TOLL ROAD RECENT DEVELOPMENT IN INDONESIA
Kuala Lumpur 25 May 2015 EKA PRIA ANAS BOARD MEMBER, INDONESIA TOLL ROAD AUTHORITY MINISTRY OF PUBLIC WORKS AND HOUSING
OUTLINE Indonesia Toll Road History Toll Road Master Plan Investment Scheme and Procurement Process Toll Road Projects Indonesia Toll Road Authority
ABOUT BADAN PENGATUR JALAN TOL/ INDONESIA TOLL ROAD AUTHORITY
•
• •
ITRA was established by Ministry of Public Works Regulation No. 295/PRT/M/2005 as amended by Ministry of Public Works Regulation No. 15/2014; ITRA is responsible directly to the Minister of Public Works and Housing; ITRA is responsible to: • Recommend the initial and adjusment of toll tariff to the Minister; • Conduct the toll road investment under PPP; • Monitor the construction of toll road; • Monitor the toll road operation; • Monitor the Toll Road Company during all phases of concession period (Design, Construction, Operation and Maintenance, Transfer).
Indonesia Toll Road Authority
INDONESIA TOLL ROAD AUTHORITY : ORGANIZATION STRUCTURE
Board of ITRA MPWH Representative
Head of ITRA
Profesional Association Representative
MoF Representative
Academic Representative
Secretary of ITRA
Head of Technical Division
Head of Investment Division
Head of Supervision and Monitoring Division
Head of General Affairs Division
Head of Funding Division
Head of Study Sub Division
Head of Investment Preparation & Service Sub Division
Head of Supervision Sub Division I
Head of Financial Sub Division
Head of Planning & Feasibility Sub Division
Head of Data & Technical Information Sub Division
Head of Investment Control Sub Division
Head of Monitoring Sub Division II
Head of Administration and Human Resource Sub Division
Head of Distribution & Repayment Sub Division
Head of Legal and Public Relation Sub Division
Indonesia Toll Road Authority
4
INDONESIA’S TOLL ROAD HISTORY (1)
1978 : The completion and operation of the 59 km Jakarta Bogor Ciawi Toll Road by PT. Jasa Marga (regulator and operator – not a good practice!) 1987 : Private sectors have actively participated in the toll road by signing the concession agreement (PKP) with PT. Jasa Marga
1997 : Monetary crisis caused the government to suspend toll road constructions program 1998 : Government issued a Presidential Decree No. 7/1998 on Public Private Partnership on the Procurement of Infrastructure Projects
Indonesia Toll Road Authority
INDONESIA’S TOLL ROAD HISTORY (2)
2002 : Government issued Presidential Decree No. 15/2002 on the recommencement of Infrastructure Projects. 2004 : from 2001 to 2004, four segments of toll roads were constructed of 41.80 Km in length 2004 : Law No. 38/2004 on Road mandated the formation of BPJT/ITRA as the substitute of the regulator role that was previously held by PT. Jasa Marga
2005 : ITRA was established as the toll road regulator in Indonesia. 19 toll road projects that were suspended in 1997 was recommenced.
Indonesia Toll Road Authority
TOLL ROAD MASTERPLAN
•
Total Length: 6.115 Km
•
Investment Cost (Est): IDR 723 T
No
Toll Roads SUMATRA ISLAND A. Trans-Sumatra
1
2 3 4 5
I. Main Projects a. Banda Aceh-Medan b. Medan-Pekanbaru c. Pekanbaru- Palembang d. Palembang-Bakauheni II. Connecting Projects a. Tebing Tinggi-Sibolga b. Pekanbaru-Padang c. Palembang-Bengkulu
B. Non Trans-Sumatra JAVA ISLAND A. Trans-Java (Merak-Banyuwangi) B. Jabodetabek C. Non-Trans Java and Non-Jabodetabek KALIMANTAN ISLAND BALI ISLAND SULAWESI ISLAND TOTAL
Indonesia Toll Road Authority
Operation Construction (until 2014) (Until 2019) 43 346 43 346 43 43 -
324 16 197 111 22 22
749 363 209 177 10 18
1,078 654 250 174 99 39
820
1,562
Program (2015 - 2025) 2,476 2,451 1,681 455 335 556 335 770 200 240 330
TOTAL 2,865 2,840 2,048 471 575 667 335 792 200 240 352
25 988 170 71 747 219 50
25 2,815 1,187 530 1,098 99 229 107
3,733
6,115
TOLL ROAD ACHIEVEMENT : 2005 – 2015 No
Toll Road Project
Length (Km)
Toll Road Company
Operation Date
1
Cikampek - Purwakarta - Padalarang
58.50
PT Jasa Marga (Persero) Tbk
26 April 2005
2
JORR W2S (Pondok Pinang-Veteran)
5.72
PT Jasa Marga (Persero) Tbk
11 November 2005
3
JORR S1 North Section 3 (Pondok Pinang-Taman Mini)
4.35
PT Jasa Marga (Persero) Tbk
1 September 2006
4
JORR E3 (Cakung-Cilincing)
3.75
PT Jasa Marga (Persero) Tbk
24 May 2007
5
JORR E1 North Section 4 (Hankam Raya-Cikunir)
3.75
PT Jasa Marga (Persero) Tbk
28 August 2007
6
SS Waru-Bandara Juanda
12.80
PT Citra Margatama Surabaya
27 April 2008
7
Makassar Section IV
11.60
PT Jalan Tol Seksi Empat
24 September 2008
8
Surabaya Madura Bridge
5.40
PT Jasa Marga (Persero) Tbk
10 June 2009
9
Kanci-Pejagan
35.00
PT Semesta Marga Raya
26 January 2010
10
JORR W1 (Kebon Jeruk-Penjaringan)
9.85
PT Jakarta Lingkar Baratsatu
22 February 2010
11
Surabaya-Mojokerto Section I (Waru Sepanjang)
1.89
PT. Marga Nujyasumo Agung
26 August 2011
12
Semarang Solo Section I (Semarang-Ungaran)
11.00
PT. Trans Marga Jateng
10 November 2011
13
Bogor Ring Road Section I (Sentul Selatan-Kedung Halang)
3.85
PT Marga Sarana Jabar
29 November 2011
14
Cinere-Jagorawi Section I (Jagorawi-Raya Bogor)
3.50
PT Translingkar Kita Jaya
3 February 2012
15
Bali Mandara (Nusa Dua-Ngurah Rai-Benoa)
10.00
PT Jasamarga Bali Tol
23 September 2013
16
Semarang-Solo Section II (Ungaran-Bawen) Bogor Ring Road Section IIA (Kedung Halang-Kedung Badak)
11.95
PT Trans Marga Jateng
4 April 2014
1.95
PT Marga Sarana Jabar
28 May 2014
18
JORR W2 North (Kebon Jeruk-Ulujami)
7.87
PT Marga Lingkar Jakarta
21 July 2014
19 20
Kertosono-Mojokerto Section I (Bandar-Jombang) Porong - Gempol
14.41 3.5
PT Marga Harjaya Infrastruktur PT Jasa Marga (Persero) Tbk
13 October 2014 18 May 2015
17
Total
Indonesia Toll Road Authority
213.64
TRANS JAVA TOLL ROAD DEVELOPMENT Serang
9 TRANS JAVA TOLL ROAD PROJECTS WITH THE TOTAL LENGTH OF 615 KM
DKI Jakarta
Banten
73 KM
288 KM
Cikampek
177,12 KM
76,77 KM
Palimanan
Bogor
1 Pejagan Pemalang
Kanci Sukabumi
Ciranjang
Bandung
Semarang Demak
(K) Batang
2
Remarks : Jawa Barat : Operation : Land Acquisition and Construction : Preparation of Land Acquisition Investment Cost Total : IDR 51.41 Trillion Land Cost Total : IDR 511 Billion Length Total : 615 KM
3
4
9
Ngawi
5
Jawa Tengah
Solo
7
Kertosono
6 Yogyakarta
8
Pasuruan
Gempol Pandaan
Probolinggo
DIY
Malang
Jawa Timur *) as of 15 May 2015
3
Cikampek – Palimanan
Pejagan Pemalang
Pemalang Batang
Batang Semarang
Semarang - Solo
Solo - Ngawi
Ngawi - Kertosono
MojokertoJombangKertosono
Mojokerto Surabaya
Toll Road Company
PT. Lintas Marga Sedaya
PT. Pejagan Pemalang Toll Road
PT. Pemalang Batang Toll Road
PT. Marga Setia Puritama
PT. Trans Marga Jateng
PT. Solo Ngawi Jaya
PT. Ngawi Kertosono Jaya
PT. Marga Harjaya Infrastruktur
PT. Marga Nujyasumo Agung
Length (km)/Section Number
116.75/6
57.50/4
39.20/2
75.00/5
72.64/5
90.10/4
87.02/4
40.50/4
36.27/5
12.6
5.52
4.08
7.23
6.21
5.14
3.83
3.48
3.4
0.691/1,076
1.081/429.79
0.803/279.36
1.575/666.67
1.842/691.89
1.778/748.03
1.084/619.19
0.485/281.56
1.508/280.36
Operation (overall)
2015
2018
2018
2018
2018
2018
2018
2017
2017
Concession Period (years)
35
45
45
45
45
35
35
35
42
100.00%
41.95%
1.86%
17.58%
57.42%
91.57%
68.70%
93.28%
89,52%
Section I (96.14%), Section II (79.43%), Section III (99.08%), Section IV (86.80%), Section V (89.67%), Section VI
Section I (23.16%) Section II (25.33%)
Investment Cost (IDR Trillion) Land Cost (IDR Trillion)/Ha
Land Acq *)
Progres s
Construction Indonesia Toll Road Authority***)
-
Section I –II (100%), Section III—V (0%), Total (31.43%)
6
7
Banyuwangi
2
Project Name
5
***) as of 15 May 2015
1
No/ Project
4
Surabaya
Mojokerto
8
Total
Govt
Private
Total
Govt
Private
15.20%
48%
6.15%.
-
-
-
Section I (100%), Section II ((48.26%) (Brantas Bridge 99.10%)), Section III (16.17%), Section IV
9
Section IA (97.57% (IA-I : 100%)), Section IB (36.52%), Section II – III (0%), Section IV (67.76%),
JABODETABEK TOLL ROAD DEVELOPMENT Pluit
Rawa Buaya
Akses Tanjung Priok
1 Tomang
2
6 Toll Road Projects in DKI Jakarta
Kemayoran Sunter 4
2
3
7
5 Ulujami
Pulo Gebang
Kp.Melayu
6 TMII
9
2
Semanan Sunter
3
Sunter – Pulo Gebang
Ps.Minggu
: : : : Investment Cost Total : Land Cost Total : Length Total :
4
Operation Land Acquisition and Construction CA Preparation Procurement Preparation IDR 33.19 T IDR 8.26 T 171 Km
4 5 6
10
2
1
6
5
8
*) as of 15 May 2015 **) Land Acquisition Support IDR 350 Billion ***) as of 15 May 2015 No
3
Length (Km)
1
1
3 Remarks :
Project
No
4
5
6
7
20.23
11,060
9.44
4,918
12.65
8,167
Kemayoran – Kampung Melayu
9.60
4,934
Ulujami – Tanah Abang
8.70
6,114
Duri Pulo – Kampung Melayu
Pasar Minggu – Casablanca 9
8
Investmen t Cost (IDR Billion)
TOTAL
9.16 10
69.77
5,981 1-6
41,174
Project Name
JORR W2 Utara
Cengkareng – Batu – Ceper – Kunciran
Kunciran – Serpong
Serpong – Cinere
Cinere – Jagorawi
Cimanggis – Cibitung
Cibitung – Cilincing
Depok – Antasari
Bekasi – Cawang – Kp. Melayu **)
Bogor Ring Road
6 Toll DKI Jakarta
Toll Road Company
PT. Marga Lingkar Jakarta
PT. Marga Kunciran Cengkareng
PT. Marga Trans Nusantara
PT. Cinere Serpong Jaya
PT. Translingkar Kita Jaya
PT. Cimanggis Cibitung Tollways
PT. MTD CTP Expressway
PT. Citra Waspphutowa
PT. Kresna Kusuma Dyandra Marga
PT. Marga Sarana Jabar
PT Jakarta Tollroad Developmen t
Length (km)/Section
7.67/2
14.19/4
11.19/2
10.14/2
14.64/3
25.39/4
34.02/4
21.54/5
21.04/2
11.00/3
69.77/6
Investment Cost (IDR. Trillion)
2.229
3.507
2.623
2.219
2.621
4.524
4.22
3.0
7.2
0.983
41.174
0.610/57.63
1.219/122.65
0.989/99.97
0.712/76
0.930/134.21
1.314/333.98
0.288/193.47
0.769/178
0.449**/95.30
0.983/50.64
5.28/59.41
Operation (Overall)
2014
2019
2019
2019
2018
2019
2019
2019
2019
2019
2021
Concession Period (years)
40
35
35
35
35
35
40
40
45
45
45
91.83%
18.86%
27.65%
-
63.71%
0.30%
10.56%
26.42%
16.95%
61.76%
-
-
-
-
-
-
Package I (0.87%) Package II (0%) Package III (0%)
Section I (5.49%)
Section I (100%), Section II (48.75%), Section IIA (100.00%), Section III (0%), Total (38.67%)
-
Land Cost (IDR Trillion)/Ha
Land Acq *)
Progres s
Construction ***)
In operation since 2014
Indonesia Toll Road Authority
Section I (100%), Section II (27.05%), Section III (0 %), Total (35.44%)
NON TRANS JAVA TOLL ROAD DEVELOPMENT 7/8 Serang
DKI Jakarta Cikampek
Banten
Palimanan
Bogor Ciranjang
1
Bandung
Kanci
Sukabumi
Investment Cost Land Acquisition Length Description
Batang
Semarang Demak
(K)
Remarks : : : : : : :
6
Pejagan Pemalang
Surabaya
Ngawi
Jawa Tengah
Jawa Barat Operation Land Acq. and Construction Procurement Preparation IDR 32.932 Trillion IDR 3.791 T 222.7 Km 2 1
5
Mojokerto
Solo
Kertosono
Pandaan
Yogyakarta
DIY
3
4
Gempol
3 Pasuruan 2 4
Probolinggo
Malang
Jawa Timur *) As of 21 April 2015 ***) As of 15 May 2015
5
6
7
8
Banyuwangi
Ciawi - Sukabumi
Gempol – Pandaan
Gempol – Pasuruan
Pasuruan – Probolinggo
Waru (Aloha) – Wonokromo – Tj. Perak
Bali Mandara (Nusa DuaNgurah RaiBenoa)
MedanKualanamuTebing Tinggi
Medan-Binai
Toll Road Company
PT. Trans Jabar Tol
PT. Jasamarga Pandaan Tol
PT. Trans Marga Jatim Pasuruan
PT. Transjawa Paspro Jalan Tol
PT. Margaraya Jawa Tol
PT Jasamarga Bali Tol
PT. Jasamarga Kualanamu Tol
PT Hutama Karya
Length (km)/Section
54/4
13.61/1
34.15/3
31.30/3
18.20/4
10,07/1
61.70
16.72
Investment Cost (IDR Trilion)
7.775
1.472
2.769
3.551
11.111
2.485
4.072
1.604
0.824/567.53
0.191/102.84
0.256/318.42
0.216/360
1.425/72.8
0.456/10.48
0.441/445.43
-
Operation (overall)
2019
2015
2018
2019
> 2019
2013
2017
2018
Concession Period (years)
45
37
45
45
50
45
40
40
53.07%
-
-
100%
85.98%
69.70%
Project Name
Land Cost (IDR Trillion)/Ha
Land Acq 24.04% 100% Indonesia Toll Road Authority *)
INVESTMENT SCHEME AND TOLL ROAD VIABILITY SBOT/HYBRID
BOT TRC
GOI
TRC
GOI
O&M/LEASE TRC
GOI
ASSIGNMENT*
SOE
Land Acquisition
Construction
O&M
EIRR >>> FIRR >>>
TRC : Toll Road Company GOI: Government of Indonesia SOE: State Owned Enterprise
EIRR >>> FIRR Marginal
EIRR >>> FIRR <<<
EIRR >>> FIRR <<<
*) PP 43 /2013 : assignment of SOEs due to limited budget of GOI in providing infrastructure.
Indonesia Toll Road Authority
STAGES OF TOLL ROAD PROCUREMENT Directorate General of Highways SOLICITED PROJECT
Indonesian Toll Road Authority
UNSOLICITED PROJECT
TOLL ROAD PLANNING POLICY
1
TOLL ROAD MASTER PLAN
2
TOLL ROAD SECTION PLAN
3
PROJECT PROPOSAL
1a
PROPOSAL APPROVAL
1b
Toll Road Company
CONCESSION AGREEMENT
TENDER PREPARATION
LAND ACQUISITION
4
5
TENDER
6
Indonesia Toll Road Authority
TOLL TARIFF
FINANCING
7
TECHNICAL DESIGN
8
CONSTRUCTION
OPERATION & MAINTENANCE
CONCESSION TAKE OVER
9
10
11
TRANSACTION PROCESS
PRIVATE SECTOR
GOVERNMENT PROJECT PREPARATION
PREPARE PQ DOCUMENT
PQ AND BID INVITATION
SUBMIT PQ DOCUMENT
PREQUALIFICATION OF BIDDER
PREPARE BID PROPOSAL
PRE BID CONFERENCE-BID PREPARATION (± 14 months)
SUBMIT BID PROPOSAL & BID BOND
SUBMISSION AND OPENING BID
RECEIVE NOTICE AWARD
EVALUATION OF BID
PREPARE SPECIAL PURPOSE VEHICLE
APOINTMENT OF SUCCESFUL BIDDER
SIGN CONTRACT
PERFORMANCE BOND, LAND ACQUISITION COST, FINANCIAL CLOSE
CONCESSION AGREEMENT
IMPLEMENTATION OF THE AGREEMENT
Indonesia Toll Road Authority
(± 4-6 months)
PROCUREMENT PROCESS
1 • • • •
•
Pre-Qualification (PQ) Process
PQ process will be announced in local mass media. PQ criteria will be set out in the pre-qualification document. Participants who meet the requirement and eligible criteria will be announced as shortlisted bidders and will be invited to tender. Should there be less than three participants, there will be re-PQ. Should the above condition is recurred, the tender process will be continued by negotiation.
Evaluation Criteria For PQ 1. Compliance with submission requirements in the prequalification document and eligibility to participate in Indonesian PPP Procurement; 2. Financial capacity to raise the required finance for the Project; 3. Track record in financing, designing, constructing and operating projects similar to this Project, particularly in Indonesia and / or South East Asia and experience in fulfilling PPP projects.
Indonesia Toll Road Authority
Tender Process • •
2
Participants who meet the requirement and eligible will be announced as shortlisted bidders and will be invited to tender. Should there is one tender participant, the tender process will be conducted by negotiation.
Evaluation Criteria For Tender Tender process are evaluated using two methods : 1. Lowest tariff; 2. Lowest government support;
RISK ALLOCATION Allocation No
Type of Risk Government
1.
Land Acquisition
2.
Engineering Plan
3.
Toll Road Construction
4.
Operation and Maintenance
5.
Toll Tariff
6.
Traffic Volume
7.
Law Amandment
8.
Force Majeur
Indonesia Toll Road Authority
Toll Road Company
CONSTRAINT AND EXPECTED CONDITION OF TOLL ROAD BUSINESS IN INDONESIA
PAST
PRESENT Land acquisition implementation in accordance with the Law of 2/2012 and Presidential Regulation of 30/2015 Financing and its implementation are conducted by Government
Land Acquisition
No certainty on the completion of land acquisition financed by business entity
Financing Facility
Limited financing from lender (only from bank)
Availability of other financing institutions apart from banking. (PT SMI/IIF)
Bidding
Most of toll road segments are based on the national road network determined by the Minister of Public Works and Housing Bidding includes land acquisition cost
Private’s initiative Investment cost excludes land acquisition cost Bidding is carried out upon completion of land acquisition (minimum 1 section)
Contingent Liability
Absence of Government guarantee to reduce the risks
Use of Government guarantee management through PT PII / IIGF
Indonesia Toll Road Authority
in
risk
PPP STRUCTURE GENERAL
Government/ITRA
VGF IIGF
Directorate General of Highways
Tripartite Agreements
Guarantee Agreement
Ministry of Finance
Concession Agreement Loan Agreements
Land Acquisition
Lenders
Toll Road Company Equity Mezzanine D&C Contract
Investors
O&M Contract
Lenders Construction Contractor
Indonesia Toll Road Authority
Operator
PPP STRUCTURE : RECENT DEVELOPMENT
SBOT with Government Guarantee (Optional) National Budget/ Borrowing
Rp
Land Acquisition
Rp
Government
Rp
• Land acquisition cost
paid by Government • Part of toll road section constructed by Government • TRC builds other sections and operate the Toll Road in total
MoPW & H
Rp
Ministry of Finance Guarantee
Toll Road Assets
Rp Recourse Agreement
IIGF
BPJT Concession Agreement
EQUITY
Equity Sponsor
SERVICE
Rp DIVIDEND LOAN
Lender
Toll Road Company
Road Users Rp
Rp
TOLL TARIFF
REPAYMENT CONSTRUCTION COST Rp
Construction, Operation & Maintenance
Construction
Indonesia Toll Road Authority
Rp
Operation & Maintenance Cost
Operation & Maintenance
TOLL ROAD INVESTMENT OPPORTUNITIES 2015
4 3
1 2 No.
1
2
3
Project Name
Cileunyi – Sumedang Dawuan
Pandaan – Malang
Balikpapan – Samarinda
Manado – Bitung
Length (km)
60.27
37.62
99.02
39.00
Investment Cost (IDR Bio)
10,033
2,968
11,400
4,163
Land Acquisition Cost (IDR Bio)
1,295
294
1,266
365
Land Acquisition (28.18%)
Land Acquisition (21.99%)
Land Acquisition (83 %)
Land Acquisition (30.69 %)
Project Status
Indonesia Toll Road Authority
4
1st IRF Asia Regional Congress & Exhibition Bali, November 17 - 19, 2014 Better Roads. Better World.
CONCLUDING REMARKS
• Government is facilitating land acquisition before the start of new toll construction; • Government is committed to continuously improve the PPP scheme; • PPP scheme with Government support is more viable, with Government support on land acquisition and part of the toll construction.
Indonesia Toll Road Authority
THANK YOU Indonesia Toll Road Authority – Ministry of Public Works and Housing Jl. Pattimura No. 20, Kebayoran Baru - Jakarta Selatan 12110 Indonesia E-mail: