DRAINAGEdesign
Perencanaan Drainase Analisa Hidrologi
Bulan Januari Februari Maret April Mei Juni Juli Agustus September Oktober Nopember Desember MAKS
Bulan Januari Februari Maret April Mei Juni Juli Agustus September Oktober Nopember Desember MAKS
Bulan Januari Februari Maret April Mei Juni Juli Agustus September Oktober Nopember Desember MAKS
Tahun 2006 2007 84 70 103 51 76 54 58 73 60 19 0 70 0 16 0 0 0 27 0 0 0 20 121 104 121 104
2008 110 85 140 25 45 51 0 5 0 65 43 78 140
2009 80 84 25 67 60 52 5 5 5 20 45 58 84
2010 45 85 35 32 41 24 67 61 82 180 71 125 180
2011 43 13 54 31 34 4 5 5 9 60 53 23 60
2012 46 60 70 58 33 8 32 0 25 43 22 23 70
2005 75 102 41 0 0 75 0 0 0 95 21 21 102
Tahun 2006 2007 0 0 0 0 99 0 67 R 42 10 0 25 0 0 0 0 0 0 0 66 5 56 0 42 99 66
2008 84 54 69 37 13 0 0 0 0 86 27 69 86
2009 27 80 35 43 31 51 0 0 0 3 11 17 80
2010 28 72 63 48 44 47 29 25 24 67 58 39 72
2011 0 0 34 67 44 47 29 32 22 12 31 39 67
2012 6 72 62 30 54 34 25 53 24 67 58 39 72
2005 15 45 50 40 0 52 20 0 0 22 35 57 57
Tahun 2006 2007 55 5 65 5 51 10 56 5 30 4 0 40 0 0 0 0 0 0 0 40 0 5 6 5 65 40
2008 5 7 40 30 3 2 0 0 0 3 21 7 40
2009 7 9 6 8 3 5 0 0 0 0 19 5 19
2010 7 9 7 5 4 2 3 1 7 9 5 8 9
2011 5 5 6 15 7 6 3 5 9 32 24 34 34
2012 8 5 23 6 6 4 6 6 21 13 16 23 23
2001 117 53 76 37 40 10 0 0 0 54 34 60 117
2002 115 60 52 53 60 40 0 0 0 0 54 41 115
2003 58 78 55 70 55 35 0 0 0 1 24 63 78
2004 27 25 94 15 20 0 20 R R R 25 0 94
2005 R R R 64 32 55 0 30 2 0 51 80
2001 R R 31 46 47 15 0 0 0 69 20 68 69
2002 169 40 80 18 30 0 0 0 0 0 17 64 169
2003 49 49 77 17 30 0 0 0 0 10 25 35 77
2004 37 60 0 0 R 0 0 0 0 0 0 0 60
2001 96 67 96 60 46 34 34 0 0 34 23 74 96
2002 130 30 25 30 0 0 0 0 0 0 37 54 130
2003 52 40 24 10 0 0 0 0 0 15 15 15 52
2004 0 0 0 0 0 0 0 0 0 0 0 0 0
80
Sta. Hujan Socah
Sta. Hujan Labang
Sta. Hujan Kamal
Pembahasan
Perencanaan Drainase Analisa Hidrologi
AN SAL. KIRI
DAERAH ALIR
2%
5%
2m
7m
DAERAH ALIR SAL. TEN AN GAH
5%
ALIRAN DAERAH GAH SAL. TEN
5%
5%
2m
5m
5%
2m
Pembahasan
DAERAH ALIR AN SAL. KAN AN
5%
7m
Gambar. Pembagian Daerah Pengaliran pada perhitungan t0 Debit saluran kiri/kanan Diketahui : Ξ± = 1/3,6 Q = πΆ πͺ. π°. π¨ π = Γ π, πππ Γ ππ, πππ Γ (π, ππππ + π, ππππ) π,π
= 0,175 m3/dt Debit saluran tengah Diketahui : Ξ± = 1/3,6 Q = πΆ πͺ. π°. π¨ π = Γ π, ππ Γ ππ, πππ Γ (π. π, ππππππ + π, ππππππ ) π,π
= 0,2585 m3/dt
Debit periode ulang
5th
5%
2m
0.20
0.50
0.20
Perencanaan Drainase Analisa Hidrolika
0 0.70
0.90 Tipikal Saluran Tepi
Pembahasan
Perencanaan Drainase Analisa Hidrolika
Tipikal Saluran Tengah
Pembahasan
Perencanaan Drainase Analisa Hidrolika
Tipikal Box Culvert (Prcast)
No. 1
Kode GG I
2
GG II
3
GG III
4
GG IV
5
GG V
6
GG VI
7
GG VII
8
GG VIII
Q
0.829 0.745 0.699 1.095 0.636 0.637 1.131 0.678
Sumber : Hasil Perhitungan
Hhitung
0.74 0.70 0.68 0.85 0.65 0.65 0.87 0.67
Hpakai
1 1 1 1 1 1 1 1
Bpakai
1 1 1 1 1 1 1 1
Pembahasan
A
P
R
I
1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3
0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33
0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016
CONSTRUCTIONcost
Analisa Anggaran Biaya
Volume Pekerjaan
Pembahasan
Volume Galian PERMUK AAN TANA H
48247746,44 m3
EKSISTING
LUAS PENAMPANG GALIAN PERMUKAAN TANAH RENCANA
Volume Timbunan 160462,395 m3
LAPISAN PERKERASAN PERMUKAAN TANAH RENCANA
LUAS PENAMPANG TIMBUNAN PERMUK
AAN TANA H EKSISTIN G
Laston Ms 744 (AC/WC) Base Course (Agg. B) Sub Base Course (Sirtu Kelas A) Subgrade (Soil Improvement) Prime Coat Tack Coat
= = = = = =
71698,01 Ton 40651,268 m3 70433,8 m3 78656,34 m3 285162, 55 liter 81475,016 liter
Analisa Anggaran Biaya
Volume Pekerjaan
0.20
0.50
0.20
Sal. Batu Kali
0 0.70
Saluran Tepi 0.90
13843,54 m3
Plesteran 69218 m2
Sal. Precast 12124 buah Saluran Tengah
Box Culvert Precast 176 m
Box Culvert (Prcast)
Pembahasan
Analisa Anggaran Biaya
Volume Pekerjaan
0.20
Dinding Penahan (Beton) 198,2 m3
H
0.50 LASTON MS744 10cm BATU PECAH KELAS B 20cm SIRTU PITRUN KELAS A 20cm
2.50
Pengaman Talud (Tipe I) 184,65 m3
DINDING PENAHAN TIPE III
5m
Pengaman Talud (Tipe II) 4705,42 m3
8m
5m 0.12 m
Marka Jalan 1396,70 m2
Pembahasan
Analisa Anggaran Biaya Biaya Konstruksi
Pembahasan
UPAH PEKERJA Uraian
Satuan
1
Mandor
O.H
2
Operator
3
Pembantu Operator
4
Supir
5
Pembantu Supir
6
O.H
Upah/Hari (Rp)
Upah/Jam
85000
10625
125000
15625
75000
9375
75000
9375
O.H
67500
8437.5
Pekerja/Pembantu Tukang
O.H
70000
8750
7
Tukang Besi
O.H
75000
9375
8
Kepala Tukang Besi
O.H
80000
10000
9
Kepala Tukang Batu
O.H
80000
10000
10
Tukang Batu
O.H
75000
9375
SEWA ALAT No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Uraian Motor Grader 125-140 pk Truck Tangki Air Walles Asphalt Mixing Plant Generator Set Wheel Loader 10-15 HP Dump Truck 8-10 m3 (5T) Asphalt Finisher Tandem Roller Pneumatic Tire Roller Alat Bantu Pembuatan Aspal Emulsi Asphalt Spayer Compessor 400 - 600 L/M Excavator (6m3) Vibrator Roller BullDozer Tandem Roller (min 5 jam)
Kode
Satuan Jam Hari Jam Jam Unit Jam Jam Jam Jam Jam Unit Jam Jam Jam Jam Jam Jam
Harga (Rp) 261250 470250 100320 3762000 522500 543400 61750 992750 250800 209000 19000 26125 88825 123500 128250 385695 250800
Uraian Uraian Pasir Pasir Beton Beton (Kasar) (Kasar) Pasir Pasir Pasang Pasang Pasir Pasir Urug Urug Agregat Agregat Kasar Kasar Agregat Agregat Halus Halus Filler Filler Kayu Kayu meranti meranti bekisting bekisting Kayu Kayu Kamper Kamper balok balok 3/5 3/5 Plywood Plywood tebal tebal 99 mm mm Paku Paku Usuk Usuk Minyak Minyak Bekisting Bekisting
Kode Kode M01a M01a M01d M01d M03 M03 M04 M04 M05 M05
Thermoplastic Thermoplastic Glass Glass Beed Beed
Batu Batu Kali Kali Batu Batu Pecah Pecah Mesin Mesin 1/2cm 1/2cm Batu Batu Pecah Pecah Mesin Mesin 2/3cm 2/3cm Batu Batu Pecah Pecah Mesin Mesin 0,5/1cm 0,5/1cm Batu Batu Krikil Krikil Beton Beton Tanah Tanah Urug Urug Sirtu M16 Sirtu M16 Aspal Curah Aspal Curah Tack Coat Tack Coat Geotextile M30 Geotextile M30 Minyak Minyak Tanah Tanah Semen Portland (40kg) Semen Portland (40kg) Air Air (Biaya (Biaya Air Air Tawar) Tawar) Besi Besi Beton Beton Kawat Beton Kawat Beton U U Gutter Gutter U/1000/1000-2400 U/1000/1000-2400 U U Gutter Gutter U/1200/1200-2400 U/1200/1200-2400 U Gutter U/1500/1500-2400 U Gutter U/1500/1500-2400 Kayu Meranti Kayu Meranti Bekisting Bekisting Katu Katu Kamper Kamper Balok Balok 3/5 3/5 Plywood 9mm Plywood 9mm Paku Usuk Paku Usuk Minyak Minyak Bekisting Bekisting Box Box Culvert Culvert 1500X1500X1200 1500X1500X1200 Box Culvert Box Culvert 2400x2400x1200 2400x2400x1200 Box Culvert 4500x2500x1200 Box Culvert 4500x2500x1200 Box Culvert Box Culvert 4300x2500x1200 4300x2500x1200 (t (t == 200mm) 200mm) U-Ditch U-Ditch 600x600x1200 600x600x1200 U-Ditch 600x800x1200 U-Ditch 600x800x1200 U-Ditch U-Ditch 800x800x1200 800x800x1200 U-Ditch U-Ditch 1000x1000x1000 1000x1000x1000 U-Ditch 1000x1000x1200 U-Ditch 1000x1000x1200 (t=150mm) (t=150mm) U-Ditch 1000x1500x1200 U-Ditch 1000x1500x1200 U-Ditch 1000x1200x1200 U-Ditch 1000x1200x1200 U-Ditch 1200x1200x1200 U-Ditch 1200x1200x1200
Satuan Satuan
m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 Kg Kg m3 m3 m3 m3 lembar lembar Kg Kg ltr ltr Kg Kg Kg Kg
m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 Kg Kg Liter Liter m2 m2 liter liter Zak Zak Liter Liter Kg Kg Kg Kg Bh Bh Bh Bh Bh Bh m3 m3 m3 m3 Lembar Lembar Kg Kg Liter Liter Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh Bh
Harga Harga (Rp) (Rp) Keterangan Keterangan 151525 151525 151525 151525 120175 120175 167200 167200 161975 161975 1568 1568 1966500 1966500 5700000 5700000 84170 84170 15675 15675 6270 6270 21898 21898 40945 40945
125400 125400 271700 271700 175085 175085 155705 155705 130625 130625 120175 120175 130625 130625 7315 7315 12540 12540 15200 15200 8360 8360 49685 49685 25 25 8645 8645 15675 15675 2448435 2448435 2938122 2938122 3672652 3672652 1966500 1966500 5700000 5700000 84170 84170 15675 15675 6270 6270 6880000 6880000 11257000 11257000 17635000 17635000 15330000 15330000 1317000 1317000 1530000 1530000 1591000 1591000 1910000 1910000 1602000 1602000 2646000 2646000 2579500 2579500 2175000 2175000
HARGA BAHAN
Berdasarkanharga hargadari dariPT. PT.Boral BoralPipeline Pipeline Berdasarkan andPrecast PrecastIndonesia Indonesia| |Sumber Sumber and :http://esourcing.surabaya.go.id/profil/bor :http://esourcing.surabaya.go.id/profil/bor al?page=5 al?page=5
No.
No. No. 11 22 33 44 55 66 77 88 99 10 10 11 11 12 12 13 13 14 14 15 15 16 16 17 17 18 18 19 19 20 20 21 21 22 22 23 23 24 24 25 25 26 26 27 27 28 28 29 29 30 30 31 31 32 32 33 33 34 34 35 35 36 36 37 37 38 38 39 39 40 40 41 41 42 42 43 43 44 44 45 45 46 46 47 47 48 48
Analisa Anggaran Biaya Biaya Konstruksi
No.
Uraian Pekerjaan
1 Pekerjaan Tanah 1.1 Pembersihan Lahan 1.2 Galian Tanah 1.3 Timbunan Tanah
Volume
Harga Satuan Pekrjaan
Jumlah Harga
160462.395
m2 m3 m3
Rp Rp Rp
32,655.28 Rp 20,942.05 Rp 169,477.83 Rp
2 Perkerjaan Perkerasan 2.1 Lapis Permukaan (AC-WC) 2.2 Lapis Pondasi Atas (Agregat B) 2.3 Lapis Pondasi Bawah (Sirtu Pitrun Kelas B) 2.4 Perbaikan Tanah (Soil Improvement) 2.5 Lapis Resap Perekat (Prime Coat) 2.6 Lapis Perekat (Tack Coat)
71698.01 40651.268 70433.8 78656.34 285162.55 81475.016
Ton m3 m3 m3 liter liter
Rp Rp Rp Rp Rp Rp
880,342.93 310,309.67 202,863.89 169,477.83 13,113.47 12,925.99
Rp Rp Rp Rp Rp Rp
63,118,836,431.59 12,614,481,491.62 14,288,474,471.72 13,330,505,425.66 3,739,471,528.36 1,053,145,242.07
3 Pekerjaan Drainase 3.1 Saluran Tepi (Batu Kali Belah) 3.2 Plesteran (1 pc : 4 ps) 3.3 Saluran Tengah (U-Ditch Precast) 3.3 Gorong-Gorong Precast (1500 x 1500 x 1200)
13843.54 69218 12124 176
m3 m2 m' m'
Rp Rp Rp Rp
621,358.21 48,904.86 1,259,413.01 6,358,625.70
Rp Rp Rp Rp
8,601,797,234.46 3,385,096,779.45 15,269,123,310.39 1,119,118,122.87
4 Pekerjaan Pengaman Longsor 4.1 Dinding Penahan Beton (Tipe I) 4.2 Dinding Penahan Batu Kali (Tipe II) 4.3 Dinding Penahan Batu Kali (Tipe III)
198.2 184.65 4705.42
m3 m3 m3
Rp Rp Rp
5,087,333.35 Rp 621,358.21 Rp 621,358.21 Rp
1,008,309,469.97 114,733,793.48 2,923,751,348.50
m2 m2
Rp Rp
648,099.51 Rp 648,099.51 Rp
1,131,510,457.88 905,200,589.11
Rp Rp
1,193,507,919,227.61 119,350,791,922.76
Rp
1,312,858,711,150.38
5 Pekerjaan Minor 5.1 Marka Menerus (Solid) 5.2 Marka Putus-putus Jumlah PPN (10%) TOTAL
407375.08
Satuan
48247746.44
1745.89 1396.7
Pembahasan
13,302,948,117.17 1,010,406,597,714.44 27,194,817,698.89
Terbilang Satu Triliun Tiga Ratus Dua Belas Miliar Delapan Ratus Lima Puluh Delapan Juta Tujuh Ratus Sebelas Ribu Seratus Lima Puluh Ribu Rupiah
Total Biaya Konstruksi
Rp. 1.312.858.711.150,Terbilang :
βSatu Triliun Tiga Ratus Dua Belas Miliar Delapan Ratus Lima Puluh Delapan Juta Tujuh Ratus Sebelas Ribu Seratus Lima Puluh Ribu Rupiahβ
projectCONCLUSION
KESIMPULAN Kesimpulan dan Saran
1. Jalan direncanakan dengan tipe 4/2 D, dengan dimensi : - Lebar lajur = 3,5 meter - Lebar Jalur = 7 meter - Lebar Median = 5 meter - Lebar Bahu = 2 meter - Kecepatan rencana : 80 km/jam
3.Perkerasan jalan Segmen I dan III - Lapis permukaan - Lapis pondasi atas - Lapis pondasi bawah - Soil Improvement Segmen II - Lapis permukaan - Lapis pondasi atas - Lapis pondasi bawah
= = = =
Pembahasan
2. Geometrik jalan Alinyemen Horisontal : 11 PI S-C-S 3 PI S-S Alinyemen Vettikal : 14 PVI (Cembung) 11 PVI (Cekung) Superelevasi : Maksimum 10%
16 cm (Laston Ms744 AC-WC) 20 cm (Agregat Kelas B) 60 cm (Sirtu pitrun Kelas A) 100 cm (CBR 5%)
= 16 cm (Laston Ms744 AC-WC) = 20 cm (Agregat Kelas B) = 60 cm (Sirtu pitrun Kelas A)
KESIMPULAN Kesimpulan dan Saran
4. Desain Geometrik Persimpangan Simpang Suramadu - Burneh Approach : Wa = 10,5m; We = 10,5m; WLTOR = 3,5m; Wx = 7m. - Akses Approach : Wa = 10,5m; We = 10,5m; WLTOR = 3,5m; Wx = 7m. - Sampang Approach : Wa = 7m; We = 7m; WLTOR = 3,5m; Wx = 7m. - Suramadu Approach : Wa = 10,5m; We = 10,5m; WLTOR = 3,5m; Wx = 7m.
Simpang Suramadu - Bangkalan Approach : Wa = 7m; We = 7m; WLTOR = 3,5m; Wx = 7m. - Akses Approach : Wa = 10,5m; We = 10,5m; WLTOR = 3,5m; Wx = 7m. - Kamal Approach : Wa = 7m; We = 7m; WLTOR = 3,5m; Wx = 7m. - Pelabuhan Approach : Wa = 10,5m; We = 10,5m; WLTOR = 3,5m; Wx = 7m.
Pembahasan
5. Desain Drainase Pada desain drainase terdapat beberapa tipe dimensi saluran, yaitu : Saluran Tepi (Pasangan Batu Kali) Tipe SS I = (40cm x 80cm); Waking = 20cm Tipe SS II = (40cm x 90cm); Waking = 20cm Tipe SS III = (30cm x 70cm); Waking = 20cm Tipe SS IV = (40cm x 70cm); Waking = 20cm Tipe SS V = (30cm x 60cm); Waking = 20cm Tipe SS VI = (20cm x 50cm); Waking = 20cm
Saluran Tengah (Precast) Tipe ST I = 60cm x 60cm Gorong-gorong (Precast) Tipe A = (100cm x 100cm)
KESIMPULAN Kesimpulan dan Saran
6.
Pembahasan
Biaya Konstruksi
Rp. 1.312.858.711.150,Terbilang : βSatu Triliun Tiga Ratus Dua Belas Miliar Delapan Ratus Lima Puluh Delapan Juta Tujuh Ratus Sebelas Ribu Seratus Lima Puluh Ribu Rupiahβ
SARAN Pembahasan
1.
2. 3. 4. 5. 6.
Dalam perencanaan tugas akhir kali ini hendaknya memperhatikan beberapa hal berikut : Perencanaan jalan sebaiknya menggunakan data selengkap mungkin, khususnya data pengukuran langsung baik itu data cross section maupun long section lokasi rencana. Hal ini dimaksudkan untuk mendapatkan hasil perhitungan yang lebih optimal, khusunya pada perhitungan dimensi dan biaya konstruksi. Perlunya beberapa alternatif trase yang disediakan, agar dapat memperoleh trase yang terbaik nantinya. Perlunya dilakukan studi lebih lanjut tentang metode pelaksanaan pembangunan konstruksi. Perlunya pengawasan yang baik pasa saat masa konstruksi berlangsung, agar hasil perencanaan dapat terealisasi secara optimal Perlunya studi lanjut tentang perkuatan lenreng dan dinding penahan longsor. Perlunya studi lanjut pada bagian detail konstruksi jembatan.
SEKIAN WASSALAMUALAIKUM