STRUCTURES KONSTRUKCE
NEW POWER SOURCE AT THE LEDVICE POWER PLANT BUILDINGS OF THE MAIN POWER GENERATION UNIT MGU NOVÝ ZDROJ ELEKTRÁRNY LEDVICE HLAVNÍ VÝROBNÍ BLOK
37
Ivo VRBKA
Jiří JUNEK
Metrostav a.s., Division 8
Metrostav a.s., Division 8
[email protected]
[email protected]
region, near the spa town of Teplice. Apart from generating electric power, it also supplies heating to Teplice and nearby Bílina. In 2006, ČEZ, a power generating company, decided to significantly reduce harmful emissions concurrently with increasing the output of the power plant. ČEZ adopted the idea of developing a new power unit with the output of 660 MWe with an estimated service life of 40 years. The total investment cost exceeds 37 billion CZK, i.e. 1.45 billions EUR. Construction of the main power generation facility in Ledvice started in January 2009 and is to be completed by 2012. Approximately 80% of the construction works were finished by February 2010, before assembly of the machinery equipment had started. In order to meet these deadlines, the construction works had to be carried out continuously 24/7 from the very beginning. The performance and completion of all vital on-site activities was planned and reviewed by means of so-called S-curves. There were 2,111 m2 of secant pile walls built on the site. The secant pile walls protected the excavation pit from earth slide and ground water leakage. Furthermore, as much as 107,150 m3 of soil was excavated and removed from site. Special foundations of the MGU building included 938 friction piles of total length 20.2 km and securing of the excavation pit by 5.5 km of overlapped piles. As much as 120,000 m3 of concrete was cast and 22,000 t of steel was used during the construction. Construction of the MGU was split into five basic building units (Fig. 1): Control Centre, Boiler House, Turbine House, Gallery and Cooling Water Pipeline. There is a steel coal supply extension built on top of the Gallery structure. The coal supply extension consists of two steel 72 m high towers. The towers are linked by a steel hall housing coal conveyer. This article describes the structures of the Turbine House, Gallery and Boiler House (Fig. 2). STABILITY AND FOUNDATIONS Fig. 1 Overall view of the MGU buildings Obr. 1 Celkový pohled na objekty HVB
The MGU buildings are located on site with difficult geological condition. The MGU building has been founded on clayey tuff rock, which can be rated as fine particle soils or even clays. The geological situation on site is furthermore complicated by basalt rock extrusive. The Boiler House, Turbine House and Gallery buildings include basement substructure. Due to the ground water table being at the depth of 5 m, the basement floor level was set to be on the level -4.5 m under the ground floor level. The MGU building is founded on a special foundation structure based on friction piles 1.2 m in diameter.
BASIC PROJECT DATA ČEZ, a. s. ŠKODA PRAHA Invest s.r.o. ŠKODA PRAHA Invest s.r.o.
CLIENT GENERAL DESIGNER GENERAL CONTRACTOR CONTRACTOR OF CONCRETE STRUCTURES
Metrostav a.s., Division 8
CONSTRUCTION TIME
2009–2012
INTRODUCTION
The protection of the excavation pit for the MGU was designed The Ledvice power plant is located in the Ústí nad Labem as overlapped piles and secant pile walls. During the periods Tab. 1 Summary of main parameters of the MGU
BUILDING
STRUCTURE
FOUNDATIONS
Control Center
steel frame with RC in-situ floor slabs
RC piles, prefabricated frames
Turbine House Gallery
RC frame with steel extension
Boiler House Staircase towers
184
I
185
basement: RC frame superstructure: steel structure RC wall structure
foundation slab supported by friction piles
MAIN DIMENSIONS FOOTPRINT X HEIGHT [M]
NET FLOOR AREA [M2]
ENCLOSED VOLUME [M3]
18 x 55 x 23.6
2,970
23,364
45 x 90 x 39.8 21 x 90 x 39
42,985
258,720
80 x 90 x 4.6
11,820
1,008,000
13 x 13 x 140.3
7,035
48,976
STRUCTURAL CONCRETE IN THE CZECH REPUBLIC 20062009
184
KONSTRUKČNÍ BETON V ČESKÉ REPUBLICE 20062009
185 Fig. 2 MGU buildings – Machinery hall, Gallery and staircase towers Obr. 2 Objekty HVB – strojovna, mezistrojovna a schodišťové věže
ZÁKLADNÍ DATA PROJEKTU ČEZ, a.s. ŠKODA PRAHA Invest s.r.o. ŠKODA PRAHA Invest s.r.o.
INVESTOR GENERÁLNÍ PROJEKTANT GENERÁLNÍ DODAVATEL DODAVATEL BETONOVÝCH KONSTRUKCÍ
Metrostav a.s., divize 8
DOBA VÝSTAVBY
2009 až 2012
ÚVOD Elektrárna Ledvice leží v Ústeckém kraji nedaleko lázeňského města Teplice. Kromě výroby elektrické energie zajišťuje dodávku tepla do Teplic a nedaleké Bíliny. V roce 2006 se energetická společnost ČEZ rozhodla výrazně snížit škodlivé emise se současným zvýšením výkonu. Přistoupila tak na myšlenku vybudování nového bloku elektrárny o výkonu 660 MWe. Předpokládaná doba provozu má být 40 let a celkové náklady činí více než 37 mld. Kč, tj. cca 1,45 mld. EUR. Stavební práce na výstavbě hlavního výrobního bloku v Ledvicích začaly v lednu 2009 a skončí v květnu 2012, přičemž přibližně 80 % objemu stavebních prací bylo provedeno do února 2010, kdy začala montáž technologické části díla. Splnění těchto termínů znamenala od samého počátku výstavby pracovní nasazení 24 hodin denně 7 dní v týdnu. Výkony rozhodujících činností byly plánovány a kontrolovány formou tzv. S-křivek. Na stavbě bylo postaveno 2.111 m2 milánských stěn (pro zajištění stavebních jam proti sesuvu a pronikání spodní vody), vykopáno a odvezeno 107.150 m3 zeminy. Pro speciální založení objektů HVB bylo realizováno 938 plovoucích pilot o celkové délce 20,2 km a pro zajištění stavební jámy 5,5 km převrtávaných pilot. Na stavbě bylo uloženo 120.000 m3 betonu a 22.000 tun oceli.
používaly se pro utěsnění jednotlivých záběrů jílocementové těsnící stěny. V místě založení stolice turbogenerátoru (TG) byl v hloubce 6 m v části půdorysu zastižen mocný a tvrdý horizont čediče, který nebylo možno převrtat. Technologické zařízení TG je vysoce náročné zařízení na chvění, poklesům a pootočení základu. Proto návrh, konstrukce a založení stolice TG je vysoce náročná záležitost. Vzhledem k předepsanému maximálnímu sednutí pilot do 5 mm a různorodému podloží bylo nutné provést v tomto místě zatěžovací zkoušky vybraných pilot (Obr. 3), které současně potvrdily teoretické výpočty. Následně pak muselo dojít k úpravě délek, profilů a rozmístění vrtaných pilot.
Stavba HVB je rozčleněna na pět základních objektů (Obr. 1): dozorna, kotelna, strojovna, mezistrojovna a potrubí chladící vody. Na mezistrojovně je ještě umístěna ocelová konstrukce nástavby zauhlování skládající se ze dvou ocelových věží dosahujících do výšky 72 m. Věže jsou propojené ocelovou halou, ve které je STROJOVNA A MEZISTROJOVNA umístěn pásový dopravník uhlí.
V článku je popsáno konstrukční řešení objektů strojovny, me- Konstrukční systém strojovny i mezistrojovny (Obr. 5) je tvořen mohutným železobetonovým skeletem odpovídajícím přenázistrojovny a kotelny (Obr. 2). šenému zatížení. Sloupy o rozměrech 800 x 800 mm – 1500 x 2000 mm jsou uspořádány v modulové síti 6,0 x 6,0 m, 6,0 x ZAJIŠTĚNÍ A ZALOŽENÍ OBJEKTŮ 7,5 m a 6,0 x 9,5 m. Ve strojovně na úrovni + 15,0 m je na želeObjekty HVB se nacházejí na území se složitými základovými zobetonových obvodových sloupech v řadě A uložena ocelová poměry. HVB je založen na zjílovatěných tufech, které jsou kla- konstrukce haly se střešním příhradovým prostorovým vaznísifikovány převážně jako jemnozrnné zeminy až jíly. Staveniště kem a jeřábovou dráhu mostového jeřábu o nosnosti 128/40 je navíc problematické nerovnoměrnou polohou čedičových tun. V mezistrojovně, která je železobetonová, jsou stropní úrovvýlevů. Kotelna, strojovna a mezistrojovna jsou podsklepeny. ně tvořeny většinou trámovými a roštovými deskami. Největší Z důvodu výskytu podzemní vody v hloubce 5 m pod úrovní rozpony jsou až 17,0 m s trámy výšky 2,0 m. Na úrovni betonové terénu byla úroveň podlahy suterénu stanovena na kótě -4,5 m. střechy na kótě + 39 m je umístěna těžká ocelová technologická Vlastní založení HVB je provedeno pomocí speciálního zakládá- konstrukce, která vnáší do betonové konstrukce značná svislá ní na plovoucích pilotách průměru 1,20 m. a vodorovná zatížení. Stavební jáma HVB byla navržena z převrtávaných pilot a milán- K návrhu konstrukce bylo použito prostorového modelu, který ských stěn. V době, kdy nebyla celá jáma kompletně uzavřená, obsahoval betonové i ocelové prvky. Hlubinné založení na skuOBJEKT
TYP KONSTRUKCE
ZALOŽENÍ OBJEKTU
Dozorna
ocelový skelet se železobetonovými monolitickými stropy
železobetonové piloty, prefabrikované rámy
Strojovna Mezistrojovna
železobetonový skelet s ocelovou nástavbou
Kotelna Schodišťové věže
suterén: železobetonový skelet vrchní stavba: ocelová konstrukce železobetonová stěnová konstrukce
základová deska založená na plovoucích pilotách
HLAVNÍ ROZMĚRY PŮDORYS X VÝŠKA [M]
UŽITNÁ PLOCHA [M2]
OBESTAVĚNÝ PROSTOR [M3]
18 x 55 x 23,6
2970
23 364
45 x 90 x 39,8 21 x 90 x 39
42 985
258 720
80 x 90 x 4,6
11 820
1 008 000
13 x 13 x 140,3
7035
48 976
Tab. 1 Přehled rozhodujících parametrů objektů HVB
STRUCTURES
NEW POWER SOURCE AT THE LEDVICE POWER PLANT BUILDINGS OF THE MAIN POWER GENERATION UNIT MGU
KONSTRUKCE
NOVÝ ZDROJ ELEKTRÁRNY LEDVICE HLAVNÍ VÝROBNÍ BLOK when the excavation pit was not fully enclosed, clay-cement any vibrations of the turbine set during its operation (second sealing curtains were used to seal the individual working areas. ultimate state), which were basic design conditions. A substantial and hard layer of basalt was found at the depth of 6 m under a part of the building footprint where the foundations of the turbine set deck (TG) were to be built. It was not possible to drill through the basalt layer. The turbine set is extremely sensitive to any vibration, displacement or rotation of the foundations. Therefore, the design, construction and foundation of the turbine set deck were extremely difficult. The maximum permissible subsidence of the piles was specified up to 5 mm and with respect to the various bed rock properties it became inevitable to carry out load tests on selected piles at this place (Fig. 3). The load tests have confirmed outcomes of the theoretical calculations. Consequently, the length, size and layout of the proposed piles had to be adjusted. MACHINERY HALL AND GALLERY Machinery hall and gallery (Fig. 5) structure scheme is composed of a bulky reinforced concrete frame system, which corresponded with carrying loads. Columns with cross sections 0.8 x 0.8 mm – 1.5 x 2.0 mm are mainly ordered in modular grid 6.0 x 6.0 m, 6.0 x 7.5 m a 6.0 x 9.5 m. In the machinery hall, at level +15.0 m, there is placed on reinforced concrete perimeter columns row A the steel structure of the hall supporting three – dimensional roof girder and crane runway for bridge crane 128/40 t. The ceiling levels in the gallery are mostly created by slab and girders structure or grid of beams and slab structure, the longest span is about 17.0 m with beams 2.0 m high. At the level of the concrete roof +39.0 m is placed weighty steel technological structure brought into concrete structure high vertical and horizontal loads. For structure design, the three-dimensional model was applied It contained both concrete and steel members. A deep foundation on a group of piles was modelled by thick slabs in the head of piles which included interaction with foundation subsoil by spring constants.
Fig. 3 Photo of load test on a pile Obr. 3 Snímek ze zatěžovací zkoušky pilot
A reinforced concrete deck supports the turbo-generator set in the machinery hall (Fig. 4). The new foundation of the turbogenerator set consists of a massive RC top slab, elastic Gerb bearing, horizontal beams, transfer beams and the bottom slab. The 3.5 m thick bottom slab rests on piles. The deck has to transfer all static and dynamic loads that occur during the assembly and operation (first ultimate state) and has to prevent
A concrete mix resistant to shrinkage cracks was used for construction of the turbo-generator deck. The top deck is 15 x 55 x 3 m in size. Concrete casting of the top deck was carried out in three phases across the 1.0 m overall height. The slab was cast layer by layer, each approximately 300 to 400 mm thick. The reason for this was to minimize the occurrence of shrinkage cracks. Each layer was adequately compacted. The formula of the concrete mixture was selected with the aim to avoid any distortion of the concrete structure by the setting heat. All formulas selected in advance were tested in laboratories and afterward the concrete of the finished foundation slab was tested as well. BOILER HOUSE A further building within the scheme is the Boiler House, which is formed by reinforced concrete peripheral walls with inner columns and reinforced concrete slab. The main features of these areas are four massive columns of cross-section 5 x 5 m making up the load bearing structure supporting the boiler and eight pairs of foundations for the mill structure (Fig. 6). The foundations are formed by up-standing ribs on top of the foundation slab. Furthermore, bulky concrete blocks are sitting on spring bearings manufactured by Gerb and installed on the ribs. These members ensure elastic fastening of upper massive foundation blocks carrying coal crushing mills. Elastic supports prevent transition of the dynamic loads and vibrations generated by the mill operation to the building structure itself. Two staircase towers erected using climbing formwork of total area 49.121 m2 are part of the boiler house. The overall height of the simultaneously cast towers is 140.3 m, which makes them the highest building structures in the Czech Republic. The north tower features a glazed steel structure on the top allowing for an amazing view of the České středohoří and Krušné hory mountains. STAIRCASE TOWERS Bearing structure of towers with layout dimensions 13 x 13 m is reinforced concrete cast in-situ, composed of load bearing perimeter walls with thicknesses 400 and 500 mm, internal walls with thicknesses 250 and 300 mm (Fig. 7) and ceiling slabs with thickness 250 mm, subsequently fixed into internal and perimeter walls and fitted by many openings. In structure development both three – dimensional and bar-shaped static model were used; the main static scheme is cantilever fixed in Boiler house basement structure. In optimization calculations – e.g. for seismic and temperature loading bar-shaped models proved competent. The whole section plan was modelled by the bars with corresponding material- physical properties. These models were also used for creeping calculation, 2nd order effects, sequences of construction and stability calculations. The structure was modelled by 2D (shells) and 1D (bars) members in three-dimensional models that were used for obtaining of dimension internal forces (Fig. 8).The foundation was modelled by spring constants that substituted piles, the stiffness of them were derived from real loadings and settlements. More than 2,300 t of reinforcement bars and 10,000 m3 of concrete were used to build the towers’ structure. Concrete was poured continuously 24 hours a day and 7 days a week, at a velocity of 2.5-3.3 m/day. The towers were interconnected by a bridge, on which two concrete distribution arms delivering concrete mixture to both towers were installed. The concrete
186
I
187
STRUCTURAL CONCRETE IN THE CZECH REPUBLIC 20062009
186
KONSTRUKČNÍ BETON V ČESKÉ REPUBLICE 20062009
187 Fig. 4 Trusses and view of the turbine set deck area Obr. 4 Obrázek vazníků a pohled do prostoru stolice TG
pinách pilot bylo namodelováno jako masivní deska, která je nejvyšším objektem v České republice, přičemž na severní věži v hlavách pilot se zahrnutím interakce se základovou půdou je osazena prosklená ocelová konstrukce umožňující výhled pomocí pérových konstant. na České středohoří, Krušné hory a na uhelný lom. Ve strojovně se nachází železobetonová stolice pro turbogenerátor (Obr. 4). Základ TG se skládá z horní masivní železobetonové desky, pružného uložení na gerbech, vodorovných trámů a příčníků a základové desky. Spodní deska tloušťky 3,5 m spočívá na pilotách. Stolice musí přenést jak všechna statická a dynamická zatížení, která se vyskytnou během montáže a provozu (první mezní stav), tak zamezit vibracím od provozu parogenerátoru (druhý mezní stav), což bylo základním návrhovým kritériem.
SCHODIŠŤOVÉ VĚŽE
Nosná konstrukce věží o půdorysných rozměrech 13 x 13 m je železobetonová monolitická, tvořená nosnými obvodovými stěnami tloušťky 400 a 500 mm, vnitřními stěnami tloušťky 250 a 300 mm (Obr. 7) a stropními deskami s četnými otvory, které jsou vetknuty do vnitřních a obvodových stěn. Při návrhu konstrukce byly použity prostorové i prutové výpočetní modely, v nichž je základním statickým schématem věže konzola vePro betonáž stolice byly použity betony s odolností proti smrš- tknutá do konstrukce suterénu kotelny. ťovacím trhlinám. Horní rám stolice má rozměr 15 x 55 x 3 m. Betonáž horní desky probíhala po vrstvách cca 300 až 400 mm V optimalizačních výpočtech – např. při zatížení seizmicitou na tři výškové etapy cca 1,0 m z důvodu minimalizace smršťova- a teplotou se osvědčily prutové modely, kdy je celý půdorysný cích trhlin. Každá vrstva se dostatečně zhutnila. Receptura be- průřez věže modelován pruty s odpovídajícími průřezovými tonové směsi byla zvolena tak, aby vznikem hydratačního tepla nedocházelo k přetvoření betonové konstrukce. Na předem zvolené receptury byly provedeny průkazní laboratorní zkoušky a poté zkoušky na již hotové konstrukci základové desky. KOTELNA Dalším navazujícím objektem je kotelna, kterou z konstrukčního hlediska tvoří v suterénu železobetonové obvodové stěny s vnitřními sloupy a železobetonová deska. Zajímavostí jsou čtyři masivní sloupy průřezu 5 x 5 m tvořící nosnou konstrukci kotle a osm párů základů pro konstrukci mlýnů (Obr. 6). Základy jsou tvořeny pasy nad základovou deskou, na kterých jsou umístěny pružné podpory od firmy Gerb, a betonovými bloky osazenými na těchto „gerbech“. Prvky zajišťují pružné uložení masivních bloků základů mlýnů sloužících k rozmělňování uhlí. Pružné uložení je vyžadováno z důvodu dynamického zatížení a vibrací způsobovaných činností mlýnů. Součástí kotelny jsou dvě železobetonové schodišťové věže, prováděné technologií posuvného bednění o celkové ploše 49 121 m2. Celková výška tažených věží je 140,3 m a tím se staly
Fig. 5 View of the gallery and staircase towers Obr. 5 Pohled na mezistrojovnu a schodišťové věže
STRUCTURES
NEW POWER SOURCE AT THE LEDVICE POWER PLANT BUILDINGS OF THE MAIN POWER GENERATION UNIT MGU
KONSTRUKCE
NOVÝ ZDROJ ELEKTRÁRNY LEDVICE HLAVNÍ VÝROBNÍ BLOK mixture was pumped up to the bridge. Composition of the concrete mixture was regularly checked during each pour and was amended depending on the actual weather condition and the required concrete strength in order to enable continuous concrete casting. Casting of concrete into the formwork proceeded in 250300 mm lifts. When the formwork was filled and a check of concrete consistency was completed, lifting of the entire formwork system started. Concrete consistency was checked with a steel rod 10 mm in diameter, which was stuck by force into the concrete. Typically, there was a 500 mm thick layer of hard concrete, 300 mm layer of setting concrete and a 300 mm layer of fresh concrete in the formwork. One stroke of the hydraulic lifting jack was 23 mm. The height of one element of the sliding formwork was 1.1 m. The formwork elements were interlocked every two meters by a vertical bracing bar and interconnected by two horizontal beams, which made up the frame of the basic structural element of the formwork. Here, a hydraulic jack of 6 t bearing capacity was placed and mounted on a bar of 28 mm diameter, resting on the foundation slab. A protection tube was screwed on the bottom of the hydraulic lifting jack allowing for a space between the lifting bar and concrete. After coupling of the hydraulic system, the formwork was ready for actuation. Measurement of verticality of the concrete structure was carried out by a laser measuring apparatus every 500 mm of height. Concrete structures produced by the pull-up technique using sliding formwork and continuous casting of the concrete mixture are distinguished by a high quality of structure. The towers were pulled-up in 57 days. Reinforcement bars were transported by cranes, which climbed up along with the concrete structure so that the final height of the cranes was 147 m (including the first floor level height). As many as 90 workers and site technicians were working in each shift. The sliding formwork technique turned out to be a step enabling speeding-up of the construction works while maintaining all of
Fig.6 View from the staircase towers on the boiler house construction site and mill foundations Obr. 6 Pohled za schodišťových věží na staveniště kotelny se základy mlýnu
188
I
189
the quality targets set by the investor. Application of the sliding formwork was not a matter of routine work, but all the technical, technological and management aspects of the work were carefully considered. Successful application of this technology and meeting the deadlines would not be possible without the close operation of many disciplines participating in the works. CONCLUSION Approximately eight key subcontractors participated in the construction of the main power production unit under the leadership of Metrostav. There were not only big reputable construction companies participating in the scheme, but also small entrepreneurs and sole traders. All of them contributed their expertise to the completion of this exceptional structure, for which there has been no match in the Czech Republic in the last 20 years. Over 2,000 workers took part in the works during 2009, under the leadership of the director Ing. Radek Zeman of Metrostav, Division 8. Metrostav Divisions 6 and 7 were hired as internal subcontractors responsible for casting of the foundation slab and delivery and assembly of steel structures. Furthermore, Division 11 was hired to provide six tower cranes. KEY SUBCONTRACTORS ZAKLÁDÁNÍ STAVEB, A.S. AND TOP GEO GROUP CZ SPOL. S R.O., SPECIÁLNÍ STAVBY MOST SPOL. S R.O. OMEGA-TEPLOTECHNA PRAHA A.S. HOCHTIEF CZ A. S. VHS TEPLICE S.R.O.
excavation pit support and specialist foundation excavation pit support and blinding concrete construction of RC boiler house towers construction of RC structures of the gallery and turbine house construction of RC structures of the boiler house up to the ground floor level ± 0.0 m
STRUCTURAL CONCRETE IN THE CZECH REPUBLIC 20062009
188
KONSTRUKČNÍ BETON V ČESKÉ REPUBLICE 20062009
189 Fig. 7 View down the staircase towers interior Obr. 7 Pohled do vnitřního prostoru věží
i materiálově – fyzikálními charakteristikami. Těchto modelů bylo dále využito i při výpočtech dotvarování, účinků II. řádu, postupu výstavby i při stabilitním výpočtu. V prostorových modelech (Obr. 8), které byly použity pro získání dimenzačních vnitřních sil, byla konstrukce namodelována pomocí 2D (skořepiny) a 1D (pruty prvků). Založení bylo modelováno pomocí pérových konstant nahrazujících piloty, jejichž tuhosti byly odvozeny od skutečného zatížení a sedání.
Věže byly vytaženy za 57 dní. Pro montáž výztuže byly použity jeřáby, které šplhaly společně s postupem betonáže, takže jejich konečná výška byla 147 m (včetně výšky 1NP). Na každé směně pracovalo najednou 90 dělníků a techniků. Technologie posuvného bednění se projevila jako krok umožňující zrychlení výstavby při dosažení všech kvalitativních požadavků investora a generálního dodavatele. Vlastní použití bednění nebylo rutinní záležitostí, ale předcházela mu složitá příprava jednotlivých složek systému jak po stránce technické, technologické, tak i organizační. Bez součinnosti mnoha subjektů by úspěšné použití této technologie a splnění termínů stavby nebylo vůbec možné.
Na obě věže bylo použito přes 2 300 tun ocelové výztuže a 10 000 m3 betonu. Betonáž probíhala 24 hodin denně a 7 dní v týdnu s rychlostí 2,5 m/den. Věže byly spojeny propojovacím mostem, na kterém byla umístěna dvě distribuční ramena, zásobující obě věže betonem, který byl na distribuční most dopravován čerpadlem. Při každé betonáži proběhla kontrola betonové směsi a vzhledem k povětrnostním podmínkám a požadavkům ZÁVĚR na pevnost betonu byla operativně upravována receptura beto- Na realizaci hlavního výrobního bloku se pod vedením nu, aby betonáž mohla probíhat kontinuálně. Metrostavu podílelo cca 8 rozhodujících subdodavatelů. Zalití bednění betonem se provádělo po výškách 250 až 300 mm Nejedná se pouze o stavební firmy renomovaných jmen, ale v jedné vrstvě. Po zaplnění bednění a ověření pevnosti betonu také o malé podnikatele a živnostníky. Všichni svou odborností se začalo se zvedáním celého systému konstrukce bednění. přispěli k provedení stavebního celku, který nemá za posledPevnost betonu se zkoušela pomocí ocelové tyče o průměru ních 20 let v České republice obdoby. V průběhu roku 2009 se 10 mm tak, že se tyč silou vpichovala do betonu. Standardně na stavbě vystřídalo přes 2000 pracovníků pod vedení ředitele bylo v bednění 500 mm tvrdého betonu, 300 mm tuhnoucího výstavby Ing. Radka Zemana z Metrostavu Divize 8. betonu a 300 mm čerstvého betonu. Jeden zdvih hydraulického Interní subdodavatelé Metrostavu byly z Divizí 6 a 7 pro betonáž zvedáku byl 23 mm. základové desky a dodávku s montáží ocelových konstrukcí Použité posuvné bednění mělo výšku bednícího prvku 1,1 m a dále z Divize 11 k zajištění šesti věžových jeřábů. a každé cca 2 m bylo spřaženo vertikální výztuhou a spojeno dvěma horizontálními nosníky, tím se vytvořil rám základního ROZHODUJÍCÍ SUBDODAVATELÉ konstrukčního prvku – „jochu“. Zde se umístil hydraulický zvepro zajištění stavební jámy dák o nosnosti 6 t, který byl nasazen na tyč o průměru 28 mm ZAKLÁDÁNÍ STAVEB, A.S a speciální zakládání opřenou o základovou desku. Na spodním konci zvedáku byla A TOP GEO GROUP CZ SPOL. S R.O. pro zajištění stavební jámy našroubována ochranná trubka, která vytváří meziprostor mezi SPECIÁLNÍ STAVBY MOST SPOL. S R.O. a podkladních betonů zvedací tyčí a betonem. Po propojení hydraulického systému pro realizaci železobetonových bylo bednění připraveno. Měření svislosti konstrukce a tažení se OMEGA-TEPLOTECHNA PRAHA A.S. věží kotelny provádělo laserovými měřidly každých 0,5 m výšky. Betonové stavby tažené tímto posuvným bedněním s kontinuálním litím betonu se vyznačují vysokou kvalitou provedení konstrukce.
HOCHTIEF CZ A. S. VHS TEPLICE S.R.O.
pro betonové konstrukce mezistrojovny a strojovny pro betonové konstrukce kotelny do ± 0.000 m
Fig. 8 Calculation model of the towers Obr. 8 Výpočetní model věží