1 TEMPAT PENIMBUNAN STOCK PILE AND WASTE DUMP2 Jenis tempat penimbunan STOCK PILE AND WASTE DUMP3 TEMPAT PENIMBUNAN 1. WASTE DUMP LOKASI PEMBUANGAN OV...
TEMPAT PENIMBUNAN 1. WASTE DUMP LOKASI PEMBUANGAN OVERBURDEN ATAU MATERIAL KADAR RENDAH DAN ATAU MATERIAL BUKAN BIJIH YANG HARUS DIGALI DARI PIT UNTUK MEMPEROLEH BIJIH DALAM OPERASI TAMBANG TERBUKA
TEMPAT PENIMBUNAN 2. STOCK PILE TEMPAT PENYIMPANAN MATERIAL YANG AKAN DIGUNAKAN PADA SAAT YANG AKAN DATANG
STOCK PILE (S.P.)
S.P. BIJIH KADAR RENDAH YANG DAPAT DIPROSES PADA WAKTU YG AKAN DATANG
S.P. TANAH PUCUK YANG DAPAT DIGUNAKAN UNTUK REKLAMASI
WASTE DUMP
LUAS WASTE DUMP SEKITAR 2-3 KALI LUAS DAERAH PENAMBANGAN PERTIMBANGAN: 1. SWELL FACTOR 30-45% 2. SUDUT KEMIRINGAN LEBIH LANDAI 3. MATERIAL PADA UMUMNYA TIDAK DAPAT DITIMBUN SETINGGI KEDALAMAN PIT
JENIS DUMP
1. VALLEY FILL ATAU CREST DUMP
2. TERRACE DUMP
Valley fill or terrace dump?
Valley fill or terrace dump?
VALLEY FILL ATAU CREST DUMP A. DITERAPKAN PADA TOPOGRAFI YANG CURAM B. DUMP CREST DITETAPKAN PD AWAL PEMBT DUMP C. DIBANGUN BERDASARKAN ANGLE OF REPOSE D. DUMPING DIMULAI PADA DUMP FINAL TOE E. PEMADATAN DIPERLUKAN UNTUK REKLAMASI
TERRACE DUMP DITERAPKAN PADA TOPOGRAFI TIDAK CURAM TIMBUNAN DARI BAWAH KE ATAS TINGGI LIFT 20-40M LIFT BERIKUTNYA TERLETAK DIBELAKANG OVERALL SLOPE ANGLE MENDEKATI YG DIPERLUKAN UNTUK REKLAMASI: 22-27 DERAJAT
PEMILIHAN LOKASI
LOKASI DAN UKURAN PIT: FUNGSI WAKTU TOPOGRAFI VOLUME WASTE ROCK: FUNGSI WAKTU BATAS KONSESI PERTAMBANGAN JALUR PENIRISAN YANG ADA PERSYARATAN REKLAMASI KONDISI FONDASI PERALATAN PENANGANAN MATERIAL
PEMILIHAN LOKASI WASTE DUMP
2001
2002 EAST DUMP
EAST DUMP
RL150
RL360
2003
RL195
EAST DUMP
RL330
RL60
RL315
PARAMETER RANCANGAN
1. ANGLE OF REPOSE: 34-37 DERAJAT TINGGI DUMP, BONGKAH BATUAN, KEC DUMP 2. SWELL FACTOR: 30-45% MATERIAL DPT DIPADATKAN 5-15%. DT VS BC? 3. TINGGI LIFT: 15-40M, REKLAMASI 2H:1V, 2,5h:1V 4. JARAK DARI PIT 5. ARAH LIMPASAN AIR HUJAN DIRANCANG MENJAUHI CREST
PENAKSIRAN VOLUME 1. PENAMPANG HORISONTAL (PLAN VIEW) UKUR LUAS DAERAH PADA TOE DAN CREST SETIAP LIFT LUAS LIFT = RATA2 LUAS TOE DAN CREST TINGGI LIFT UNTUK MENAKSIR VOLUME VOLUME TOTAL DUMP = PENJUMLH VOL TIAP LIFT
PENAKSIRAN VOLUME
LANJUTAN
2. PENAMPANG VERTIKAL (X-SECT)
BUAT BBRP X-SECT DENGAN JARAK SAMA UKUR LUAS TIAP PENAMPANG BUAT X-SECT SELANJT DAN UKUR LUAS HIT VOLUME VOLUME TOTAL = PENJMLH VOL TIAP X-SECT
PENAKSIRAN VOLUME
LANJUTAN
3. TRIAL AND ERROR (COBA-COBA)
a. RANCANGLAH DUMP SECARA COBA-COBA DAN TAKSIR VOLUME b. BANDINGKAN DG VOLUME DUMP YANG DIPERLUKAN c. SESUAIKAN RANCANGAN DAN UKUR KEMBALI SAMPAI VOLUME YG DIINGINKAN DICAPAI (2-3 X)
PROSEDUR RANCANGAN TIMBUNAN 1. JUMLAH MATERIAL YG DITIMBUN: ORE/WASTE 2. LOKASI TIMBUNAN – DIGITASI TOPO 3. MERANCANG TIMBUNAN DARI ELEVASI TERENDAH MENUJU ELEVASI TERTENTU SESUAI TONASE MATERIAL 4. LAKUKAN PERHITUNGAN KAPASITAS TIMBUNAN SESUAI TONASE MATERIAL YG AKAN DITIMBUN 5. PENGISIAN MATERIAL YG AKAN DITIMBUN SHG MEMBENTUK TOPOGRAFI AKHIR 6. BENTUK TIMBUNAN DIGBRKAN DALAM BENTUK 3D
REKLAMASI
SYARAT LINGKUNGAN, RANCANGAN: 2H:1V ATAU 2,5H:1V
TUJUAN STABILITAS JANGKA PANJANG DAN MEMUDAHKAN REVEGETASI
PEKERJAAN YG HARUS DILAKUKAN:
1. TIMBUN DENGAN OB DAN TOP SOIL 2. MEMELIHARA SALURAN AIR DAN SETTLING POND 3. MEMANTAU AIR DARI DUMP (MASALAH AAT) 4. WASTE DUMP AKTIF GUNAKAN 1 TRACK-DOZER 5. JAGA DUMP TETAP BERSIH DAN PANTAU KEMIRINGAN 6. TIMBUN MAT DEKAT CREST, DOZER MENDORONG MATERIAL MELALUI CREST TSB 7. MENCEGAH PERALATAN YG TERPERANGKAP
CARA PENIMBUNAN
DOWN HILL DOZING BULLDOZER MENDORONG MATERIAL KE BAWAH HIGH WALL ATAU FLOAT DOZING BULLDOZER GALI DAN KUMPULKAN MAT KMD DORONG KE LERENG YG CURAM TRENCH ATAU SLOAT DOZING BULLDOZER MENGGUSUR MELALUI JALAN YG SAMA, SHG KANAN KIRI TERBENTUK DINDING (SPILLAGE)