DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION MINISTRY OF ENERGY AND MINERAL RESOURCES
DEVELOPMENT OF GEOTHERMAL
By:
Presented at:
Ministry of Energy and Mineral Resources Directorate General of New Renewable Energy and Energy Conservation
Direktorat Jenderal EBTKE
INTRODUCTION •
Indonesia has abundance potential on geothermal energy more than 28 GW which distributed in 299 locations along the country, yet, only less than 5% have been utilized. Total installed capacity of geothermal energy is 1,341 MW.
•
Average growth of energy consumption is 8,5% per year (RUPTL 2011-2020). Up to now Energy National demand is still fulfill from fossil fuel but the reserves are progressively decreasing. These situations have forced to perform two things, efficiency in the use of fossil fuels and find out new alternatives energy which are relatively cheaper and environmentally friendly
•
The Government of Indonesia (GoI) is concerned in energy development based on green energy, mainly geothermal. Presidential Decree No. 5 / 2006 on National Energy Policy (KEN) has targeted in 2025 electricity from geothermal energy will reach 9500 MW or contribute 5% of national energy consumption.
•
GoI has also launched “Energy Vision 25/25”. This vision targeted that in 2025 the energy utilization based on new and renewable energy will reach 25% of total national energy mix. Geothermal is expected to contribute 5.7% or about 12,000 MW in 2025
Ministry of Energy and Mineral Resources Directorate General of New Renewable Energy and Energy Conservation
Direktorat Jenderal EBTKE
INTRODUCTION (cont’d) •
To support utilization geothermal energy, the GoI have been issued crash program phase II to accelerate 10.000 MW electricity development that derived from geothermal power plant (4,965 MW)
•
Achieving the proposed 4,965 MW new geothermal capacity would automatically lead Indonesia to the single largest CO2 mitigation program in the world. The proposed program will reduce in the period of 2010 – 2025 over 400 million tCO2.
•
Up to 2012, The Government of Indonesia (GoI) has determined total of fifty eight GWAs. Nineteen of the GWAs were established before the issuance of Law No. 27/2003 (Existing GWA) while 39 of them were established afterwards (New GWA).
•
The program need more than US$ 14,000 million. In order to support the program, the GoI has issued some policies and regulations to overcome barriers in geothermal development.
Maulana Hadi:
Process
Direktorat Jenderal EBTKE
Ministry of Energy and Mineral Resources Directorate General of New Renewable Energy and Energy Conservation
GEOTHERMAL SYSTEM
? ?
Impermeabel clay cap alteration
? ?
Direktorat Jenderal EBTKE
Ministry of Energy and Mineral Resources Directorate General of New Renewable Energy and Energy Conservation
DISTRIBUTION OF GEOTHERMAL POTENTIAL PER ISLAND Potential Energy (Mwe) No
Island
Number of
Resources
Location
Reserve
Speculative Hypothetical Possible Probable
Installed
Proven
1
Sumatera
90
3089
2427
6867
15
380
12778
122
2
Java
71
1710
1826
3708
658
1815
9717
1134
3
Bali-Nusa Tenggara
28
360
417
1013
0
15
1805
5
4
Kalimantan
12
145
0
0
0
0
145
5
Sulawesi
65
1323
119
1374
150
78
3044
6
Maluku
30
545
97
429
0
0
1071
7
Papua
3
75
0
0
0
0
75
299
7247
4886
13391
823
2288
28635
Total
12.133
16.502 28.635
Source Status
Total
: Geological Agency, MEMR : December 20112
80
1.341
Direktorat Jenderal EBTKE
Distribution of GWA
Ministry of Energy and Mineral Resources Directorate General of New Renewable Energy and Energy Conservation
GEOTHERMAL DEVELOPMENT Total : 58 GWA ACEH 2 WKP Jaboi: 70 MW Seulawah Agam: 130 MW NORTH SUMATERA 5 WKP Sibayak – Sinabung: 130 MW Sibual – Buali: 750 MW Sipaholon Ria-ria: 75 MW Sorik Marapi: 200 MW Simbolon Samosir : 155 MW
Lisence – Issued Tender on Progress : Tender Preparation Tender – Failed
NORTH SULAWESI 2 WKP Kotamobagu: 410 MW Lahendong-Tompaso: 358 MW GORONTALO 1 WKP Suwawa: 110 MW
JAMBI 1 WKP Sungai Penuh: 70 MW
NORTH MALUKU 2 WKP Jailolo: 75 MW Songa Wayaua: 140 MW
SOUTH SUMATERA 3 WKP Lumut Balai: 250 MW Rantau Dedap: 106 MW Danau Ranau: 210 MW WEST SUMATERA 4 WKP Bukit Kili: 83 MW Gn Talang: 35 MW Liki Pinangawan: 400 MW Bonjol: 200 MW
: 38 GWAs 2 GWAs : 13 GWAs : 5 GWAs
BANTEN 2 WKP Kaldera Danau Banten: 115 MW G. Endut: 80 MW
BENGKULU 2 WKP Tmbg Sawah-Hululais: 873 MW Kepahiyang : 180 MW LAMPUNG 4 WKP Gn.Rajabasa: 91 MW Suoh Sekincau: 230 MW Waypanas – Ulubelu: 556 MW WEST JAVA 10 WKP Danau Ranau: 210 MW Ciater - Tgkban Perahu: 60 MW Way Ratai :105 MW Cibeureum–Parabakti: 485 MW Cibuni: 140 MW Cisolok Cisukarame: 45 MW Gn. Tampomas: 50 MW Gn. Tgkuban Perahu: 100 MW Kamojang-Darajat: 1465 MW Karaha Cakrabuana: 725 MW Pangalengan: 1106 MW G. Ciremai: 150 MW
CENTRAL SULAWESI 2 WKP Marana: 35 MW Bora Pulu : 152 MW
BALI 1 WKP Tabanan: 276 MW
CENTRAL JAVA 5 WKP Baturaden: 175 MW Dataran Tinggi Dieng: 780 MW Guci: 79 MW Gn. Ungaran: 100 MW Umbul Telomoyo : 120 MW
MALUKU 1 WKP Tulehu: 100 MW WEST NUSA TENGGARA 2 WKP Hu'u Daha: 65 MW Sembalun : 100 MW
EAST JAVA 4 WKP Blawan – Ijen: 270 MW Gn. Iyang Argopuro: 295 MW Telaga Ngebel: 120 MW Gn. Lawu: 195 MW
EAST NUSA TENGGARA 5 WKP Atadei: 40 MW Sokoria: 30 MW Ulumbu: 199 MW Mataloko: 63 MW Oka Ile Ange : 40 MW
7
DIREKTORAT PANAS BUMI DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN DAN KONSERVASI ENERGI
PENGOPERASIAN LAPANGAN UAP DAN PEMBANGKITAN LISTRIK DARI ENERGI PANAS BUMI
ILUSTRASI KEGIATAN PENGUSAHAAN PANAS BUMI
SUMUR PRODUKSI
Direktorat Jenderal INSTALLED GEOTHERMAL POWER PLANT CAPACITY 2012 EBTKE
Ministry of Energy and Mineral Resources Directorate General of New Renewable Energy and Energy Conservation
N o
Geothermal Working Area/ Location
License Holder
Developer
Power Plant
Installed Capacity (MW)
1
Sibayak – Sinabung, NORTH SUMATERA
PT. Pertamina Geothermal Energy (PGE)
PT. Pertamina Geothermal Energy (PGE)
Sibayak
12
2
Cibeureum – Parabakti, WEST JAVA
PT. Pertamina Geothermal Energy (PGE)
KOB - Chevron Geothermal Salak, Ltd (CGS)
Salak
377
3
Pangalengan, WEST JAVA
PT. Pertamina Geothermal Energy (PGE)
KOB - Star Energy Geothermal Wayang Windu, Ltd (SEGWWL)
Wayang Windu
227
4
Kamojang – Darajat, WEST JAVA
PT. Pertamina Geothermal Energy (PGE)
PT. Pertamina Geothermal Energy (PGE)
Kamojang
200
5
Kamojang – Darajat, WEST JAVA
PT. Pertamina Geothermal Energy (PGE)
KOB - Chevron Geothermal Indonesia, Ltd (CGI)
Darajat
270
6
Dataran Tinggi Dieng, CENTRAL JAVA
PT. Pertamina Geothermal Energy (PGE)
PT. Geo Dipa Energi (GDE)
Dieng
60
7
Lahendong – Tompaso, NORTH SULAWESI
PT. Pertamina Geothermal Energy (PGE)
PT. Pertamina Geothermal Energy (PGE)
Lahendong
80
8
Ulubelu, LAMPUNG
PT. Pertamina Geothermal Energy (PGE)
PT. Pertamina Geothermal Energy (PGE)
Ulubelu
110
9
Ulumbu, EAST NUSA TENGGARA
PT. PLN Geothermal
PT. PLN Geothermal
Ulumbu
5
TOTAL
1.341
Ministry of Energy and Mineral Resources Directorate General of New Renewable Energy and Energy Conservation
Direktorat Jenderal EBTKE GENERAL
•
According to the Law 27 year 2003 on Geothermal, there are 5 (five) stages in utilizing geothermal energy. The stages are preliminary survey, exploration, feasibility study, exploitation and utilization. The government could conduct two early stages, Preliminary surveys and exploration whereas private (business entity) could conduct all the five stages.
•
Geothermal activities are carried out in a Geothermal Working Area (GWA) which determined by the Minister. Following determination, GWA will be offered by the government or local governments within their authority through the tender mechanism.
•
The tender winner could initiate geothermal activities after obtaining Geothermal Businness Permit (IUP). This permit is granted by the Minister, Governor, Regent/Mayor according to their respective authorities. GEOTHERMAL BUSINESS STAGES
GEOTHERMAL DEVELOPMENT SUPPORT Higher growth in electricity demand
Great potential (28 GW) and spread almost in all over Indonesia (299 location). The Government have been issued crash program to accelerate 10.000 MW electricity generation which 49% derived from geothermal power plant (4,925 MW). National Energy Policy has targeted that in 2025 geothermal power plants will reach 9,500 MW. Oil price is becoming higher while the reserve is depleting Geothermal utilization can reduce CO2 emissions which caused greenhouse gas effect. The growing awareness of the importance in using clean and environmentally friendly energy Law No. 4/2009 on Mineral and Coal stated that in 2014 to bring mineral and raw materials outside the mining area are no no longer allowed, all material should be processed in the mining area . With the enactment of the Law, electricity demand will increase, which means more market opportunities.
Direktorat Jenderal EBTKE
Ministry of Energy and Mineral Resources Directorate General of New Renewable Energy and Energy Conservation
Policy and Geothermal Development Road Map of Geothermal Development 2006 – 2025 (based on Presidential Decree No. 5/2006 on National Energy Policy) 2006
2008
852 MW (Produksi)
2000 MW
1148 MW Existing WKP
2012
2016
2020
2025
3442 MW
4600 MW
6000 MW
9500 MW (Target)
1442 MW Existing WKP
1158 MW Existing WKP + New WKP
1341 MW Current Condition
1400 MW New WKP
3500 MW New WKP
12.000 MW Energy Vision 25/25
Direktorat Jenderal EBTKE
Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi Energi Kementerian Energi dan Sumber Daya Mineral
DEVELOPMENT PLAN GEOTHERMAL POWER GENERATION 2012 – 2025
Development Plan
ADDITIONAL CAPACITY (MW)
TOTAL CAPACITY DEVELOPMENT(MW)
Installed Capacity
Development (MW)
(MW)
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
37
1.226
115
3
225
435 1,015
300
425
535 1,110
247
130
175
40
160
1,341 1,344 1,569 2,004 3,019 3,319 3,744 4,279 5,389 5,636 5,766 5,941 5,981 6,141
L o c a t i o n Of Wayang Windu Position : Pangalengan - West Java Indonesia ± 40 km South of Bandung Elevation : +1700 meter above sea level Area
: 14,400 Ha 96 Ha (PTPN VIII) 21.54 Ha (Forestry)
Salak
Kamojang
Wayang Windu
Wayang Windu Power Station
Patuha
Darajat
Karaha Bodas
Ministry of Energy and Mineral Resources Directorate General of New Renewable Energy and Energy Conservation
Direktorat Jenderal EBTKE
Thank You
Go Green Indonesia ! green energy, future energy
MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA
DIRECTORATE GENERAL OF NEW, RENEWABLE ENERGY, AND ENERGY CONSERVATION Jalan Jenderal Gatot Subroto, Kav. 49 Jakarta 12950; Telp: 021-52904235; 5250575; Faks: 021-25529106; 25529212
Email:
[email protected] ;
[email protected]
www.ebtke.esdm.go.id