Geothermal Investment Opportunities in Indonesia by: Sugiharto Harsoprayitno, M.Sc Director for Geothermal
Thursday, July 14, 2011 © EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
Geothermal Potency in Indonesia • Potential Geothermal Indonesia is the largest in the world, 40% of world reserves, amounting to 29.038 MW, spread over 276 locations • Installed Capacity 1,189 MW (4% of whole potency), consists of field: Sibayak 12 MW, Salak Mt. 375 MW, Wayang Windu 227 MW, Kamojang 200 MW, Darajat 255 MW, Dieng 60 MW and Lahendong 60 MW • Geothermal Road Map Target 9,500 MW in 2025
© EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
GEOTHERMAL POTENTIAL MAP
No.
Island
Number of Loc.
1 2 3 4 5 6 7 8
Sumatera Java Bali Nusa Tenggara Kalimantan Sulawesi Maluku Papua T otal
86 71 5 22 8 55 26 3 276
Potency (MW) 13,516 10,092 296 1,471 115 2,519 954 75 29,038
Install Capacity (MW) 12 1,117
Source : Geological Survey, MEMR(2010)
Note: 60
1,189
Preliminary Survey
Ready to Developad
Detail Survey
Already Developed © EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
INSTALLED GEOTHERMAL POWER PLANT CAPACITY 2010 No.
Geothermal Working Area/ Location
License Holder
Developer
Name of Geothermal Power Plant
Installed Capacity (MW)
1
Sibayak – Sinabung, SUMUT
PT. Pertamina Geothermal Energy (PGE)
PT. Pertamina Geothermal Energy (PGE)
Sibayak
12
2
Cibeureum – Parabakti, JABAR
PT. Pertamina Geothermal Energy (PGE)
KOB - Chevron Geothermal Salak, Ltd (CGS)
Salak
375
3
Pangalengan, JABAR
PT. Pertamina Geothermal Energy (PGE)
KOB - Star Energy Geothermal Wayang Windu, Ltd (SEGWWL)
Wayang Windu
227
4
Kamojang – Darajat, JABAR
PT. Pertamina Geothermal Energy (PGE)
PT. Pertamina Geothermal Energy (PGE)
Kamojang
200
5
Kamojang – Darajat, JABAR
PT. Pertamina Geothermal Energy (PGE)
KOB - Chevron Geothermal Indonesia, Ltd (CGI)
Darajat
255
6
Dataran Tinggi Dieng, JATENG
PT. Pertamina Geothermal Energy (PGE)
PT. Geo Dipa Energi (GDE)
Dieng
60
7
Lahendong – Tompaso, SULUT
PT. Pertamina Geothermal Energy (PGE)
PT. Pertamina Geothermal Energy (PGE)
Lahendong
60 1.189
© EBTKE KESDM - 2011
4
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
REGULATIONS ON GEOTHERMAL ENERGY I. Law No. 27/2003 on Geothermal II. Government Regulation No. 59/2007 jo Government Regulation No. 70/2010 on
Geothermal Business Activities III. Government Regulation No. 62/2008 jo No. 1/2007 on Income Tax Facilities IV. Presidential Regulation No. 4/2010 on Assignment to PT. PLN to Accelerate Power Plant
Development Using Renewable Energy, Coal and Gas V. Ministerial Regulations MEMR Regulation No. 11/2008 on Mechanism for Determining Geothermal Working
Area MEMR Regulation No. 02/2009 on The Guidelines for Geothermal Pre-Survey
Assignment MEMR Regulation No. 05/2009 on The Guidelines for Electricity Purchasing Price by PT.
PLN from Cooperation and Other Business Entities MEMR Regulation No. 11/2009 on The Guidelines for Geothermal Enterprises MEMR Regulation No. 31/2009 on Purchasing Power by PT. PLN from Power Plant using
Small – Medium Scale of Renewable Energy MEMR Regulation No. 15/2010 on Projects List of Power Plant Accelerated Development
using Renewable Energy, Coal and Gas as well as Related Transmission MEMR Regulation No. 2/2011 on an Assignment to PLN to buy electricity from
geothermal power plant
© EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
GOVERNMENT POLICIES TO SCALE UP GEOTHERMAL DEVELOPMENT IN INDONESIA 1. Presidential Regulation No. 04/2010 jo Ministerial Regulation No. 15/2010 (2nd
Stage of 10,000 MW Crash Program) in order to speed up the development of geothermal power to the amount of 3,967 MW by the year 2014 which will require a total of US$ 12 Billions. 2. Government provide fiscal incentives for geothermal:
■ Income Tax Facilities (Based on Government Regulation No. 62/2008 jo No. 1/2007) which provide: - 30% (thirty percent) net income tax deduction of the total Investment, for 6 (six) years, 5% (five percent) annually - Income tax charge for dividend paid to Foreign Tax Subject shall be 10% (ten percent), or lower tariff according to effective Double Taxation Avoidance Agreement - Compensation of financial loss for more than 5-10 years ■ Custom Duties Exemption for Importing Items (based on MoF Decree No. 177/PMK.011/2007) ■ Value Added Tax of Import Items Covered by Government (based on MoF Decree No. 22/PMK.011/2011) © EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
GOVERNMENT POLICIES TO SCALE UP GEOTHERMAL Continue …... DEVELOPMENT IN INDONESIA 3. Government support in the form of reducing upstream geothermal risk by providing revolving funds (for exploration and FS), particularly for the Eastern parts of Indonesia. 4. The GoI is in process of establishing a State-Owned Company in the geothermal business to support its development. 5. To accelerate geothermal development, the Government offers a Preliminary Survey Assignment to third part (investor) which provides “first right refusal”. 6. The Government has determined Regulations on Geothermal Price Structure (based on MEMR Regulation No. 02/2011) : • Purchase price of electricity by PT PLN from a Geothermal Power Plant, as the result of a GWA tender, is used for the Power Purchase Agreement, the electricity price is final and non negotiable • Ceiling price for geothermal energy: US$ 9.7 cents/kWh 7. In order to enhance certainty in geothermal investment, the government has set a Standard Power Purchase Agreement. © EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
Implementation of Geothermal Policies Existing GWA
New GWA
President Decree No 45/1991, No 49/1991,
Law No. 27/2003
Business structure based on JOC and ESC
Business structure in the form of Permit:
34% of Net Operating Income (NOI), that had
Obligation to pay for taxes and royalty
Project Management : Under Pertamina (JOC)
Project Management :Under Permit Holder
Project Type:
Project Type:
and No 23/1992
Geothermal Mining Permit Enterprise Permit for Electricity
included all kinds of taxes and retribution, except personal tax. and PLN (ESC)
Total (Integrated) Project Partial Project
Total (Integrated) Project WKP holder will be granted as generally plan operation
© EBTKE KESDM - 2011
8
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
Development of Geothermal Energy Western Part of Indonesia
Eastern Part of Indonesia
Big geothermal potential → development in mid-big scale project
Small geothermal potential → development in small scale project
Existing projects as brown fields → detail data is unavailable
Most of the area are green fields → detail data is not available
Conducive investment condition is enough → attractive to investor (B to B approach)
Not attractive to investor. Not only need conducive investment condition, but also funding support from government Government support in the form of reducing upstream geothermal risk (GoI allocates budget for exploration and FS)
© EBTKE KESDM - 2011
9
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
GEOTHERMAL VALUE CHAIN (Current Regulations)
(S-1)
(S-2)
Surve y APBN
Rep.
Evaluati on
GWA/WKP Tendering (S-3)
WKP
IUP Issuance (S-4)
(S-5)
(S-6)
FS
Exploitat ion
GWA/WKP Determination
Explorat ion
MEMR
Potential Map
Pre-Survey
Electricity Price
(S-0)
BUSINESS STADIUM (S-X) Report of Tendering Process
Units
Geothermal Potential
Potential/ Stadium
(S-7)
(S-8)
(S-9)
Production/ Utilization
(S-10)
IUP-N
WKP-N
(S4-N)
(S3-N) Tender Winner
Survey APBD Prov.
WKP-P
Pemda Kab./ Kota
Survey APBD Kab./ Kota
WKP-K
Corporation
IUP-P
(S3-P) Tender Winner
(S4-P)
The Golden Bridge
Prov. Gov.
IUP-K
(S3-K)
(S4-K)
Tender Winner
Assignment Other Parties
Assignment
PLN
PPA © EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
Road Map of Geothermal Development 2006 – 2025 (based on Presidential Decree No. 5/2006 on National Energy Policy)
2006
2008
852 MW (Produksi)
1148 MW Existing WKP
2000 MW
1442 MW Existing WKP
2012
2016
2020
2025
3442 MW
4600 MW
6000 MW
9500 MW (Target)
1158 MW Existing WKP + New WKP
1400 MW New WKP
3500 MW New WKP
1189 MW Current Condition
5156 MW Plus 2nd Phase Crash Program Scenario
© EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
STRATEGICAL TARGET FOR GEOTHERMAL DEVELOPMENT 2010 S.D 2014 Presidential Regulation No. 04/2010 on Assignment to PT. PLN to Accelerate Power Plant
Development Using Renewable Energy, Coal and Gas MEMR Regulation No. 15/2010 on Projects List of Power Plant Accelerated Development
using Renewable Energy, Coal and Gas as well as Related Transmission Target for Geothermal Power Plant Development on Crash Program 10.000 MW
Phase II Development for Production on Existing Field : 645 MW Development for not yet in production on Existing Field : 1535 MW New Development Geothermal Working Area : 1787 MW Total of Geothermal Development 3967 MW
© EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
Geothermal Contribution on 2nd Phase 10,000 MW Power Development Acceleration Program (Based on Ministerial Decree No. 15/2010 on Projects List of Power Plant Accelerated Development using Renewable Energy, Coal and Gas as well as Related Transmission)
Additional Installed Capacity of Geothermal Power Plant up to 2014 is 3,967 MW
Existing GWA→ → 2180 MW New GWA → 1787 MW
Java → 1970 MW Outside Java → 1997 MW
Total investment needed for achieving this target is about 12 Billion USD (with assumption, development cost of 1 MW = 3 Million USD)
With developing 3,967 MW Geothermal Power Plant until 2014, could reduce emission about 24 Million ton CO2/Year (6,000 t CO2e/MW/Year) © EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
INVESTMENT OPPORTUNITIES - Development of 3,967 MW electricity from Geothermal in 10,000 MW Crash Program Stage II up to the year 2014 is required more than US$ 12,000 millions for the investment. - Development plan of 12,000 MW Geothermal Power Plant up to the year 2025, international supports are needed. - Foreign ownership in Geothermal Business is allowed up to 95 %; - Business opportunities in geothermal sector: Geothermal direct use; Low temperature geothermal potential; Small scale power plant. Partners and Investors are welcomed to be parts of Indonesia development as the largest geothermal producer.
© EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION MINISTRY OF ENERGY AND MINERAL RESOURCES
Jalan Jenderal Gatot Subroto, Kav. 49 Jakarta 12950 Telp/Faks : 021-5250575 www.ebtke.esdm.go.id www.energiterbarukan.net © EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
Geothermal Power Plant Projects included in Crash Program Phase II Geothermal Power Status NO Plant Project 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Seulawah Agam Jaboi Sarulla 1 Sarulla 2 Sorik Merapi Muaralaboh Lumut Balai Rantau Dadap Sungai Penuh Hululais Rajabasa Ulubelu 3 dan 4 Rawa Dano Kamojang 5 & 6 Cibuni Cisolok-Cisukarame Darajat Karaha Bodas Patuha Salak Tampomas Tangkuban Perahu I
Province
New WKP Aceh New WKP Aceh Existing WKP North Sumatera Existing WKP North Sumatera New WKP North Sumatera New WKP West Sumatera Existing WKP South Sumatera New WKP South Sumatera Existing WKP Jambi Existing WKP Bengkulu New WKP Lampung Existing WKP Lampung New WKP Banten Existing WKP West Java Existing WKP West Java New WKP West Java Existing WKP West Java Existing WKP West Java Existing WKP West Java Existing WKP West Java New WKP West Java New WKP West Java
Note : Cost to develop 1 MW = US$ 3 Million
Estimation Installed Required Geothermal Power Status of Capacity Capacity Financing 2014 NO Plant Project (MW) 2014 (MW) (US$ Million) 1x55 1x7 3x110 2x55 1x55 2x110 4x55 2x110 2x55 2x55 2x110 2x55 1x110 1x40 & 1x60 1x10 1x50 2x55 1x30 & 2x55 3x60 1x40 1x45 2x55
55 7 330 110 55 220 220 220 110 110 220 110 110 100 10 50 110 140 180 40 45 110
165 21 990 330 165 660 660 660 330 330 660 330 330 300 30 150 330 420 540 120 135 330
23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
Province
Estimation Installed Required of Capacity Capacity Financing 2014 (MW) 2014 (MW) (US$ Million)
Tangkuban Perahu II Existing WKP West Java 2x30 Wayang Windu Existing WKP West Java 2x120 Batu Raden New WKP Central Java 2x110 Dieng Existing WKP Central Java 1x55 & 1x60 Guci New WKP Central Java 1x55 Ungaran New WKP Central Java 1x55 Ijen New WKP East Java 2x55 Iyang Argopuro Existing WKP East Java 1x55 Wilis/Ngebel New WKP East Java 3x55 Lahendong 5 dan 6 Existing WKP North Sulawesi 2x20 Kotamobagu 1 dan 2 Existing WKP North Sulawesi 2x20 Kotamobagu 3 dan 4 Existing WKP North Sulawesi 2x20 Bora Open Area Central Sulawesi 1x5 Merana/Masaingi New WKP Central Sulawesi 2x10 Huu New WKP West Nusa Tenggara 2x10 Sembalun Open Area West Nusa Tenggara 2x10 Atadei New WKP East Nusa Tenggara 2x2,5 Sukoria New WKP East Nusa Tenggara 2x2,5 Tulehu Existing WKP Maluku 2x10 Jailolo New WKP North Maluku 2x5 Songa Wyaua New WKP North Maluku 1x5 Total Development of Geothermal Power Plant until 2014
60 240 220 115 55 55 110 55 165 40 40 40 5 20 20 20 5 5 20 10 5 3967
© EBTKE KESDM - 2011
180 720 660 345 165 165 330 165 495 120 120 120 15 60 60 60 15 15 60 30 15 11.901
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
No. 1 2
3
GWA Sibayak-Sinabung Cibeureum - Parabakti (Gn. Salak) Pengalengan
GWA before Law No. 27/2003
IUP Holder
Field
Developer
Potency (MW)
Installed (MW)
PT. PGE
Sibayak
PT. PGE
124
12
PT. PGE
Gn. Salak
CGS, Ltd
952
375
Wayang Windu
Star Energy Geothermal Wayang Windu
400
227
Patuha
PT. Geo Dipa Energi
706
-
PT. PGE
4
Kamojang-Darajat
PT. PGE
Kamojang Darajat
PT. PGE CGI, Ltd
855 610
200 255
5
Dieng
PT. PGE
Dieng
PT. Geo Dipa Energi
780
60
6 7
Lahendong-Tompaso Sibual-Buali
PT. PGE PT. PGE
Lahendong Sarulla
PT. PGE SOL
358 1146
60 -
8
Hululais - Tambang Sawah
PT. PGE
Hulu Lais
PT. PGE
873
-
9 10 11 12 13
Lumut Balai Sungaipenuh Ulubelu Karaha-Cakrabuana Buyan Bratan (Bedugul)
PT. PGE PT. PGE PT. PGE PT. PGE PT. PGE
Lumut Balai Sungai Penuh Ulubelu Karaha Bodas Bedugul
PT. PGE PT. PGE PT. PGE PT. PGE Bali Energy, Ltd
1066 208 556 725 276
-
14
Ulumbu
PT. PLN (Persero)
Ulumbu
PT. PLN (Persero)
199
-
15
Tulehu
PT. PLN (Persero)
Tulehu
PT. PLN (Persero)
100
-
16
Cibuni
KJK Teknosa
Cibuni
KJK Teknosa
140
-
17 18
Iyang-Argopuro Kotamobagu
PT. PGE PT. PGE
Iyang Argopuro Kotamobagu
PT. PGE PT. PGE
295 410
-
19
Ciater
PT. Wahana Sembada Sakti
Ciater
PT. Wahana Sembada Sakti
90
-
10,869
1,189
Total
© EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
New GWAs Offered Through Tender Process (after Law No. 27/2003 on Geothermal) As Total Project Scenario, IPP Scheme
NO
FIELD
REGENCY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Seulawah agam Jailolo T elaga Ngebel Ungaran Mt. T ampomas Mt. Cisolok Cisukarame T angkuban Perahu Mt. Jaboi Sokoria T alang Mt. Blawan Ijen Hu'u Daha Sipaholon Ria-ria Bukit Kili Sorik Marapi Roburan Marana Songa Wayaua Atadei Suwawa Kaldera Danau Banten Rajabasa Mt. Liki Pinangawan Suoh-Sekincau Rantau Dadap Guci Baturaden
Aceh Besar West Halmahera Ponorogo and Madiun Semarang and Kendal Sumedang and Subang Sukabumi Subang, Bandung and purwakarta Sabang Ende Solok Bondowoso, Banyuwangi and Situbondo Dompu Noth Tapanuli Solok Mandailing Natal Donggala South Halmahera Lembata Bone Bolanga and Gorontalo Serang and Pandeglang South Lampung Muara Laboh, Solok Selatan West Lampung Muara Enim, Lahat dan Pagar Alam T egal, Brebes and Pemalang Tegal, Brebes, Pemalang, Banyumas and
TOTAL
PROVINCE
Nangroe Aceh Darusallam North Maluku East Java Central Java West Java West Java West Java Nangroe Aceh Darusallam East Nusa Tenggara West Sumatera East Java West Nusa Tenggara North Sumatera West Sumatera North Sumatera Central Sulawesi North Maluku East Nusa Tenggara Gorontalo Banten Lampung West Sumatera Lampung South Sumatera Central Java Purbalingga Central Java
As of 10 July 2011 DEVELOP MENT TA RGETS (MW)
STATUS OF TENDER PROCESS
160 On Going 75 Finished 120 Finished 100 Finished 50 Finished 45 Finished 100 Finished 50 Finished 30 Finished 36 Preparation 270 Finished 65 Finished 75 Re-Tender 83 Re-Tender 200 Finished 36 Re-Tender 140 Preparation 40 Finished 110 Re-Tender 115 Finished 91 Finished 400 Finished 230 Finished 106 Finished 79 Finished 175 Finished © EBTKE KESDM - 2011 2981
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
GWA Determination Plan - 2011 NO
1 2 3 4 5 6 7 8 9
Area
Bonjol * Danau Ranau * Mataloko * Ciremei * Gn. Endut * Sembalun Wai Ratai Simbolon Samosir Telomoyo
Province
West Sumatera South Sumatera East Nusa Tenggara West Java Banten West Nusa Tenggara Lampung North Sumatera Central Java TOTAL
Potency (MWe)
Required Financing (US$ Million)
200 210 63 150 80 120 194 225 92
600 630 189 450 240 360 582 675 276 4,002
*) : determined April 21, 2010
© EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
Areas offered for Pre-Survey Assignment (Announcement of Director General of New Renewable Energy and Energy Conservation No. 104Pm/30/DJE/2011) No.
Location
Regency
Province
1.
Sungai Betung
Kerinci and Pesisir Selatan
Jambi and West Sumatera
2.
Sungai Tenang
Merangin
Jambi
3.
Ciseeng
Bogor and Lebak
West Java and Banten
4.
Malawa
Maros, Pangkajene Kepulauan, Bone and Barru
South Sulawesi
5.
Gn. Dua Saudara
Bitung
North Sulawesi
6.
Ulumbu
Manggarai
NTT
7.
Gn. Gede/Pangrango
Bogor, Sukabumi, and Cianjur
West Java
© EBTKE KESDM - 2011
Kementerian Energi dan Sumber Daya Mineral Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi
FLOW OF GEOTHERMAL BUSINES PROSES Local Government
MEMRE
REGULATOR
Power Purchaser (PLN)
Preliminary Survey
GWA
GWA Auction
Selling Price*)
Winner
Recommendation
BUSINESS ENTITY
Related Agencies
IUP Holder
1
Who
has th e Sen der??
Selling price approval
Buyer Candidate
Selling price agreement*)
2
Local gov. Permit yes
In Forrest?
Forestry Permit
no EXPLORATION
In Forrest?
yes Forestry Permit
no EXPLOITATION
*) main constraint
STEAM/ ELECTRICITY
Note: In Forest Area
EBTKE-KESDM KESDM- 2011 2010 ©©EBTKE