MUSHOLLA AN-NUR JL. Batas Barat Rt.005 / 010 Kel. Baru, Pasar Rebo Jakarta timur
RENOVASI MUSHOLLA AN-NUR 2008 – 2009 TAHAP II (PROPOSAL) Dokumen ini disiapkan dan diawasi oleh:
Panitia Renovasi Musholla An – Nur i
Daftar Isi Daftar Isi............................................................................................................................. ii Daftar Gambar .................................................................................................................. ii Daftar Tabel ...................................................................................................................... ii I. KONDISI SAMPAI DENGAN SAAT INI..................................................................... 1 I. 1. Kegiatan – kegiatan ............................................................................................. 2 I. 2. Laporan Keuangan .............................................................................................. 6 II. RENCANA PERENCANAAN TAHAP II ................................................................... 6 III. JADWAL PELAKSANAAN ........................................................................................ 8 IV. SANGAT DIHARAPKAN PARTISIPASI DAN DUKUNGAN DARI PARA DONATUR....................................................................................................................... 10 IV. 1. BENTUK SUMBANGAN / DONASI............................................................. 11 IV. 2. CARA PENYAMPAIAN SUMBANGAN....................................................... 11 V. PENUTUP................................................................................................................... 11 Lampiran.......................................................................................................................... 12 1. Salinan Surat Keterangan Pembukaan Rekening Renovasi .......................... 12 2. Kepanitiaan ............................................................................................................. 13 3. Kondisi Musholla & Gambar Rencana Teknis ................................................... 14 4. Gambar Rencana Teknis ...................................................................................... 16 5. Rencana Anggaran Biaya ..................................................................................... 17 6. Laporan Keuangan Terakhir................................................................................. 20 7. Salinan Sertifikat Wakaf ........................................................................................ 38
Daftar Gambar Gambar Gambar Gambar Gambar Gambar Gambar Gambar Gambar
1 Pembentukan Kepanitiaan................................................................................ 2 2 Persiapan tempat kerja untuk tukang............................................................... 3 3 Pembongkaran Mushalla lama......................................................................... 4 4 Kegiatan Pengecoran Lt II ............................................................................... 4 5 Status Pekerjaan per 11 Februari 2009 ........................................................... 5 6 Musholla An-Nur Sebelum Direnovasi........................................................... 14 7 Kegiatan Kerja Bakti Menjelang Romadhon 1429H/2008 M ........................ 14 8 Kondisi Pembangunan Musholla Saat ini ...................................................... 15
Daftar Tabel Tabel Tabel Tabel Tabel Tabel
1 Kondisi Keuangan Per Tgl 22 Januari 2009 ........................................................ 6 2 Sumbangan Material Per Tgl 22 Januari 2009.................................................... 6 3 Jadwal Pelaksanaan Pekerjaan............................................................................ 9 4 Rencana Anggaran Biaya ................................................................................... 17 5 Laporan Keuangan Tanggal 16 Februari 2009 ................................................. 20
ii
RENOVASI TAHAP II MUSHOLLA AN-NUR 2008 - 2009 RT 05/10 KEL. BARU, PASAR REBO, JAKARTA TIMUR (PROPOSAL)
Hanyalah yang memakmurkan masjid-masjid Allah ialah orang-orang yang beriman kepada Allah dan hari kemudian, serta tetap mendirikan sholat, menunaikan zakat dan tidak takut (kepada siapapun) selain kepada Allah, maka merekalah orang-orang yang diharapkan termasuk golongan orang-orang yang mendapat petunjuk. (QS. 9:18)
Ass. Wr. Wb.
Pembaca yang berbahagia, proposal ini akan berisi penjelasan ringkas tahap I renovasi Musholla An-Nur (http://mushollaannur.wordpress.com) . Setelah tahap I selesai dilaksanakan per tanggal 18 Januari 2009 yang lalu, selanjutnya dilaksanakan pekerjaan tahap II. Masih banyak beban dan pekerjaan yang harus diselesaikan. Oleh karenanya, sangat diharapkan bantuan dari pembaca sekalian untuk bersama – sama memikul tanggung jawab dalam syiar Agama ini. Mudah – mudahan proposal ini mampu memberikan gambaran mengenai beban dan tanggung jawab tersebut. Panitia tetap menerima saran dan sumbangsih yang lain demi perbaikan dan penyempurnaan kegiatan renovasi secara keseluruhan.
I. KONDISI SAMPAI DENGAN SAAT INI Secara resmi renovasi Musholla An-Nur telah dimulai tanggal 11 Nopember 2008 dengan dibentuknya kepanitiaan renovasi dan dimulainya pencarian dana renovasi.
1
I. 1.
Kegiatan – kegiatan Secara kronologis kegiatan – kegiatan yang telah dilakukan kurang lebih sebagai berikut: 1. Pembentukan Kepanitian, Dilaksanakan tanggal 11 Nopember 2008 yang lalu. Susunan kepanitian dapat dilihat pada lampiran dokumen proposal ini.
Gambar 1 Pembentukan Kepanitiaan 2. Pencarian Dana Secara resmi kegiatan pencarian dana dilaksanakan 2 minggu setelah kepanitaan
terbentuk.
Dengan
diselesaikannya
proposal
tahap
I,
perlengkapan kesekretariatan dan rekening bersama (joint account) yang menggunakan nama Ketua Panitia dan Bendahara
3. Persiapan Pekerjaan Dilaksanakan pada Hari Ahad 7 Desember 2008 yaitu dengan melakukan kerja bakti guna menyiapkan tempat kerja untuk tukang agar cuaca dan musim hujan tidak mengganggu aktivitas tukang.
2
Gambar 2 Persiapan tempat kerja untuk tukang 4. Pembongkaran Musholla lama Pembongkaran Musholla lama dilakukan dengan kerja bakti jamaah pada tanggal 21 Desember 2008. Selanjutnya tukang meneruskan pekerjaan menaikkan bata tembok lantai I dan persiapan infrastruktur pengecoran lantai dua.
3
Gambar 3 Pembongkaran Mushalla lama 5. Kegiatan Pengecoran Lantai II Sebagai pekerjaan akhir tahap I, dilakukan pengecoran dak lantai II. Kegiatan ini dilaksanakan pada tanggal 18 Januari 2009.
Gambar 4 Kegiatan Pengecoran Lt II
4
6. Kondisi Saat ini Sampai dengan saat ini (11 Februari 2009) penembokan lantai 2 sudah dilakukan. Demikian juga tiang penyangga kuda – kuda rangka atap telah selesai dicor. Tiang – tiang dak penyangga pengecoran telah dibongkar dan dirapikan
Gambar 5 Status Pekerjaan per 11 Februari 2009
5
I. 2.
Laporan Keuangan Kondisi dana dan laporan keungan secara ringkas dapat dijelaskan sebagai berikut: Tabel 1 Kondisi Keuangan Per Tgl 22 Januari 2009 No
Jumlah (Rp.)
Uraian
A
Dana Kas Musholla
20,000,000
B
Sumbangan/Donatur
68,345,000
D
Total (A+B)
88,345,000
E
Pengeluaran
65,896,000
F
Sisa saldo (D-E)
22,449,000
Diterima sumbangan material sebagai berikut: Tabel 2 Sumbangan Material Per Tgl 22 Januari 2009 No
Material
Satuan
Jumlah
1
Batu bata
buah
5,000
2
Pasir
truk
1
3
Split
truk
1
4
Semen
sak
58
5
Ember Ngecor
unit
10
Selengkapnya mengenai kondisi keuangan dan material dapat dilihat di lampiran proposal ini atau di situs renovasi Musholla http://mushollaannur.wordpress.com
II. RENCANA PERENCANAAN TAHAP II Setelah pengecoran lantai dilaksanakan, kegiatan berikutnya adalah melanjutkan pembuatan tembok lantai 2 yang sekarang sudah dimulai. Sampai dengan saat ini (3 Februari 2009) tembok lantai 2 semuanya sudah dibangun. Namun demikian,
6
untuk sementar kegiatan terpaksa dihentikan karena ketidakcukupan dana yang tersedia saat ini. Untuk sampai selesai, kegiatan yang harus dilakukan adalah : 1. Pengadaan dan pemasangan kuda – kuda, rangka atap dan genteng 2. Pengadaan dan pemasangan pintu, kusen dan angin – angin/ventilasi 3. Penyelesaian
pembangunan
tempat
wudhu,
peturasan
dan
perlengkapannya 4. Finishing, pekerjaan penyelesaian akhir berupa pengacian, pengecatan dan pagar.
Untuk keseluruhan pekerjaan tersebut, diperkirakan masih diperlukan dana sebesar Rp.93.937.656,- (Sembilan puluh tiga juta sembilan ratus tiga puluh tujuh ribu enam ratus lima puluh enam rupiah) dengan rincian sbagai berikut.
No
Komponene Biaya
I II III IV V VI
Material & Jasa Rangka - Atap Material & Jasa Pintu, Jendela dan Ventilasi Material Tempat Wudhu & Peturasan Material Pagar, Tangga Material Finishing Jasa Tukang & Kenek Pekerjaan III, IV, V Total Biaya Tak Teduga 2.5 % Total Estimasi Biaya
Estimasi Biaya (Rp.) 22,411,694 19,395,700 1,685,500 17,143,600 10,850,000 20,160,000 91,646,494 2,291,162.3 93,937,656
Selanjutnya rincian anggaran biaya tersebut disertakan dalam lampiran.
Sumber Dana Dalam pembangunan tahap II musholla An Nur ini, panitia mengandalkan sumber dana dari: 1. Sisa saldo renovasi tahap I Sisa saldo pembangunan tahap I sebesar Rp. 5.000.000,- (Lima puluh juta rupiah) 2. Sumbangan dari Jamaah/Pengurus Panitia terus mengupayakan agar diperoleh sumbangan dana / material dari para jamaah sekitar, penguru, maupun panitia. 3. Donatur dan sumber – sumber dana yang lain
7
Mengingat biaya yang diperlukan masih culup besar, maka panita dan jamaah Musholla sangat mengharapkan bantuan dan dukungan dari para donatur. Selain pengajuan proposal, panitia juga mengunakan model yang lain seperti penjualan kupon sumbangan yang nilai nominalnya Rp. 10.000,- per kupon. Donatur juga dapat memberikan sumbangan dananya dengan mengisi kotak amal yang disediakan di teras musholla.
Kondisi keuangan terakhir disertakan dalam lampiran dokumen proposal ini.
Dengan kondisi keuangan saat ini, maka dengan terpaksa pembangunan fisik sementara akan dihentikan. Panita akan fokus untuk mencari dana sehingga mencukupi batas minimal untuk melaksanakan pekerjaan (minimal pekerjaan rangka atap dan genteng). Sementara agar tidak terjadi rembesan saat hujan, atap akan ditutup dengan terpal. Meskipun demikian, pekerjaan – pekerjaan untuk merapikan lantai bawah tetap dilanjutkan sehingga musholla dapat segera difungsikan kembali minimal untuk keperluan dasar yaitu shalat berjamaah.
III. JADWAL PELAKSANAAN Mengingat keterbatasan dana yang tersedia saat ini, maka pembangunan fisik akan dilanjutkan jika dana yang tersedia sudah mencukupi untuk pekerjaan utama yaitu pengerjaan rangka atap dan genteng.
8
Tabel 3 Jadwal Pelaksanaan Pekerjaan Bulan/Minggu
No I I.1 I.2 II II.1 II.2 II.3 II.4 III
Kegiatan
Feb-09 141Feb Mar
Mar-09 1631Mar Mar
Apr-09 1530Apr Apr
May-09 1530May May
Jun-09 1429Jun Jun
Jul-09 1429Jul Jul
Aug-09 1328Aug Aug
Pencarian Dana Pencarian Dana Tahap Rangka Atap Pencarian Dana Pekerjaan Lainnya Pekerjaan Tahap II Rangka Atap + Genting Tempat Wudlu Pintu, Jendela, Ventilasi Pagar & Finishing Peresmian, Penggunaan Pertama Ramadhan 1430H
9
IV. SANGAT DIHARAPKAN PARTISIPASI DAN DUKUNGAN DARI PARA DONATUR Sudah kita pahami bersama bahwa kegiatan dakwah dan syiar Islam merupakan fardu ‘ain yang menjadi kewajiban setiap individu muslim. Kegiatan syiar dan dakwah tersebut tentu saja disesuaikan dengan kemampuan dan keahlian masing – masing individu tiap muslim. Masing – masing individu dapat mengambi peran yang berbeda satu sama lain namun dengan tetap mengacu kepada satu tujuan bersama yaitu demi kemajuan bersama ummat muslim dalam beribadah, baik ibadah yang bersifat ritual maupun amaliah.
Dengan pemahaman demikian, maka kami panitia renovasi dan pengurus Musholla An Nur mengharapkan partisipasi dan dukungan Bapak / Ibu sekalian dalam mendukung pengembangan Musholla An Nur. Dalam hal ini dukungan yang kami harapkan adalah berupa sumbangan material pembangunann baik berupa dana maupun bahan material yang dibutuhkan dengan tetap diharapkan do’a dan dukungan moral lainnya. Panitia dan pengurus menyadari bahwa yang paling berkepentingan terhadap Musholla tersebut adalah masyarakat sekitar. Oleh karena itu, tahap pertama dan prioritas utama target pengumpulan dana tersebut adalah jamaah dan masyarakat sekitar. Namun dikarenakan kebutuhan dana yang cukup besar dan di sisi lain kemampuan jamaah dan masyarakat sekitar yang terbatas, maka dirasakan perlu untuk memperluas target sumber dana (donasi) di luar jamaah dan masyarakat sekeliling. Oleh karena itulah, maka proposal dan permohonan dana ini sampai ke tangan Bapak / Ibu yang terhormat.
10
IV. 1. BENTUK SUMBANGAN / DONASI Panitia menerima donasi/sumbangan berupa 1. Dana / uang 2. Bahan / material bangunan yang diperlukan. Dengan catatan, jika material yang kami terima ternyata melebihi kebutuhan maka bahan / material tersebut akan kami lelang dengan tetap memberikan laporan kepada semua donator.
IV. 2. CARA PENYAMPAIAN SUMBANGAN 1. Dana / uang
Donator dapat memberikan sumbangan dana dengan cara ditransfer ke rekening panita renovasi Bank Mandiri Capem Pasar Rebo a.n. a.n. : Sujarot & Mujiono No.: 129-00-0680336-1
Untuk wilayah Jabotabek, panita dapat mengambil ke tempat yang telah ditentukan oleh donator
2. Bahan / material bangunan
Donator dapat menyampaikan sumbangan tersebut ke alamat : Musholla An Nur, Jl. Batas Barat, RT 05/10 Kel. Baru, Pasar Rebo, Jakarta Timur
Panita dapat mengambil ke tempat yang telah ditentukan oleh donator, dengan catatan lokasi di area Jabodetabek
V. PENUTUP Tidak ada niat lain dari pembuatan dan penyampaian proposal ini Insyaallah semata untuk mencari keridlaan Allah S.W.T dengan jalan menyediakan fasilitas ibadah baik ritual maupun amaliah bagi ummat Islam di lingkungan Kelurahan Baru khususnya maupun
ummat
Islam
secara
keseluruhan
pada
umumnya.
Kami,
panitia
pengembangan, pengurus Musholla, maupun jamaah mengucapkan terima kasih yang setulusnya atas dukungan material maupun moral dari Bapak/Ibu sekalian, disertai do’a Mudah – mudahan Allah S.W.T meridhai dan menerima segala amal ibadah yang kita lakukan.
Panita pembangunan menerima segala sumbang saran, maupun komentar guna kemajuan dan kejayaan syiar Islam. Saran tersebut dapat disampaikan kepada panitia melalui berbagai saluran, antara lain : 1. Musholla An Nur, Jl. Batas Barat RT 05/10 Kel. Baru, Pasar Rebo, Jakarta Timur
11
2. Kontak person masing – masing anggota panitia seperti pada lampiran Kepanitiaan 3. Email melalui email address :
[email protected],
[email protected] 4. Blog pengembangan musholla di http://mushollaannur.wordpress.com
Lampiran 1. Salinan Surat Keterangan Pembukaan Rekening Renovasi
12
2. Kepanitiaan MUSHOLLA AN-NUR JL. Batas Barat Rt.005 / 010 Kel. Baru, Pasar Rebo Jakarta timur PENGEMBANGAN & RENOVASI MUSHOLLA 2008 – 2009
SUSUNAN KEPANITIAN
PENASEHAT
: 1.
H. M. ISHAQ
2.
H.SUNGKONO
3. 4.
KAPTEN RASMIN SUGIMAN / KETUA RT.005
5.
H. BAMBANG,SE.
KETUA
:
Ir. MUJIONO, M.T
WAKIL KETUA
:
MUJI SANTOSO
SEKRETARIS
:
MISWAN, S.Ag.
WAKIL SEKRETARIS
:
AGUS SUTEJO
PENGAWAS KEUANGAN
:
MUKTY ROSYID,S.Pd
BENDAHARA
:
SUJAROT
KORD. DANA ANGGOTA
PENGAWAS BANGUNAN SEKSI PERLENGKAPAN
ANDI FAIZAL 1.
KEMIN SUSENO
2.
REMAJA MUSHOLLA
:
Ir. SUNGKONO
: 1.
IVAN SANTOSO
2.
MARALI
087878134119 08161308754 087709688/ 02168608642
081510109832 081314789915 081310433729 081905271036 081398054499 081546055665 08128506858
081389918 081310920087 0218728753
13
3. Kondisi Musholla & Gambar Rencana Teknis
Gambar 6 Musholla An-Nur Sebelum Direnovasi
Gambar 7 Kegiatan Kerja Bakti Menjelang Romadhon 1429H/2008 M
14
Gambar 8 Kondisi Pembangunan Musholla Saat ini
15
4. Gambar Rencana Teknis
16
5. Rencana Anggaran Biaya
PENGEMBANGAN & RENOVASI MUSHOLLA 2008 – 2009 RENCANA ANGGARAN BIAYA TAHAP II Tabel 4 Rencana Anggaran Biaya
MUSHOLLA AN-NUR JL. Batas Barat Rt.005 / 010 Kel. Baru, Pasar Rebo Jakarta timur PENGEMBANGAN & RENOVASI MUSHOLLA 2008 – 2009 RENCANA ANGGARAN BIAYA TAHAP II
NO
JENIS PEKERJAAN
VOL
SATUAN
HARGA SAT. (Rp.)
JUMLAH (Rp)
Material & Jasa Rangka Atap
I 1
Rangka Atap Baja Ringan 8M x 17 M
2
Genteng Morando
3
Gipsum Plafon bawah
Total (Rp)
22,411,693.99 96
M2
130,000.00
12,480,000.00
2,500
BH
2,500.00
6,250,000.00
33
Lembar
55,000.00
1,803,278.69
34
Lembar
55,000.00
1,878,415.30
3
M3
2,160,000.00
6,480,000.00
2.928 4
Gipsum Plafon Atas 2.928
5
II
Kaya Plafon 2.928 Material & Jasa Pintu, Jendela dan Ventilasi
19,395,700.00
1
Pintu Alumunium Keliling 3 buah x (2.2+2) *2 2 buah x (2.1 + 2) * 2
41.60
M
80,000.00
3,328,000.00
2
Jendela Alumunium Keliling 8 buah x (1.5+0.5) *2 14 buah x (0.9 + 1.5) * 2
99.20
M
80,000.00
7,936,000.00
3
Ventilasi Alumunium Keliling 47 buah x (0.4+0.3) * 2
65.80
M
80,000.00
5,264,000.00
17
NO
JENIS PEKERJAAN
VOL
SATUAN
HARGA SAT. (Rp.)
JUMLAH (Rp)
4
Kaca Pintu 3 buah x (2.2x2) 2 buah x (2.1x 2)
21.60
M2
55,000.00
1,188,000.00
5
Kaca Jendela 8 buah x (1.5x0.5) 14 buah x (0.9 x1.5)
24.90
M2
55,000.00
1,369,500.00
6
Kaca Ventilasi 47 buah x (0.4x0.3)
5.64
M2
55,000.00
310,200.00
III
Material Tempat Wudhu & Peturasan
Total (Rp)
1,685,500.00
1
Pipa Paralon 1/2 inch
10.00
Pcs
16,000.00
160,000.00
2
Pipa Paralon 3/4 inch
5.00
Pcs
25,000.00
125,000.00
3
Pipa Paralon 3 inch wavin
3.00
Pcs
55,000.00
165,000.00
4
Knee 3 inch
3.00
Pcs
3,500.00
10,500.00
5
Knee 3/4 inch
5.00
Pcs
3,000.00
15,000.00
6
Knee 1/2 inch
10.00
Pcs
3,000.00
30,000.00
7
Kran Air
10.00
BH
25,000.00
250,000.00
8
Tangki Air 500 l
1.00
BH
700,000.00
700,000.00
9
Stop Kran
1.00
BH
50,000.00
50,000.00
10
Radar Air Otomatis
1.00
SET
80,000.00
80,000.00
11
Lain - lain (lem, solasi, dll)
1.00
LS
100,000.00
100,000.00
IV 1
Material Pagar, Tangga Tangga Luar
17,143,600.00
a
Batu Bata
640.00
BH
340.00
217,600.00
b
Besi Pagar (7 +14 ) M * 0.8 M
12.00
M
350,000.00
4,200,000.00
18
NO 2
JENIS PEKERJAAN
SATUAN
JUMLAH (Rp)
1,400.00
BH
340.00
476,000.00
35.00
M
350,000.00
12,250,000.00
Batu Bata (7 +14 +14) M * 0.8 M
b
Besi Pagar
Material Finishing
10,850,000.00
1
Cat
5.00
FIL
350,000.00
1,750,000.00
2
Aquaprof
1.00
FIL
850,000.00
850,000.00
3
Semen
125.00
SACK
54,000.00
6,750,000.00
4
Amplas, Peralatan lain - lain
1.00
LS
1,500,000.00
1,500,000.00
VI
Total (Rp)
Pagar Balkon 2 * 2 * 2 * 1/2
a
V
HARGA SAT. (Rp.)
VOL
Jasa Tukang & Kenek Pekerjaan III, IV, V
20,160,000.00
1
Tukang 2 org x 3 bulan x 6 hari x 4 minggu
144.00
OH
65,000.00
9,360,000.00
2
Kenek 3 org x 3 bulan x 6 hari x 4 minggu
216.00
OH
50,000.00
10,800,000.00
JUMLAH BIAYA TAK TERDUGA
TOTAL BIAYA
91,646,493.99 2.50%
2,291,162.35
93,937,656.34
19
6.
Laporan Keuangan Terakhir Laporan Keuangan Tanggal 16 Februari 2009 Tabel 5 Laporan Keuangan Tanggal 16 Februari 2009
Penerimaan (Rp.) No 1 2 3 4 5 6
Tanggal 09-Nov08 09-Nov08 09-Nov08 09-Nov08 11-Nov08 11-Nov08
Uraian Saldo Awal Kas Musholla H. Kusnan (RT. 7)
Pengeluaran(Rp.) Debet
Tanggal 09-Nov-08
20,000,000
8 9 10 11
17-Nov08 17-Nov08 17-Nov08 17-Nov08 23-Nov-
Kredit 1,000,000
Saldo (Rp.) 19,000,000
5,000,000
24,000,000
500,000
24,500,000
200,000
24,700,000
P Helmi (Kel. Kalisari) P Muji Santoso (RT 7) P Mujiono (Kel. Kalisari) P M Rasyid (RT 7 )
1,500,000 1,000,000
26,200,000 11-Nov-08
Biaya Meterai
14-Nov-08
Papan Pengumuman & Kotak amal Spanduk & Photo Copy Ongkos bongkar bata
16-Nov-08 7
Uraian Pengeluaran Keskretariatan
H. Madil (Kalisari)
17-Nov-08 50,000
Sdr. Rizal Pondok Gede Sdri. Martha (Bengkulu) P Lukman (RT 7) P Mochdar (Kel. Kalisari)
20,000
27,180,000
400,000
26,780,000
250,000
26,530,000
100,000
26,480,000
100,000
26,580,000
50,000
26,630,000
50,000 500,000
26,680,000
20
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
08 23-Nov08 23-Nov08 25-Nov08 25-Nov08 25-Nov08 25-Nov08 25-Nov08 25-Nov08 27-Nov08 27-Nov08 29-Nov08 30-Nov08 30-Nov08 30-Nov08 30-Nov08 30-Nov08
27,180,000 P Sugimin (RT 7)
500,000
27,680,000
1,000,000
28,680,000
1,000,000
29,680,000
200,000
29,880,000
100,000
29,980,000
3,000,000
32,980,000
200,000
33,180,000
100,000
33,280,000
200,000
33,480,000
100,000
33,580,000
250,000
33,830,000
150,000
33,980,000
100,000
34,080,000
150,000
34,230,000
100,000
34,330,000
500,000
34,830,000
P Surya Saputra (RT 7) P Endang Rachman (RT 7) P Agus Sutejo (RT 7) Ibu Endang Susilowati (Kebon Pala) P Rasmin (RT 5) P Kemin (RT 7) P Ivan Santoso (RT 7) Bp. Sujarot Bp. Beno Salinas (Bekasi) Bp. Wartam Bp Ribut Bp. Suparjan Bp. Ishak Bp. M Adhi Kurnia Bp. Sigit (Kalisari)
Total
36,600,000
1,770,000
34,830,000
21
LAPORAN KEUANGAN 28 Desember 2008 Penerimaan (Rp.) No 27
Tanggal 01-Dec-08
28
01-Dec-08
Uraian Saldo Awal bulan Desember Bp. Harsono, Kalisari
29
04-Dec-08
Bp. Ivan Santoso
30
05-Dec-08
Bp. Agus Sudarta, RT 5
31
05-Dec-08
Bp. H. Hubri
32
05-Dec-08
33
05-Dec-08
Bp. Irdiantoro Susanto, Bekasi Bp. Widodo, Kalisari
34
06-Dec-08
Bp. Misbach, Kalisari
35
06-Dec-08
Bp. Suparno, RT 7
36
06-Dec-08
Bp. Siswoyo, Pembina
37
07-Dec-08
Bp. H. Hasan, RT 5
38
07-Dec-08
Bp. Hanafi Zain, RT 5
39
08-Dec-08
Bp. Sukarsa, Dekel
40
08-Dec-08
Bp. Endang Rachman
41
08-Dec-08
Bp. Soni A., Bintaro
Pengeluaran(Rp.) Debet
Tanggal
Uraian
36,600,000
Kredit 1,770,000
Saldo (Rp.) 34,830,000
100,000
34,930,000
500,000
35,430,000
300,000
35,730,000
400,000
36,130,000
500,000
36,630,000
1,500,000
50,000
06-Dec08
Ongkos Bongkar Batu Bata
38,130,000
100,000
38,080,000
50,000
38,130,000
50,000
38,180,000
500,000
38,680,000
500,000
39,180,000
500,000
39,680,000
300,000 1,000,000
39,980,000
22
40,980,000 42
08-Dec-08
Bp. Maksum, Bintaro
43
10-Dec-08
Bp. Harry Fitri, Jakarta
44
10-Dec-08
Ibu Suminah, Bekasi
45
10-Dec-08
Bp. Budi Siswanto, RT 7
46
10-Dec-08
47
10-Dec-08
Hasil Penjualan Kupon, Kurban Kupon Karyawan TMIN
48
12-Dec-08
49
13/12/2008
Bp. Apik Paksa Driya, Bandung Bp. Thony Lordian
1,000,000
41,980,000
500,000
42,480,000
250,000
42,730,000
500,000
43,230,000
120,000
43,350,000
1,500,000
44,850,000
100,000
44,950,000
100,000
50
51
13-Dec-08
52
13-Dec-08
53
13-Dec-08
Ibu Nani Kurnia/Ibu Pono Saweran ibu -2 majlis ta'lim An Nur Sri Kustiono
54
13-Dec-08
Bu Sumarsono RT 03/02
55
13-Dec-08
Bp Sugiman RT 05
56
13-Dec-08
Bp. Tomo
57
13-Dec-08
Bu Rajina RT 07
58
15-Dec-08
Bu Andi E Sutarto
14-Dec08
Pengeluaran Biaya Kerja Bakti
45,050,000
40,000
45,010,000
300,000
45,310,000
300,000
45,610,000
50,000
45,660,000
150,000
45,810,000
300,000
46,110,000
100,000
46,210,000
50,000 1,000,000
15-Dec08
46,260,000
Pasir 1 truk 1,200,000
46,060,000
23
Cakar Ayam 10 bh Benang
59
16-Dec-08
Bp, Namri RT 07 50,000
16-Dec08 17-Dec08
Ongkos bongkar pasir Besi 12 inch 12 btg Pahat Beton Pacul Buku 1 bh
550,000 4,000
45,506,000
20,000
45,486,000
1,200,000
44,336,000
24,000
44,312,000
32,000
44,280,000
10,000
44,270,000
2,000
44,268,000
6,000
44,262,000
160,000
44,302,000
350,000
44,002,000
40,000
43,962,000
26,000
43,936,000
24,000
43,912,000
350,000
43,562,000
540,000
43,022,000
30,000
42,992,000
23,000
42,969,000
Pulpen Spidol 60
18-Dec-08
Bp. Widodo, RT 08
61
18-Dec-08
Bp. Suroto (TMMIN, Jakarta)
200,000 50,000
18-Dec08
Besi 6 inch 10 btg Besi 10 inch 10 btg Kawat bendrad 2 kg mata gergaji besi 2 bh gegep 2 bh split 2 colt semen 10 sak ember 6 buah kunci besi
45,510,000
24
batu kali 1 colt palu 1 bh pensil 1 62
19-Dec-08
63
19-Dec-08
64
20-Dec-08
Penjualan Kupon @ 50000 Penjualan Kupon @ 50000
Majlis Taklim Al Muttaqin
135,000
19-Dec08
50,000
200,000
20-Dec08
Besi 10 inch 10 btg Papan cor 10 bh Paku 5 cm 1 kg Semen 15 sak Besi 12 inch 30 btg Besi 6 inch 20 btg Kawat ayakan Triplek 9 mm 2 bh Paku 7 cm 1 kg Besi ring 12 inch Paralon 3 inch 1 bh Kne 3 inch 2 bh Lem Paralon 1 bh Pasir 2 truk Ongkos bongkar pasir
160,000
42,809,000
15,000
42,794,000
1,000
42,793,000
450,000
42,478,000
120,000
42,408,000
16,000
42,392,000
810,000
41,582,000
1,800,000
39,982,000
320,000
39,662,000
20,000
39,642,000
190,000
39,452,000
16,000
39,436,000
120,000
39,316,000
65,000
39,251,000
30,000
39,221,000
6,000
39,215,000
2,400,000
36,815,000
50,000
36,765,000
25
65
21-Dec-08
Bp. Kastono
66
22-Dec-08
Bp. Eko RT 06
67
22-Dec-08
Hamba Allah
68
22-Dec-08
Ibu Rusli Cijantung
69
22-Dec-08
Bp. Sudaya RT 07
70
22-Dec-08
Bp. H Joni, Bekasi
71
22-Dec-08
Bp. Johan
72
22-Dec-08
Bp. Tomo, Kalisari
73
23-Dec-08
Bp. Samsuhadi
74
23-Dec-08
Bp. Kamsudi, SMK 22
75
23-Dec-08
Bp. Muslim, SMK 22
76
23-Dec-08
Bp. Utin, SMK 22
77
23-Dec-08
78
24-Dec-08
Bp. Win Kusdiatmono RT 4 H. Lukman
79
24-Dec-08
Hamba Allah
21-Dec08 500,000 200,000
22-Dec08
1,000,000 100,000
1,000,000
Ongkos Tukang + Kenek Pengeluaran Biaya Kerja Bakti Besi 8 inch 30 btg Kawat bendrad 5 kg Besi ring 21 bh Ongkos Bongkar Batu Bata
1,180,000
35,585,000
100,000
35,985,000
990,000
35,195,000
90,000
36,105,000
71,000
36,134,000
30,000
37,104,000
100,000
37,204,000
300,000
37,504,000
200,000 500,000
23-Dec08
500,000 200,000 200,000
Pulsa Operasional Papan cor 20 bh Paku 10 cm 2 kg Paku 7 cm 2 kg
37,704,000 100,000
38,104,000
190,000
38,414,000
36,000
38,578,000
36,000
38,742,000
500,000
39,242,000
100,000
39,342,000
200,000
39,542,000 25-Dec-
Semen 10
540,000
26
08 80
26-Dec-08
Lelang Genteng
81
26-Dec-08
Hj Tammah
82
26-Dec-08
Bp. Wahyu Hidayat, PT. Mahatetra
83
27-Dec-08
Hamba Allah
84
27-Dec-08
Hamba Allah
550,000
26-Dec08
Kaso 1 kubik
150,000 500,000
300,000
27-Dec08
5,000,000
27-Dec08
85
28-Dec-08
Bp. Dody RT 7
86
28-Dec-08
Ibu Mardhani
50,000 60,000
sak benang 2 buah Paku 4 kg
28-Dec08 29-Dec08
Kaso balok 10 btg Papan Cor 100 lbr Ongkos Tukang gegep 2 bh Kaso 4x6 1/2 kubik Besi 10 inch 100 btg Kayu balok 10 btg Besi 12 inch 100 btg Papan 3 lbr
39,002,000 4,000
38,998,000
64,000
39,484,000
2,160,000
37,474,000
640,000
37,334,000
900,000
36,434,000
2,055,000
34,679,000
24,000
39,655,000
1,080,000
38,575,000
4,300,000
34,275,000
640,000
33,635,000
6,000,000
27,635,000
135,000
27,550,000 27,610,000
Papan 6 lbr Kaso 4x6 1/2 kubik Paku 7 cm 5 kg Triplek 8 ml 5 lbr
270,000
27,340,000
1,080,000
26,260,000
80,000
26,180,000
475,000
25,705,000
27
87
30-Dec-08
Bp. Parjan, RT 7
88
31-Dec-08
Bp. Tata Mulyana, RT 7
200,000 300,000
Total
30-Dec08 31-Dec08
Triplek 6 mm 20 lbr Paku 4 xm 1 kg Photo Copy+lakban Paku 5 cm 4 kg Kaso 4x6 1 kubik
62,565,000
1,300,000
24,405,000
16,000
24,389,000
100,000
24,489,000
64,000
24,725,000
2,160,000
22,565,000
40,000,000
22,565,000
LAPORAN KEUANGAN 22Januari 2009 Penerimaan (Rp.) No 88 89
Tanggal 01/01/09 01/01/09
90
02/01/09
91
02/01/09
92
04/01/09
93
04/01/09
Uraian Saldo Awal bulan Januari Bp. Bambang RT 5
Bp. Wasiran, RT 7 Bp. Sarto, RW 9 Bp. Hari Winarko Bp. Juminianto, Kalisari
Pengeluaran(Rp.) Debet
Tanggal
Uraian
62,565,000 2,500,000
01-Jan09
110,000
02-Jan09
1,000,000 03-Jan09 300,000 100,000
04-Jan09
Papan Cor 75 lbr Paku 7 cm 3 kg Kaso 4x6 1kubik Paku 7 cm 3 kg Ongkos Tukang+Kenek Paku 7
Kredit
Saldo (Rp.)
40,000,000
22,565,000
675,000
24,390,000
48,000
24,342,000
2,160,000
22,292,000
48,000
23,244,000
1,895,000
21,649,000
48,000
21,701,000
28
94 95
04/01/09 05/01/09
96
06/01/09
97
06/01/09
98
06/01/09
99
07/01/09
Penjualan Kupon Penjualan Kupon
Bp. Sungkono, RT 7 Bp. Arifin Junaedi, Kalisari Bp. Mujiono, Kalisari
Alm. Ibu Maryanah
Paku 4 cm 360,000
Cakar Ayam
650,000
500,000 1,000,000
04-Jan09 05-Jan08
Triplek 6 mm 30 lmbar Bambu Bagesting, 30 unit Rokok Kerja Bakti Paku 5 cm
48,000
22,013,000
116,000
22,547,000
1,320,000
21,227,000
285,000
20,942,000
100,000
20,842,000
48,000
21,294,000
48,000
22,246,000
75,000
22,271,000
24,000
22,247,000
81,000
22,366,000
64,000
22,302,000
280,000
22,022,000
625,000
21,397,000
396,000
21,001,000
1,380,000
19,621,000
90,000
19,531,000
Paku 7 cm
100,000
06-Jan09
Konsumsi Lembur Lampu Neon 2
200,000
07-Jan09
Konsumsi Lembur Kawat Bendrad Kaso 4 x 6 2 ikat Kaso 4 x 6 5 ikat Triplek 6 mm 6 lmbar Besi 12 inch, 23 btg Kawat Bendrad Meteran 2
19,505,000
29
buah 100 101
08/01/09 08/01/09
102
09/01/09
103
09/01/09
Bp. Hernowo, Vietnam Hamba Allah, Austria
Pendapatan Kotak Amal Bp. Sungedi (RT 7)
2,000,000
08-Jan09
4,500,000
1,700,000 09-Jan09 100,000
Potokopi Proposal Kawat Bendrad Papan Cor 15 lbr Kaso 4 x 6, 5 ikat Paku 7 cm, 2 kg Ongkos Tukang+Kenek
26,000 100,000
21,405,000
54,000
25,851,000
135,000
25,716,000
625,000
25,091,000
32,000
26,759,000
2,780,000
24,079,000
135,000
23,944,000
860,000
23,084,000
32,000
23,052,000
54,000
22,998,000
500,000
22,498,000
120,000
22,378,000
48,000
22,330,000
5,000
22,325,000
375,000
21,950,000
25,000
21,925,000
Papan Cor 15 lbr Besi 10 inch, 20 btg Paku 7 cm, 2 kg Kawat Bendrad Kaso 4 x 6, 4 ikat Reng 1 ikat Paku 5 cm, 3 kg Test pen 10-Jan09 10-Jan09
Kaso 4 x 6, 3 ikat Gembok
30
104
11/01/09
Bu Eni,
Reng 3 x 4, 2 ikat Paku 7cm, 2kg
100,000 105
11/01/09
H. Didi, RT 4 100,000
Paku 5 cm, 1 kg Besi 10 inch, 10 btg Triplek 6 mm, 1 lbr Besi 10 inch, 5 btg Kawat bendrard, 3 kg 14-Jan09
250,000
21,775,000
32,000
21,843,000
16,000
21,827,000
430,000
21,397,000
66,000
21,331,000
215,000
21,116,000
54,000
21,062,000
250,000
20,812,000
32,000
20,780,000
5,000
20,775,000
32,000
20,743,000
150,000
20,593,000
84,000
20,509,000
4,320,000
16,189,000
1,200,000
15,089,000
50,000
15,139,000
250,000
14,919,000
Reng 2 ikay Paku 7cm 2 kg Benang Paku 7cm 2 kg Ember Cor 30 bh Pengki, 12 bh
106
17/01/09
Bp. Suwanto
107
17/01/09
Gongseng Motor
108
17/01/09
Hamba Allah
100,000
100,000 30,000
14-Jan09 17-Jan09
17-Jan09
Semen 80 sck Pasir 1 Truk Ongkos bongkar material Cetak Kupon 40 pcs
31
109
17/01/09
Hamba Allah, Cimanggis H. Komarudin Bp. Misbach Bp. Rasmin Kupon Karyawan Toyota Penjualan Kusen Bp. Machbul, RT 4 Bp. Drs. Yanto SMK 22
110 111 112 113
17/01/09 17/01/09 17/01/09 17/01/09
114
17/01/09
115
18/01/09
116
18/01/09
117
18/01/09
118
18/01/09
119
18/01/09
Ibu Herni Sp.d, SMK 22
120
18/01/09
121
18/01/09
122
18/01/09
123
18/01/09
Bp. Drs. Eko Suryono, SMK 22 Bp. Sutarmo, RT 4 Bp. Letkol H. Sukabi Bp. Anang, RT 7
3,000,000 500,000 50,000 1,000,000
17,919,000 18,419,000 18,469,000 19,469,000
480,000
19,949,000
300,000
20,249,000
500,000
18-Jan09
1,000,000 Bp. Suwito, RT 4 Penjualan Kupon
Kerja Bakti, rokok Ongkos bongkar material Sewa Molen+ Operator
500,000
150,000
20,749,000
Ongkos Tukang+Kenek
50,000
1,850,000
19,899,000
227,000
20,172,000
40,000
20,282,000
300,000
20,032,000
1,200,000
18,882,000
1,200,000
17,982,000
86,000
18,096,000
700,000
17,446,000
860,000
16,586,000
16,000
16,570,000
Pasir 1 Truk 50,000 Split 1 Truk 300,000
Besi 10 inch, 2 btg Split 1 colt
200,000 50,000
20-Jan09
Besi 20 btg Paku 5 cm 1 kg
32
Besi 12 inch 10 Kawat bendrad 2kg besi 8 inch 5btg Lot 1 bh Kwt bendrad 2kg Kaso 4 x 6 4 btg reng 5 btg
124
21/01/08
Bp. Juhaeni
125
21/01/09
Hamba Allah
126 127 128
21/01/09 21/01/09 23/01/09
H. Herman Cs Bp. Sukamto BKM Toyota Sunter
500,000 150,000 500,000 1,000,000
21-Jan09
23-Jan09
300,000 23-Jan09 25-Jan09 129
26/01/09
130
26/01/09
Bp. Sarbandiyanto, RT 4 Bp. Wasiran,
500,000 150,000
paku campur 1kg Paku 7 cm 2 kg Bata Merah, 500 pcs Uang rokok bongkar
Ongkos Tukang + Kenek Biaya Kuli Material Bambu Steger
600,000
15,970,000
36,000
15,934,000
165,000
15,769,000
10,000
15,759,000
36,000
15,723,000
88,000
15,635,000
60,000
15,575,000
16,000
15,559,000
32,000
15,527,000
1,500,000
14,527,000
65,000
14,612,000 15,112,000 16,112,000
1,000,000
15,412,000
100,000
15,312,000
54,000
15,258,000 15,758,000 15,908,000
33
131 132
26/01/09 26/01/09
133
26/01/09
134
26/01/09
135 136
26/01/09 27/01/09
RT 6/ 10 Hamba Allah Bp. Kamsudi, SMK 22 Ibu Ema, Kalisari Bp. Hendra, RT 4 Hamba Allah Bp. Hj Ali bin Abdul Halim, Kuningan
130,000
16,038,000
70,000
16,108,000
100,000
16,208,000
500,000 100,000
16,708,000 16,808,000
1,000,000
26-Jan09
Besi 10inch 8 btg Kawat bendrad 1 kg
17,808,000 264,000
17,544,000
18,000
17,526,000
140,000
17,386,000
180,000
17,206,000
20,000
17,186,000
132,000
17,054,000
20,000
17,234,000
270,000
17,554,000
Cincin 2 ikat
27-Jan09
137
28/01/09
138
29/01/09
139
30/01/09
Bp. Hari Murtijo, Jakarta Penjualan Kupon Kotak Amal Keliling RT 7
28-Jan09
papan cor 20 lbr Kwt ayakan Glass box 8 bh Biaya bongkar pasir
200,000 Semen 5 sak 590,000 940,000
18,494,000 29-Jan09
Besi 8 inch 10 btg besi 10 inch 20 btg
330,000
18,164,000
860,000
17,304,000
34
30-Jan09
140
31/01/09
Hj. Abdul Rachim
31-Jan09 1,000,000 31-Jan09
Total
No 1 2 3 4 5 6 7 8 9
Nama Donatur
besi 12inch 10btg Paku 7 cm
CV. Ba Ta Tsa Bp. H Sungkono Bp. H Sungkono Bp. H Akhmad Khozin Ucok Warung, Kalisari Material Yasmin Kalisari Material Yasmin Kalisari Hamba Allah Sahrudin
Material
Satuan
16,704,000
32,000
16,672,000
16,000
16,656,000 16,656,000
1,625,000
16,031,000
270,000
15,761,000
78,214,000
15,761,000
Paku 5 cm 1 kg Ongkos Tukang + Kenek Semen 5 sak
93,975,000
Nama Donatur
600,000
Jumlah
No
Material
Batu bata Split Pasir
truk truk
5,000 1 1
1 3 2
Batu bata Split Pasir
Pasir Semen Semen Ember Ngecor Semen Semen
truk sak sak unit sak sak
1 10 4 10 5 20
3 4 5
Split Semen Ember Ngecor
LAPORAN KEUANGAN 12 Februari 2009 Penerimaan (Rp.) No 88
Tanggal 01-Feb09
Uraian Saldo Awal bulan Januari
Pengeluaran(Rp.) Debet 93,975,000
Tanggal
Uraian
Kredit 78,214,000
Saldo (Rp.) 15,761,000
35
03-Feb-09
Besi 10inch 20btg Paku 7 cm 2kg paku 5 cm 2kg kawat bendrad 2 kg
89
05-Feb09
Penjualan Kupon
04-Feb-09
Mata gergaji 1 pcs Glass box 8 bh
05-Feb-09
Paku 7cm 1 kg
30,000
860,000
14,901,000
32,000
14,869,000
32,000
14,837,000
32,000
14,805,000
13,000
14,792,000
120,000
14,672,000
16,000
14,686,000
16,000
14,670,000
430,000
14,240,000
430,000
13,810,000
13,000
13,797,000
70,000
13,727,000
1,415,000
12,312,000
265,000
12,047,000
270,000
11,777,000
1,200,000
10,577,000
Paku 5cm 1kg
06-Feb-09 06-Feb-09
Besi 10" 10 btg Besi 10" 10 btg Pahat 1 bh Reng 1 ikar
07-Feb-09
Ongkos Tukang+Kenek
08-Feb-09
Bata merah 1000pc Semen 5 sack
09-Feb-09
Pasir Putih 1 truck
36
90 91 92 93 94 95
11-Feb09 11-Feb09 12-Feb09 12-Feb09 12-Feb09 12-Feb09 12-Feb09
Penjualan Kayu Bekas Bp. Hj. Mustopha Ibu Hj. Danarti
09-Feb-09
50,000 500,000
PT. Suar Amarta Solusindo Mujiono Kalisari Penjualan Kayu Bekas Kotak Amal
Total
Bongkar Pasir
400,000
20,000 12-Feb-09
10,957,000 11,007,000
Semen 5 sack 270,000
11,237,000
1,500,000
12,737,000
500,000
13,237,000
650,000
13,887,000
1,100,000
14,987,000
98,705,000
83,718,000 14,987,000
37
7.
Salinan Sertifikat Wakaf
38