PPA MODEL FOR PPP PROJECT Workshop - MKI
Assistia Semiawan – PT PLN (Persero)) Jakarta – July 17, 2012
Risk Allocation IPP Procurement Process Financing Government Guarantee
Construction of PPA template
PLN
PLN
IPP Structure & Risk Allocation
General Structure of IPP Project Contractors and Suppliers (EPC, O&M, Fuel)
PLN GOI
PPA IPP Project Co Equity
Project Sponsor
Gov. Guarantee
Debt Lenders
IPP vs EPC Project Structure PLN GOI PPA
Contract ors and Supplier s (EPC, O&M, Fuel)
GOI IPP Project Company
Equity
Debt
Project Sponso r
Guarantee
Guarantee /Recourse Contractors and Suppliers (EPC, O&M, Fuel)
PLN Debt
Lenders Lenders
Proyek IPP
Proyek EPC PLN
• IPP project : Construction risk dan financing risk will be handled by IPP • EPC project : Construction risk and financing risk will be handled by PLN
5
RISK ALLOCATION FOR IPP PROJECT Risk
PLN
IPP
Land Aq.
V
Environmental & Social Issues
V
Fuel Supply V
O and M
V
Exchange Rate
V
Inflation
V
Financing and Interest Rate V
Regulatory
V
Risk is allocated to Party that has the capacity and capability to handle risk more efficiently than the other Party *) Procurement Risk : IPP Fuel Price Risk : IPP
V
Demand
Force Majeure
Share
V *)
Construction
PLN
V 6
Risk Identification Specific to Mine Mouth Site Risk
Risk Tree
Power Plant Site (land acquisition, resettlement , etc) Coal Mine Site
License, AMDAL, other permits
Design and Construction Risk
Power Plant
Geological research failure
Operation Risk
Power Plant Operation
Sponsor Risk*1 Financial Risk*2
Coal supply and processing facility
Coal Supply and Processing Operation
Coal price hike (cost hike) Coal mine operation failure
Revenue Risk*3 Coal processing ops failure
Connectivity Risk Political Risk*4 Regulatory Risk
General changes in law
Coal mine bankruptcy/owner shift Dispute with mine owner (e.g. shift to export) Coal transaction price related
Force Majeure
Specific changes affecting mine mouth
Coal tax, royalty related
*1:poor sub-contractor performance, early termination ,etc. *2:inflation, FX, interest rate, etc. *3: end-user tariff adjustment, end-user nonpayment, *4: currency inconvertibility, currency transfer, expropriation, - adopted from JICA Study on Mine mouth Project
7
PLN
History of IPP Mgt & Procurement Process
KRONOLGI
PENGELOLAAN IPP
Menyesuaikan dengan dinamika perubahan IPP GENERASI I
IPP GENERASI II
IPP GENERASI III
Opsi I: PPP
PPA AWAL Ex. 27 IPP
Renegosiasi Generasi I
IPP DOMESTIK
IPP INFRASTRUKTUR
(Jaminan Pemerintah) Opsi II: PPA “B to B”
1999 - 2003
1992 - 98 EVALUASI MASALAH
2004 – 06 MEYAKINKAN PASAR DENGAN ANAK-ANAK PERUSAHAAN PLN
2005- 07
2009 Bankabie PPA PLTU Jawa Tengah RENCANA JAMINAN PEMERINTAH
Tahun 1992 – 97 : Tahun 1997 : Tahun 1999 – 03 : Tahun 1998 – 2005: Tahun 2004 – 06 : Tahun 2006 – 08 :
Generasi I, alokasi risiko kepada PLN dan ada Government Support Penangguhan dan pengkajian kembali proyek-proyek listrik swasta Renegosiasi 27 IPP Tidak ada pembangkit IPP yang baru Program kemitraan, skema “B to B”, tanpa jaminan Pemerintah Generasi II, risks sharing, skema “B to B”, tanpa jaminan Pem.
PROSES BISNIS PANJANG DAN RISIKO TINGGI 1) PLN umumkan Prakualifikasi IPP
Pengembang check Lokasi & Studi Awal
Pengembang menyiapkan data kemampuan & Bentuk Konsorsium
Pengembang jajaki Lahan, EPC Contractor, Lender, dll
PLN PLN umumkan hasil prakualifikasi
Pengembang Ajukan usulan Harga
PLN umumkan pengadaan IPP
Risiko-risiko: Kenaikan biaya konstruksi Kenaikan nilai tukar Rp, USD, JPY, RMB dll Risiko politik dll
Pengembang melakukan Feasibility Study, AMDAL, bebaskan tanah, cari EPC Contractor, Cari Lender.
Pengembang menyiapkan dokumen, Garansi dll untuk PPA
PLN umumkan pemenang Pengadaan & klarifikasi
PLN & Pengembang ttd PPA
7 – 9 bulan
12 bulan
36 - 54 bulan
Lender melakukan Due diligence
Bank mencairkan Pendanaan / Financial Close
Proyek Dibangun
IPP beroperasi
CJIPP Tender Process (1)
Legal Basis CJIPP tender process is based on PPP Law According to RFP: PPP Law is Presidential Regulation 67/2005 as amended by Perpres 13/2010, including its Appendix
CJIPP (1) – Project Preparation and PQ Process Start
PQ Result:
GOI announcement in IICE 2006
Inclusion of CJIPP in RUPTL 2007-2016
(November 2006)
Nine qualified Lead Members under seven bid consortiums:
◦ China Shenhua
Article 7(1) (March 2008)
◦ Yudean Corp., ◦ J Power and GDF-Suez
CJIPP Discussion Forum (Market Sounding)
Article 8 (February 5, 2009)
◦ KEPCO ◦ Marubeni ◦ Mitsubishi
PQ Announcement
PQ Meeting
Article B.2 (June 22, 2009)
(July 2 2009)
PQ Date and Evaluation
Article B.2 (July 28 – Nov 4, 2009)
Notification of PQ Result
Article B.2 (Nov 5, 2009)
A
◦ Mitsui and International Power
B
Note: Article X.X.X.X refers to the Appendix of the PPP Law (Date refers to completed or scheduled proceedings)
CJIPP (2) – RFP and Negotiation Process B
A
Yes
RFP
Article B.4 (Feb 25, 2010)
Pre-Bid Conference
Article B.5 (Mar 25, 2010)
FS and Government Support Proposal to MOF
(July 16, 2009)
Presentation, Term Sheet ,and Draft Guarantee Agreement
(April 14, 2010)
Negotiation of RFP / Project Agreements
(Mar 25, 2010 – Mar 25, 2011)
Negotiation of Guarantee Agreement
Amendment of RFP / Project Agreements
20 Amendments
Amendment of Guarantee Agreement
Yes
Any Material Concerns None Final Project Agreements and amendment
C
Any Material Concerns
Bid Negotiation:
In CJIPP, bid negotiation is conducted prior to bid date, creating an open, fair, and competitive process
After finalization of RFP, Project Agreements and Guarantee Agreement, no material changes (changes in risk allocations) is allowed
None (April 20, 2011)
CJIPP (3) – Evaluation of Bids C Final RFP, Project Agreements and Amendment
Note: Article X.X.X.X refers to the Appendix of the PPP Law (Date refers to completed or scheduled proceedings)
Article B.6 (April 29, 2011)
Bid Submission
Evaluation of Administrative and Technical Proposal (Envelope I)
@
Article B.5 (April 20, 2011)
Article B.7 (April 29 – May 23, 2011)
Comply with RFP? Yes
No (May 24, 2011)
Responsive Bidders >1?
No (May 24, 2011)
Return Unopened Envelope II and Proposal Security
(May 24 – June 8, 2011)
Yes Evaluation of Financial Proposal (Envelope II)
Rankings of Preferred Bidders
Article B.8
Article B.8.c.6 Article B.9
Evaluation of Financial Proposal (Envelope II)
Single Responsive Bidder
D
Article B.8 (May 24, 2011)
Article B.8.c.6 (May 24, 2011) Article B.10
CJIPP (4) – Appointment of Bid Winner D Article B.10.b (May 31, 2011)
Report to CEO of PLN
No Negotiation
Retender
Article B.10.d.7
Yes Article B.10.c (May 31, 2011)
Negotiation with Single Bidder
Article B.10.d.8 (May 31, 2011)
PLN’s CEO determine Single Bidder
Article B.10.d.10 (June 1, 2011)
Announcement of Single Bidder Objection
Evaluation and Response to Objection
Issuance of LOI to the Single Bidder
Announcement to All Bidders End
Article B.11 (June 1, 2011) Article B.12 (June 1 - 10, 2011)
(June 10 - 16, 2011)
Article B.14.a (June 17, 2011)
Section 26 of RFP (June 17, 2011)
Note: Article X.X.X.X refers to the Appendix of the PPP Law (Date refers to completed or scheduled proceedings)
Procurement Processes For IPP Projects With PPP Scheme Pre FS review and preparation of GAP Appointment of Consultants PPP scheme determined
Draft Submission RFP EOI and PQ of GAP released process
Pre-FS Finalisation
Award & Bid Signing Final One on Submission & RFP one Evaluation meetings released
Structuring Appraisal
Issuance of In-Principle Approval
Screening
Consultation
IIGF Guarantee Provision Process
Signing of: 1. Power Purchase Agreement 2. Guarantee Agreement 3. Recourse Agreement 16
PLN
Financing
PLN
Debt and Equity Requirement Project Size (MW)
Project Cost ($ million)
Equity ($ million) (25%)
Debt ($ million) (75%)
1600
2,400
600
1,800
2000
3,000
750
2,250
A 2000 MW project will require at least $2 billion debt financing At any size, the project would classify as large project financing for developing country, requiring high quality investors Shortlisted lead investors (equity interest of more than 20%): In IPP project with international sponsor, domestic banks is less likely to participate in large project financing
18 18
Financing Plan
PLN
Traditionally, and given the current state of credit markets, commercial banks would limit participation in B loans only Central Java IPP would be heavily reliant on ECAs financing Potential lenders include: ◦ Multilateral lenders (e.g. ADB, IFC, MIGA, IDB) ◦ B loans under multilateral cover from commercial banks ◦ Export Credit Agencies (e.g. JBIC, KEXIM, Sinosure) ◦ Bilateral financial institutions (e.g. JBIC)
1600 MW
2000 MW
$1.8 b
$2.25 b
Multilateral 1
$ 250 m
$ 250 m
Project limit
Multilateral 2
$ 200 m
$ 200 m
Project limit
B loans under multilateral cover
$ 200 m
$ 200 m
$ 1,150 m
$1,150 m
0
$ 450 m
Debt requirement
Export Credit Agencies Bilateral
Note
19 19
PLN
Why ECA or Bilateral or Multilateral?
Large debt financing will definitely require ECA participation – ECAs are allowed to cover a majority of eligible capital costs and can provide loans or loan guarantees of over $1 billion each Multilaterals and commercial banks are not capable of meeting this size of financing by themselves (current underwriting limit for a bank is $75 m; for multilaterals (eg. ADB) it is $250m for Indonesia) Commercial banks will not lend to an IPP in Indonesia (or similar countries) on “un-covered” basis – i.e., without an ECA, multilateral or bilateral cover All large IPPs in Indonesia have used ECA/bilateral financing (eg US Exim, OPIC, JBIC, KEXIM) – none to date have done without Even Middle East IPPs (which have A rated offtakers and gov support) have used ECA/multilateral/bilateral cover for most of the international commercial bank tranches
20
20
PLN
Government Guarantee
Kebutuhan Jaminan Pemerintah Semua proyek IPP besar di Indonesia menggunakan ECA/bilateral financing (mis: USPLN Exim, HERMES, JBIC, KEXIM) Pembiayaan internasional ECA/bilateral mensyaratkan adanya sovereign guarantee Pihak investor (project sponsor) meminta adanya sovereign guarantee untuk melindungi investasi mereka (dalam hal political force majeure dan PLN’s default)
Jaminan pemerintah perlu untuk melindungi dari: Risiko Politik Perceived political risk Indonesia masih tinggi: OECD’s Indonesia political risk rating: 5 (bandingkan Vietnam, 4) Euromoney ranking: 85 (dari lebih 100 negara) Institutional Investor ranking: 76 (Bandingkan India, 58)
Risiko PLN’s Default PLN credit risk masih tinggi: Sub-investment grade rating (SP: BB, Moodys: Ba2) Ketergantungan pada subsidi pemerintah TDL masih dibawah nilai keekonomian dan diputuskan secara politik oleh Pemerintah/DPR Berdampak pada kemampuan PLN untuk membayar tarif PPA
KRONOLOGI IPP GENERASI I
JAMINAN / DUKUNGAN IPP GENERASI II
IPP GENERASI III
Opsi I: PPP
PPA AWAL Ex. 27 IPP
Renegosiasi Generasi I
IPP DOMESTIK
IPP INFRASTRUKTUR
(Jaminan Pemerintah) Opsi II: PPA “B to B”
1999 - 2003
1992 - 98
2004 – 06
2005- 07
2009 Bankabie PPA PLTU Jawa Tengah
Jaminan / Support
Tidak ada Jaminan
Jaminan
Perpres 4/2010 (Jaminan Kelayakan Usaha PLN)
Perpres 67/2005 jo 13/2010
Road Map of Guarantees for Indonesia’ IPPs (PPRFpresentation – April 2010)
Policy shifting toward better guarantee management . .. Support Letter
Confirmation Note
Guarantee Agreement
1
Addressee
Project Company
• Lender (JBIC)* • Insurer (NEXI)**
Project Company
2
Coverage
Not stated
Not stated
Financial obligations of contracting agency as stated in PPA
3
Issuer
Ministry of Finance signed by Minister
Ministry of Finance signed by Head of Fiscal Policy Office
• Indonesia Infrastructure Guarantee Fund (IIGF); and/or • Third party (MDA); and/or • GoI.
*) Under Umbrella Note of Mutual Understanding between the Ministry of Finance of the Government of Republic of Indonesia and Japan Bank for International Cooperation (JBIC); **) Under the Umbrella Note of Mutual Understanding between the Ministry of Finance of the Government of Republic of Indonesia and Nippon Export and Investment Insurance (NEXI).
Legal Framework for PPP *PPP Structure & Procurement Procedures *Guarantee Scheme
PPP Structure & Procurement Scheme Presidential Regulation no. 67/2005 on Government Cooperation with Business Entities in the Provision of Infrastructure • contains the main provisions regulating public procurement and concession projects
Presidential Regulation no. 13/2010 on 1st Amendment to Presidential Regulation no. 67/2005 • Revision on Government Guarantee • Revision on main provisions • Revision on Pre Qualification Procedure • etc
Presidential Regulation no. 56/2011 on 2nd Amendment to Presidential Regulation no. 67/2005 • Revision on Pre Qualification Procedure • Revision on Unsolicited Projects • etc
Government Guarantee Scheme through IIGF (Indonesia Infrastructure Guarantee Fund) Presidential Regulation no. 78/2005 on Guarantee of Infrastructure Projects for Government with Business Entities Cooperation Through Infrastructure Guarantee Fund - contains the main provisions regulating the establishment of IIGF (Indonesia Infrastructure Guarantee Fund)
Ministry of Finance Regulation no. 260/PMK.011/2010 on Guidance for Guarantee of Infrastructure Projects for Government with Business Entities Cooperation
25
Skema Penjaminan Proyek KPS Counter Guarantee
6
Penanggung Jawab Proyek Kerjasama (PJPK)
Kemenkeu Single Window 1 Policy 5
Perjanjian Regres
PT. PII
Cooperation Agreement
MDA Risk Sharing
4
Perjanjian Penjaminan
2
3
acessoir
Backstop Facility
Project Company Ekuitas
Sponsor
Pinjaman
Lender
Perjanjian Kerjasama
PLN
Penjaminan Infrastruktur dilaksanakan oleh Menteri Keuangan melalui Badan Usaha Penjaminan Infrastruktur (dhi. PT Penjaminan Infrastruktur Indonesia) dengan Single Window Policy 2. PJPK dan Project Company akan bersepakat untuk melakukan kerjasama dalam penyediaan infrastruktur yang dituangkan dalam Perjanjian Kerjasama yang antara lain memuat hak, dan kewajiban dari masing-masing pihak 3. PT PII akan menjamin kewajiban – kewajiban PJPK kepada project company yang dituangkan dalam perjanjian penjaminan 4. Atas penjaminan yang diberikan kepada PJPK, PT PII memiliki hak regres apabila timbul klaim dari project company 5. Dalam rangka meningkatkan kredibilitas penjaminannya, PT PII melakukan kerjasama dengan Multilateral Development Agency (MDA) ataupun pihak lainnya 6. Dalam hal diperlukan, Menteri Keuangan akan memberikan counter guarantee guna mendukung kerjasama PT PII 1.
26
Contractual Structure PLN 3
PLN 1
Sponsors / Shareholders
6
4
PPA (Cooperation Agreement)
ECP Contractor
and/or
MOF 2
PPP Co.
Sponsor Agreement/ Shareholders Agreement
EPC Agreements
IIGF
Recourse agreement
7
Fuel Supply Agreement
Fuel Supplier
5
Guarantee Agreement
Loan Agreement
8
Lenders
O&M Agreements
O&M Contractor
27
FINANCIAL OBLIGATION CLAUSE CLAUSE
EXPOSURE
Clause 4.4 Delays caused by PLN in Construction Phase
Price Adjustment
Clause 5.7.1(c) Tax imposed as result of the Special Facilities transfer
(PPN 10% from transfer price)
PLN
PLN
Clause 8.1.1 Payment during commissioning each Unit
Clause 8.1.2 Payment from Unit COD until the Project COD for Unit one
Clause 8.1.3 Payment from Project COD until termination of Agreement
PLN
Clause 8.2.1 Payment for Deemed Commissioning Clause 8.3 Supplemental Payment for Emergency Output
Clause 14.3.3 Payment for Deemed Dispatched Political Force Majeure
PLN
Clause 14.4.1 Payment for Deemed Dispatched caused by Force Majeure affect PLN Clause 15.1 Consequences in Triggering Event Clause 16.3.4 Project Purchase caused by PLN Event of Default and/or Political Force Majeure before Project COD
PLN
Clause 16.3.5 Project Purchase caused by PLN Event of Force Majeure before Project COD
Clause 16.3.6 Project Purchase caused by Political Force Majeure affect Seller and PLN and/or Event of Force Majeure affect PLN after Project COD
33
TIMELINE PPA
Financing
Date
Plant Construction period
Project COD
Termination Agreement & Transfer Project
PPA signing Unit COD (___ month)
Financing Period (12 month)
Commissioning period ----days
Operation period (25 years)
Pokok-Pokok PPA (1) No.
Subyek
PPA
1
Sifat PPA
Take-or-pay PPA, dengan opsi untuk membeli proyek pada akhir masa kontrak. Walaupun IPP mempunyai take-or-pay PPA contract, risiko off-taker PLN masih ada (non-payment risk, political risk)
2
Periode PPA
+ /- 25 tahun, tidak termasuk masa satu tahun untuk pencapaian financial close dan untuk pekerjaan konstruksi
3
Availability Factor
+ 80%, setelah Project COD + 50%, setelah Unit COD
4
PPA Tariff
Dalam rupiah, terdiri dari 5 komponen A: capital cost recovery B: biaya tetap O&M C: biaya bahan bakar D: biaya variabel O&M E: capital cost recovery untuk Special Facilities (jaringan transmisi dan GITET)
5
Project security
Escrow account sesudah PPA signing Bank Guarantee saat PPA signing Bank Guarantee II saat financial close
34
PLN
Pokok-Pokok PPA (2) No.
Subyek
PPA
6
Pasokan batubara
Pengadaan oleh IPP dengan persetujuan PLN Harga batubara di-pass-through ke PLN
7
Liquidated damage
Denda keterlambatan COD di-cap
8
Grace period on FM
2 + 7 hari (selama operasi) 48 jam (untuk net dependable capacity test)
9
Pengadaan lahan
Dilakukan oleh IPP, PLN membantu koordinasi dan sosialisasi dengan masyarakat dan pemerintah daerah
10
Deemed Commissioning
Natural FM pada PLN atau political FM pada IPP dan PLN yang mengganggu commissioning diperlakukan sebagai deemed commissioning
11
Deemed Dispatch
Natural FM pada PLN atau political FM pada IPP dan PLN yang menggangu operasi diperlakukan sebagai deemed dispatch
12
Termination Right
PLN Event of default dan prolonged political FM memberikan IPP Termination Right. Rumus: net present value dari pembayaran komponen A dan E plus outstanding debt and interest plus EPC termination cost
35
PLN
PLN
Adaptation of PPA
37
Claim and Payment Procedure for Non-Payment Default
*Subject to GA scheme
Remedial Notice cc to IIGF Claim Due/Payable
Applicable Cure Period 45 days
Consultation phase
30 Days Guarantee Payment
Termination Notice II
PPA 30 Days
Remedial Program 30 Days
____ Days *
Transfer Project *
Termination Notice 1
45 Days 1. PLN notify unability; or 2. PLN disputes amount.
Guarantee Demand
60 Days
Payment by IIGF
Determination Date
GA IIGF copied received remedial notice
Deemed no dispute
Verification Period 60 Days
18 Months
Payment by GoI
38
Claim and Payment Procedure for Payment Default*Subject to GA scheme Remedial Notice cc to IIGF Claim Due/Payable
Applicable Cure Period 45 days Guarantee Payment
PPA ___ Days *
Remedial Program 30 Days Guarantee Demand
45 Days 1. PLN notify unability; or 2. PLN disputes amount.
Guarantee Demand
60 Days Determination Date
GA IIGF copied received remedial notice
Deemed no dispute
Verification Period 60 Days
18 Months
Payment by IIGF
Payment by GoI
RECITALS This Project was procured, conducted and based on Presidential Decree No. 67 of 2005 jo. No. 13 of 2010 concerning Government Cooperation with Entity in Infrastructure Provision (Peraturan Presiden No. 67 Tahun 2005 jo. No. 13 Tahun 2010 tentang Kerjasama Pemerintah dengan Badan Usaha dalam Penyediaan Infrastructure)
CHANGE IN PPA
PLN
PLN
Clause 16.3.4 -- In the event of termination of this Agreement after the Financing Date pursuant to Section 16.1.4 due to a PLN Event of Default or pursuant to Section 16.2.4(a), PLN shall purchase the Project at the purchase price determined in accordance with paragraph 2.2 of Appendix F with reference to Claim Procedure and Payment Mechanism under Guarantee Agreement. Clause 16.3.5 -- In the event of termination of this Agreement after the Financing Date pursuant to Section 16.2.4(b), PLN shall purchase the Project at the purchase price determined in accordance with paragraph 2.2 of Appendix F with reference to Claim Procedure and Payment Mechanism under Guarantee Agreement. Clause 16.3.6 -- In the event of termination of this Agreement pursuant to Section 16.2.3(b) or Section 16.2.3(c), PLN shall purchase the Project at the purchase price determined in accordance with paragraph 2.2.2 of Appendix F with reference to Claim Procedure and Payment Mechanism under Guarantee Agreement.
CLAUSE 16.3
PLN
GUARANTEE AGREEMENT
DEVELOPER
POWER PURCHASE AGREEMENT
GUARANTOR (IIGF &GoI)
RECOURSE AGREEMENT
PLN
Guarantee Scheme
Legal Basis
◦ Presidential Regulation No. 78 / 2010 ◦ Regulation of Finance Minister No. 260/2010
Parties : PLN – IIGF and PLN – GoI Aim : enable IIGF/GoI as Guarantor to claim from PLN payments made by them under the Guarantee Agreement (GA)
Heads of Terms
PLN
43
Claim & Payment Procedure
PLN Demand from Seller
REGRES
Claim Due/Payable
Payment by IIGF & GoI PLN confirm
Determination Date PLN doesn't confirm Verification Payment Period Period
Revised Payment Schedule in separate recourse settlement agreement
10 days
Notification to PLN with IIGF deliver Notification of Payment Negotiations Schedule
Negotiations 20 days
If not agree - arbitration
Terms of payment Interest shall accrue from date of IIGF payment under the GA to PLN payment date under RA
[Discussion: interest shall accrue starting from PLN’s payment due date until the actual payment]
PLN may not dispute any payment made by IIGF under GA including any changes thereof
[Discussion: PLN’s consent also be required to any payments agreed outside the terms of GA]
PLN may request a change in Payment Schedule which will trigger negotiation, then the Revised Payment Schedule will be stated in separate recourse settlement agreement
Payment made in Rupiah without (and free and clear of any deductions fo) set-off or counterclaim
Heads of Terms
PLN
Indemnification ◦ PLN to indemnify IIGF for all payments made by it under GA [Discussion: payments made by IIGF due to Gov FM should be excluded] ◦ A dispute in relation to, or the enforcement by the Seller of the Guarantee Agreement [Discussion : PLN has no control over whether or not IIGF brings a dispute under GA, therefore PLN cannot indemnify IIGF and it should be Seller who indemnify IIGF]
Heads of Terms
PLN
Consent
◦ PLN is required to obtain consent from IIGF and GoI for any termination of the PPA by PLN which is covered under GA, as part of giving the consent, IIGF and GoI need to state that they are each satisfied that PLN has the financial resources available to it to pay the purchase price when due and payable [Discussion: even if PLN doesn’t have enough funds to pay the purchase price immediately, the consent still can be issued if terminating the PPA is the most appropriate course of action rather than PLN have to pay deemed dispatched]
Heads of Terms
PLN
PLN
PPA Signing
FC
COD
End of PPA
Prior to FC
After FC – Prior to COD
On and After COD
Case A
Case B
Case C
PLN’s Default
-
Case D
Case E
PFM
-
Case D
Case E
PLN FM (Other than PFM)
-
Case D
Case E
Seller’s Default
Termination – Possible Cases
Case
Cause
Termination
PLN
A
- Seller’s inability to reach CP on FC date [16.3.1]
- PLN seize Stage I Guarantee (IDR 276 billion/US$ 30 million), except (i) inability to secure project site and special facilities and (ii) MAC, of which US$ 5 million is entitled to PLN
B
- Seller’s Event of Default after FC but prior to COD [16.3.2]
- PLN seize Stage II Guarantee (IDR 644 billion/US$ 70 million) - PLN has option to purchase the Project equal to - Outstanding debt plus interest due and payable, minus - Yet-to-disburse equity commitment
C
- Seller’s Event of Default after COD [16.3.3]
- PLN has option to purchase the Project equal to - Outstanding debt plus interest due and payable, minus - Yet-to-disburse equity commitment
Termination Treatment
Case
Cause
Termination
PLN
D
- PFM after FC but prior to COD [16.3.4] or - PLN FM (other than PFM) after FC but prior to COD [16.3.5] - PLN’s Event of Default after FC but prior to COD [16.3.4]
- PLN shall purchase the Project equal to: - Outstanding debt plus interest due and payable, plus - Actual equity contribution (capped at equity commitment), plus - ROE of 15% of the actual equity contribution, minus - DSRA and payment made by PLN during deemed period
E
- PLN’s Event of Default after COD [16.1.4] - PFM after COD [16.3.6] - PLN FM (Other than PFM) after COD [16.3.6]
- Purchase price based on outstanding debt and interest due and payable plus net present value of future CCR/CCRT, adjusted by average NDC, exchange rate, equity cash flows percentage at 33%, 45% and 60%; and discount rate of 15% (see 2.2 of Appendix F)
Termination Treatment
RFP, PPA & GA Negotiation Process. Non – PPP project
PPP - CJPP
Negotiation Method
Only with the winning Bidder
With all bidders through 1 on 1 meeting
Process of RFP issuance (Request for Proposal)
One time issuance.
Amended RFP through negotiation and 1 on 1 meeting
PPA Negotiation process
Conducted after appointment / award of winner, only with the winning bidder. PPA is signed after negotiation process Negotiation and clarification of PPA continues until Financial Close
Conducted before Bid Date with all bidders. PPA will be signed after awarded of winner No more clarification nor negotiation after awarded of winning bidder
GA negotiation and issuence process.
Conducted after appointment / award of winner, only with the winning bidder.
Conducted before Bid Date with all bidders
Transparency of the negotiation process
Only with the winning bidder
Open to all bidders
Beberapa Issues dari Investor Isu
Uraian
Bahasa kontrak
PPA menggunakan Bahasa Inggris dan Bahasa Indonesia, dimana Bahasa Indonesia menjadi acuan utama dalam hal dispute
Posisi PLN Mengikuti peraturan perundang-undangan
Cakupan definisi Tidak mencakup badan Government pemerintah dibawah Instrumentalities daerah tingkat 2 (kabupaten/kotamadya)
Mencakup perpanjangan pemerintah dibawah Pemda Kabupaten/Kotamadya
Pengadaan lahan
Lahan tetap tanggungjawab IPP
Permintaan dari bidders agar PLN melakukan fasilitas ipengadaan lahan
PLN
Thank You