REPUBLIC OF INDONESIA MINISTRY OF PUBLIC WORKS DIRECTORATE GENERAL OF HIGHWAY DIRECTORATE OF PLANNING
QUARTERLY PROGRESS REPORT NO. 3
OCTOBER - DECEMBER 2014
TECHNICAL ASSISTANCE FOR SUPPORT OF PROJECT MANAGEMENT UNIT OF REGIONAL ROADS DEVELOPMENT PROJECT UNDER : ADB LOAN NUMBER 2817-INO IDB FINANCING NUMBER 0161 IND
RENARDET S.A. CONSULTING ENGINEERS
Joint Venture With : 1. PT. Multi Phi Beta 2. PT. Widya Graha Asana 3. PT. Disiplan Consult 4. PT. Anugerah Kridapradana
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
TABLE OF CONTENTS Table of Contents ..................................................................................................... i 1.
2
3
Executive Summary ................................................................................................ 1 1.1
Project Description. ........................................................................................ 1
1.2
Current Implementation Situation ................................................................... 1 1.2.1
Procurement ....................................................................................... 1
1.2.2
Civil Works ......................................................................................... 2
1.2.3
Consultancy Services ......................................................................... 8
1.3
Current Status of Loan ................................................................................... 8
1.4
Current Problems and Action Required at End of fourth Quarter 2014 ........... 9
General ..................................................................................................................... 9 2.1
Reporting Requirements ................................................................................ 9
2.2
Loan Status.................................................................................................. 10
2.3
Financial Management ................................................................................. 11
2.4
Project Cost Monitoring ................................................................................ 12
2.5
ADB Missions .............................................................................................. 13
2.6
Project Steering Committee Meeting ............................................................ 13
2.7
Loan Closing Date ....................................................................................... 13
Project Management and Implementation ........................................................... 14 3.1
Procurement Plan ........................................................................................ 14
3.2
Procurement Status ..................................................................................... 14
3.3
Implementation Status – Civil Works ............................................................ 15
3.4
Variation Details ........................................................................................... 16
3.5
Ongoing Consultancy Services .................................................................... 16
3.6
Implementation of the Anti-Corruption Plan .................................................. 18
3.7
3.8
3.6.1
Community Representative Observer (CRO) .................................... 18
3.6.2
Third Party Monitoring (TPM) ........................................................... 18
3.6.3
Complaint Handling System (CHS)................................................... 19
Implementation of the Environmental Management Plan ............................. 19 3.7.1
HIV-AIDS and Anti Human Trafficking Program................................ 20
3.7.2
Monitoring of Health and Safety ....................................................... 20
Resettlement & Rehabilitation Activities ....................................................... 21 3.8.1
Preparation of LARP ........................................................................ 21
3.8.2
LARP Implementation....................................................................... 21
i
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
4.
Seminars, Workshops & Training ........................................................................ 24
5.
Loan Utilisation for Civil Works............................................................................ 24 5.1 Estimated Funding Status for RRDP Civil Works .............................................. 24
6.
RRDP Website ..................................................................................................... 24
7.
Documentation Collection and Scanning ........................................................... 24
ii
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Forms Form A
General
2 Sheets
Form B
Summary of Implementation
2 Sheets
Form C
Status of Problems
2 Sheets
Form D
Contract Package Status
Form E
Details of the Budget
15 Sheets 1 Sheets
iii
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendices Appendix 1
The overall Financial Status
Appendix 2
Procurement Plan
Appendix 3
Project and Cost Monitoring
Appendix 4
Details Variation Orders Up to End December 2014
Appendix 5
Summary of Contract Data
Appendix 6
Unsettled Complains
Appendix 7a
CROs Activities on RRDP
Appendix 7b
Status of CRO Reports
Appendix 8
EMP Compliance ( Up to end December 2014 )
Appendix 9
Status of Social Safeguard Study.
Appendix 10
Status of Monitoring of Environmental Mitigation on RRDP
Appendix 11
Overall Land Acquisition Status End December 2014
Appendix 12
Environmental Safeguards
Appendix 13
Construction programme
Appendix 14
Cost Estimated of Civil Works Packages
Appendix 15
Monitoring Health Safety During Construction
Appendix 16
Abbreviation and Acronyms
iv
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
1.
Executive Summary 1.1
Project Description The RRDP project is aided project of ADB loans (No.2817-INO) and financing IDB (No.0161-IND). The proposed Project 1 will improve strategic national road corridors in northern Kalimantan and southern Java to support economic growth in these two less developed and poorer areas of Indonesia. The National Road network in southern Java is incomplete, with some road sections of the southern Trans Java Highway not yet constructed resulting in gaps in the network. Similarly, road network improvements are needed to support economic development in the less developed and remote districts in northern Kalimantan and road connections in Kalimantan to the border. The project includes a component for the rehabilitation of 476 km of national roads consisting of new construction, resurfacing and widening and bridge 3390 meters in two (2) Provinces in Java and two (2) Provinces in Kalimantan.
1.2
Current Implementation Situation 1.2.1
Procurement All sub-projects started with pre-qualification in 20 December 2011 through ICB procurement process. West Kalimantan One (1) of the three (3) packages in West Kalimantan, CW-05 (SosokTayan; Tanjung – Batas Kota Sanggau), Bid Documents were submitted to ADB on 25 April 2014; ADB commented
on the draft Bidding
Documents (retendering) on 23 June 2014 and agreed that DGH may apply the full e-procurement system for this package as a pilot test. Bid opening (Re-tender) for package 30RCP01 (CW-05) (Sosok – Tayan) was held on 9 September 2014 and Bid Evaluation Report (BER) sent to ADB. However, ADB instructed DGH by letter to open an additional bid which was submitted by Spanish Contractor not previously accepted. POKJA sent revised BER to ADB on 22 October 2014 including the additional bid opening result held on 16 October 2014. ADB issued “No Objection Letter” on 9 December 2014 and Minister approved BER on 11 December 2014. East Kalimantan Revised Bid Evaluation Report IV for package 34-RCP01(CW-08) was sent to ADB on 11 September 2014 and was concurred by ADB on 25 September 2014. Contract was signed 3 November 2014; ADB concurred with the contract on 19 November 2014. Commencement of Work NTP was issued on 12 December 2014.
1
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Central Java Bid opening for 3 Packages; 24-RCP-01(CW-01) (Tambakmulyo – Wawar), 24-RCP-02(CW-02) (Giriwoyo - Duwet (Section 1)) and 24RCP-03(CW-03) (Wawar - Congot), was held on 15 July 2014 at Semarang, Central Java. The Procurement Team completed the Bid Evaluation Report and this was sent to IDB on 23 September 2014; IDB issued “No Objection Letter” for all three (3) Packages on 1 December 2014. DSC-2, who will cover the Central Java province, has not been mobilized yet. At the meeting held on 29 October 2014 among the related parties, IDB instructed to DGH to expedite the process of selection. POKJA submitted a detailed analysis of Consultants Technical proposals and the IDB issued a “No Objection Letter” on 4 December 2014. The Consultant Financial proposals were consequently opened on 12 December 2014. 1.2.2
Civil Works Seven (7) out of eleven (11) packages have been contracted through ICB tender process as shown in the table below:
Ref
Package No
Package Name
Contract Sign
COW
Province
CW-04
28-RCP-01
Jolosutro – Sandang Biru
21 Aug 2013
18 Oct 2013
East Java
CW-06
30-RCP-02
Tebas – Singkawang (Sec 1) Tebas – Singkawang (Sec. 2) ByPasss Sambas Galing-Tanjung Harapan
14 Nov 2013
17 Dec 2013
West Kalimantan
CW-7
30-RCP-03
27 Nov 2013
4 Dec 2013
West Kalimantan
CW-08
34-RCP01
Tanjung Selor-Sp.3 Tj. Palas Sekatakbuji
3 Nov 2014
12 Dec 2014
East Kalimantan
CW-09
34-RCP02
Sp.3 Tanjung Palas –Sekatak Buji (Section 2)
25 Jun 2014
4 Sept 2014
East Kalimantan
CW-10
34-RCP-03
Sp. Tiga Apas - Simanggaris (Section 1)
11 Apr 2014
10 July 2014
East Kalimantan
CW-11
34-RCP-04
Sp. Tiga Apas – Simanggaris (Section 2); Simanggaris - Bts. Negara (Serudong)
11 April 2014
1 Oct 2014
East Kalimantan
Sp.Tanjung – Galing Aruk(Bts.Serawak-Sp.Tanjung
Seven (7) packages out of eleven (11) packages are already ongoing. The table below shows the actual physical progress at the end of this fourth quarter of 2014:
2
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Package
JolosutrioSendangbiru
Tebas- Singkawang. Bypass Sambas Galing-Tj.harapan
Sp.Tanjung-Galing Sp.Tanjung -Aruk
Province
East java
West Kalimanatan
West Kalimantan
Tanjung Selor – Sp.3 Tj.Palas- Sekatakbuji (Sect 1)
East Kalimantan
Sp.3 Tanjung Palas – Sekatak Buji (Section 2 ).
East Kalimantan
Sp.Tiga Apas – Simanggaris (Section 1).
East Kalimantan
Sp.Tiga Apas – Simanggaris (Section 2). SimanggariBts.Negara (Serudong)
East Kalimantan
Contractor
Physical Progress % Sche Actual Diff. d
Remarks Since January 2014, accomplishment/ progress of work has been very low.
PT.Hutama Karya
57,49
29.04
-28,45
PT.Brantas Abipraya. Tri Citra Perdana Trifa Abadi -JO
18,52
25,76
7,24
PT.Waskita Karya PT.Yasa Patria Perkasa
20,48
14,06
-6,42
Behind Schedule
PT. Waskita Karya
0.09
0,10
0,01
COW 12 December 2014
PT. Brantas Abipraya ; PT.Mahir Jaya Mahakam Raya – JO
1,653
2,28
1,23
0,627
PT.Perdasa- JO
5.19
6.49
1,30
HALLA Corporation
0,73
0,52
-0,21
PT Pem.Perumahan
The location of all Packages is shown on the following Project Location Map.
3
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
WEST KALIMANTAN
4
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
EAST KALIMANTAN
5
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
EAST JAVA
6
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
CENTRAL JAVA
7
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
1.2.3
Consultancy Services
TA Consultant
Planned Mobilization from the Project Admin Manual up to date June 2011
Contract Signed
Actual Mobilization
Responsible Agency
CTC (CSP-1)
April 2012
12 Feb 2014
3 Mar 2014
DGH
DSC-1 (CSP-2)
April 2012
21 Nov 2013
16 Dec 2013
DGH
DSC-2
Not Yet
DSC-3 (CSP-3)
Not yet 16 Oct 2013
18 Oct 2013
Remarks
DGH DGH
Road Safety Support (CSP-4)
Jan 2013
Not yet
DGH
Institutional development for Road Network Management (CSP-5)
Jan 2013
Not yet
DGH
Road safety awareness Campaign and Training (CSP-6)
Jan 2013
Not yet
DGLT
Integrated Vehicle overloading Control Strategy (CSP-7)
Jan 2013
Not yet
DGLT
Overloading and Speed Enforcement (CSP-8)
Jan 2013
Not yet
DGNTP
Indonesia Transport Sector Dev. Strategy and Policy (CSP-9)
Jan 2013
Not yet
Bappenas
HIV/AIDS anti Trafficking Program (CSP-10))
Jan 2013
Not yet
DGH
Road safety Equipment
Sept 2013
Not yet
DGNTP
As can be seen from the above table the appointment of all Consultancy Services have been late for a number of reasons including delay of procurement process Consultant Services DSC-2 and delay in the procurement process for civil works in Central Java. Also there has been delay for Technical Assistant Consultant services CSP-4 to CSP-10 1.3
Current Status of Loan At the end of this fourth quarter 2014, (December 2014) some US $ 21,686.86 representing 8.85% of the available loan, has been disbursed. Disbursement is therefore considerably behind schedule as 21.74% (10 months) of the loan availability period has already elapsed with the main reasons for the delay being:
8
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
a) The long period elapsing waiting for the NOL for tender documents packages in Central Java. b) The delay of disbursement of Advance Payment for package 34-RCP03 (Sp.3 Apas – Simanggaris, section 1) and 34-RCP04 Sp.3 Apas – simanggaris – section 2; ; Simanggaris – bts. Negara). c) Late appointment of Technical Assistance (TA) Consultants for CSP 4 to CSP10 yet contracted. Details of the overall loan situation are presented a series in forms A through E found immediately after the main text in this report. These forms are an English translation of the quarterly report prepared by PMU for Bappenas. 1.4
Current Problems and Action Required at End of fourth Quarter 2014 Item
Suggested Solution
Three to five packages will not be completed within the current loan period
An extension to the loan period to be proposed for acceptance/ consideration by ADB
Technical Assistant for Road Sector Development Program
Until end of December 2014 still not running.
Accelerate the process of procurement / contracting
Package Jolosutro Sendangbiru
This package has fallen way behind schedule, looks like contractor has cash flow problems
PPK must invite contractor for Show cause meeting. Contractor should achieve catch up targets/ revised schedule to complete their Contract
LRAP Issues
Many problems have arisen with the acquisition of land and the compensation process.
CTC should cross check directly on site, to determine the real situation and coordinate with PPK and local government.
Loan Period Extension
2
Problem Areas
General 2.1
Reporting Requirements Quarterly Progress Reports: This is the third quarterly progress report to be prepared and covers the fourth quarter of 2014. Report
Period Covered
Final Version Issued
Quarterly Progress Report No.1
March 2014 – June 2014
May 2015
Quarterly Progress Report No.2
July – September 2014
May 2015
Quarterly Progress Report No.3
October – December 2014
May 2015
Financial Monitoring Reports: Reports have been prepared for each quarter since the beginning of 2014 although the first and the second issued in July 2014,
9
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
covered the period January – June 2014. Reports have since been prepared each quarter on schedule as shown in the table below. Report
Period Covered
Date Issued
Financial Monitoring Report No.1
January – March 2014
10 July 2009
Financial Monitoring Report No.2
April – June 2014
Financial Monitoring Report No.3
July – September 2014
5 November 2014
Financial Monitoring Report No.4
October - December 2014
January 2015
CTC Monthly Progress Reports: These reports have been prepared covering each month since CTC mobilized on March 2014. The first, covering the month of April 2014, was issued in May 2015. Subsequent reports have been submitted on a more regular monthly basis. Reports are vetted and edited where PMU requires it. Report
2.2
Period Covered
Final Version Issued
Monthly Progress Report No. 1
April 2014
15 July 2014
Monthly Progress Report No. 2
May 2014
18 July 2014
Monthly Progress Report No. 3
June 2014
15 August 2014
Monthly Progress Report No.4
July 2014
15 September 2014
Monthly Progress Report No.5
August 2014
26 September 2014
Monthly Progress Report No.6
September 2014
6 November 2014
Monthly Progress Report No.7
October 2014
27 November 2014
Monthly Progress Report No.8
November 2014
15 January 2015
Monthly Progress Report No.9
December 2014
23 February 2015
Loan Status The agreed allocation of loan funds from the original loan agreement together with the % disbursed to the end of the quarter is presented in the following table:
Category
Works Works (Central Java)
Original Amount of loan Allocated in US$
Total Disbursed to 30 Dec 2014 in %
Distribution to 30 Dec 2014 in US$
ADB
IDB
Percentage of Expenditure to be financed
155,000,000
-
70%
9.74%
20.300.87
-
53,500,000
100%
0
0
100%
0
0
100%
9.12%
1,385.99
Road Safety Equipment
1,300,000
Consultant’s services and training
12,200,000
3,000,000
10
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
- Road Safety Support - Institutional Dev. for Road Network Management. - Road Safety awareness campaign and Training
4,300,000
-
100%
0
0
Over loading and speed Enforcement
2,200,000
-
100%
0
0
- Indonesia Transport Sector development Strategy and Policy study. - Integrated Vehicle Overloading Control Strategy - HIV/AID and anti Trafficking Prevention Program
2,400,000
-
100%
0
0
Unallocated
2,600,000
8,500,0000
0
0
0
TOTAL AMOUNT
180,000,000
65,000,000
8,85
21.686.86
Details of the overall loan Status can be found in Appendix No.1
2.3
Financial Management S-Curve for Financial Progress The following curve shows the financial disbursement progress up to the end of December 2014 with the loan scheduling.
11
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
2.4
Project Cost Monitoring A summary of the project cost monitoring in tabular format is presented as Appendix No. 3. Status December 2014
No.
Contract No.
Contract Description
Type of Works
Estimated Cost
Contractor
6
IDR (x10 )
Contract Sign Date
Category
21-Aug-13
Civil Works
ICB
Procurement Method
Contract Price (IDR 10⁶) Including Tax Original Addendum
ADB
Cost During this Quarter (IDR)
Financing Ratio (%)
Actual
93,350,000
70.00
691,290,730
Planned
ADB Share
Cummulative Cost (IDR) Actual as % of Planned
To Last Quarter
Total
Actual to date ADB Share
2.46
25,564,945,646
26,256,236,376
Physical Progress % Planned to date
Actual as % of Planned
Scheduled
Actual
Difference
14,250,065,103
53,666,915,000
49
57.49
29.04
-28.45
4
01-28-RCP-01A/RB/ADB/2817/0813
Jolosutro - Bale kambang - Sendang New Road Reconstruction biru Resurfacing
151,916.793
6
02-30-RCP-02/RB/ADB/2817/1113
Tebas - Singkawang (Section 1); Tebas -Singkawang (Section 2) Bypass Sambas Galing - Tanjung Harapan
Reconstruction Resurfacing
430,578.648
PT.Brantas Abipraya-Tri Citra Perdana-Trifa Abadi, JO
14-Nov-13
Civil Works
ICB
292,603,385
70.00
39,509,508,507
39,569,978,575 27,656,655,955
99.85
58,501,897,975
98,011,406,482
62,370,895,034
98,071,876,550
100
18.52
25.76
7.25
7
03-30-RCP-02/RB/ADB/2817/1113
Sp. Tanjung - Galing; Aruk (bts.Serawak - Sp.Tanjung
Reconst + widening Reconstruction
333,214.553
PT Waskita Karya - Yasa Patria Perkasa, JO
27-Nov-13
Civil Works
ICB
238,974,973
70.00
17,766,915,317
41,385,255,129 12,436,840,722
42.93
43,400,675,542
61,167,590,859
38,924,830,547
84,785,930,671
72
20.48
14.06
-6.42
8
01-34-RCP/LOAN/PJN.III/11.14
Tanjung Selor- Sp.3 Tj.Palas Sekatakbuji (section 1)
333,214.553
PT.Waskita Karya (Persero)
3-Nov-14
Civil Works
ICB
189,970,248
70.00
26,682,184,833
28,666,510,423 18,677,529,383
93.08
0
26,682,184,833
16,979,572,166
28,666,510,423
93
0.09
0.1
0.01
9
02-34-RCP/LOAN/PJN.III/06.14
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
Reconstruction Grade Improvement
215,483.495
PT.Brantas Abipraya -Mahir Jaya Mahakam Raya- JO
25-Jun-14
Civil Works
ICB
165,332,338
70.00
1,888,644,484
2,732,945,047
1,322,051,139
69.11
24,799,849,200
26,688,493,684
18,681,945,579
27,532,794,247
97
1.65
2.28
0.63
10
03-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis (Sect 1)
Reconstruction Resurfacing
322,919.917
PT.Pemb. PerumahanPT.Perdasa JO
11-Apr-14
Civil Works
ICB
289,000,000
70.00
18,764,844,504
15,001,990,000 13,135,391,153
125.08
43,350,000,000
62,114,844,504
43,480,391,153
58,351,990,000
106
5.19
6.49
1.30
11
04-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis (Sect 2); Simanggaris - Bts.Negara
Reconstruction Resurfacing
407,483.774
Halla Corporation
11-Apr-14
Civil Works
ICB
359,652,697
70.00
19,303,518,965
18,809,835,971 13,512,463,276
102.62
37,763,533,267
57,067,052,232
39,946,936,562
56,573,369,238
101
0.73
0.52
-0.21
234,634,636,144
407,649,386,130
PT.Hutama Karya
TOTAL
1,628,883,641
12
28,101,969,354
483,903,511
124,606,907,340 174,268,484,500 87,224,835,138
233,380,901,630 357,987,808,970
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
2.5
ADB Missions The following table summarizes all Bank missions to the RRDP to date: Dates
Mission Team
From
To
ADB
15 Dec 13
20 Dec 13
Soewartono, HS
21 Apr 14
24 April 2014
-
23 Sept 14
November 14
Soewartono, HS
IDB
- Dr.Nizar Zaied - Murad Gurmeric -
During this fourth quarter, ADB Midterm Review mission visited to the project commencing on 23 September 2014. As can be seen from the table below the mission started their visit to the East Java project at end September 2014. One (1) site visit to RRDP projects in West Kalimantan was made in middle of October and one (1) site visit made mid November 2014 for Packages in North Kalimantan, with meetings for every province prior to site visits. The meeting were attended by the mission delegates, Bappenas, Finance Ministry staff, Balai, PMU and CTC. Date
Activity
23 September 2014
Kick of Meeting at 5 Fl , Bina Marga.
30 September 2014
Meeting at Santika Hotel Malang.
1 October 2014
Site Visit Jolosutro- Sendangbiru
2 October 2014
Meeting at BPPJN V office Surabaya.
7 October 2014
Meeting at Mercure Hotel Pontianak.
10 – 11 October 2014
Site Visit to Package 30-RCP02 and 30-RCP03 Wes Kalimantan.
10 November 2014
Coordination Meeting in Balikpapan
11 – 15 November 2014
Site visit to three Packages in North Kalimantan
5 December 2014
Wrap up meeting at 5 Fl, Bina Marga
At the beginning of October 2014, the ADB Midterm mission made a site visit to East Java and West Kalimantan only, a Coordination meeting with Ministry of Finance, DGLT, DGNTP, Bappenas and PMU being held in Bappenas meeting room on 23 October 2014. 2.6
Project Steering Committee Meeting No Steering Committee meetings have been held to date.
2.7
Loan Closing Date During the ADB Midterm Review Mission, informal discussions were again held relating to the completion date for the packages in Kalimantan and three (3)
13
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Packages in Central Java. It was agreed that most Packages were unlikely to be completed before their scheduled Project Hand Over (PHO) dates. 3
Project Management and Implementation There were no major changes in project management during the quarter 3.1
Procurement Plan Appendix No. 2 presents a copy of the general Procurement Plan for all, Civil Works, Goods and Consulting Services, of the project as updated to the end of the fourth quarter 2014.
3.2
Procurement Status (A) Works Procurement is being conducted under the Bank’s Procurement Procedures as described in the Loan Agreement. International Competitive Bidding (ICB) will apply for packages with the estimated total cost of more than US$10 Million to comply with the Bank’s threshold. According to Government of Indonesia (GOI) regulation, prequalification shall be apply to all packages with construction estimated cost to be more than IDR 100 Billion. All subprojects have been started with prequalification since 20 December 2011 for ICB multiple contracts. This was an advanced procurement action agreed between the DGH and the Asian Development Bank (ADB) prior to the establishment of a CTC. The deadline for submission of Qualification Document by Applicants was 27 April 2012. Procurement is now complete for seven (7) packages: two (2) packages in West Kalimantan, one (1) package in East Java and four (4) packages in East Kalimantan. One package CW-05, 30-RCP01, Sosok – Tayan; Tanjung – Batas Kota Sanggau, NOL for Bid Evaluation Report was approved by ADB on 9 December 2014 and by the Ministry of PU on 11 December 2014. Three Packages in Central Java Province, CW-01, 24-RCP01, Tambakmulyo Wawar ; CW-02, 24-RCP02 Giriwoyo – Duwet and CW-03,24-RCP03, Wawar – Congot , NOL for Bid Evaluation Report was approved by IDB (Islamic Development Bank)
on 1 December 2014 and by the Ministry PU on 8
December 2014. (B) Goods There was no Goods procurement processed during the fourth quarter 2014.
14
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
(C)
Services
The status of Core Team Consultant (CTC), Design and Supervision Teams (DSC-1 and DSC-3), are shown in Section 3.5 of this report. : 3.3
Implementation Status – Civil Works Contracts have been signed for Seven (7) Packages; one (1) for East Java Province (CW-4), two (2) for West Kalimantan (CW-6 and 7) and four (4) for East Kalimantan and construction has commenced. One Package 28-RCP-01A, Jolosutro – Sendangbiru progress
is behind
schedule at 28.456%. First SCM (Show Cause Meeting) was held by PPK at project level between PPK, Consultant and Contractor on 7th October 2014. Contractor had to follow the test case agreed, however failed to fulfill the target set. A Second SCM also was held in Balai Besar V Surabaya on 3rd November 2014, attended by Chief of Implementation Section of Balai Besar V Surabaya, Satker Pembangunan Jalan Wilayah 1, PPK, Consultant DSC-3, Field Team Consultant and Contractor. At this 2nd stage the Contractor also failed to improve his performance. It appears that it is difficult for the Contractor to continue the project due to a cash flow problem. One (1) Package 30-RCP03, Sp.Tanjung – Galling; Aruk- Bts Serawak is behind schedule at 6.42%, DSC team is aware of this situation and are monitoring. One Package is ahead of schedule at 7.24% , Tebas – Singkawang (section 1 & 2) ; Bypass Sambas; Galing – Tj.Harapan. Package 34-RCP02 (CW-09) (Sp.3 Tanjung Palas- Sekatak Biji ) (Section 2). The Contractor commenced work on 4 September 2014 and Physical progress is slightly ahead schedule at 0.63%. The Contractor should be encouraged because less progress this month. Package 34-RCP03 (CW-10), Sp. Tiga Apas –Simanggaris (Section 1), the Commencement of work was issued on 10 July 2014. The Contractor progress is now was ahead schedule at 1.29%. ADB concurred with the Contract for 34-RCP04 (CW-11) (Sp. Tiga Apas Simanggaris (Section 2) and (Simanggaris – Bts Negara (Serudong)) on 14 May 2014. Commencement of Work was issued on 1 October 2014; to date physical progress is slightly behind schedule at -0.21%. The summary of Implementation Status and Cost Monitoring of RRDP project is shown in Appendix No. 3.
15
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
3.4
Variation Orders The first variations was made for package CW-04. For this variations no additional cost (balance budget) only there is a change in the quantity of items common excavation, rock excavation, common embankment , excavation of existing asphalt Pavement, CTB was raised and mortared stone work in V ditch C3 reinforced concrete, clearing and grubbing, aggregate base class S, aggregate base class A decreased during this period. The variations was covered in Addendum No.1
3.5
Ongoing Consultancy Services a) Technical Assistance for Core Team Consultants (CTC) to Support the Project Management Unit (PMU) Consultant: Renardet,S.A
Joint Venture with
Local Consultants
PT.Widya Graha Asana; PT.Multi Phibeta; PT. Anugerah Krida Pratama; PT.Disiplan Consultant as the Core Team Consultant (CTC). Contract No.03-02/CTC/PM/LN/ADB/2817.0214 was signed on 12 February 2014, between the Ministry of Public Works, Directorate General of Highways and Lead Consultant Renardet S.A. Notice to Proceed (NTP) was issued on 25 February 2014 and Contract is scheduled to be completed by 29 February 2016. If the Civil Works Loan period is extended the CTC Contract will also have to be amended. A Draft Addendum No.1 to the CTC Contract is currently being prepared to formalize a number of issues such as additional professional and sub professional personnel in the CTC Contract. This Draft Addendum No.1 reflects additional requirements to CTC services as summarized below. a)
Additional TOR for Third Party Monitoring (TPM) activities
b)
Amendment of the CTC Team composition and staffing schedule
c)
Additional professional Staff for Traffic Engineer and Transport Economist.
d)
Replacement of Professional Staff for Environmental Specialist.
e)
Replacement of Professional Staff Road safety Audit Engineer.
f)
Replacement of Professional Staff Social Impact Specialist
b) Technical Assistance for Construction Supervision Consultant (DSC1) for packages in West and East Kalimantan. Lead Consultant: CECI (China Engineering Consultants Inc), Taiwan DSC-1 Contract No. 01/DSC-1/CS/ADB/2817/1113 was signed on 21 November 2013 between the Ministry of Public Works, Directorate of Western Region, DGH and CECI in Joint venture with PT.Wira Wydiatama; 16
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
PT.Hasfarm
Dian Konsultan; PT.Yodya Karya; PT.Seecons; PT.Pola
Agung Consulting. The original Contract value for DSC-1 is US$ 936.570 and IDR 30.372.995.000 (excl VAT). The mobilization of DSC-1 was behind schedule - construction work already started on 16th December 2013. c) Technical Assistance for Construction Supervision Consultant (DSC2) for Package in East Java. Consultant: PT. Perentjana Djaya. DSC-3 Contract No. 01/DSC-3/CS/ADB/2817/1013 was signed on 16 October 2013 between the Ministry of Public Works, Directorate of Western Region, DGH and PT.Perentjana Djaya. Notice to Proceed (NTP) was issued on 18th October 2013. On 29 October 2014 ADB concurred to the draft Addendum No.2 DSC-3 having the value of IDR Rp.8.256.578.000. d) Technical Assistance for Construction Supervision Consultant (DSC2) for Package in Central Java. The submission of final Evaluation Report (Technical and Financial) and draft contract for Design and supervision Consultant (DSC-2) was submitted to the IDB by DGH on 24 December 2014. e) Other Consultants for Technical Assistant Road Sector Development Program. CSP-4: Road Safety Engineering Support (DGH) EOI was submitted by the Consultants on 20 September 2014 and the Evaluation Report for the Short List of Consultant was sent to ADB on 28 October 2014. “No Objection Letter” for the short list of the consultant and draft of Request for Proposal (RFP) was issued by ADB on 9 December 2014. CSP-5: Capacity Development Program (DGH) Coordination meeting was held among the related sections of DGH and CTC presided by Secretary General of BINA MARGA on the scope of works on 31 October 2014, but the program has only just started to move and the TOR is still under discussion. CSP-6: Road Safety Awareness Campaign & Training (DGLT) A Meeting was held between DGLT and CTC on Terms of Reference (TOR) for which ADB already gave the comment to revise on the first submission. DGLT is preparing the revised TOR for the approval of ADB.
17
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
CSP-7: Overloading and Speed Enforcement (DGNTP) ADB selected another institution to support INTPC to draft the short list of consultants due to conflict of interest. Short list of the consultants was completed including Request for Proposal (RFP) and Terms of Reference (TOR), sent to ADB 26 September 2014. This was concurred by the Bank on 19 November 2014. Invitation of RFP was conducted by POKJA of DGNTP on 4 December 2014. Bid submission is expected to be on 19 January 2015. CSP-8: Indonesia Transport Sector Development Strategy and Policy Study (Bappenas) A Short list of consultants including Request for Proposal (RFP) and TOR was sent to ADB on 10 July 2014 and this was concurred on 24 September 2014. CSP-9: Integrated Vehicle Overloading Control Strategy A Meeting was held between DGLT and CTC on Terms of Reference (TOR) for which ADB already gave the comment to revise on the first submission. DGLT is preparing the revised TOR for the approval of ADB. CSP-10: Human Trafficking Prevention and HIV/AIDS Campaign Programs EOI was submitted by the Consultants on 20 September 2014. Evaluation Report for Short List of Consultant was sent to ADB on 28 October 2014. “No Objection Letter” for short list of the Consultant and draft of Request for Proposal (RFP) was issued by the ADB on 9th December 2014. 3.6
Implementation of the Anti-Corruption Plan 3.6.1
Community Representative Observer (CRO) Bid openings for three (3) packages in West Kalimantan and four (4) packages in East Kalimantan (3) three Packages in Central Java were attended by the selected CROs who are required to prepare reports with the results of their observations. A CRO did not attend in the bid opening ceremony for one (1) Package in East Java. See Appendix 7 for a tabular summary of CRO activities.
3.6.2
Third Party Monitoring (TPM) The Terms of Reference and budget for the TPM are contained in CTC draft Amendment No.1, now in preparation. All operational costs will come from the Technical Assistance component of the Loan for RRDP through the Core Team Consultant (CTC). It was decided that the best method of recruitment for TPM was through the universities closest to each individual package and PMU mailed 18
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
invitations asking them to express their interest in forming independent monitoring teams of Third Party Monitors. This concept is based on the fact that Universities/Technical Faculties have engineers available for recruitment and Universities could use this opportunity to be involved in public service.
It is hoped that this concept will be more effective and
more efficient in getting legitimate, competent, independent Third Party Monitoring (TPM). The duties of a TPM include a) Report to the PPK for his package and obtain copies of all drawings and contract documentation. b) Report to the PPK for his package and obtain copies of all drawings and contract documentation. c) Make at least three (3) separate visits to site, with each visit lasting up to four (4) days long, to ascertain that the works are being carried out in compliance with the drawings and documentation. d) Following each visit prepare a report and submit to the PMU. 3.6.3
Complaint Handling System (CHS) Up to December 2014, there are 3 (three) complaints have now received as listed in the table below: Packages
Complaints
Complainant
Remarks
Nos 34-RCP-01 Sp.3 Apas – Tj.Selor 30-RCP-01 Sosok- Tayan
3.7
2
1
PT.Bumirejo – PT.
Answer by Pokja
Sujainco JO PT. Multi structure
Procurement
PT.Brantas Abipraya JO
team Pokja
Implementation of the Environmental Management Plan All contractors have been informed that they must prepare an Environmental Management and Monitoring action plan (Rencana Kerja Pengelolaan dan Pemantauan Lingkungan) prior to commencement of each construction package. DSC will provide technical assistance to each contractor in the preparation of the required documents
19
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
The status of planned preparation is as follows: Safeguard Document
Pack. No.
Project Name
28-RCP 01A (CW-01)
Jolosutro Sendangbiru
AMDAL
Tebas Singkawang (Section-1 & Section-2)
AMDAL
Bypass Sambas
UKL-UPL
Galing-Tj.Harapan
UKL-UPL
30-RCP 02(CW-06)
Sp.Tanjung-Galing (Section-1) 30-RCP 03 (CW-07)
Date Draft
Final
Status Will be conducted to brief Contractors Will be conducted to brief Contractors
AMDAL
Sp.Tanjung-Galing (Section-2)
UKL-UPL
Aruk-Sp.Tanjung
UKL-UPL
34-RCP02 (CW-09)
SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
UKL-UPL
34-RCP03 (CW-10)
SP.3 Apas Simaranggis (Section- 1)
UKL-UPL
Will be conducted to brief Contractors
Will be conducted to brief Contractors Will be conducted to brief Contractors
A summary of the monitoring of environmental mitigation conducted by CTC for all packages is presented in Appendix No. 8 and a detailed record of the Status of environmental safeguard documentation in presented in Appendix No. 12. 3.7.1
HIV-AIDS and Anti Human Trafficking Program The Program for HIV/AID and Anti Human Trafficking has not yet started, still in the process of procurement.
3.7.2
Monitoring of Health and Safety Each contractor must take reasonable precautions to maintain the health and safety of his employees including collaboration with local health authorities. The object of this program is to minimize any accident and health problems during construction work execution; is part of CTC monitoring activities. Health and Safety Monitoring for each package can be found in Appendix 15. From the details in this Appendix it can be seen that the minimum attainment is “mildly satisfactory” with “good” being attained only for a few number of factors. Each package is made aware of the results and is encouraged to improve as necessary.
20
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
3.8
Resettlement & Rehabilitation Activities 3.8.1
Preparation of LARP In accordance with the requirement set forth in the safeguard document from
ADB
that
needed
monitoring
of
LARP
preparation
and
implementation of the for each package on RRDP program. Monitoring conducted by the CTC has been prepared in five (5) documents of LARP while one (1) LARP will be prepared for two (2) physical work packages that are 34-RCP-03 and 34-RCP04. 3.8.2
LARP Implementation Based on the results of monitoring, data collection and coordination with local government and projects, the progress of the implementation of the LARP can be grouped as follows: 1. East Java For Package 28-RCP 01A (CW-04): Determination and acquisition of land replacement located in Bondowoso District. The candidate of replacement land has been surveyed on September 2013 and status of the land replacement for forestry permits in form of that is the recommendation from Bondowoso Regent issued on February 2014. Socialization of project affected people has been carried out several times, in May, July and September 2014. In general, people understand the land acquisition plan. This will be supported by preparing documents related to the land acquisition process. The Local Government of Malang District has allocated budget for livelihood restoration assistance to affected households. The programs are geared to restore, the socio-economic conditions of affected households, including vulnerable households. However, up to now the income restoration program not yet implemented due to the program still not discussed with related agencies. The BPM (Badan Pemberdayaan Masyarakat/ Community Empowerment Office) has already prepared an Action Plan for related project, otherwise budgets still wait TAPD allocation (List of Malang District Project). Assistance programs in order to improve the welfare of society, especially those located around the project will be met through a program of related work units of the Government of Malang. 2. Central Java Package24-RCP-01 (CW-01): Tambak Mulyo-Wawar. Package 24RCP-02: Giriwiryo - Duwet (CW-02) and Package 24-RCP 03: Wawar(CW-03)-Congot. Compensation payment for Packages 24 21
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
RCP01 : Tambakmulyo – Wawar (CW-01) and 24-RCP03 : Wawar Congot
(CW-03)
has
already
been
implemented/completed
December 2006 to January 2013 consisting of (8) sub-districts in Kebumen District. For Package 24-RCP-02 (CW-02): Giriwoyo – Duwet, is still waiting for data from PPK. Compensation payment in addition to last compensation for depreciation in value of buildings is already in process. Kebumen District supporting project on community empowerment for the Affected People of road project is still developed among Bappeda and BPM. 3. West Kalimantan Package 30-RCP 01(CW-05): Sosok-Tayan; Tanjung-Sanggau City Border. and Acquisition Sosok - Tayan is 100 % complete and currently preparing recapitulation. Package 30-RCP 02 (CW-06): Tebas-Singkawang (Section-1 and Section-2), Bypass Sambas, Galing-Tanjung Harapan. Pakage 30-RCP 03 (CW-07): Simpang Tanjung-Galing (Section-1 dan Section-2), Aruk (Batas Serawak) - Simpang Tanjung. a. Singkawang City Based on data obtained by CTC, residents were identified who will be affected by the project that is in the Bambang Ismoyo Street on Tebas-Singkawang (Section-1) link which is part of the Package 30-RCP 02 (CW-06). Singkawang government has set aside for the purpose of land acquisition, but up to now still to be identified PAPs (Project Affected Persons). Planned in October 2014 at the location of the land acquisition process will be completed. However, on a field trip with the ADB mission, in Nov 2014 these activities had still not been completed. Currently the process is still in the stage of consultation with PAPs. b. Sambas District CTC team has had discussions with the Public Works Agency of Sambas district, and agreed to be clarification and validation of differences in the number and name of the PAPs. Corrective action based on the LARP document there are programs that have yet to be implemented, namely: - Allowances of lost revenue; - Assistance to vulnerable groups;
22
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Currently budget is not available to implement the program, the regional government will propose assistance from the Provincial Government. Directorate General of Highways, through the Balai Besar of the Region VII Kalimantan, has sent a letter to LG Regent Sambas and Singkawang concerning Implementation of Land Acquisition and Resettlement for RRDP in Sambas and Singkawang District of West Kalimantan Province. Recovery back to the communities affected by land acquisition, until now there has been no program of Sambas district government and Singkawang. However, the local government has planned an empowerment program for people whose land is affected by land acquisition. 4. North Kalimantan Package 34-RCP 01 (CW-08): Tanjung Selor- SP. 3 Tanjung Palas and Sp. 3 Tanjung Palas Sekatak Buji (Section-1); Package 34-RCP 02 (CW-09): Sp. 3 Tanjung Palas Sekatak Buji (Section-2); Package 34-RCP 03 (CW-10): SP.3 Apas - Simaranggis (Section- 1); Packages 34-RCP 04 (CW-11): SP.3 Apas - Simaranggis (Section2) and Simanggaris-Bts Negara (Serudong). a) Bulungan District Activities that have been carried out on 34-RCP Package 01 (CW-08) and Package 34-RCP 02 (CW-09) is a form of socialization and data collection of the residents who have the building and crops affected by the project in August 2014. Contractors have not been measuring the community lands that have been identified land affected by land acquisition, because still rainy season and measurement could not be done. b) Nunukan District Until now for Package 34-RCP 03 (CW-10) and Package 34RCP 04 (CW-11) activities related to land acquisition for road construction have not been carried out. In connection with the realignment in Package CW-10 and CW11 a new survey and measurement should be conducted and data collected for LARP. Preparation for LARP can be done with financing (proposed) included in Addendum 01 CTC-RRDP.
23
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
A detailed summary of the land acquisition requirements for all packages base on LARP studies are included in Appendix No. 11. 4.
Seminars, Workshops & Training No seminars, workshops or training courses were held during this fourth quarter 2014, due to the personnel for Training specialist not yet mobilized.
5.
Loan Utilization for Civil Works 5.1 Estimated Funding Status for RRDP Civil Works The estimate for Civil Works Packages in RRDP can be seen in Appendix No.14, using current exchange rates of 1US$ = 12,000 IDR for all future payments.
6.
RRDP Website The RRDP-CTC website has now been running on the fixed server site and can be found on http://www.pmu-rrdp.com . The RRDP-CTC website contains all of the following items: a)
General RRDP information including copies of all reports i.e. Monthly Progress Reports and Quarterly Progress Reports with the latest uploaded reports being the MPR , QPR for the first quarter of 2014, Social and Environmental Status Reports and the Road Safety Audit Reports.
b)
Project list and Project Progress Status including Procurement Plan and winners of bids, and Copies of all Bid Documents currently without drawings awaiting the original CAD files to be converted to PDF files)
c)
ACAP and Complaint Handling System including contact points, list of Community Representation Observers, and list of Third Party Monitors who have already been appointed.
d)
Announcements (current and archived)
e)
Newsletter
f)
Documents, (including all reports and bidding documents)
g)
Package Location Map
h)
Responses from the CHU following contract signing.
Any member of the public may submit a complaint via the website regarding the implementation of any RRDP package. Complaints can be submitted anonymously and they will be followed up by a responsible person from a related institution. 7.
Documentation Collection and Scanning CTC have set up a system whereby all RRDP documentation is being scanned and stored as soft copies with an appropriate well documented retrieval system. scanning
24
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
commenced to include the design documents (drawings, Engineers Estimates & Special Specifications), contract documentation (originals and amendments), procurement documentation, progress reports (weekly & monthly) and letters (corresponden,..ADB..comments.&..site..visit..reports).
25
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM A : GENERAL REPORT OF ACTIVITIES FINANCED BY LOAN AND OR GRANT OF FOREIGN FISCAL YEAR 2014
NAMA KEMENTERIAN NEGARA/LEMBAGA
: Ministry of Public Works
NAMA PEMBERI PHLN
: Asian Development Bank (ADB) dan Islamic Development Bank (IDB)
A.
DESRIPTION I.
PROJECT NAME LOAN / GRANT
: Regional Roads Development Project (RRDP)
II.
NPPHLN NUMBER AND REGISTER
: ADB No.2817-INO, Register : 10846401 IDB No. 0161-IND, Register : 10848804
III.
DATE OF NPPHLN SIGNED
: ADB : 7 Mei 2012 IDB :17 April 2012
IV.
EFFECTIVE DATE OF NPPHLN A. DATED OF EFFECTIVE TENTATIVE
: -
B. DATED OF REAL EFFECTIVE
: ADB : 3 Juli 2012 : IDB : 2 Mei 2013
V.
DATE OF CLOSING NPPHLN A. ORIGINAL
: ADB : 31 Agustus 2016 IDB : 30 April 2016
VI.
B. ACTUAL
:-
AMOUNT OF LOAN / GRANT
:
A. ORIGINAL
:ADB USD 180 billion
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
: IDB : USD 65 billion VII.
B. ACTUAL PURPOSE
:: To promote economic growth and poverty reduction in the region North of the island of Kalimantan corridor through the construction and improvement of road and bridges, with some target to be achieve through this project are:: (i)improvement / construction of road along the 854 km; (ii) improvement / construction of bridges along the 3.860 m; (iii) improve governance policy support in the road sector and (iv) increasing the capacity of human resources in the management of the road.
VIII.
TARGET
: Southern Cross access Java and Kalimantan Border Crossing Access
IX X.
INSTANSI PENANGGUNG JAWAB (EXECUTING AGENCY) INSTANSI PELAKSANA (IMPLEMENTING AGENCY) NO.
INSTANSI PELAKSANA
1
Ditjen Bina Marga (DGH)
2
Dijen Perhubungan Darat (DGLT)
3
Ditjen Kepolisian Lalulintas (DGNTP)
Kategori
ALOKASI DANA (JUTA VALAS )
REVISI
Civil Works
USD
208.50
-
Goods
USD
1.30
-
Consulting Services
USD
24.10
-
Unallocated
USD
11.10
-
Total
USD
245.00
-
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
XI. KATEGORI PINJAMAN NO.
DANA ALOKASI DANA PENDAMPING (JUTA VALAS) (JUTA VALAS)
KATEGORI PINJAMAN
1 2 3
Civil Works Goods Consulting Services & Training
4
Unallocated Total
USD 208.50 1.30 USD USD 24.10 USD 11.10 USD 245.00
REVISI
USD 88.50 USD USD USD 47.00 USD 135.50
XII. LINGKUP PEKERJAAN 1. Pekerjaan Jasa Konstruksi/Civil Works untuk 11 paket 2. Pekerjaan Jasa Konsultansi (civil works) yaitu CTC (Dit. Bina Program), DSC-1, DSC-2 dan DSC-3 (Dit. Bina Pelaksanaan Wilayah II) 3. Pekerjaan Jasa Konsultansi (roads sector developmet program) yaitu Road Safety Support, Institutional Development for Road Network Management, Road Safety Awareness Campaign and Training, Overloading and Speed Enforcement, Indonesia Transport Sector Development Strategy and Policy Study, Integrated Vehicle Overloading Control Strategy dan HIV/AIDS and Anti-Trafficking Program XIII. LOKASI (PROVINSI/KABUPATEN/KOTA) NO. 1 2 3 4
PROVINSI/KABUPATEN/KOTA Jawa Tengah Jawa Timur Kalimantan Barat Kalimantan Timur
ALOKASI DANA (JUTA VALAS ) USD 76.60 USD 21.30 USD 187.80 USD 191.40 USD 477.10
REVISI Non PPN Consultant Civil Work
6,563.36 100,634.36
0.000
XIV. DISBURSEMENT PLAN DAN REALISASI PHLN (Juta Rp) Rp
Tahun a. b.
2013 2014
Triwulan I : 4,762.72
Rp Actual 0.00 1,345.26
Triwulan II 0.00 11,929.28
Rp Actual 0.00 3,090.24
Triwulan III 0.00 101,483.97
Rp Actual 0.00 90,473.86
Triwulan IV 107,197.72 166,719.17
Actual 107,197.72 92,637.82
Total Disbursement Plan (Rp) 107,197.72 284,895.14
Total DIPA (Rp) 374,930.79 441,338.27
Total Realisasi DIPA (Rp) 107,197.72 187,547.18
Persentase Penyerapan (%) 28.59 42.50
B. PETUGAS YANG DAPAT DIHUBUNGI I. KETUA PELAKSANA HARIAN PMU RRDP Nama : DR.Ir. Slamet Mulyono M.Eng Alamat Kantor : Jl. Pattimura No. 20, Jaksel Nomor Telp : 021-7210218 Nomor Faksimili : 021-7210219 Alamat E-mail :
[email protected]
II. ESELON II PENANGGUNG JAWAB Nama : Ir. Harris H.Batubara, M.Eng.Sc Jabatan : Direktur Bina Program Ditjen Bina Marga Alamat Kantor : Jl. Patimura No.20 Jakarta Selatan Nomer Telp : 021- 7200281 Nomer Faksimili : 021- 7201760 Alamat E-mail :
[email protected]
III.A PROJECT IMPLEMENTING UNIT I #### Nama : DR. Ir.Didik Rudjito, MSc Jabatan : PPK Kegiatan Penyiapan Program dan Administrasi Pinjaman Luar Negeri Alamat Kantor : Jl. Pattimura No. 20, Jaksel Nomer Telp : 021-7248870 Nomer Faksimili : 021-7248870 Alamat E-mail :-
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM B.1 : SUMMARY IMPLENTATION IN FISCAL YEAR 2014 A. FINANCED (in IDR) No. Paket
PAKET KONTRAK
[a1] I.
TATA CARA PENARIKAN (PP/PL/LC/RK)
NILAI KONTRAK DAN STATUSNYA PADA AKHIR TAHUN SEBELUMNYA
PENYERAPAN KUMULATIF SAMPAI DENGAN DESEMBER TAHUN SEBELUMNYA
REALISASI PENYERAPAN WITHDRAWAL APLICATION (WA) TH YL
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
[e]
[f]
[g]
[h]
[i]
[j]
[k]
[l]
[m]
[n]
[a2]
[b1]
(b2)
[c]
[d]
PENYERAPAN PADA TAHUN ANGGARAN 2014 TRIWULAN I (1 Jan - 31 Maret)
TRIWULAN II (1 Apr - 30 Jun)
TRIWULAN III (1 Juli - 30 Sept)
TRIWULAN IV (1 Okt - 31 Des)
TOTAL TA 2014
Civil Works CENTRAL JAVA
24-RCP01
Tambakmulyo - Wawar
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
-
-
0.00
0.00
0.00
41,821,587,300
0.00
41,821,587,300
0.00
24-RCP02
Giriwoyo - Duwet (Section 1)
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
-
-
0.00
0.00
0.00
25,717,998,895
0.00
25,717,998,895
0.00
24-RCP03
Wawar - Congot
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
-
-
0.00
0.00
0.00
10,716,725,250
0.00
10,716,725,250
0.00
Pembayaran Langsung
93,350,000,000.00
23,011,025,595.00
23,011,025,595.00
14,250,065,103.00
1,164,447,900
0.00
2,355,687,250
1,625,221,851
7,162,465,450
1,548,644,269
11,229,538,250
3,173,866,120.00
29,381,213,197
26,135,334,348
38,679,370,633
EAST JAVA 28-RCP01
Jolosutro - Sendangbiru
546,937,650
0.00
WEST KALIMANTAN 30-RCP01
Sosok - Tayan Tanjung - Bts. Kota Sanggau
Menunggu Persetujuan ADB untuk Re-Tender
Pembayaran Langsung
Tebas - Singkawang (Section 1) 30-RCP02
Tebas - Singkawang (Section 2) Bypass Sambas
Pembayaran Langsung
292,603,385,000.00
43,890,507,750.00
43,890,507,750.00
27,930,323,114.00
614,467,109
0.00
4,219,340,812
3,090,244,128
9,810,991,499
6,207,913,308
11,490,534,929
Pembayaran Langsung
238,974,973,000.00
35,846,245,950.00
35,846,245,950.00
22,811,247,423.00
501,847,443
0.00
3,446,019,111
0.00
8,012,830,845
4,942,149,546
7,711,722,379
13,960,756,514
19,672,419,777.4
18,902,906,060
Galing - Tanjung Harapan 30-RCP03
Sp. Tanjung - Galing Aruk (Bts. Serawak) - Sp. Tanjung
EAST KALIMANTAN 34-RCP01
Tanjung Selor - Sp.3 Tanjung Palas
Pembayaran Langsung
0.00
0.00
0.00
0.00
34-RCP02
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
Pembayaran Langsung
165,332,328,425.00
0.00
0.00
0.00
34-RCP03
Sp. Tiga Apas - Simanggaris (Section 1)
Pembayaran Langsung
289,000,000,000.00
0.00
0.00
0.00
Pembayaran Langsung
359,652,598,000.00
0.00
0.00
0.00
1,438,913,284,425.00
102,747,779,295.00
102,747,779,295.00
34-RCP04
Sp.3 Tanjung Palas-Sekatak Buji (Section 1)
Sp. Tiga Apas - Simanggaris (Section 2) Simanggaris - Bts. Negara (Serudong)
TOTAL CIVIL WORKS II.
Road Saftey Enforcment
Pembayaran Langsung
0.00
-
0.00
-
-
0.00
1,663,252,201.80
0.00
-
0.00
24,127,254,199
18,133,523,673
24,127,254,198.93
18,133,523,673.00
-
0.00
-
15,781,722,218
19,674,548,222
2,282,946,209
19,674,548,222.00
18,064,668,427.00
-
0.00
32,185,930,000
27,586,363,636
10,115,000,000
14,627,608,357
42,300,930,000.00
42,213,971,993.00
0.00
39,676,885,643
34,330,484,788
4,204,340,040
4,452,948,752
43,881,225,682.98
38,783,433,540.00
-
0.00
8,829,807,822.36 3,090,244,128.00
92,042,325,237.10 90,473,855,347.00 162,742,176,663.68 84,387,640,971.00 265,277,561,924.94 177,951,740,446.00
-
-
-
0.00
102,747,779,295.00
102,747,779,295.00
-
64,991,635,640.00
-
0.00
0.00
0.00
-
0.00
0.00
0.00
-
0.00
0.00
0.00
0.00
0.00
0.00 0.00
0.00 0.00
0.00
Consulting Services & Training CTC RRDP
Pembayaran Langsung
0.00
0.00
0.00
0.00
DSC-1(ADB-KALIMANTAN)
Pembayaran Langsung
30,384,233,888.00
6,074,599,000.00
6,074,599,000.00
6,074,599,000.00
DSC-2(ISLAMIC - JATENG)
Pembayaran Langsung
0.00
0.00
0.00
0.00
DSC-3 (ADB-JATIM)
Pembayaran Langsung
7,633,945,000.00
0.00
1,040,992,500.00
1,040,992,500.00
2,412,421,320.00 687,051,000.00
-
0.00
2,412,421,320
5,806,675,050.00
0.00
1,583,638,650
5,196,212,520
7,390,313,700.00
5,196,212,520.00
0.00
2,412,421,320.00
0.00
1,809,315,990
1,188,780,000
9,046,579,950.00
2,534,041,456.00
0.00
-
0.00
535,500,000.00
0.00
126,000,000
0.00
661,500,000.00
0.00
0.00
687,051,000
0.00
687,051,000.00
0
458,034,000
1,865,182,640
2,519,187,000.00
1,865,182,640.00
0.00
-
0.00
0.00
0.00
0.00 1,345,261,456.00
Road Safety Support
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
Institutional Development for Road Network Management
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
0.00
-
0.00
-
0.00
-
Road Safety Awareness Campaign and Training
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
Overloading and Speed Enforcement
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
0.00
-
0.00
-
0.00
-
Indonesia Transport Sector Development Strategy and Policy Study
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
Integrated Vehicle Overloading Control Strategy
Pembayaran Langsung
0.00
0.00
0.00
0.00
-
0.00
-
HIV/AIDS and Anti-Trafficking Program
TOTAL Consulting Services IV.
0.00 -
GOODS TOTAL GOODS
III.
64,991,635,640.00
-
Unallocated TOTA L
Pembayaran Langsung
0.00
0.00
0.00
38,018,178,888.00
6,074,599,000.00
7,115,591,500.00
7,115,591,500.00
3,099,472,320.00
1,345,261,456.00
0.00
0.00
0
0.00
0.00
0.00
1,476,931,463,313.00
211,570,157,590.00
212,611,150,090.00
137,098,862,780.00
4,762,724,521.80
1,345,261,456.00
0.00
-
0.00
-
0.00
-
0.00
-
0.00
0.00
0.00
0.00
-
0.00
-
0.00
0.00
0.00
0.00
-
0.00
-
0.00
0.00
0.00
0.00
-
0.00
-
0.00
0.00
0.00
0.00
-
0.00
-
0.00
0.00
0.00
0.00
-
0.00
-
0.00
0.00
3,099,472,320.00 0.00
0.00 0.00
9,441,647,370.00 0.00
0.00 0.00
3,976,988,640.00 0.00
8,250,175,160.00 0.00
0.00
19,617,580,650.00
9,595,436,616.00
0
0
11,929,280,142.36 3,090,244,128.00 101,483,972,607.10 90,473,855,347.00 166,719,165,303.68 92,637,816,131.00 284,895,142,574.94 187,547,177,062.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM B : SUMMARY OF IMPLEMENTATION FOR FISCAL YEAR 2014 B. PHYSICAL IMPLMENTATION ( %) No.
PAKET KONTRAK
[a]
TANGGAL PENANDATANGANAN KONTRAK
TANGGAL AKHIR KONTRAK (PHO)
KUMULATIF s.d TA.2013
PERKEMBANGAN FISIK TAHUN ANGGARAN 2014 Akhir Triwulan I Target Realisasi
Akhir Triwulan II Target Realisasi
Akhir Triwulan III Target Realisasi
Akhir Triwulan IV Target Realisasi
[b]
[c]
[d]
[e]
[f]
[g]
[h]
[i]
[j]
[k]
1
24-RCP-01
Tambakmulyo - Wawar
-
-
-
-
-
-
-
-
-
-
-
2
24-RCP-02
Giriwoyo - Duwet (Section I)
-
-
-
-
-
-
-
-
-
-
-
3
24-RCP-03
Wawar -Congot
-
-
-
-
-
-
-
-
-
-
-
4
28-RCP01A
Jokosutro -Kedungsalam
21-Aug-13
13-Sep-15
14.65%
5.86%
22.88%
14.27%
23.03%
30.02%
25.79%
57.5%
29.04%
5
30-RCP01
Sosok - Tayan;
Menunggu Persetujuan ADB untuk Re-Tender Tanjung- Bts. Kota Sanggau Tembas - SIingkawang Sec.1 + Sec.2
6
30-RCP02
Bypass Sambas (Tanah Hitam /Tanjung Harapan - Sambas)
14-Nov-13
15-Dec-16
19.00%
1.07%
1.95%
2.37%
3.90%
5.47%
9.73%
18.52%
25.76%
26-Nov-13
2-Dec-16
19.00%
1.84%
0.47%
4.21%
4.02%
10.23%
8.35%
20.48%
14.06%
3-Nov-14
-
-
-
0.14%
0.23%
0.090%
0.101%
0.55%
5.19%
6.49%
0.00%
0.73%
51.80%
Galing - Tanjung Harapan Simpang Tanjung - Galing
7
30-RCP03 SP.3 Aruk /Bts. Serawak-Simpang. 3 Tanjung
8
34-RCP01
Tanjung Selor- SP.3 Tanjung Palas - Sekatak Buji (Sec.1)
9
34-RCP02
Tanjung Palas -Sekatak Buji (Sec.2)
25-Jun-14
-
-
-
-
-
-
0.95%
10
34-RCP03
SP.Tiga Apas - Simanggaris (Section 1)
14-Apr-14
-
-
-
-
-
-
0.00%
11
34-RCP04
Sp. Tiga Apas - Simanggaris - Bts. Negara (Serudong)
11-Apr-14
-
-
-
-
-
-
-
-
-
-
-
-
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM C : STATUS / PROBLEM 2817-INO / IND-0161
Regional Roads Development Project (RRDP) - Jumlah Pinjaman
13-Feb-09 s/d
245,000,000.00
-
Tandatangan
:
7 Mei 2012 (ADB) & 17 April 2012 (IDB)
Asian Development Bank
USD
180,000,000.00
-
Loan Efektif
:
3 Juli 2012 (ADB) & 2 Mei 2013 (IDB)
Islamic Development Bank
USD
85,000,000.00 21,686,801.05
31-Dec-14
- Penyerapan Kumulatif
: USD
2147 hari
- Waktu Terpakai (bulan)
:
- Realisasi PenyerapanTA-2014
:
`
1 Loan
: USD
71.57 IDR 188,677,142,382
2 Civil Works Jawa Tengah 1. 24 RCP-01
- No Objection to Awarding oleh IDB tanggal 1 Desember 2014
(CW-01)
dan Draf Kontrak sudah disetujui Menteri PU Pera tanggal 8
2. 24 RCP-02
Desember 2014 No Objection to Awarding oleh IDB tanggal 1 Desember 2014
(CW-02)
dan Draf Kontrak sudah disetujui Menteri PU Pera tanggal 8 Desember 2014 No Objection to Awarding oleh IDB tanggal 1 Desember 2014
3. 24 RCP-03 (CW-03)
- Draf Kontrak sudah dikirim ke IDB tanggal 24 Desember 2014 Diperkirakan tandatangan kontrak 12 Januari 2015 - Draf Kontrak sudah dikirim ke IDB tanggal 24 Desember 2014 Diperkirakan tandatangan kontrak 12 Januari 2015 - Draf Kontrak sudah dikirim ke IDB tanggal 24 Desember 2014 Diperkirakan tandatangan kontrak 12 Januari 2015
Jawa Timur 1. 28 RCP-01A
- Pekerjaan fisik terlambat
(CW-04)
- Mengingat sisa waktu pelaksanaan 433 hari (59.30% dan sisa pekerjaan sebesar 48.68% maka pekerjaan ini berpotensi mengalami keterlambatan apabila kontraktor kurang serius dalam
- Seharusnya sudah SCM 3 Tingkat Pusat,
melaksanakan pekerjaan - Hasil dari Test Case SCM 2 sudah dilakukan akifitas pekerjaan cukup significan pelapisan, hotmic ACWC, CTB, pekerjaan mixer jalan, menunggu persetujuan addendum I yang akan menambah
- Justek sudah selesai
volume bahan dibandingkan dengan volume original Addendum No, 2 sudah disetujui ADB tanggal 16 Desember 2014
Kalimantan Barat 1. 30 RCP01 (CW-05) 2. 30 RCP02 (CW-06)
3. 30 RCP03 (CW-07)
-
BER sudah dikirim ke ADB 3 Oktober 2014
- Menunggu persetujuan ADB
- Implementasi LARAP belum selesai
- sedang diproses oleh PemKab Sanggau
- Masih ada masalah LARAP (Land Acquisition Resettlement Plan)
- masih ada sebagian data Corrective Action ditindaklanjuti PPK/ Panitia Pembebasan Tanah
- Justifikasi Teknis masih belum selesai
yang
perlu
- lahan 200 m didalam kota Singkawang masih menunggu komitmen pendanaan dari Pemkot Singkawang
- Pembahasan review design telah disampaikan kepada Balai
- Masalah LARAP (Land Acquisition Resettlement Plan)
sudah dilakukan - Terdapat perbedaan data pembebasan, pembebasan dengan Pemda setempat dan pematokan. Masih ada
- Tidak ada material aggregate disekitar lokasi proyek
sebagian data Corrective Action yang perlu ditindaklanjuti PPK/ - Justifikasi Teknis masih belum selesai - Terdapat perbedaan data pembebasan lahan - Terdapat perbaikan geometrik. Penurunan grade sehingga perlu re-alignment di Sta 50 dari 13 % menjadi 8% sepanjang 350 m
Panitia Pembebasan tanah. - Pembahasan review design akan disampaikan kepada Balai Hasil pembahasan review desain akan disampaikan ke Wilayah - Rencana kontraktor mengimport material aggregate dari Serawak dan dari Merak - DSC-1 agar membantu mempercepat penyelesaian Justifikasi Teknis
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Kalimantan Timur 1. 34 RCP01
- Sudah Kontrak tanggal 3 Nopember 2014 dan SPMK tanggal 12
(CW-08) 2, 34 RCP02 (CW-09)
- Sudah menerima Uang Muka
Desember 2014 - Mobilisasi peralatan belum lengkap - Persediaan material belum maksimal -
Adanya pekerjaan tambahan terhadap penanganan longsor harus
- Pembebasan lahan masih tahap sosialisasi bentuk dan besaran ganti rugi - Tim external monitoring perlu dilapangan
diaddendum - Masalah LARAP (Land Acquisition Resettlement Plan)
- Pembebasan lahan baru 45% sampai saat ini - Terdapat 8 Desa terkena dampak
- Pekerjaan masih direct overlay
- Hasil Pre Construction Meeting (basic document) telah disepakati dibuat secara rasional guna menghindari potensi masalah
- LARAP (Land Acquisition Resettlement Plan)
- sudah melakukan sosialisasi lahan dan tanaman untuk perkebunan sawit telah dilakukan stacking out antara kontraktor dan pemilik
dikemudian hari. 3. 34 RCP03 (CW-10)
- Pembayaran kompensasi yang sudah dilaksanakan hanya untuk bangunan dan tanaman. Sedangkan untuk lahan masih akan dilakukan verifikasi data
perkebunan - Masih ada sebagian data Corrective Action yang perlu ditindak lanjuti PPK / Panitia Pembebasan tanah. - Tim external monitoring perlu kelapangan - sedang dikoordinasikan rencana pelaksanaan verifikasi data dan pembiayaan kompensasi untuk lahan.
4. 34 RCP04 (CW-11)
- SPMK tanggal 1 Oktober 2014 - Field
engineering
terdapat
perbedaan
koordinat
dilakukan survei lebih detail - Re-alignment sepanjang 16 km + 3.75 km
sehingga
- Kontraktor sudah melaksanakan pekerjaan sebesar 0.518% - Sedang dilakukan pengukuran terkait perbedaan koordinat - Sudah terima Uang Muka
- Perlu survey / data LARAP 3 Konsultan a CTC sudah menerima Uang Muka Proses Addendum I b DSC 1 Kalimantan belum mengajukan MC 1 sd MC 9 untuk Porsi Rupiah sedangkan Invoice 1-10 porsi sudah ditagihkan
- Untuk Invoice belum bisa ditagihkan karena tidak ada alokasi di DIPA 2014 Addendum I ini masih harus direvisi terkait penambahan personil - Segera memproses penagihan menunggu Addendum I - Addendum I ini masih harus direvisi
c DSC 3 Jawa Timur sudah menagih Invoice I -13 (Oct 13 - Oct 14) d Technical Assistance (TA) yang belum terkontrak CSP-4 : Road Safety Support
Status sampai 31 Desember 2014 Evaluasi dan Daftar Pendek (Termasuk permintaan proposal dan Kerangka Acuan Kerja) telah dikirim ke ADB tgl 28 Oktober 2014
CSP-5 : Institutional Devl for Road Network Management
Belum dimulai
CSP-6 : Road Safety Awareness Campaign and Training
Komentar atas Kerangka Acuan Kerja, belum ada tindak lanjut dari Kemenhub
CSP-7 : Overloading and Speed Enforcement
Evaluasi Daftar Pendek sudah disetujui ADB tanggal 19 Nopember 2014
CSP-8 : Indonesia Transport Sector Development Strategy and Policy
Evaluasi dan Daftar Pendek (Termasuk permintaan proposal dan Kerangka Acuan Kerja) telah disetujui oleh ADB tgl 24 Sept 2014
CSP-9 : Integrated Vehicle Overloading Control Strategy
Belum dimulai
CSP-10 : HIV Aids and Trafficking program
Evaluasi dan Daftar Pendek (Termasuk permintaan proposal dan Kerangka Acuan Kerja) telah dikirim ke ADB tgl 28 Oktober 2014
CSP-11 : Design and Supervision Consultant -DSC-2 Central Java (IDB)
Hasil Evaluasi Kombinasi (Proposal Teknis dan Keuangan) telah dikirim ke IDB tanggal 24 Desember 2014
4 DIPA 2014 - Alokasi PHLN untuk RKAKL 2014 sebesar Rp.534.468.867.000,- Penyerapan yang masih rendah hanya 38.40% dari Total DIPA 2014
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 28-RCP01A (Jawa Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 21 Agustus 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 8 September 2013
Oleh Penanggung Jawab Kegiatan
1-Mar-12
27-Jun-12
- Periode Kontrak
: 730 hari Kalender
Persetujuan Pemberi Pinjaman
15-Mar-12
6-Feb-13
- Tanggal Akhir Kontrak
: 17 Oktober 2015
- Nama kontraktor/konsultan/suplayer
: PT.Hutama Karya
Pasca Kualifikasi Undangan Lelang
24-Mar-12
1-Mar-13
30 Mei 201228Juni 2012
2 Mei 2013 4 Juni 2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
10-Jul-13 Status Kemajuan :
KONTRAK Tandatangan Kontrak
Rencana : 57.498 % ; Actual : 29.042 % ; Deviasi : -28.456 %
21-Aug-13
Status Penyerapan : Rp. 27,998,529,498 (29.99.%)
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
Waktu Terpakai : 433 hari (59.32 %)
9-Sep-13
Permintaan Uang Muka
Slipage : 297 hari (40.68 %)
18-Sep-13
Penarikan Uang Muka
9-Oct-13
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
(f)
(g)
Triwulan 1
Triwulan 2
Triwulan 3
Triwulan 4
TOTAL TA 2014
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
1,625,221,851.00
7,162,465,450
1,548,644,269.00
93,350,000,000.00 23,011,025,595 546,937,650 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
1,164,447,900
-
2,355,687,250
11,229,538,250.00
Realisasi (p) 3,173,866,120.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP01 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
15-Juni-2012
- Periode Kontrak
:
25-Juni-2013
- Tanggal Akhir Kontrak
:
Oleh Penanggung Jawab Kegiatan
8-Apr-12
Persetujuan Pemberi Pinjaman
22-Apr-12
18-Sep-12 (Comment)
Undangan Lelang
- Nama kontraktor/konsultan/suplayer
30-Apr-12
1-May-14
5 Juli 2012-3 Sept 2012
10 Juli 2014-24 Agustus 2014
17-Sep-12
21-Sep-14
:
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
* No Objection to Awarding oleh IDB tanggal 1 Desember 2014
7-Okt-2014
Persetujuan oleh Bappenas (bila diperlukan)
* Draf kontrak sudah disetujui Menteri 8 Desember 2014
Persetujuan Pemberi Pinjaman
* Draf Kontrak sudah dikirim ke IDB
Permintaan Uang Muka
* Kontrak diperkirakan Minggu kedua Januari 2015
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
41,821,587,300
TOTAL TA 2014
-
41,821,587,300.00
-
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP02 (Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
15-Juni-2012
- Periode Kontrak
:
25-Juni-2013
- Tanggal Akhir Kontrak
:
Oleh Penanggung Jawab Kegiatan
8-Apr-12
Persetujuan Pemberi Pinjaman
22-Apr-12
18-Sep-12 (Comment)
Undangan Lelang
- Nama kontraktor/konsultan/suplayer
30-Apr-12
1-May-14
5 Juli 2012-3 Sept 2012
10 Juli 2014-24 Agustus 2014
17-Sep-12
21-Sep-14
26-Sep-12
7-Okt-2014
:
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
* No Objection to Awarding oleh IDB tanggal 1 Desember 2014
Persetujuan oleh Bappenas (bila diperlukan)
* Draf kontrak sudah disetujui Menteri 8 Desember 2014
Persetujuan Pemberi Pinjaman
* Draf Kontrak sudah dikirim ke IDB
Permintaan Uang Muka
* Kontrak diperkirakan Minggu kedua Januari 2015
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
25,717,998,895
TOTAL TA 2014
-
25,717,998,895.47
-
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 24-RCP03(Jawa Tengah )
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
:
Pasca Kualifikasi Undangan Lelang
24-Jan-14
Persetujuan Pemberi Pinjaman
1-May-14 25-Apr-14
Evaluasi Pengadaan 10 Juli 2014-24 Agustus 2014
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
21-Sep-14
KONTRAK Tandatangan Kontrak
* No Objection to Awarding oleh IDB tanggal 1 Desember 2014
7-Okt-2014
Persetujuan oleh Bappenas (bila diperlukan)
* Draf kontrak sudah disetujui Menteri 8 Desember 2014
Persetujuan Pemberi Pinjaman
* Draf Kontrak sudah dikirim ke IDB
Permintaan Uang Muka
* Kontrak diperkirakan Minggu kedua Januari 2015
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
-
10,716,725,250
TOTAL TA 2014
-
10,716,725,250.00
-
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP01 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
:
Pasca Kualifikasi Undangan Lelang
23-Apr-12
26-Feb-13
29 Juni 2012 27 Agust 2012
21 Mei 2013 - 11 Sep 2013 11-Okt-2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
Catatan : Proses Usulan untuk Tender Ulang KONTRAK Sedang Proses Evaluasi Penawaran
Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
(f)
(g)
Triwulan 1
Triwulan 2
Triwulan 3
Triwulan 4
TOTAL TA 2014
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
Realisasi (p) -
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP02 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 14 Nopember 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 28 November 2013
Oleh Penanggung Jawab Kegiatan
31-Mar-12
27-Jun-12
- Periode Kontrak
: 1.095 hari kalender
Persetujuan Pemberi Pinjaman
14-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 15 Desember 2016
- Nama kontraktor/konsultan/suplayer
: PT.Brantas Abipraya (persero)- PT. Citra Persada PT. Trifa Abadi, JO
Pasca Kualifikasi Undangan Lelang
23-Apr-12
26-Feb-13
29 Juni 2012 27 Agust 2012
23 Mei 2013 - 28 Agust 2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
13-Sep-13
KONTRAK Tandatangan Kontrak
Status Kemajuan :
14-Nov-13
Rencana : 18.517 % ; Actual : 25.763 % ; Deviasi : + 7.246 %
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
27-Nov-13
Permintaan Uang Muka
28-Nov-13
Penarikan Uang Muka
17-Dec-13
Status Penyerapan : Rp. 104,672,375,854 (35.77%) Waktu terpakai : 273 hari (34.06 %) Slipage : 752 hari (65.94 %)
D5. STATUS PENYERAPAN
Dalam Rupiah PENYERAPAN TA 2014
NILAI KONTRAK *)
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
Triwulan 1
292,603,385,000.00 43,890,507,750 614,467,109 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
4,219,340,812
Triwulan 3
3,090,244,128.00
9,810,991,499
Triwulan 4
6,207,913,308
11,490,534,929
TOTAL TA 2014
29,381,213,197.00
26,135,334,348.20
Realisasi (p) 35,589,126,505.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 30-RCP03 (Kalimantan Barat)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 26 November 2013
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 29 November 2013
Oleh Penanggung Jawab Kegiatan
31-Mar-12
27-Jun-12
- Periode Kontrak
: 1.095 hari kalender
Persetujuan Pemberi Pinjaman
14-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
: 2 Desember 2016 : PT.Waskita Karya (persero), - PT. Yasa Patria Perkasa, JO
23-Apr-12
26-Feb-13
29 Juni 2012 27 Agust 2012
24 Mei 2013 5 Sep 2013
Pasca Kualifikasi Undangan Lelang Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
12-Oct-13
KONTRAK 26-Nov-13
Status Kemajuan :
Persetujuan Pemberi Pinjaman
28-Nov-13
Status Penyerapan : Rp. 65,339,006,208 (27.3 %)
Permintaan Uang Muka
29-Nov-13
Waktu Terpakai : 295 hari (26.94 %)
Penarikan Uang Muka
17-Dec-13
Tandatangan Kontrak
Rencana : 20.479 % ; Actual : 14.057 % ; Deviasi : -6.422 %
Persetujuan oleh Bappenas (bila diperlukan)
Slipage : 832 hari (73.06 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
Triwulan 1
238,974,973,000.00 35,846,245,950 501,847,443 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
3,446,019,111
Triwulan 3
-
8,012,830,845
Triwulan 4
4,942,149,546
7,711,722,379
TOTAL TA 2014
13,960,756,514.00
19,672,419,777.36
Realisasi (p) 18,902,906,060.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP01 (Kalimantan Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
:
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
: :
Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
Comment ADB 4
Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
Mar 2014,
4 -Okt-2012
Klarifikasi -
KONTRAK Status Kemajuan :
Tandatangan Kontrak
Rencana : 0.090 % ; Actual : 0.101 % ; Deviasi : 0.011 %
Persetujuan oleh Bappenas (bila diperlukan)
Status Penyerapan : Rp. 28,495,537,199 (15 %)
Persetujuan Pemberi Pinjaman
Waktu terpakai : 13 hari (1.78 %)
Permintaan Uang Muka
Slipage : 717 hari (98.22 %)
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
(f)
(g)
Triwulan 1
Triwulan 2
Triwulan 3
Triwulan 4
TOTAL TA 2014
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
-
-
-
-
-
24,127,254,199
18,133,523,673
24,127,254,199
Realisasi (p) 18,133,523,673
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP02 (Kalimantan Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 14 April 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 Mei 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 730 Hari kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
: 2 September 2015 : PT.Brantas Abipraya - PT.Mahir Jaya Mahakam Raya, J.O
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013 9 Maret 2014, Proses persetujuan Mentri
Pasca Kualifikasi Undangan Lelang Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
Persetujuan Pemberi Pinjaman
4 -Okt-2012
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak
Status Kemajuan :
25-Jun-14
Rencana : 1.047 % ; Actual : 2.284 % ; Deviasi : + 1.237 %
Persetujuan oleh Bappenas (bila diperlukan)
Status Penyerapan : Rp. 28,494,960 (17.23%)
Persetujuan Pemberi Pinjaman Permintaan Uang Muka
11-Aug-14
Penarikan Uang Muka
29-Aug-14
Waktu Terpakai : 112 hari (15.34 %) Slipage : 618 hari (48.66 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
Triwulan 1
165,332,328,425.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
-
Triwulan 4
15,781,722,218.00
19,674,548,222
TOTAL TA 2014
2,282,946,209.00
19,674,548,222.00
Realisasi (p) 18,064,668,427.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP03 (Kalimantan Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 11 April 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 Mei 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 900 Hari Kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak - Nama kontraktor/konsultan/suplayer
: 27 September 2015 : PT.Pembangunan Perumahan (Persero) Tbk PT.Perdasa,JO
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
4 -Okt-2012
11-Des-2013
Pasca Kualifikasi Undangan Lelang Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK Status Kemajuan : Tandatangan Kontrak
11-Apr-14 Rencana : 5.191 % ; Actual : 6.490 % ; Deviasi : +1.299 %
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
Status Penyerapan : Rp. 66,336,241,703 (22.95%)
14-May-14
Permintaan Uang Muka
3-Jul-14
Penarikan Uang Muka
4-Aug-14
Waktu Terpakai : 168 hari (18.67 %) Slipage : 732 hari (81.33 %)
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
10,115,000,000
14,627,608,357.00
Triwulan 1
289,000,000,000.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
32,185,930,000
Triwulan 4
27,586,363,636.00
TOTAL TA 2014
42,300,930,000.00
Realisasi (p) 42,213,971,993.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : 34-RCP04 (Kalimantan Timur)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 11 April 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 14 May 2014
Oleh Penanggung Jawab Kegiatan
15-Apr-12
27-Jun-12
- Periode Kontrak
: 1095 Hari Kalender
Persetujuan Pemberi Pinjaman
23-Apr-12
6-Feb-13
- Tanggal Akhir Kontrak
: 10 April 2017 : Butt Halla Corporation
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang
2-May-12
11-Mar-13
7 Jul 2012 - 20 Sep 2012
13 Jun 2013 10 Sep 2013
4 -Okt-2012
11-Des-2013
Persetujuan Pemberi Pinjaman Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK Status Kemajuan : Tandatangan Kontrak
11-Apr-14 Rencana : 0.726 % ; Actual : 0.518 % ; Deviasi : -0.208 %
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
Status Penyerapan : Rp. 60,945,395,586 (16.95%)
14-May-14
Permintaan Uang Muka
Waktu terpakai : 85 hari (7.76 %)
23-Jul-14
Penarikan Uang Muka
Slipage : 1010 hari (92.24 %)
20-Aug-14
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
Triwulan 1
359,652,598,000.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
39,676,885,643
Triwulan 4
34,330,484,788.00
4,204,340,040
TOTAL TA 2014
4,452,948,752.00
43,881,225,682.98
Realisasi (p) 38,783,433,540.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : Core Team Consultant (CTC)
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
: 12 Februari 2014
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 24 Februari 2014
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 42 bulan
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
: 31 Desember 2016
- Nama kontraktor/konsultan/suplayer
: Renardet SA in JV with
Pasca Kualifikasi
PT. Widya Graha Asana
Undangan Lelang
PT. Multy Phibeta
Persetujuan Pemberi Pinjaman
PT.Anugerah Kridapradana PT. Disiplan Consult
Evaluasi Pengadaan Oleh Penanggung Jawab Kegiatan
D4. STATUS TERAKHIR
Persetujuan Pemberi Pinjaman
KONTRAK Direncanakan penarikan Uang Muka akan dilaksanakan pada Awal Oktober 2014
Tandatangan Kontrak Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
24-Feb-14
Permintaan Uang Muka
Porsi IDR
2,920,875,000.00
Porsi USD
178,860.00
2-Oct-14
Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
5,806,675,050.00
Triwulan 4
-
1,583,638,650.00
TOTAL TA 2014
5,196,212,520.00
7,390,313,700.00
Realisasi (p) 5,196,212,520.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : DSC-1 Kalimantan
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
11 Nopember 2013
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
:
37 bulan
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
:
- Nama kontraktor/konsultan/suplayer
:
Pasca Kualifikasi
21 Nopember 2013
Nopembe 2016 CECI Engineriing Consultant in Ass PT. Wira Widyatama ; PT. Seecons
Undangan Lelang
26-Feb-13
Persetujuan Pemberi Pinjaman
PT. Hasfarm Dian Konsultan
0-Jan-00
PT. Yodya Karya, PT. Pola Agung Consulting
Evaluasi Pengadaan 24 Mei 2013 5 Sep 2013
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
12-Oct-13
KONTRAK Tandatangan Kontrak
Status Penyerapan Uang Muka
26-Nov-13
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
28-Nov-13
Permintaan Uang Muka
9-Dec-13
Penarikan Uang Muka
28-Mar-14
Porsi USD
117,984.00
Porsi IDR
6,074,599,000.00
Belum menarik Invoice 1 - 10 karena menunggu Addendum
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
1,345,261,456.00
2,412,421,320.00
Triwulan 1
30,384,233,888.00 2,412,421,320.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
Triwulan 3
-
2,412,421,320.00
Triwulan 4
-
1,809,315,990.00
TOTAL TA 2014
-
9,046,579,950.00
Realisasi (p) 1,345,261,456.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : DSC-2 Jawa Tengah
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
:
Prakualifikasi
- Tanggal Persetujuan Peminjam
:
- Periode Kontrak
:
- Tanggal Akhir Kontrak
:
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
7-Jun-13
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang Persetujuan Pemberi Pinjaman Evaluasi Pengadaan 15 Nop 2013 Mei 2014 2013
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
KONTRAK Tandatangan Kontrak Evaluasi Pengadaan dikirim ke IDB tanggal 18 Juni 2014, saat ini menunggu persetujuan dari IDB
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman Permintaan Uang Muka Penarikan Uang Muka
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
Triwulan 1
*) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
-
Triwulan 3
-
535,500,000.00
Triwulan 4
-
126,000,000.00
TOTAL TA 2014
-
661,500,000.00
-
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORM D : CONTRACT PACKAGE STATUS (Precontract, Contract, Amendement for additional works and other changes) D1. PAKET KONTRAK : DSC-3 Jawa Timur
D2. LANGKAH-LANGKAH KEGIATAN
(a)
TANGGAL
TANGGAL
TANGGAL
D3. STATUS KONTRAK
RENCANA
PERUBAHAN
AKTUAL
Untuk kontrak berjalan pada s/d bulan Desember 2014
(b)
(c)
(d)
PROSES PENGADAAN
- Tanggal Kontrak
Prakualifikasi
- Tanggal Persetujuan Peminjam
: 6 Oktober 2013 : 11 Nopember 2013
Oleh Penanggung Jawab Kegiatan
- Periode Kontrak
: 25 bulan
Persetujuan Pemberi Pinjaman
- Tanggal Akhir Kontrak
: 16 Nopembe 2015 : PT. Perentjana Djaja
- Nama kontraktor/konsultan/suplayer Pasca Kualifikasi Undangan Lelang
26-Feb-13
Persetujuan Pemberi Pinjaman
0-Jan-00
Evaluasi Pengadaan 24 Mei 2013 5 Sep 2013
Oleh Penanggung Jawab Kegiatan Persetujuan Pemberi Pinjaman
D4. STATUS TERAKHIR
12-Oct-13
KONTRAK Tandatangan Kontrak
Status Penyerapan Uang Muka
26-Nov-13
Persetujuan oleh Bappenas (bila diperlukan) Persetujuan Pemberi Pinjaman
7-Nov-13
Permintaan Uang Muka
26-Nov-13
Penarikan Uang Muka
9-Dec-13
D5. STATUS PENYERAPAN
NILAI KONTRAK *)
(e)
Dalam Rupiah PENYERAPAN TA 2014
PENYERAPAN KUMULATIF SAMPAI DENGAN DES. TAHUN SEBELUMNYA
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
Realisasi
Target
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(n)
(o)
Triwulan 1
7,633,945,000.00 1,040,992,500.00 687,051,000.00 *) : Perkiraan Jumlah pada saat prakontrak atau jumlah yang terkontrak
Triwulan 2
-
687,051,000.00
Triwulan 3
-
687,051,000.00
Triwulan 4
-
458,034,000.00
TOTAL TA 2014
1,865,182,640.00
2,519,187,000.00
Realisasi (p) 1,865,182,640.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
FORMULIR E : RINCIAN DOKUMEN ANGGARAN Nomer NPPHLN : ADB 2817-INO, Register : 10846401 IDB 0161-IND, Register : 10848804 PLN
Rupiah ( dalam juta) Dana Pendamping
Nama Kegiatan dan Nomor Kode DIPA
Rupiah Ekivalen (juta)
Valas
(a)
Rupiah Murni
Rencana Penarikan PLN 2014
(b)
(c)
Pagu
Realisasi
Pagu
Realisasi
( Juta Rupiah )
(d)
(e)
(f)
(g)
(h)
Nomor DIPA : Kegiatan : Civil Works Jawa Tengah 1
24-RCP-01
Tambakmulyo - Wawar
USD
3,708.13
42,643.5
8,474.00
-
29,275.11
2
24-RCP-02
Giriwoyo - Duwet
USD
3,050.72
35,083.3
11,375.04
-
18,002.60
3
24-RCP-03
Wawar - Congot
USD
3,236.48
37,219.5
5,699.00
-
7,501.71
Jolosutro - Sendang biru
USD
2,244.66
25,813.6
21,000.00
-
7,860.68
Jawa Timur 4
28-RCP01A Kalimantan
Sosok - Tayan 5
30-RCP01
USD
-
Tanjung- Bts. Kota Sanggau
-
39,913.12
-
-
-
Tebas - Singkawang Sec.1 + Sec.2 6
30-RCP02
Bypass Sambas (TANAH HITAM /TANJUNG HARAPAN - SAMBAS) Galing - Tanjung Harapan
USD
3,702.48
42,578.5
18,247.89
18,294.73 -
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
PLN
Rupiah ( dalam juta) Dana Pendamping
Nama Kegiatan dan Nomor Kode DIPA
Rupiah Murni
Rencana Penarikan PLN 2014
Rupiah Ekivalen (juta)
Valas
Pagu
Realisasi
Pagu
Realisasi
( Juta Rupiah )
Simpang Tanjung - Galing 7
30-RCP03
USD
1,808.10
20,793.2
8,911.37
Simpang Aruk /Bts. Serawak-Simpang 3 Tanjung
13,770.69 -
8
34-RCP01
Tanjung Selor- SP.3 Tanjung Palas - Sekatak Buji (Sec.1)
USD
5,018.39
9
34-RCP02
Tanjung Palas -Sekatak Buji (Sec.2)
USD
4,050.00
10
34-RCP03
SP.Tiga Apas - Simanggaris (Section 1)
USD
11
34-RCP04
SP. Tiga Apas - Simanggaris - Bts. Negara (Serudong)
USD
57,711.5
39,155.94
-
16,889.08
46,575.0
39,286.15
-
13,772.18
4,148.14
47,703.6
51,470.79
-
29,610.65
4,787.86
55,060.4
40,422.36
-
30,716.86
Consultant Services DG Bina Marga , KemenPU 1
CSP-1
Core Team Consultant
USD
495.65
5,700.00
-
-
7,390.31
2
CSP-2
DSC-1 (ADB-Kalimantan)
USD
1,120.00
12,880.00
-
-
9,046.58
3
CSP-11
DSC-2 (IDB - Jawa Tengah)
USD
620.11
7,131.25
-
-
661.50
4
CSP-3
DSC-3 (ADB-Jawa Timur)
USD
304.35
3,500.00
-
-
2,519.19
5
CSP-10
HIV /AIDS and Anti Trafficking Program
USD
16.96
195.00
-
-
6
CSP-4
Road Saftey Engineering Support
-
-
TOTAL
USD USD
65.22 38,377.24
750.00 441,338.27
283,955.65
205,311.87
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Regional Roads Development Project (RRDP) Detail Contract, Alocation and Disbursement DIPA 2014 as of 31 December 2014 ADB Loan No.2817-INO & IDB Financing No.IND-0161 TOTAL KONTRAK NO
USD 10 Jawa Tengah
3
-
Rp 10
6
443,994.65
PLN 10
Eqv.USD
6
10 -
3
ALOKASI
PDP 10
-
% Alokasi & Penyerapan DIPA 2014
DIPA 2014
KONTRAK
PAKET TOTAL
6
10 -
PLN
6
10 -
PDP
6
10
PENGAJUAN TOTAL
6
10
PENYERAPAN
PLN Eqv.USD PDP TOTAL
6
10
6
10
3
10
6
10
6
PLN 10
Eqv.USD
6
10
3
Luncuran 2014
PDP 10
TOTAL
6
10
PLN 10 6
6
PDP 10
6
PLN
PDP
% Total DIPA terhadap N.Kontrak
TOTAL DIPA PLN 10
PDP
6
10
TOTAL
6
10
PLN
6
PDP
PENYERAPAN BERDASARKAN LFIS ADB SD saat ini TAHUN 2014 PLN 10
Eqv. USD
6
10
3
PDP 10
TOTAL
6
10
6
114,996.21
40,849.04
155,845.24
-
-
-
-
-
-
-
-
114,996.21
-
161,512.31
58,659.29
220,171.60
-
-
-
-
1
24-RCP01 Tambakmulyo - Wawar
243,741.56
-
-
-
-
42,643.5
8,474.0
51,117.45
-
-
-
-
-
-
-
-
42,643.45
-
70,296.45
16,622.00
86,918.45
-
-
-
-
2
24-RCP02 Giriwoyo - Duwet (Section 1)
142,000.00
-
-
-
-
35,083.3
11,375.0
46,458.29
-
-
-
-
-
-
-
-
35,083.25
-
45,799.35
18,637.29
64,436.65
-
-
-
-
3
24-RCP03 Wawar - Congot
58,253.09
-
-
-
-
37,269.5
21,000.0
58,269.51
-
-
-
-
-
-
-
-
37,269.51
-
45,416.51
23,400.00
68,816.51
-
-
-
-
Jawa Timur 4
-
28-RCP01 Jolosutro - Sendangbiru Kalimantan Barat
5 6 7
-
Sosok - Tayan Tanjung - Bts. Kota Sanggau Tebas - Singkawang (Section 1) Tebas - Singkawang (Section 2) 30-RCP02 Bypass Sambas Galing - Tanjung Harapan 30-RCP03 Sp. Tanjung - Galing Aruk (Bts. Serawak) - Sp. Tanjung 30-RCP01
93,350.00
65,345.00
5,357.84
28,005.00
93,350.00
25,813.57
21,000.00
46,813.57
-
-
-
-
3,173.87
263.99
1,496.25
4,670.12
22,639.70
-
12.30%
7.13%
53,890.57
47,555.94
101,446.50
82.47%
189.06%
17,423.93
1,476.23
8,832.21
26,256.14
93,350.00
65,345.00
5,357.84
28,005.00
93,350.00
25,813.57
21,000.00
46,813.57
-
-
-
-
3,173.87
263.99
1,496.25
4,670.12
22,639.70
-
12.30%
7.13%
53,890.57
47,555.94
101,446.50
82.5%
169.8%
17,423.93
1,476.23
8,832.21
26,256.14
997,225.90
372,104.85
27,580.26
159,473.51
531,578.36
63,371.77
27,159.26
90,531.03
-
-
-
-
57,582.28
4,758.13
26,934.12
84,516.40
5,789.50
-
90.86% 99.17%
196,396.90
98,278.55
294,675.45
52.78%
73.94%
108,323.85
8,955.12
50,855.15
159,179.00
-
-
-
-
57,822.57
26,555.94
84,378.50
465,647.54
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
292,603.39
204,822.37
15,199.47
87,781.02
292,603.39
42,578.49
18,247.89
60,826.38
-
-
-
-
38,679.37
3,202.28
18,234.56
56,913.93
3,899.12
-
90.84% 99.93%
89,343.03
42,820.81
132,163.84
43.6%
48.8%
66,609.69
5,512.48
31,401.71
98,011.41
-
238,974.97
167,282.48
12,380.80
71,692.49
238,974.97
20,793.29
8,911.37
29,704.66
-
-
-
-
18,902.91
1,555.86
8,699.56
27,602.47
1,890.38
-
90.91% 97.62%
49,231.31
28,901.80
78,133.11
29.4%
40.3%
41,714.15
3,442.64
19,453.44
61,167.59
1,003,955.27
702,768.69
54,556.15
301,186.58
1,003,955.27
207,050.76
160,337.16
367,387.92
-
-
-
-
117,195.60
9,869.52
55,249.35
172,444.95
89,855.16
-
340,692.39
230,620.50
571,312.89
117,195.60
9,869.52
55,356.98
172,552.58
189,970.25
132,979.17
9,795.52
56,991.07
189,970.25
57,711.49
39,155.94
96,867.43
-
-
-
-
18,133.52
1,472.24
8,548.66
26,682.18
39,577.96
-
31.42% 21.83%
80,517.60
52,125.08
132,642.67
18,133.52
1,472.24
8,548.66
26,682.18
165,332.33
115,732.63
11,022.16
49,599.70
165,332.33
46,575.03
29,288.15
75,863.18
-
-
-
-
18,064.67
1,533.11
8,516.20
26,580.87
28,510.36
-
38.79% 29.08%
75,090.03
42,344.84
117,434.87
64.9%
85.4%
18,064.67
1,533.11
8,623.83
26,688.49
Kalimantan Timur Tanjung Selor - Sp.3 Tanjung Palas Sp.3 Tanjung Palas-Sekatak Buji (Section 1)
8
34-RCP01
9
34-RCP02 Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
10
34-RCP03 Sp. Tiga Apas - Simanggaris (Section 1)
-
289,000.00
202,300.00
15,041.72
86,700.00
289,000.00
47,703.82
51,470.71
99,174.52
-
-
-
-
42,213.97
3,564.42
19,900.87
62,114.84
5,489.85
-
88.49% 38.66%
81,649.76
71,037.47
152,687.22
40.4%
81.9%
42,213.97
3,564.42
19,900.87
62,114.84
11
34-RCP04
Sp. Tiga Apas - Simanggaris (Section 2) Simanggaris - Bts. Negara (Serudong)
-
359,652.70
251,756.89
18,696.75
107,895.81
359,652.70
55,060.43
40,422.36
95,482.78
-
-
-
-
38,783.43
3,299.76
18,283.62
57,067.05
16,276.99
-
70.44% 45.23%
103,435.01
65,113.12
168,548.13
41.1%
60.3%
38,783.43
3,299.76
18,283.62
57,067.05
Pusat
2,341.87
65,327.63
87,053.64
6,905.58
-
87,053.64
30,156.25
-
30,156.25
-
-
-
-
10,725.40
801.90
-
10,725.40
19,430.85
-
22.75%
15,565.66
1,385.93
-
15,565.66
CTC RRDP
1,311.64
21,419.75
35,191.97
2,776.08
-
35,191.97
5,700.00
-
5,700.00
-
-
2,920.88 2,275.34 3,664.01
243.00 189.61 217.05
-
2,920.88 6,074.60 3,664.01
243.00 189.61 497.71 217.05
-
2,920.88
-
2,920.88 2,275.34 3,664.01
-
9,738.61
1,865.18
152.24
-
1,865.18
2,906.18
238.55
1 2
DSC-1 Kalimantan (ADB)
3
DSC-2 Jawa Tengah (IDB)
4
DSC-3 Jawa Timur (ADB)
1,030.23
33,410.29 2,863.64
-
7,633.95
44,227.72
3,402.46
7,633.95
-
727.04
-
44,227.72 7,633.95
-
-
12,880.00
12,880.00
7,131.25
7,131.25
-
-
-
-
3,500.00
3,500.00
-
-
-
-
503.79
0
0.00%
91.16%
61,427.64
-
61,427.64
14,756.71
-
14,756.71
-
22,174.68 -
28.45%
-
22,174.68 -
-
-
-
17,331.25
-
17,331.25
-
53.29%
-
6,220.00
-
6,220.00
9,215.99
-
7,131.25 1,634.82
70.56% 41.9% 50.1%
0.00% -
81.5%
-
5 Road Safety Support
-
-
-
750.00
750.00
-
-
-
-
750.00
750.00
-
750.00
-
-
6 Institutional Development for Road Network Management
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
195.00
195.00
195.00
195.00
-
195.00
7 HIV/AIDS and Anti-Trafficking Program TOTAL
2,341.87
2,603,853.45
1,227,272.18
$94,399.84
488,665.09
1,715,937.27
441,388.55
249,345.45
690,734.01
-
$
42.75
-
-
188,677.14 $ 15,693.54
83,679.73
272,356.87
252,711.41
-
42.75% 33.56%
813,919.81
435,114.28
1,249,034.08
2,906.18 -
-
66.32%
89.04%
258,509.04
$21,686.80
115,044.33
373,553.37
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Current ADB Loan No. 2817-IND and IDB Financing No. IND-0161 Total Disbursed to end of Dec (US$)
Loan Amount (US$) Category
ADB
Civil Work Road Safety Equipment
Consultant Services
IDB
% Disbursed
155,000.00
53,500.00
20,300.87
9.74
12,200.00
3,000.00
1,385.99
9.12
Road Sector Development Program
6,900.00
-
-
-
Road Sector Program
3,300.00
-
-
-
Unallocated
2,600.00
8,500.00
180,000.00
65,000.00
Loan Amount
-
-
21,686.86
8.85
Current Loan Allocation and Disbursement (%) to Date 100 90
% complete
80 70 60 50 40 30 20 10
Actual Disbursement
43311
43281
0
43190
0
43100
0
43008
0
42916
0
42825
Planned Disbursment
0
42735
0
42643
0
42551
0
42460
42369
42277
42185
Original based PAM
42094
42004
41912
41820
41729
0
41639
0
41547
0
41455
41364
0
8.85178002 5.770582959 2.600906139 0 0 0 2.491936343 2.443779608
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix 1 Regional Roads Development Project (RRDP)
The Overall Financial Status as of 30 December 2014 ADB Loan No.2817-INO & IDB Financing No.IND-0161 in US$ 000's
1 USD = IDR 9,000 Loan Cat
1
Details of Category
2
1 2 3 3A 3B 3K 3C 3D 3E 3F 3G 3H 3I 3J 4
Original Loan Allocation ADB IDB
Civil Works Goods : Road Safety Equipment Consultant Services Core Team Consultant Design and Supervision Kalimantan Region Construction Supervision - Central Java Region Design and Supervision East Java Region Road Safety Support Institutional Development for Road Network Management Road safety awareness campaign and training Overloading and Speed Enforcement Indonesia Transport Sector Development Strategy and Policy Study Integrated Vehicle Overloading Control Strategy HIV/AiDS and Anti Trafficking Prevention Program Unallocated
TOTAL
3a 155,000.0 1,300.0
4a
53,500.0 -
76,769.6 -
4b 0.00 -
Current Balance ADB
Current Quarter ADB IDB
IDB
5a = (3a-4a) 5b = (3b-4b) 78,230.4 1,300.0
53,500.0 -
6a
6b
6,865.0 -
6,000.0
-
2,809.2
-
3,190.8
-
432.61
5,300.0
-
3,451.1
-
1,848.9
-
99.07
-
3,000.0
900.0
-
400.0
0.00 574.3
-
0.0
3,000.0
Disbursement Year to Date ADB IDB
7a
7b
8,026.7
Cummulative to Date ADB IDB
%=(8a /4a)
8a -
Loan Balance
20,300.87 0.00
%=(8b/ 4b)
8b
26.44
-
-
20.71
-
-
432.61 117.98
714.76 0.00
-
53,500.0 0.0
3,190.8
0.0
1,848.9
0.0
0.0
3,000.0
152.30
238.61
325.7
0.0
-
400.0
-
-
0.00
400.0
0.0
900.0
-
900.0
-
0.00
900.0
0.0
3,000.0
-
3,000.0
-
0.00
3,000.0
0.0
2,200.0
-
2,200.0
-
0.00
2,200.0
0.0
1,300.0
-
1,300.0
-
0.00
1,300.0
0.0
0.00
800.0
0.0
-
-
78,230.4 1,300.0
-
-
-
IDB
9b=(3b-4b)
325.7
-
41.55
ADB
9a=(3a-4a)
800.0 300.0 2,600.0
180,000.0
Assumption to Government Budget in FY 2014 1 USD = IDR 11,500
3b
Awarded Contracts ADB IDB
-
800.0
-
300.0
8,500.0
65,000.0
2,600.0
83,604.2
0.0
96,395.8
-
-
-
-
8,500.0
65,000.0
7,548.93
0.00
8,144.67
0.00
0.00
300.0
0.0
0.00
2,600.0
8,500.0
21,686.86
25.94
96,395.81
65,000.00
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix 2 PROCUREMENT PLAN OF IMPLEMENTATION SUPPORT AND SECTOR INSTITUTIONAL DEVELOPMENT REGIONAL ROADS DEVELOPMENT PROJECT Project Cost (US$) Ref. No
Name of Package Allocated
1
Implementation Support
a
CSP-1 : Core Team Consultant
b
CSP-2 & CSP-3 : Design and Supervision Consultant (DSC-1 (Kalimantan) and DSC3 (East Java Province))
c
CSP-11 :Design and Supervision Consultant (DSC-2 (Central Java Province))-
d
CSP-5: Capacity Development Program
6,000,000 5,300,000
EE/OE
Contract
3,914,374
2,809,186
5,827,926
Evaluation and Result of Evaluation Combination (Technical Submission Result of Technical Proposal Evaluation Submission Submissi shortlist (including and Financial Proposals) Review Invitation of Opening RFP and TOR) of TOR , on of Negotiation Metoda By Bank Plan/ NOL REOI Advert to ShortTechnical of Sign OE and EOI by and Draft Send to Send to Seleksi (Prior/Po Actual dari Donor of REOI List and Financial Contract Draft REOI Consulta Send to NOL by Send to NOL by Minister NOL by Send to NOL by Minister NOL by of Contract st) Consultants Financial Proposal to the Bank nts the Bank Bank Bank Bank of Public Minister Bank Bank of Public Minister Proposals Works Works
QCBS
900,000
3,000,000
900,000
777,754
2,778,567
QCBS
QCBS
01-Jun-11 30-Jun-11
01-Jun-11
23-Feb-12
10-Jul-12
27-Oct-11
13-Dec-11 19-Dec-11
23-May-12
28-May-12
29-Jan-13
Plan
01-Jun-11
01-Jun-11 30-Jun-11
01-Jun-11
23-Feb-12
10-Jul-12
Actual
27-Oct-11
13-Dec-11 19-Dec-11
15-Jun-12
15-Jun-12
07-Dec-12
Plan
01-Jun-11
01-Jun-11 30-Jun-11
01-Jun-11
25-Mar-12
Actual
5-Jun-12
04-Jan-12
20-Jan-12
20-Jun-12
20-Jun-12
Plan
01-Jan-12
23-Dec-11
01-Jan-12
01-Jan-12
01-Jan-12
23-Dec-11
01-Jan-12
01-Jan-12
08-Jul-14 12-Aug-14
20-Sep-14
01-Jan-12
01-Jan-12
09-Oct-14
23-Oct-14
08-Jul-14 12-Aug-14
20-Sep-14
28-Oct-14
09-Dec-14
26-Sep-14
19-Nov-14
10-Jul-14
24-Sep-14
17-Jul-12
31-Aug-12
30-Sep-12
07-Oct-12
08-Oct-12
10-Oct-12
11-Oct-12
21-Oct-12
28-Oct-12
28-Oct-12
29-Oct-12
18-Sep-13
11-Nov-12
07-Oct-12
22-Jan-14
25-Nov-12
17-Jul-12
31-Aug-12
30-Sep-12
08-Oct-12
10-Oct-12
15-Jul-12
22-Jul-12
05-Sep-12
05-Oct-12
12-Oct-12
07-Jun-13
16-Jul-13
15-Nov-13
18-Jun-14
04-Dec-14
09-Oct-14
23-Oct-14
07-Jan-15
23-Feb-15
04-Mar-15
11-Mar-15
-
28-Oct-14
09-Dec-14 07-Jan-15
23-Feb-15
04-Mar-15
11-Mar-15
-
11-Oct-12
05-Dec-14
08-Dec-14 20/12/2014
21-Oct-12
28-Oct-12
28-Oct-12
29-Oct-12
19-Dec-14
22-Dec-14
19-Dec-14
22-Dec-14
12-Feb-14
03-Mar-14
11-Nov-12
25-Nov-12
07-Nov-13
21-Nov-13
16-Dec-13
23-Dec-14
24-Nov-14
5-Jan-15
Prior
570,032.00
Not Yet
01-Jun-11
Prior
3,451,054 QCBS
Plan Actual
Service Start Date
07-Jun-13
Prior 12-Dec-14
24-Dec-14
-
18-Mar-15
25-Mar-15
01-Apr-15
-
-
08-Apr-15
15-Apr-15
22-Apr-15
-
18-Mar-15
25-Mar-15
01-Apr-15
-
-
08-Apr-15
15-Apr-15
22-Apr-15
Prior Actual Plan
e
CSP-4: Road Safety Engineering Support
400,000
QCBS
Prior Actual
f
CSP-10 :Human Trafficking Prevention and
Plan 300,000
QCBS
Actual
2
Road Sector Institutional Development
g
CSP-6 :Road Safety Awareness Campaign & Trainning
3,000,000
h
CSP-7 : Overloading and Speed Enforcement
2,200,000
Plan QCBS
j
01-Jan-12
23-Dec-11
01-Jan-12
23-Dec-11
01-Jan-12
01-Jan-12
01-Jan-12
01-Jan-12
Actual Plan QCBS
800,000
CSP-8 : Indonesia Transport Sector Development Strategy and Policy Study
1,300,000
QCBS
19-Jan-15
Prior Actual
CSP-9 : Integrated Vehicle Overloading Control Strategy
TOTAL
23-Dec-11
Prior
Plan i
01-Jan-12
Prior
HIV/AIDS Campaign Programs
01-Jun-14 01-Jan-12
23-Dec-11
01-Jan-12
01-Jan-12
01-Jan-12
23-Dec-11
01-Jan-12
01-Jan-12
Prior Actual Plan
QCBS
Prior Actual
04-Dec-14
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 3 Regional Road Development Project (RRDP) Progress And Cost Monitoring For Civil Works Status December 2014 Estimated Cost Contract Description Type of Works IDR (x106)
Contractor
Contract Price (IDR 10⁶) ADB Including Tax Contract Sign Category Procurement Financing Date Method Original Addendum Ratio (%)
No.
Contract No.
4
01-28-RCP01A/RB/ADB/2817/0813
Jolosutro - Bale kambang Reconstruction Sendang biru
151,916.793
PT.Hutama Karya
21-Aug-13
Civil Works
ICB
93,350,000
6
02-30-RCP02/RB/ADB/2817/1113
Tebas - Singkawang (Section 1); Tebas Singkawang (Section 2) Bypass Sambas
Reconstruction Resurfacing
430,578.648
PT.Brantas Abipraya-Tri Citra PerdanaTrifa Abadi, JO
14-Nov-13
Civil Works
ICB
7
03-30-RCP02/RB/ADB/2817/1113
Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
Reconst + widening Reconstruction
333,214.553
PT Waskita Karya - Yasa Patria Perkasa, JO
27-Nov-13
Civil Works
8
01-34-RCP/LOAN/PJN.III/11.14
3-Nov-14
9
02-34-RCP/LOAN/PJN.III/06.14
Sp.3 Tanjung Palas Sekatak Buji (Section 2)
Reconstruction Grade Improvement
215,483.495
10
03-34-RCP/LOAN/PJN.III/04.14
SP.3 Apas - Simaranggis (Sect 1)
Reconstruction Resurfacing
11
04-34-RCP/LOAN/PJN.III/04.14 (Sect 2); Simanggaris -
Reconstruction Resurfacing
Cost During this Quarter (IDR) Actual
Planned
70.00
691,290,730
28,101,969,354
292,603,385
70.00
39,509,508,507
ICB
238,974,973
70.00
Civil Works
ICB
189,970,248
25-Jun-14
Civil Works
ICB
322,919.917 PT.Pemb. Perumahan- PT.Perdasa JO
11-Apr-14
Civil Works
407,483.774 Halla Corporation
11-Apr-14
Civil Works
Cummulative Cost (IDR)
ADB Share Actual as % of Planned
To Last Quarter
Actual to date Total ADB Share
Physical Progress % Planned to date
Actual as % Scheduled of Planned
Actual
Difference
New Road
2.46
25,564,945,646
26,256,236,376
14,250,065,103
53,666,915,000
49
57.49
29.04
-28.45
39,569,978,575 27,656,655,955
99.85
58,501,897,975
98,011,406,482
62,370,895,034
98,071,876,550
100
18.52
25.76
7.25
17,766,915,317
41,385,255,129 12,436,840,722
42.93
43,400,675,542
61,167,590,859
38,924,830,547
84,785,930,671
72
20.48
14.06
-6.42
70.00
26,682,184,833
28,666,510,423 18,677,529,383
93.08
0
26,682,184,833
16,979,572,166
28,666,510,423
93
0.09
0.1
0.01
165,332,338
70.00
1,888,644,484
2,732,945,047
1,322,051,139
69.11
24,799,849,200
26,688,493,684
18,681,945,579
27,532,794,247
97
1.65
2.28
0.63
ICB
289,000,000
70.00
18,764,844,504
15,001,990,000 13,135,391,153
125.08
43,350,000,000
62,114,844,504
43,480,391,153
58,351,990,000
106
5.19
6.49
1.30
ICB
359,652,697
70.00
19,303,518,965
18,809,835,971 13,512,463,276
102.62
37,763,533,267
57,067,052,232
39,946,936,562
56,573,369,238
101
0.73
0.52
-0.21
234,634,636,144
407,649,386,130
483,903,511
Resurfacing
Tanjung Selor- Sp.3 Tj.Palas - Sekatakbuji (section 1)
SP.3 Apas - Simaranggis Bts.Negara
333,214.553 PT.Waskita Karya (Persero)
PT.Brantas Abipraya -Mahir Jaya Mahakam Raya- JO
TOTAL
1,628,883,641
124,606,907,340 174,268,484,500 87,224,835,138
233,380,901,630 357,987,808,970
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 4 Details of Variation Orders To End December 2014 Package No.
Original Contract value (Rp.)
Jolosutro - Bale kambang - Sendang biru
28-RCP01A
93,350,000,000.00
Tebas - Singkawang (Section 1); Tebas Singkawang (Section 2) Bypass Sambas Galing - Tanjung Harapan
30-RCP02
292,603,385,000.00
Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
30-RCP03
217,249,975,454.55
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
34-RCP02
165,332,338,000.00
SP.3 Tj.Palas - Simaranggis (Sect 1)
34-RCP03
289,000,000,000.00
SP.3 Tj.Palas - Simaranggis (Sect 2)
34-RCP03
359,652,697,000
No.
Design Review (Rp.)
Design Review %
Prie Escalation
Escalation %
Total Current Modified Contract Price (Rp.)
Total Current Modified %
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 5 Regional Road Development Project (RRDP) Summary Of Contract Data Up to December 2014
NO.
DESCRIPTION
Jolosutro-BalekambangSendangbiru
Tebas - Singkawang (Section 1); Tebas -Singkawang (Section 2) Bypass Sambas Galing - Tanjung Harapan
Sp. Tanjung - Galing; Aruk (bts.Serawak Sp.Tanjung
Sp.3 Tanjung Palas Sekatak Buji (Section 2)
SP.3 Apas - Simaranggis (Sect 1)
SP.3 Apas Simaranggis (Sect 2); Simanggaris Bts.Negara
a
b
c
d
e
f
g
h
1
Package No.
28-RCP01A
30-RCP02
30-RCP03
34-RCP02
34-RCP-3
34-RCP04
2
Contract No. Contract Sign Dated
02-30-RCP02/RB/ADB/2817/1113 14 November 2013.
03-30-RCP02/RB/ADB/2817/1113 27 November 2013.
02-34RCP/LOAN/PJN.III/06.14 25 June 2014.
03-34-RCP/LOAN/PJN.III/04.14
3
01-28-RCP01A/RB/ADB/2817/0813 21 August 2013.
04-34RCP/LOAN/PJN.III/04.14 11 April 2014.
4
Contractor
PT.HUTAMA KARYA
PT. Brantas Abipraya ; Tri Citra Perdana; Trifa Abadi- JO
PT. Waskita Karya ; PT.Yasa Patria Perkasa
PT.Brantas Abipraya Mahir Jaya Mahakam Raya- JO
PT.Pemb. Perumahan; PT.Perdasa-JO
Halla Corporation
5
Original Contract Amount (Rp.) Construction Period (Days) Commencement of Work
93,350,000,000.00
292,603,385,000.00
238,974,973,000.00
165,332,338,000.00
289,000,000,000.00
359,652,697,000.00
730 Days
1095 Days
1095 Days
730 Days
900 Days
1095 Days
18-Oct-13
17-Dec-13
4-Dec-13
4-Sep-14
10-Jul-14
1 Oct 14
Addendum Contract No.01
Not yet
Not yet
Not yet
Not yet
Not yet
Not yet
6 7
8
11 April 2014.
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
NO.
DESCRIPTION
Tj Selor-S.3 Tj.Palas Sp.3 Tj.Palas-Sekatakbuji
Sosok – Tayan Tanjung – batas\Kota Sanggau
Tambakmulyo Wawar
Giriwoyo - Duwet
Wawar - Congot
a
b
c
d
e
f
g
1
Package No.
34-RCP01
2
Contract No.
01-34-RCP/LOAN/PJN.III/11.14
3
Contract Sign Dated
3 November 2014.
4
Contractor
PT.WASKITA KARYA
5
Original Contract Amount (Rp.) Construction Period (Days) Commencement of Work
189,970,248,000.00
Addendum Contract No.01
Not yet
6 7
8
730 Days
30-RCP01
24-RCP01
24-RCP02
24-RCP03
1095 Days
1095 Days
730 Days
900 Days
Not yet
Not yet
Not yet
Not yet
12 December 2014
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix . 6 Summary of Unsettled Complaints As of Dec 2014 No.
Complainant
1.
Budi Sarwono, Pemimpin JO PT. Bumi Rejo-PT. Sujainco,JO
2
Budi Sarwono, Pemimpin JO PT. Bumi Rejo-PT. Sujainco,JO
Recipient of complaints
RRDP Package
Media of complaint
Category of complaint
Complaint Issue
Date of complaint
Minister of Public Works of the Republic of Indonesia
No :34-RCP-01, Letter Tanjung SelorNo.050/BRDTanjung Palas, SJ/X/2014 Tanjung PalasSekatak (Section 1)
Refutations
Complaints differences morbidities Auction Process Package no: 34 - RCP - 01 , Tanjung Selor -Tanjung Palas , Tanjung Palas Sekatak ( section 1 ) Loan RRDP no. 2817 INO , East Kalimantan
31 October 2014
Procurement Committee
No :34-RCP-01, Tanjung SelorTanjung Palas, Tanjung PalasSekatak (Section 1)
Refutations
Disclaimer the announcement of the winner of the tender package no.34-RCP01, Tanjung SelorTanjung Palas-Sekatak (section 1) RRDP ADB Loan No. 2817-INO, East Kalimantan
22 October 2014
Letter No. 048/BRDSJ/X/2014
Date received by PMU/CTC
Date of response
24 October 2014
Responded by
Pokja RRDP East Kalimantan Chairman
Proposed Response
Announcement of the winner determination based on the evaluation procurement team that submitted trough bid evaluations report (BER) was revised on 1 september 2014 and according to no objection letter (NOL) from ADB date 25 September 2014 and based on a determination of the winner by minister of public works in 16 october 2014, so the announcement of the winner determination not associate with extention of period for bid validity and bid security. The procurement team take time to clarify the updating data of bidder’s
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
No.
Complainant
Recipient of complaints
RRDP Package
Media of complaint
Category of complaint
Complaint Issue
Date of complaint
Date received by PMU/CTC
Date of response
Responded by
Proposed Response
qualification specially the consistency with the pre-qualification data that given to the procurement team. There are inconsistent data on the experience of the PT. Sujainco with PT. AngkasaPura 1 (Pesero), it is not appropriate with the financial report you gave to the procurement team ( the data has been clarified to PT. Angkasa Pura 1 (Pesero) and the public Accountants Achmad, Rasyid, Hisbullah & Jerry. Reprimand letter from Word Bank about sanction case no. 193 – letter reprimand dated 16 June 2014 3.
Kukuh Bandiono Kuasa JO PT. Multi StrukturePT.Brantas Abipraya
Working Group ( WG ) RRDP ADB Loan No.2017 INO In West Kalimantan .
Package 30 RCP01, Sosok Tayan - Bts . Sanggau City West Kalimantan.
Letter No. 225/MSMKT/KP/XII/2 014
Specific
Rebuttal to the Tender 19 December winner Package 30 2014 RCP01, Sosok - Tayan - Bts . Sanggau City West Kalimantan.
19 December 2014
Procurement Team Pokja
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 7a CROs ACTVITIES ON RRDP December 2014
No
Province
Package Observed
Package Number
Date of Invitation to Bid
CROs Involvement in the Bidding Process Date of Bid Opening
Announcement Date of Bid Winner
1
EAST JAVA
JolosutroSendangbiru
28RCP01A
1-Mar-13
1-May-13
18-Aug-13
1
WEST KALIMANTAN
Sosok - Tayan
30-RCP01
25-Jul-14
9-Sep-14
NY
TanjungBts.Kota Sanggau TebasSingkawang (Section1 &2)
2
Bypass Sambas Sp. Tanjung Galing; Aruk (bts.Serawak - Sp.Tanjung
3
30-RCP02
26-Feb-13
22-May-13
19-Oct-13
Selected CRO Reports of CRO Activity Name ·
Process Verbal of the CRO selection for RRDP package of Tebas - Singkawang, West Kalimantan SNVT of Roads and Bridge Development, February 2013
· 30-RCP02
26-Feb-13
23-May-13
12-Nov-13
·
Process Verbal of the CRO selection for RRDP package of Sp.Tanjung - Galing, West Kalimantan SNVT of Roads and Bridge Development, February 2013
· 1
EAST KALIMANTAN
Tj.SelorSp.3Tj. Palas
Sp.3 Tanjung Palas Sekatak Buji (Sect 1)
34-RCP01
11-Mar-13
13-Jun-13
Not Yet
Telephone
Email
Process Verbal of the CRO selection for RRDP package of Jolosutro- Sendangbiru, East Java SNVT of Roads and Bridge Development, May 2013 Process Verbal of the CRO selection for RRDP package of Sosok - Tayan, West Kalimantan SNVT of Roads and Bridge Development, June 2014
·
Address
Process Verbal of the CRO selection for RRDP package of Tj.Selor - Sp.3 Tanjung Palas, East Kalimantan SNVT of Roads and Bridge Development, June 2013
Chandra Yuliana , ST,MT Ir.Retna Hapsari Kartadipura, MT Ikrar Chandra Bachtiar, SKM
0812.50018822 Tanjungpura University
0811.501.584
NA
NA
NA
NA
NA
NA
Tanjung Pura University Lydia Gusti Resanika ,SE Ikrar Chandra Bachtiar, SKM Tanjung Pura University Lydia Gusti Resanika ,SE Rahayu Widasari
Ulfatu Munawaroh
Mulawarman University
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
No
Province
2
Package Observed
Package Number
Date of Invitation to Bid
Sp.3 Tanjung Palas Sekatak Buji (Sect 2)
34-RCP02
11-Mar-13
CROs Involvement in the Bidding Process Date of Bid Opening
Announcement Date of Bid Winner
13-Jun-13
4-May-14
Selected CRO Reports of CRO Activity Name ·
Process Verbal of the CRO selection for RRDP package of Sp.3 Tanjung Palas sekatak buji (serction 2), East Kalimantan SNVT of Roads and Bridge Development, June 2013
Rahayu Widasari
Address
3
34-RCP03
11-Mar-13
13-Jun-13
10-Feb-14
·
Process Verbal of the CRO selection for RRDP package of Sp.3 Apas - Simanggaris (serction 1), East Kalimantan SNVT of Roads and Bridge Development, June 2013
· SP.3 Apas Simaranggis (Sect 2); Simanggaris Bts.Negara
4
34-RCP04
11-Mar-13
13-Jun-13
6-Feb-14
·
CENTRAL JAVA
Tambakmulyo - Wawar
24-RCP01
14-May-14
15-Jul-14
2
Giriwoyo Duwet
24-RCP02
14-May-14
15-Jul-14
3
Wawar Congot
24-RCP03
14-May-14
15-Jul-14
NY
= Not Yet
NA
Process Verbal of the CRO selection for RRDP package of Sp.3 Apas - Simanggaris (serction 2) and Simanggaris - bts Negara, East Kalimantan SNVT of Roads and Bridge Development, June 2013
Process Verbal of the CRO selection for RRDP package of Tambakmulyo - Wawar, Central Java SNVT of Roads and Bridge Development, June 2014 Process Verbal of the CRO selection for RRDP package of Giriwoyo - Duwet, Central Java SNVT of Roads and Bridge Development, June 2014 Process Verbal of the CRO selection for RRDP package of Wawar - Congot, Central Java SNVT of Roads and Bridge Development, June 2014
Rahayu Widasari
NA
Mulawarman University
Ulfatu Munawaroh
· 1
Rahayu Widasari
Email
Mulawarman University
Ulfatu Munawaroh SP.3 Apas Simaranggis (Sect 1)
Telephone
NA
Mulawarman University
Ulfatu Munawaroh Ir.Yuniarto Adi, MT
Diponegoro University
Ir.Yuniarto Adi, MT
Diponegoro University
Ir.Yuniarto Adi, MT
Diponegoro University
NA
NA
NA
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 7b Status of CRO Reports December 2014 Status of Bidding Process No
RRDP Packages
Province
Bid Opening
Report Submission
Date of NOL to BER
Remarks
(BO) Complete report of bid opening and bid winner 4
Jolosutro - Sendangbiru (East Java)
5
Sosok - Tayan ; Tanjung - Batas Kota Sangga
6
Tebas - Singkawang (Section 1 &2); Bypass Sambas ; Galing - Tanjung Harapan
7
East Java
1-May-13
10-Jul-13
OK announcement.
9-Sep-14
9-Dec-14
OK
Complete report of bid opening and bid winner announcement.
22-May-13
13-Sep-13
OK
Complete report of bid opening and bid winner announcement.
Sp.Tanjung - Galing ; Aruk - Batas Serawak
15-Jun-13
11-Oct-13
OK
Complete report of bid opening and bid winner announcement.
8
Tj.Selor - Sp.3 Tanjung Palas (Section 1)
13-Jun-13
25-Sep-14
OK
Complete report of bid opening and bid winner announcement.
9
Tj.Selor - Sp.3 Tanjung Palas (Section 2)
13-Jun-13
20-May-14
West Kalimantan
OK
Complete report of bid opening and bid winner announcement.
East Kalimantan 10
Sp.3 Apas - Simaggaris (Section 1)
22-Oct-07
11-Dec-13
OK
Complete report of bid opening and bid winner announcement.
11
Sp.3 Apas - Simaggaris (Section 2); Simanggaris - Bts Negara
13-Jun-13
11-Dec-13
OK
Complete report of bid opening and bid winner announcement.
1
Tambakmulyo - Wawar
15-Jul-14
1-Dec-14
OK
Complete report of bid opening.
2
Giriwoyo - Duwet
15-Jul-14
1-Dec-14
OK
Complete report of bid opening.
3
Wawar - Congot
15-Jul-14
1-Dec-14
OK
Complete report of bid opening.
Central Java
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 8 Environmental Management and Monitoring Plan (EMP) Compliance on Regional Roads Development Project (RRDP) As Desember 2014 Contractor Performance on EMP Package No.
Contract No.
1
01-28-RCP01A/RB/ADB/2817/0813
Contract Description (Length)
Contractor
Road Safety Measures
Awareness & Readiness to EMP
Document Availability
Camp Cleanliness
Labour Camp
Disposal of Waste (Sludges)
Handling of Bitumen
Pollution Control Measures
Vehicle Management
Disposal of Wastewater
Total Score Obtained
Ranking (%)
Level
Jolosutro - Balekambang-Sendangbiru (21.30km)
PT.Hutama Karya
4
4
4
4
3
3
3
4
3
3
35
70
Good
4
4
3
3
3
3
3
2
3
3
31
62
Good
Remarks
2
02-30-RCP02/RB/ADB/2817/1113
Tebas- Singkawang; Bypass Sambas; Galing - Tj.Harapan (55.97 Kms)
PT.Brantas Abipraya; PT.Tri Citra Perdana; PT.Trifa Abadi JO
3
03-30-RCP02/RB/ADB/2817/1113
Sp.Tanjung - Galing; Sp.Tanjung - Aruk (52.04 kms)
PT. Waskita Karya; PT. Yasa Patria Perkasa - JO
2
3
3
3
3
3
3
3
2
3
28
56
Satisfactory
4
Sp.3 Tanjung Palas - Sekatakbuji 02-34-RCP/LOAN/PJN.III/06.14 (65.03 kms)
PT. Brantas Abipraya; PT.Mahir Jaya Mahakam Raya - JO
3
3
4
3
3
3
3
3
3
3
31
62
Good
5
Sp.3 Apas - Simanggaris (Section 1) 03-34-RCP/LOAN/PJN.III/04.14 45.00 kms
PT. Pembangunan Perumahan; PT. Perdasa- JO
4
3
4
3
3
3
3
3
3
3
32
64
Good
6
04-34-RCP/LOAN/PJN.III/04.14
Halla Corporation
2
3
3
3
3
3
2
3
3
3
28
56
Satisfactory
8
3
3
3
4
4
3
3
2
3
3
31
62
Good
Monitoring report had been prepared Being monitored during construction Monitoring report had been prepared
9
2
3
3
3
3
3
2
3
3
3
28
56
Satisfactory
Monitoring report had been prepared
10
4
3
3
3
3
3
3
3
3
3
31
62
Good
Monitoring report had been prepared
11
2
3
3
4
3
3
2
3
3
3
29
58
Satisfactory
Monitoring report had been prepared
Sp.3 Apas - Simanggaris (Section 2); Simanggaris - Bts.Negara 43.04 kms
7
Score
0
1
2
3
4
5
% Compliance
0-20
20-40
40-60
60-80
80-100
Scale
N.A.
Below Par
Mildly Satisfactory
Satisfactory
Good
Excellent
Ranking
Below Par
Mildly Satisfactory
Satisfactory
Good
Excellent
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 9 Status of Social Safeguard Studies on Regional Roads Development Project (RRDP) As Desember 2014
No.
Package No.
Project Name
Length (Km)
District
Type of Works
Safeguard Document
Jolosutro - Sendang biru
21.30
Malang
New Road Construction incl. raising grade and New Bridge Construction
LARP
EAST JAVA
1
28-RCP01 (CW01)
CENTRAL JAVA
2
24-RCP01 (CW02)
Tambak Mulyo – Wawar
38.46
Kebumen
Widening, Resurfacing and New Bridge Construction
3
24-RCP02 (CW03)
Giriwoyo - Duwet (Section-1)
23.75
Wonogiri
New Road Construction, Widening and New Bridge Construction
4
24-RCP03 (CW04)
Wawar – Congot
14.13
Purworejo
Widening and Resurfacing
79.20
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
LARP
55.97
Singkawang & Sambas
Reconstruction, Resurfacing and Widening
LARP
LARP
WEST KALIMANTAN
Sosok - Tayan; 5
30-RCP01 (CW05) Tanjung-Batas Kota Sanggau
6
30-RCP02 (CW06)
Tebas - Singkawang (Section-1);
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
No.
Package No.
Project Name
Length (Km)
District
Type of Works
Safeguard Document
Tebas - Singkawang (Section-2); Bypass Sambas; Sambas Galing-Tanjung Harapan; Sp.Tanjung-Galing (Section-1); 7
30-RCP03 (CW07)
Sp.Tanjung-Galing (Section-2);
52.04
Sambas
New Road Construction incl. raising grade and Reconstruction
34.82
Bulungan
New Road Construction incl. raising grade and Reconstruction
Aruk (Bts.Serawak)-Sp. Tanjung
EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW08) SP. 3 Tanjung Palas - Sekatak Buji (Secton-1)
LARP
9
34-RCP02 (CW09)
SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
65.03
Bulungan
Grade Improvement and Resurfacing
10
34-RCP03 (CW10)
SP.3 Apas - Simaranggis (Section- 1)
45.00
Nunukan
New Road Construction incl. raising grade and Reconstruction Possible for Updated LARP study related to relocation of road
SP.3 Apas - Simaranggis (Section-2) 11
34-RCP04 (CW11)
43.04 Simanggaris-Bts Negara (Serudong)
Nunukan
Widening and Reconstruction
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 10 Status of Monitoring of Environmental Mitigation on Regional Roads Development Project (RRDP) As Desember 2014 No.
Package No.
Project Nam e
Length (Km )
District
Type of Works
Construction Status
Contract Date
2014
2013
2015
Remarks Start (COW)
Finish (PHO)
10
11
12
1
2
3
4
5
6
7
8
18-Oct-13
17-Oct-14
√
√
√
√
√
√
√
√X
√
√
√
9
10
11
12
√
√
EAST JAVA
1
28-RCP01 (CW-01) Jolosutro - Sendang biru
21.30
Malang
New Road Construction incl. raising grade and New Bridge Construction
OC
√X √X
CENTRAL JAVA 2
24-RCP01 (CW-02) Tambak Mulyo – Waw ar
38.46
Kebumen
Widening, Resurfacing and New Bridge Construction
-
-
-
3
24-RCP02 (CW-03) Giriw oyo - Duw et (Section-1)
23.75
Wonogiri
New Road Construction, Widening and New Bridge Construction
-
-
-
4
24-RCP03 (CW-04) Waw ar – Congot
14.13
Purw orejo
Widening and Resurfacing
-
-
-
79.20
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
-
-
-
Reconstruction, Resurfacing and Widening
OC
17-Dec-13
15-Dec-14
√
√
√
√
√
√X
√
√
√
√
√
√
√X
√
WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05) Tanjung-Batas Kota Sanggau Tebas - Singkaw ang (Section-1);
30-RCP02 (CW-06)
√X
Singkaw ang & Sambas
Tebas - Singkaw ang (Section-2); 6
55.97
√
√X
√
√X
√
√
√X
√
√X
√
√
Bypass Sambas; Sambas Galing-Tanjung Harapan; Sp.Tanjung-Galing (Section-1); 7
30-RCP03 (CW-07) Sp.Tanjung-Galing (Section-2);
52.04
Sambas
New Road Construction incl. raising grade and Reconstruction
OC
4-Dec-13
2-Dec-14
34.82
Bulungan
New Road Construction incl. raising grade and Reconstruction
-
-
-
Aruk (Bts.Seraw ak)-Sp. Tanjung EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08) SP. 3 Tanjung Palas - Sekatak Buji (Secton-1)
√X
9
34-RCP02 (CW-09) SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
65.03
Bulungan
Grade Improvement and Resurfacing
CS
4-Sep-14
2-Sep-14
√
√
√
√
√
√X
√
10
34-RCP03 (CW-10) SP.3 Apas - Simaranggis (Section- 1)
45.00
Nunukan
New Road Construction incl. raising grade and Reconstruction
CS
10-Jul-14
26-Dec-14
√
√
√
√
√
√X
√
43.04
Nunukan
Widening and Reconstruction
CS
-
-
√
√
√
√
√
√X
√
SP.3 Apas - Simaranggis (Section-2) 11
34-RCP04 (CW-11) Simanggaris-Bts Negara (Serudong)
Note: OC
= Ongoing Construction
IFB
= Invitation For Bid
CS
= Contract Sign
BER
= Bid Evaluation Report
RT
= Retender
AMDAL
= Environmental Impact Assessment
NY
= Not yet
UKL/UPL
= Environmental Management & Monitoring Plans
NR
= Not required
SOP's
= Standard Operating Procedure
PHO
= Provisional Hand Over
√
= Monitored by DSC
COW
= Commencement of Work
X
= Monitored by CTC
2016
√
√
1
2
3
4
5
6
7
8
9
10
11
12
1
2
3
4
5
6
7
8
9
10
11
12
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 11 Overall Land Acquisition Status on Regional Roads Development Project (RRDP) As Desember 2014
No.
Package No.
Project Name
Total To Be Acquired (m2)
Total Acquired (m2)
Progress In %
Remarks
Forest land affected is replaced by another with an area of land equivalent and are in the Bondowoso Regency
EAST JAVA
1
28-RCP01 (CW-01)
Jolosutro - Sendang biru
1,481,400
1,481,400
100
1,192,988
1,192,988
100
CENTRAL JAVA
2
24-RCP01 (CW-02)
Tambak Mulyo – Wawar
3
24-RCP02 (CW-03)
Giriwoyo - Duwet (Section-1)
No LA
NR
-
4
24-RCP03 (CW-04)
Wawar – Congot
No LA
NR
-
Sosok - Tayan;
No LA
NR
-
Tanjung-Batas Kota Sanggau
No LA
NR
-
Tebas - Singkawang (Section-1);
286
420
0
Not required land acquisition because for the design need is in accordance with the existing ROW Not required land acquisition because for the design need is in accordance with the existing ROW It has been verified against the land data and necessary to acquisition
Tebas - Singkawang (Section-2);
3,543
4,730
0
It has been verified against the land data and necessary to acquisition
WEST KALIMANTAN
5
6
30-RCP01 (CW-05)
30-RCP02 (CW-06)
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
No.
Package No.
Total To Be Acquired (m2)
Total Acquired (m2)
Progress In %
No LA
NR
-
130
610
0
Sp.Tanjung-Galing (Section-1);
No LA
NR
-
Sp.Tanjung-Galing (Section-2);
No LA
NR
-
Aruk (Bts.Serawak)-Sp. Tanjung
176
0
0
3,326
0
0
8,400
0
0
2,690,249
2,680,148
Project Name
Bypass Sambas; Galing-Tanjung Harapan;
7
30-RCP03 (CW-07)
Remarks
It has been verified against the land data and necessary to acquisition
EAST KALIMANTAN
Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08) SP. 3 Tanjung Palas - Sekatak Buji (Secton1)
9
34-RCP02 (CW-09)
SP.3 Tanjung Palas - Sekatak Buji (Sect ion2)
10
34-RCP03 (CW-10)
SP.3 Apas - Simaranggis (Section- 1)
SP.3 Apas - Simaranggis (Section-2) 11
34-RCP04 (CW-11) Simanggaris-Bts Negara (Serudong)
GRAND TOTAL
land area affected will be confirmed after preparation of the LARP document
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 12 Environmental Safeguard on Regional Roads Development Project (RRDP)
No.
Package No.
Intial Environ mental Examin ation (IEE)
Length (Km)
District
Type of Works
Cons truc. Statu s
Jolosutro - Sendang biru
21.30
Malang
New Road Construction incl. raising grade and New Bridge Construction
OC
October 2011
Project Name
As Desember 2014 Environme Safeguard Document ntal Manageme nt and Monitoring Environ Approval Plan mental by BLHD (EMMP) or RKPPL
EAST JAVA
1
28-RCP01 (CW-01)
AMDAL (A)
2009
Not Yet
CENTRAL JAVA 2
24-RCP01 (CW-02)
Tambak Mulyo – Wawar
38.46
Kebumen
Widening, Resurfacing and New Bridge Construction
-
October 2011
3
24-RCP02 (CW-03)
Giriwoyo - Duwet (Section-1)
23.75
Wonogiri
New Road Construction, Widening and New Bridge Construction
-
October 2011
4
24-RCP03 (CW-04)
Wawar – Congot
14.13
Purworejo
Widening and Resurfacing
-
October 2011
Sanggau
Reconstruction and Resurfacing (Direct Overlay)
Not Yet AMDAL (A)
5 October 2005
Not Yet Not Yet
WEST KALIMANTAN Sosok - Tayan; 5
30-RCP01 (CW-05)
79.20 Tanjung-Batas Kota Sanggau
6
30-RCP02 (CW-06)
Tebas - Singkawang (Section-2); Bypass Sambas;
55.97 Sambas
UKL/UP L (B)
October 2011
UKL/UP L (B)
-
October 2011
Tebas - Singkawang (Section-1); Singkawang & Sambas
October 2011
Reconstruction, Resurfacing and Widening
OC
October 2011 October 2011
AMDAL (A)
UKL/UP L (B)
16 February 2011 16 February 2011 18 February 2013 16 February 2011
Not Yet
Not Yet Not Yet Not Yet Not Yet
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
7
30-RCP03 (CW-07)
Galing-Tanjung Harapan;
October 2011
UKL/UP L (B)
Sp.Tanjung-Galing (Section-1);
October 2011
UKL/UP L (B)
October 2011
UKL/UP L (B)
October 2011
UKL/UP L (B)
Sp.Tanjung-Galing (Section-2);
52.04
Sambas
New Road Construction incl. raising grade and Reconstruction
OC
Aruk (Bts.Serawak)-Sp. Tanjung
16 February 2011 13 January 2011 13 January 2011 13 January 2011
Not Yet
Not Yet
Not Yet
Not Yet
EAST KALIMANTAN Tanjung Selor - SP. 3 Tanjung Palas; 8
34-RCP01 (CW-08)
34.82
Bulungan
SP. 3 Tanjung Palas - Sekatak Buji (Secton-1)
October 2011
New Road Construction incl. raising grade and Reconstruction
October 2011
Not Yet UKL/UP L (B)
9
34-RCP02 (CW-09)
SP.3 Tanjung Palas - Sekatak Buji (Sect ion-2)
65.03
Bulungan
Grade Improvement and Resurfacing
CS
October 2011
10
34-RCP03 (CW-10)
SP.3 Apas - Simaranggis (Section1)
45.00
Nunukan
New Road Construction incl. raising grade and Reconstruction
CS
October 2011
UKL/UP L (B)
October 2011
UKL/UP L (B)
October 2011
UKL/UP L (B)
SP.3 Apas - Simaranggis (Section2) 11
34-RCP04 (CW-11)
43.04 Simanggaris-Bts Negara (Serudong)
Nunukan
Widening and Reconstruction
Not Yet Not Yet
-
Note : OC- Ongoing Construction; CS - Contract Signed; RT- Retender; NY- Not Yet ; IFB- Invitation For Bid; BER-Bid Evaluation Report
20 December 2010
14 August 2013 13 January 2011 13 December 2010
Not Yet
Not Yet
Not Yet
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 13 Regional Roads Development Projecr (RRDP) Construction Program Design
Procurement:
NOL Docs/Award:
Invite Bids:
NOL Re-bid:
Re-bid Period:
Sign Contract:
Commencemen of work
Ongoing Construction:
Pack. No.
As of December 2014 Package Number Contract
Location Phase
2012
Length, Kms
Code
J
F
M
A M
J
J
2013 A
S
O
N
D
J
F M
A M
J
J
2014 A
S
O N
D
J
F M
A M
J
J
2015 A
S
O N
EAST JAVA 4
Jolosutro- Sendangbiru
28-RCP01A
21.30
30-RCP01
79.20
WEST KALIMANTAN 5
Sosok - Tayan kota Sanggau
Tanjung - Batas
6
Singkawang - Tebas Sambas Bypass Tanjung Harapan -Galing
30-RCP02
55.97
7
Sp.Tanjung - Galing Sp.Tanjung Aruk (bts Serawak
30-RCP03
52.04
24-RCP01
38.46
24 - RCP02
23.75
24-RCP03
14.13
CENTRAL JAVA 1
Tambak Mulyo - Wawar
2
Giriwoyo - Duwet (Section 1)
3
Wawar - Congot
8
Tanjung Selor - Sp.3 Tanjung Palas Sp.3 Tanjung Palas - Sekatak Buji
34-RCP01
34.82
9
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
34 - RCP02
65.03
EAST KALIMANTAN
10
SP.3 Apas - Simanggaris (Section 1)
34-RCP03
45.00
11
SP.3 Apas - Simanggaris (Section 2) Simanggaris - Bts.Negara
34-RCP04
43.04
1 Oct 14
D
J
F M
A M J
J
2016 A
S
O N
D
J
F M
A M
J
J
2017 A
S
O N
D
J
F M
A M
J
J
A
S
O N
D
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 14 Cost Estimate Of Civil Work Packages Regional Roads Development Project (RRDP) - ADB LOAN NO.2817-1NO Status : Desember 2014 No.
Package No.
Length
Package Name
Type of Works
(Km)
Allocated Amount (Excluding Tax)
Contigency
Original Contract Amount (Excl. Tax) Technical Just
(US$)
(IDR)
(US$)
(IDR)
(IDR)
Total Contract Amount Excluding Tax
Remarks
Price Esc (%)
(IDR)
(%)
(US$)
(IDR)
(%)
EAST JAVA PROVINCE New Road Construction incl.raising 1
28-RCP 01A
Jolosutro - Sendang Biru
21.30
15,229,753.78
151,916,793,955.50
7,071,969.70
84,863,636,363.64
8,486,363,636.36 10.00
8,486,363,636.36
10.00
8,486,363.64
101,836,363,636.36
20.00
52,681,081.67
553,151,357,483.64
35,276,330.49
423,315,965,880.00
42,331,596,588.00 10.00
42,331,596,588.00
10.00
42,331,596.59
507,979,159,056.00
20.00
45,324,068.22
430,578,648,090.00
22,166,923.11
266,003,077,272.73
93,101,077,045.45 35.00
26,600,307,727.27
10.00
32,142,038.50
385,704,462,045.46
45.00
35,075,216.11
333,214,553,045.00
18,104,164.62
217,249,975,454.55
76,037,491,409.09 35.00
21,724,997,545.45
10.00
26,251,038.70
315,012,464,409.09
45.00
22,531,932.26
214,053,356,470.00
14,391,685.45
172,700,225,454.55
17,270,022,545.45 10.00
17,270,022,545.45
10.00
17,270,022.55
207,240,270,545.46
20.00
22,682,473.16
215,483,495,020.00
12,525,176.40
150,302,116,750.00
15,030,211,675.00 10.00
15,030,211,675.00
10.00
15,030,211.68
180,362,540,100.00
20.00
33,991,570.30
322,919,917,850.00
21,893,939.39
262,727,272,727.27
39,409,090,909.09 15.00
26,272,727,272.73
10.00
27,367,424.24
328,409,090,909.09
25.00
42,893,028.94
407,483,774,930.00
27,246,416.44
326,956,997,272.73
81,739,249,318.18 25.00
32,695,699,727.27
10.00
36,782,662.19
441,391,946,318.18
35.00
270,409,124.44
2,628,801,896,844.14
158,676,605.60
1,904,119,267,175.45
205,661,358.08
2,467,936,297,019.64
grade and New Bridge Construction
WEST KALIMANTAN PROVINCE 5
30-RCP01
Sosok - Tayan;
79.20
Tanjung - Bts. Kota Sanggau
Reconstruction and Resurfacing (Direct overlay)
Tebas - Singkawang (Section 1);
6
30-RCP02
Tebas - Singkawang (Section 2);
55.97
Bypass Sambas;
Reconstruction, Resurfacing and Widening
Galing - Tanjung Harapan Sp. Tanjung - Galing; 7
New Road Construction including
30-RCP03
52.04 Aruk (Bts. Serawak) - Sp. Tanjung
raising grade and reconstruction
EAST KALIMANTAN PROVINCE Tanjung Selor - Sp.3 Tanjung Palas; 8
34-RCP01
New Road Construction including 34.82
Sp.3 Tanjung Palas-Sekatak Buji (Sec.1)
raising grade and reconstruction
9
34-RCP02
Sp.3 Tanjung Palas - Sekatak Buji (Section 2)
65.03
10
34-RCP03
Sp.Tiga Apas - Simanggaris (Sec. 1)
45.00
Grade Improvement and Resurfacing New Road Construction including raising grade and reconstruction
Sp.Tiga Apas - Simanggaris (Sec. 2); 11
34-RCP04
Widening, Reconstruction and 43.04
Simanggaris - Bts.Negara (Serudong) Sub - Total ADB
SHARING
New Road 396.40
373,405,103,126.64
190,411,926,717.55
A D B (70 % )
189,286,387.10
111,073,623.92
143,962,950.66
1,727,555,407,913.75
G O I ( 30 % )
81,122,737.33
47,602,981.68
61,698,407.43
740,380,889,105.89
Asumsi 1 US$ = 12,000 IDR Allocated Loan ADB For Civil Works Packages
155,000,000.00
Remaining Estimate
11,037,049.34
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 15 Monitoring Health And Safety During Construction ( Keselamatan Dan Kesehatan Kerja(K3) Konstruksi ) Desember 2014 Contractor Performance on Health and Safety (K3 Konstruksi) Package No.
Contract No.
CW-04
01-28-RCP01A/RB/ADB/2817/0813
Contract Description (Length)
Contractor
Jolosutro - Bale kambang - Sendang biru (21,30 KM)
PT.Hutama Karya (Persero)
Working Schedule (RK3K)
Safety Meeting
Document Availability (Data,Picture, Interview)
Personel Protection (APD)
Labour Camp
Road Safety during Construction
System Managemen K3 (SMK3)
Disposal of Waste Material
Total Score Obtained
Ranking (%)
Level
Remarks
EAST JAVA
WEST KALIMANTAN
Sosok - Tayan; Tanjung - Bts.Kota PT.Yasa Patria Perkasa; Sanggau PT. Budi Bakti Prima JO
CW-05
CW-06
02-30-RCP02/RB/ADB/2817/1113
CW-07
03-30-RCP02/RB/ADB/2817/1113
-
-
-
-
-
-
-
-
-
-
Tebas - Singkawang (Section 1); Tebas -Singkawang (Section 2) Bypass Sambas Galing - Tanjung Harapan Sp. Tanjung - Galing; Aruk (bts.Serawak - Sp.Tanjung
PT.Brantas Abipraya-Tri Citra Perdana-Trifa Abadi, JO
-
-
-
-
-
-
-
-
-
-
PT Waskita Karya - Yasa Patria Perkasa, JO
-
-
-
-
-
-
-
-
-
-
Tanjung Selor-Sekatak Buji-Tanjung Palas Sec. 1 (34-RCP01)
PT. Waskita Karya (Persero)
-
-
-
-
-
-
-
-
-
-
EAST KALIMANTAN CW-08
01-34RCP/LOAN/PJN.III/11.14
CW-09
02-34RCP/LOAN/PJN.III/06.14
Tanjung Selor-Sekatak Buji-Tanjung Palas Sec. 2 (34-RCP02)
PT.Brantas Abipraya Mahir Jaya Mahakam Raya- JO
CW-10
03-34RCP/LOAN/PJN.III/04.14
SP.TIGA APAS - SIMANGGARIS (SECTION 1)
PT.Pemb. PerumahanPT.Perdasa JO
-
-
-
-
-
-
-
-
-
-
CW-11
03-34RCP/LOAN/PJN.III/04.14
SP. TIGA APAS - SIMANGGARIS - BTS. NEGARA (SERUDONG)
Halla Corporation
-
-
-
-
-
-
-
-
-
-
CW-01
Tambakmulyo - Wawar
PT.Pembangunan Perumahan ; PT.Armada Hada Graha
-
-
-
-
-
-
-
-
-
-
CW-02'
Giriwoyo - Duwet
PT. Hutama Karya (Persero)
CW-03
Wawar - Congot
PT. Jaya Konstruksi Manggala Pratama Tbk
CENTRAL JAVA
Ranking = (Total Score/40) * 100 %
Score
0
1
2
3
4
5
% Compliance
0-20
20-40
40-60
60-80
80-100
Scale
N.A.
Below Par
Mildly Satisfactory
Satisfactory
Good
Excellent
Ranking
Below Par
Mildly Satisfactory
Satisfactory
Good
Excellent
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
Appendix. 16 ABBREVIATIONS AND ACRONYMS ACAP ADB AMDAL ANDAS ATMS Bappedalda Bappenas BPK BPKP
CTC DSC-1 DSC-2 DSC-3 CW CHU DOP DGH DGLT DRBWR DTA DTP DFUR DGH EA EIA EIR EIRTP-2 ESAM EMP FMR FIDIC GOI HLRIP IA IDB IT ISEM IVP IG IRSMS KPKN LRAP LARF
Anti-Corruption Action Plan Asian Development Bank Environmental Management (Analisis Mengenai Dampak Lingkungan) Analisis Dampak Sosial Area Traffic Monitoring System Regional Environmental Impact Agencies Badan Perencanaan Pembangunan Nasional Badan Pemeriksaan Keuangan (Audit Board of the Government of Indonesia) Badan Pengawasan Keuangan dan Pembangunan (Development Finance Comptroller, internal auditor of the Government of Indonesia) Core Team Consultant Design and Supervision Consultant for Kalimantan Design and Supervision Consultant for Central Java Design and Supervision Consultant for East Java Civil Works Complaint Handling Unit Directorate of Planning Directorate General of Highways Directorate General of Land Transport Directorate Road and Bridge West Region Directorate of Technical Affairs Directorate of Traffic Police Directorate Freeway and Urban Road Directorate General of Highway Executing Agency Environmental Impact Assessment Eastern Indonesian Region Eastern Indonesia Regional Transport Project (Second Project) Environmental and Social Assessment Environmental Management Plan Financial Monitoring Report Federation Internationale des Ingenieur Conseils Government of Indonesia Heavy Loaded Road Improvement Project Implementation Agency Islamic Development Bank Information Technology Institutional Strengthening in Environmental Management Isolated Vulnerable People Inspectorate General Integrated Road Safety Management System Kantor Perbendaharaan Keuangan Negara Land Acquisition and Resettlement (Rencana Tindak Pengadaan Tanah dan Pemukiman Kembali) Land Acquisition Resettlement Frame Work
PMU RRDP – Quarterly Progress Report No. 3, October - December 2014
MOF MHA MPW MPR MOT NOL NRSC UKL/UPL OPRC PA PAS PMR PBCC PIP PIS PAD PMM PMU PPR PVD QPR RBRF RFP RRSP RS-SC SBD SIA SIPP SLKLL SOP SURIP SRRP SRIP SPI SC Sub Dit Lingkungan TKPM TOR TRACER WB WP-1 WPs WPM WTP
Ministry of Finance Ministry of Home Affairs Ministry of Public Works Monthly Progress Report Ministry of Transportation No Objection Letter (from World Bank) National Road Safety Council Upaya.Pengelolaan.Lingkungan.dan.Upaya.Pemantauan Lingkungan (Site Specific Environmental and Monitoring Plans) Output and Performance Based Road Contract Procurement Agent Procurement Advisory Services Performance Monitoring Reporting Performance Based Contract Consultant Project Implementation Plan Project Implementation Schedule Project Appraisal Document Project Management Manual Project Management Unit (RRDP) Project Progress Report Pre fabricated Vertical Drainage Quarterly Progress Report Reforming Road Maintenance Management and Funding Request for Proposal Road Rehabilitation Sector Project Road Safety Steering Committee Standard Bidding Document Social Impact Assessment Sistem Informasi Pemantauan Proyek Traffic Accident Reporting System Application Standard Operating Procedure Strategic Urban Road Infrastructure Project Sumatera Region Roads Project Strategic Road Infrastructure Project Support Project Implementation Steering Committee (Tim Pengarah) Sub Directorate of Environmental Tim..Penanganan..Komplain..Masyarakat..–..a.Complaints Investigation Unit within Inspectorate General Terms of Reference Studi Penyelusuran Kembali World Bank Works Program – Year 1 Work Programs Wakil Pengamat Masyarakat Warga yang Terkena Proyek