Good
Excellent
CENTRAL JAVA CW-01
01/24-RCP01/NR/IDB/0161/0115
CW-02'
HK.02.03/BJGD/24-RCP02/I/2015/01
Giriwoyo - Duwet
PT. Hutama Karya (Persero)
CW-03
02/24-RCP03/NB/IDB/016/0115
Wawar - Congot
PT. Jaya Konstruksi Manggala Pratama Tbk
Ranking = (Total Score/40) * 100 %
Score
0
Scale
N.A.
Note :
All the Contractor No much action todo of Health and Safety for Construction
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 16 ABBREVIATIONS AND ACRONYMS ACAP ADB AMDAL ANDAS ATMS Bappedalda Bappenas BPK BPKP
CTC DSC-1 DSC-2 DSC-3 CW CHU DOP DGH DGLT DRBWR DTA DTP DFUR DGH EA EIA EIR EIRTP-2 ESAM EMP FMR FIDIC GOI HLRIP IA IDB IT ISEM IVP IG IRSMS KPKN LRAP LARF
Anti-Corruption Action Plan Asian Development Bank Environmental Management (Analisis Mengenai Dampak Lingkungan) Analisis Dampak Sosial Area Traffic Monitoring System Regional Environmental Impact Agencies Badan Perencanaan Pembangunan Nasional Badan Pemeriksaan Keuangan (Audit Board of the Government of Indonesia) Badan Pengawasan Keuangan dan Pembangunan (Development Finance Comptroller, internal auditor of the Government of Indonesia) Core Team Consultant Design and Supervision Consultant for Kalimantan Design and Supervision Consultant for Central Java Design and Supervision Consultant for East Java Civil Works Complaint Handling Unit Directorate of Planning Directorate General of Highways Directorate General of Land Transport Directorate Road and Bridge West Region Directorate of Technical Affairs Directorate of Traffic Police Directorate Freeway and Urban Road Directorate General of Highway Executing Agency Environmental Impact Assessment Eastern Indonesian Region Eastern Indonesia Regional Transport Project (Second Project) Environmental and Social Assessment Environmental Management Plan Financial Monitoring Report Federation Internationale des Ingenieur Conseils Government of Indonesia Heavy Loaded Road Improvement Project Implementation Agency Islamic Development Bank Information Technology Institutional Strengthening in Environmental Management Isolated Vulnerable People Inspectorate General Integrated Road Safety Management System Kantor Perbendaharaan Keuangan Negara Land Acquisition and Resettlement (Rencana Tindak Pengadaan Tanah dan Pemukiman Kembali) Land Acquisition Resettlement Frame Work
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
MOF MHA MPW MPR MOT NOL NRSC UKL/UPL OPRC PA PAS PMR PBCC PIP PIS PAD PMM PMU PPR PVD QPR RBRF RFP RRSP RS-SC SBD SIA SIPP SLKLL SOP SURIP SRRP SRIP SPI SC Sub Dit Lingkungan TKPM TOR TRACER WB WP-1 WPs WPM WTP
Ministry of Finance Ministry of Home Affairs Ministry of Public Works Monthly Progress Report Ministry of Transportation No Objection Letter (from World Bank) National Road Safety Council Upaya Pengelolaan Lingkungan dan Upaya Pemantauan Lingkungan (Site Specific Environmental and Monitoring Plans) Output and Performance Based Road Contract Procurement Agent Procurement Advisory Services Performance Monitoring Reporting Performance Based Contract Consultant Project Implementation Plan Project Implementation Schedule Project Appraisal Document Project Management Manual Project Management Unit (RRDP) Project Progress Report Pre fabricated Vertical Drainage Quarterly Progress Report Reforming Road Maintenance Management and Funding Request for Proposal Road Rehabilitation Sector Project Road Safety Steering Committee Standard Bidding Document Social Impact Assessment Sistem Informasi Pemantauan Proyek Traffic Accident Reporting System Application Standard Operating Procedure Strategic Urban Road Infrastructure Project Sumatera Region Roads Project Strategic Road Infrastructure Project Support Project Implementation Steering Committee (Tim Pengarah) Sub Directorate of Environmental Tim Penanganan Komplain Masyarakat – a Complaints Investigation Unit within Inspectorate General Terms of Reference Studi Penyelusuran Kembali World Bank Works Program – Year 1 Work Programs Wakil Pengamat Masyarakat Warga yang Terkena Proyek