Master’s Theses March 2007 Civil Engineering Stevinweg 1 PO Box 5048 2600 GA Delft The Netherlands Telephone:
+31-(0)15-2788234
Telefax:
+31-(0)15-2784889
Table of Contents
Master’s Theses
1
March 2007
1
Table of Contents Preface What is the graduation book exactly?
3 9 10
Civil Engineering Theses Structural Engineering
13
Structural design of reinforced concrete pile caps
14
Student: A.V. van de Graaf Geboorde tunnels in ultra hoge sterkte beton
15
Student: T.W. Groeneweg Application of high strength steel in Steel pin connections and Double shear timber joints
16
Student: R.D. Hieralal De drijvende fundering
17
Student: Maarten Kuijper Externally bonded carbon fibre reinforced polymers
18
Student: R.H.Ringers Vloeistofreservoirs: Maximale afmetingen ten aanzien van vloeistofdichtheid
19
Student: L. Stapper
Civil Engineering Theses Building Engineering
21
Een Living Bridge voor Amsterdam
22
Student: L. Dietz Waarde van het ontwerp in relatie tot de waarde van het proces
23
Student: T.J. Duvivier Ondergrondse kleine infrastructuur
24
Student: M.P. Franken Research of the functional and technical feasibility of a floating football stadium
25
Student: N.T.N. Groenendijk Optimization of Dome Housing in Sri Lanka
26
Student: C. Hammer Design tools for the Virtual Wind Tunnel
27
Student: R.A.G. Kerklaan Functioneel Specificeren bij projecten van Rijkswaterstaat
28
Student: A.W. Lever Variantenonderzoek Onderbouw Parkhaventoren
29
Student: O. Los Progressive Collapse Assessment Student: M. Smith
30
I
Inhoudsopgave
0307
Optimisation of structural transfer zones in multi-use buildings
31
Student: R. van de Straat Parametric Associative Design for Free Form Architecture
32
Student: P. Vermeij
Civil Engineering Theses Hydraulic & Geo Engineering
33
Gabion Stability
34
Student: R.H.P.A. Beekx Veldproeven op steenzettingen
35
Student: J.A.H. Blom “Sandwich wall as the quay wall for the future”
36
Student: P. Bonte “Dynamic behaviour of jetty structures under seismic conditions“
37
Studente: H. de Brabander Effects of softwood vegetation within groyne fields
38
Student: M.T.B. van den Broek Floating Breakwater
39
Student: M.W. Fousert Feasibility Study on Tidal Power Barrages
40
Including plant design and site selection
40
Student: J.J. van Harn The sandhunger of the Oosterschelde
41
Student: M.L.E.B. van der Hoeven The influence of flow acceleration on the stability of stones
42
Student: M. Huijsmans Scour around an offshore wind turbine
Student: W.F. Louwersheimer Dealing with uncertainties in the design of bottom protection near quay walls
43
44
Student: A.A.Roubos “Computational modelling on the final closure gaps in the Saemangeum dam, South Korea”
45
Student: M. van der Sande Hydraulic fracture grouting
46
Laboratory experiments in sand
46
Student: M.P.M.Sanders The influence of flow acceleration on the stability of stones
47
Student: T. Schweckendieck An analysis of friction by microtunneling (N.Verburg; 1041363) Student: N. Verburg
48
0307
Inhoudsopgave
Civil Engineering Theses Watermanagement
49
Probabilistic modeling of sewer deterioration
50
Student: J. Dirksen Risk Assessment for Floods Due to Precipitation Exceeding Drainage Capacity
51
Student: U. Karamahmut The impact of the deep water extraction at the position of the fresh-salt interface
52
Student: N.L.Kramer Integrated water quantity and water quality control of lowland water systems
53
Student: B. van Rossum A distributed stream temperature model using high resolution temperature observations
54
Student: M. Westhoff
Civil Engineering Theses Transport & Planning
55
Dynamisch Railverkeersmanagement op knelpunten
56
Student: M. van Dijk De oorzaken van de verslechterde doorstroming bij 80 km zones
57
Student: H.J. Harms Systematische herinrichting van zwarte punten in Vlaanderen
58
Student: M. van ‘t Hof Modeling interaction between pedestrians and revolving doors
59
Student: R. Landman
Applied Earth Sciences Theses Resource Engineering
61
The recyclability of ultra light car designs
62
Student: M. Gadziala
Applied Earth Sciences Theses Petroleum Engineering and Geosciences
63
Using Real Data to test Reservoir Model Updating with the Ensemble Kalman Filter
64
Student: H.J. de Boer Sediment Mass Balance Study of the late-Holocene Prodelta on the Northern Adriatic Shelf
65
Student: W. Bron An Integrated Study into the Reservoir Characteristics of Miocene Mangrove Deposits of Mallorca
66
Student: H. Coppes Enhanced mass transfer of CO2 gas into water by density driven natural convection
67
Student: H.A. Delil Simultaneous Measurements of Capillary Pressure and Dielectric Constant in Porous Media from 50 Hz to 3 MHz 6 8 Student: L.M. Moreno Tirado Recovery Enhancement by Injection of Low Quality Steam with Volatile Oil Student: M.N. Guy
69
0307
Stress estimation and gas detection from seismic reflection coefficients at a non-welded interface
70
Student: J. van der Neut Produced Water Re-Injection
71
Student: C.C. Obeta Modeling sediment storage in a tidal dominated delta, the Fly River, Papua New Guinea
72
Student: Nawien R. Sheombarsing
Applied Earth Sciences Theses Engineering Geology
73
The investigation on the formulation of a new design code for MV-piles
74
Student: R.L. van Hof Influence of spatial correlation length on predicted settlements of a road embankment
75
Student: S. Kalamatas Plaxis Soft Soil Creep: de toepassing van een isotroop kruipmodel op de anisotrope ondergrond
76
Student: R. Servais
Offshore Engineering Theses Conceptual Design of a Tension Leg Platform Optimized for the Heerema Group capabilities Student: H.T. Brinkhuis Development of the Yoke Quay Mooring Concept (YQM) Student: E.W. Heerema A Practical Assessment of Lateral Buckling Sensitivity of Subsea Pipelines
78 79 80
Student: M. van Heel Feasibility study of the use of the Ampelmann in Shell
81
Student: J.M.L. Koch Fsru processes
82
Student: R.C.J. Lagers Structural analysis of impact on guides and bumpers
83
Student: P.J. Maas Basic design of hydrate mining equipment
84
Student; W.J. Overes The upgrade of “Noble to Van Langeveld” to 1500 m water depth capacity
85
Student: A. Smit Structural optimization of monopile foundations for offshore windturbines handled by integrated analysis
86
Student: Roel Swinkels A probabilistic approach to jack-up leg penetration in stratified soils
87
Student: T. van der Wal
Last year’s Theses
89
Research groups and professors within the faculty of Civil Engineering and Geosciences
99
0307
0307
0307
Preface
Once again a group of students from the Faculty of Civil Engineering and Applied Earth Sciences has successfully completed their study; once again the faculty has every reason to be proud of the high calibre of its engineers. You will share this opinion when you read the summaries of the proficiency tests which our students have passed to acquire the title of Master of Science (Engineer). The summaries clearly reflect the extensiveness and societal relevance of our education programmes. Civil Engineering with specialisations in, amongst others, Transport & Planning, Water Management,
Society has nothing to gain if our ideas remain
Hydraulic Engineering, Building and Structural
ensconced within the walls of the university. We can
Engineering; and Applied Earth Sciences, with
only contribute substantially when the professionals
its own specialisations, give our engineers the
take our ideas on board, apply them effectively,
knowledge and skills that will enable them to rise
and create safety and sustainability. Our graduates
to the challenge posed by the future problems of
play a leading role in this process. Their practical
society. They will be the people here and abroad
experience and knowledge of the real world will
who will ensure that there is clean drinking water,
make them our clients and ambassadors in the
meet the energy demands, develop new modes of
future.
transport and build with sustainable resources.
I wish our new Masters of Science an interesting and challenging future.
The faculty itself will continue to engage in scientific research on the same societal issues and look for
L. de Quelerij
new ways of solving the problems of the future.
Dean
0307
10
What is the graduation book exactly?
“Master’s Theses February 2007” contains
The Applied Earth Sciences Master’s programme has
summaries of the theses produced by various
three specialisations:
students who obtained a Master of Science degree
•
Resource Engineering
at the Delft University of Technology. The students
•
Petroleum Engineering and Geosciences
in question graduated in “Civil Engineering”,
•
Engineering Geology
“Applied Earth Sciences”, “Transport, Infrastructure and Logistics” or “Offshore Engineering”.
The Offshore Engineering Master’s programme
The purpose of this publication is to inform
The Transport, Infrastructure and Logistics Master’s
professionals working in these fields about recent
programme
developments in teaching and research at the Faculty of Civil Engineering and Geosciences. In
All of the summaries have a similar layout. Call the
many cases, the subject of the Master’s thesis is
department in question if you require further details
based on a request from professionals working
about a specific thesis (the phone number is given
in the field in question. In other cases, such
at the end of each summary).
individuals will collaborate in the realisation of a Master’s thesis. Alternatively, the thesis may be part
The section containing the new summaries is
of a wider research project within the department
followed by a comprehensive list of those produced
itself. The primary goal of the Master’s thesis is
last year. The layout of these summaries reflects
to round-off a student’s course of study at the
that of the previous publications.
TU, and to enable them to graduate as a Master of Science. As the regulations stand, this requires
A Master’s programme spans several different
an investment of 22 to 26 weeks of study. The
departments, each of which corresponds to a
summary of every completed thesis is published in
specialisation within the programme in question.
“Master’s Theses February 2007”, whether they are
At the end of this book is a comprehensive list of
merely average or truly outstanding.
specialisations, which includes the names of their respective professors.
The book’s layout
The summaries of the various theses are published per Master’s programme and specialisation:
The aim of the book
The main purpose of publishing these Master’s theses is to ensure that the outside world is better
• The Civil Engineering Master’s programme has five specialisations:
informed about the research that is carried out at the Faculty of Civil Engineering and Geosciences.
• Structural Engineering
It is also hoped that this book will enhance
• Building Engineering
communication with professionals working in this
• Hydraulic and Geo Engineering
field, and help them to become better informed
• Water Management
about the capacities of current graduates.
• Transport & Planning
0307
Further details
Contact the department in question if you require further details about one or more of the published summaries (the phone number is given at the end of each summary). A small charge is sometimes levied to cover the costs of printing and posting a thesis. It is not always possible for us to send complete theses. If you so wish, you can also make an appointment to view a particular thesis. Department of Education & Student Affairs 015-27 85444 / 81765 Department of Marketing & Communication 015-27 87685 / 84694 Further information: Delft University of Technology Faculty of CEG, Department of Communications PO Box 5048 2600 GA Delft The Netherlands
11
12
0307
0307
13
Civil Engineering Theses
Structural Engineering
14
Structural Engineering
0307
Structural design of reinforced concrete pile caps The strut-and-tie method extended with the stringer-panel method
Many foundations in the Netherlands, mainly those
friendly, to require only a moderate amount of data
in coastal areas, are on piles. These piles are
and to execute fast.
often over 15 m long at distances of 1 to 4 m. If possible, these piles are driven into the soil at the
PCA has been validated in two ways. Firstly, it
positions of walls and columns of a building. The
has been shown that the design model meets all
presence of piles of a previous building may restrict
equilibrium requirements. This has been tested for
the positions of new piles to be designed freely.
two pile caps. Both cases revealed that the design
Removing the old piles is not a solution because
model complies with horizontal and vertical force
this leaves holes in deep clay layers through which
equilibrium and moment equilibrium. From the
saline groundwater may penetrate into the upper
theory of plasticity it then follows that this model
soil. Moreover, the old piles cannot be reused
gives a safe approximation of the ultimate load.
because their quality cannot be guaranteed. As a
Secondly, the ultimate load predicted by PCA has
consequence, pile caps often have to cover piles
been compared to the ultimate load predicted by a
that are positioned in an irregular pattern.
non-linear finite element analysis. This comparison yielded several interesting conclusions whereof the most important ones are included in this summary. The ultimate load predicted by PCA is very conservative. Clearly, the real structure can carry the load in more ways than an equilibrium system (PCA) assumes. Furthermore, for the considered pile cap the design model predicted another failure mechanism than the finite element analysis. PCA predicted that the considered pile cap ‘collapsed’ because of reaching the yield strength in one of the reinforcing bars. In the finite element analysis, the pile cap collapsed because of a shear failure. This failure mechanism cannot be predicted by
The objective of this graduation project was to
PCA. For the considered pile cap the vertical pile
develop a design model for calculating the pile
reactions predicted by PCA are approximately equal
loading and reinforcement stresses for pile caps
to those predicted by the non-linear finite element
on irregularly positioned foundation piles. This
analysis. However, the reinforcement stresses
model has been based on the strut-and-tie method,
at serviceability load according to PCA are much
however, the ties have been replaced by another
higher than those determined by the finite element
model consisting of stringer elements and shear
analysis. This implies that the stresses calculated by
panel elements (see the figure above). This model
PCA are not useful for checking the maximum crack
predicts vertical pile reactions, reinforcement
width.
stresses and shear stresses in concrete. For
But the most important conclusion is that a rational
practical application, it has been implemented in
and safe design model has been developed and
a computer program called Pile Cap Applet (PCA),
implemented for pile caps on irregularly positioned
which can be found at: http://www.mechanics.citg.
foundation piles.
tudelft.nl/pca. This applet was designed to be user-
Student:
A.V. van de Graaf
Committee:
Prof.dr.ir. J.G. Rots, Dr.ir. P.C.J. Hoogenboom, Ir. W.J.M. Peperkamp,
Ir. J.W. Welleman, Ir. L.J.M. Houben
For more information about this thesis project, please contact the department, tel (+31)15-2784578
0307
Structural Engineering
Geboorde tunnels in ultra hoge sterkte beton Reductie van de tunnels liningdikte
Uit de bouwpraktijk van geboorde tunnels in slappe grond is gebleken dat een vaste verhouding tussen de tunnels diameter en vereiste liningdikte (wanddikte) bestaat. De dikte is hierdoor gelijk aan 1/20ste deel van de diameter. Bij zeer grote diameters worden de tunnelsegmenten zodoende zeer zwaar. Dit levert problemen op in de logistiek (het productieproces, vervoer naar de bouwplaats en de plaatsing van segmenten in de tunnel), die de totale kosten sterk opdrijven. De wens blijft echter bestaan om boortunnels met zeer grote diameters te maken. Hierdoor zal het mogelijk worden ook snelwegen, zoals de toekomstige snelweg A13/16 in het noorden van Rotterdam, in zo’n type tunnel aan te leggen. In deze studie is
de vereiste liningdikte. Deze zorgen ook voor de
onderzocht of de nieuwe staalvezel versterkte beton-
liningdikte uit de standaard vuistregel van 1/20 D
soorten, zeer hogesterkte beton C100/115 en ultra
voor conventioneel beton. De bouwfase mag in het
hogesterkte beton C180/210, kunnen bijdragen aan
ontwerp van een boortunnel daarom nooit buiten
een reductie van de liningdikte voor boortunnels met
beschouwing worden gelaten.
een zeer grote diameter. Zeer grote liningdikten zijn vereist om scheurvorming Verschillende mechanismen kunnen bij een boortun-
door torsie in het trompeteffect te voorkomen. Deze
nel tot schade en daardoor mogelijk tot bezwijken,
dikten liggen voor conventioneel beton boven de
leiden. In deze studie zijn voor een mogelijke boor-
standaarddikte van 1/20 D. Hierdoor zijn scheuren
tunnel voor de snelweg A13/16, met een binnendi-
tijdens de bouw te verwachten, wat in de praktijk ook
ameter van 14,9 m, de volgende vier mechanismen
inderdaad is waargenomen.
uitvoerig onderzocht: 1. Algemene ringwerking van de tunnel ingebed in grond (gebruiksfase) 2. Ringwerking na injectie van grout rond de tunnel (bouwfase)
Door toevoeging van conventionele wapening aan een tunnellining van ultra hoge sterkte beton is het mogelijk gebleken zeer dunne liningdikten toe te passen. Het benodigde wapeningspercentage is
3. Introductie van vijzelkrachten vanuit de tunnelboormachine in de segmenten (bouwfase) 4. Torsie in de tunnelsegmenten door vervormingen
sterk afhankelijk van de diepteligging van de tunnel. Hierdoor kan de liningdikte worden gereduceerd tot slechts 260 mm (1/58 D). Voor een vermindering van
ten gevolge van de groutinjectie, ook bekend als
de maatgevendheid van de groutinjectie kan een
het trompeteffect (bouwfase)
tijdelijke massa (bijvoorbeeld met zand) in de tunnel worden aangebracht. Eventueel kan deze massa na
De genoemde mechanismen resulteerden elk in een
de bouwfase probleemloos worden verwijderd. Door
grenswaarde aan de vereiste liningdikte. Het bleek
zulke tijdelijke maatregelen tijdens de bouwfase
dat de gebruiksfase nooit maatgevend wordt. De
kunnen zelfs liningdikten onder de 1/60 D worden
sterkte-eisen door de ringwerking bij de groutin-
gerealiseerd, of kan een lager wapeningspercentage
jectie en de introductie van vijzelkrachten dicteren
worden toegepast.
Student: Committee:
T.W. Groeneweg prof.dr.ir. J.C. Walraven, dr.ir. C.B.M. Blom (Ingenieursbureau GW Rotterdam), dr.ir.drs. C.R. Braam, dr.ir. O.M. Heeres (Ingenieursbureau GW Rotterdam/TU Delft) en ir. L.J.M. Houben
For more information about this project, please contact the department, tel (+31)15-2784578
15
16
Structural Engineering
0307
Application of high strength steel in Steel pin connections and Double shear timber joints The use of high strength steel has increased in the
Steel dowels and pins have been used with
last few years. Although the prices of steel increase
strengths of up to 1200 N/mm2.
with increasing yield strength, the use of high
Steel members were fabricated from steel with
strength steel may give economical gains in terms of
yield strength of up to 600 N/mm2, whereas for the
less material use or new applications.
timber joints high density hardwood (1100 kg/m3)
The field of application of these design rules
Azobé was used.
however is limited to the conventional mild steel grades.
This is an obstacle for the application of high
From the test results can be concluded that in case
strength steel in civil engineering applications.
of the Azobé specimens the design rules are very
Connections can be the weakest link in civil
conservative (38% higher test results) and in the
constructions, so it is desirable to design the
case of the softwood specimens (Spruce) the design
connection and its components as reliable as
rules predicted the test results accurate enough.
possible.
For the load-distribution model for the steel pin
The main goal is to determine whether the design
connections it can be concluded that this model
rules for calculating the load-carrying capacity of
describes the real load-distribution in the pin
both double shear timber joints (EC 5) and the steel
connection accurate enough.
pin connections (EC 3) can also be used when high strength steel dowels and/or plates are used as part of the joints.
Student:
R.D. Hieralal
Committee:
Prof.ir. F.S.K. Bijlaard, Dr.ir. J-W.G. van de Kuilen, Ir. P.A. de Vries, Dr.ir. P.C.J. Hoogenboom, Ing. P. Zanen (Groot Lemmer BV), Ir. L.J.M. Houben
For more information about this thesis project, please contact the department, tel (+31)15-2784578
0307
Structural Engineering
De drijvende fundering Een stabiele basis voor waterwonen in de 21ste eeuw
De commissie waterbeheer 21ste eeuw stelt dat het voor een duurzaam waterbeleid nodig is om meer ruimte voor water te reserveren. Deze ruimteclaim kan in de toekomst niet zondermeer worden ingevuld zonder dat ruimtelijke problemen ontstaan. Een van de oplossingen hiervoor is het meervoudig gebruiken van de ruimte. Drijvend bouwen is hierbinnen een van de manieren om invulling te geven aan meervoudig ruimtegebruik waarbij wonen, werken en waterbergen met elkaar gecombineerd worden. In dit afstudeerproject is voor deze manier van bouwen een breed toepasbare, modulaire, drijvende fundering ontworpen. Voordat begonnen is met het daadwerkelijk ontwerpen zijn enkele belangrijke mechanische aspecten beschouwd. Een parameterstudie naar de stabiliteit van drijflichamen, met een drielaagse opbouw en met gangbare waarden voor de positie
vergeleken, heeft geleid tot een drijflichaam van
van het zwaartepunt, wijst uit dat bij een breedte
EPS en hoogwaardig beton (HPC). Het modulaire
tot circa 6 meter het zwaartepunt de bepalende
basiselement is, met afmetingen van 3 bij 12 meter,
factor wat betreft de stabiliteit is. Bij een breedte
vergunningsvrij te transporteren over de weg. Een
vanaf circa 9 meter heeft de positie van het
basiselement wordt gevormd door HPC tussen
zwaartepunt nog nauwelijks invloed op de stabiliteit.
tegen elkaar geplaatste malgevormde EPS-blokken
Daarnaast is het belangrijk dat opslingering ten
te storten. Vezels in het HPC maken conventionele
gevolge van excitatie in de eigenfrequenties van
wapening overbodig. De basiselementen kunnen
het drijflichaam voorkomen wordt. Het blijkt bij
worden voorzien van een dek uitgevoerd als
een drijflichaam met een geheel waterdoorsnijdend
cassettevloer. De basiselementen worden onderling
oppervlak en variabele afmetingen niet goed
gekoppeld door voorspanning.
mogelijk om eigenfrequenties in het gebied van de golffrequenties te voorkomen. Dit gegeven en
Met behulp van een niet lineair eindige-
de onderkenning dat dynamische aspecten, in het
elementenprogramma is het ontwerp
rustige water waar de drijvende fundering voor
verder uitgewerkt: de constructievevorm is
ontworpen wordt, van ondergeschikt belang zijn
geoptimaliseerd, het HPC-gedrag is gemodelleerd
heeft geleid tot de beslissing dat geen rekening
en de constructie is voor een specifieke situatie
wordt gehouden met dynamische aspecten. Indien
gedimensioneerd.
nodig kan om de drijvende wijk een drijvende
Uit het afstudeeronderzoek kan geconcludeerd
golfbreker worden geplaatst.
worden dat de combinatie van EPS met HPC een lichte en sterke drijvende constructie oplevert en
Het ontwerpproces, waarbij verschillende
dat op eenvoudige wijze met weinig arbeid complexe
varianten zijn opgesteld die vervolgens op basis
constructies gerealiseerd kunnen worden.
van een multi-criteria analyse met elkaar zijn Student:
M. Kuijper
Committee:
Prof.dr.ir. J.C. Walraven, ir. J.A. den Uijl, ir. D. Tirimanna, ir. T. Rijcken
For more information about this thesis project, please contact the department, tel (+31)15-2784578
17
18
Structural Engineering
0307
Externally bonded carbon fibre reinforced polymers Debonding caused at shear cracks
Recent developments in ecological engineering have
Debonding initiation
put an emphasis on re-using structures. A relative
Once the shear stress has reached its maximum, the
new technique is the use of Carbon Fibre Reinforced
compressive stresses do not increase anymore, and
Polymers (CFRP). With this technique FRP laminates
the interface layer to the right of the shear crack
(strips or plates) are attached to the structure,
is loaded in tension (the vertical displacements
which strengthen the structure in flexure.
still increase). The moment that this normal stress reaches the maximum tensile strength of concrete,
Current design recommendations generally
the layer fails. This is the start of the debonding.
set acceptable levels of safety. The design
The strip still hasn’t failed, but a small part of the
recommendations take in to account the loss
strip has lost its connection to the concrete beam.
of composite action, only differ in the way they
This small part extends in the next phase, resulting
categorise different failure mechanisms.
in complete loss of composite action.
A mechanism of failure causes that the ultimate
It is concluded that this model gives insight in the
strength of full composite action will not be reached,
behaviour of the interface layer surrounding the
because debonding occurs. Of great importance
shear cracks in concrete. Still research is needed to
was found the way the bond between concrete and
come to a formula with which the failure load can be
adhesive was modelled. Several relations have been
predicted.
introduced to describe the bond-slip in this layer. Three shear-models have been tested, brittle, plastic and an energy-fracture based model. The discrete shear crack opens The moment the discrete crack opens a compressive stress occurs to the left and a tensile stress at the right side. This is caused by a small vertical displacement. By adding additional loading, both stresses increase, but horizontal tensile stresses cause compression in the perpendicular direction. Close to the discrete shear crack the compression reduces the tensile stresses in the layer (closes the gap) and prevents debonding.
Student:
R.H.Ringers
Committee:
Prof.dr.ir. J.C. Walraven, ir. A. de Boer (RWS), Dr. G.N. Wells, ir. W.J.M. Peperkamp, ir. E. Klamer (TU/e), ir. L.J.M. Houben
For more information about this thesis project, please contact the department, tel (+31)15-2784578
0307
Structural Engineering
Vloeistofreservoirs: Maximale afmetingen ten aanzien van vloeistofdichtheid Bij het gebruik van gewapende of voorgespannen
Hierbij is enigszins rekening gehouden met de
vloeistofreservoirs kunnen problemen op het gebied
invloed van de vloer op de scheurvorming in de
van vloeistofdichtheid ontstaan. Deze problemen
onderzijde van de wand. Maar naar de werkelijke
ontstaan met name door verhinderde opgelegde
invloed dient nog extra onderzoek gedaan te
vervormingen als gevolg van de temperatuur,
worden.
maar ook door krimp. Hierbij treedt scheurvorming op wanneer er sprake is van een daling van de
Uit het onderzoek blijkt dat de verhinderde
gemiddelde temperatuur ten opzichte van de
opgelegde vervormingen grote invloed hebben op
referentietemperatuur. Er wordt gekeken naar
de vloeistofdichtheid van de reservoirs. Er zullen
cilindrische en rechthoekige vloeistofreservoirs.
echter alleen problemen optreden wanneer de wand afkoelt ten opzichte van de referentietemperatuur.
Om te bepalen of een vloeistofreservoir
Hierbij moet er gekeken worden naar het verschil
daadwerkelijk vloeistofdicht zal zijn, is het
in afkoeling tussen de wand en de vloer. Er zullen
onderzoek op de hieronder beschreven wijze
problemen optreden wanneer het verschil in
opgezet. Ten eerste is geprobeerd om de
afkoeling tussen de vloer en de wand groter is
krachten als gevolg van de vloeistofbelasting op
dan -7,5 0 C. Door de opgelegde vervormingen
een analytische wijze te berekenen. Dit is bij de
zullen er verticale doorgaande scheuren ontstaan
cilindrische reservoirs gedaan met behulp van
en zal er getoetst moeten worden aan de hand
differentiaalvergelijkingen. Bij de rechthoekige
van het criterium van Lohmeijer. De resultaten
reservoirs is dit geprobeerd met behulp van het
van het onderzoek geven aan dat wanneer er
boek “Plates and Shells” van Timoshenko. Dit werd
doorgaande scheurvorming optreedt als gevolg van
echter te complex en er is uiteindelijk voor gekozen
verhinderde opgelegde vervormingen reservoirs veel
om deze reservoirs in een rekenprogramma uit te
kleiner uitgevoerd kunnen worden, dan wanneer
rekenen. Voor de berekening van de spanningen
er geen scheurvorming optreedt als gevolg van
ten gevolge van de verhinderde opgelegde
de verhinderde vervormingen. Met behulp van
vervormingen is van dezelfde rekenmethoden
voorspanning kunnen ook weer hogere reservoirs
uitgegaan. Hiervoor zijn bij de cilindrische reservoirs
gerealiseerd worden.
aparte differentiaalvergelijkingen opgesteld voor de verandering van de gemiddelde temperatuur en de krimp. Voor de rechthoekige reservoirs worden de krachten als gevolg van de verhinderde opgelegde vervormingen weer met het eerder gebruikte rekenprogramma berekend. Vervolgens wordt voor de verticale scheurvorming het scheurenpatroon bepaald aan de hand van een normaalkrachtvervorming diagram. Voor de horizontale scheurvorming zal het scheurenpatroon bepaald worden met behulp van een moment-kromming diagram. Nu kan de optredende scheurwijdte berekend worden. Deze dient bij doorgaande scheuren getoetst te worden aan de hand van het criterium van Lohmeijer. Wanneer er sprake is van buigscheuren dient de drukzone minimaal 50 mm hoog te zijn. Student:
L. Stapper
Committee:
Prof.dr.ir. J.C. Walraven, Dr.ir. C. van der Veen, Dr.ir. P.C.J. Hoogenboom
For more information about this thesis project, please contact the department, tel (+31)15-2784578
19
20
HydraulicEngineering & Geotechnical Engineering Building
0307
0307
HydraulicEngineering Building & Geotechnical Engineering
Civil Engineering Theses
Building Engineering
21
22
HydraulicEngineering & Geotechnical Engineering Building
0307
Een Living Bridge voor Amsterdam Ontwerpstudie naar een vaste oeververbinding over het IJ
Amsterdam probeert al jaren om zowel Noord als
In de ontwerpstudie is toegewerkt naar een master-
de oevers van het IJ te betrekken bij het stadsle-
plan. De living bridge bestaat hierbij uit een hoofd-
ven, maar Noord wordt pas echt een onderdeel van
verkeersader, met daaraan toegevoegd extra func-
de stad wanneer er een visuele verbinding wordt
ties. De oversteek wordt opgedeeld in vier sprongen
gemaakt. Om mensen uit het centrum naar de andere
tussen bebouwde eilanden. De brug wordt bij de
kant van het Centraal Station te krijgen, moet er
centrale oversteek uitgevoerd als hefbrug. De hefto-
een reden zijn om over te steken. Wanneer dit extra
rens vervullen daarbij niet alleen een constructieve
programma op de brug wordt geplaatst, wordt de
functie, maar behuizen ook de extra functies van
brug een living bridge. Het ontwerp van deze living
de living bridge. Ook in geheven stand is de brug
bridge was het hoofddoel van dit afstudeerproject.
toegankelijk.
In het technische vooronderzoek is de nadruk gelegd
De eilanden bestaan uit een kade, een onderbouw
op de scheepvaart. Het vervoer van gevaarlijke
tot aan het brugdekniveau en een bovenbouw. De
stoffen over het IJ zal moeten worden gereguleerd
gevels van de bovenbouw worden beschermd door
om voldoende veiligheid te garanderen op de living
een systeem van louvres, die dichtklappen bij brand.
bridge. De scheepvaart wordt daarvoor gescheiden
Door het funderen op een steigerconstructie wordt
in verschillende vaargeulen. Het vervoer van gas
de uitvoering vereenvoudigd, en worden grote
wordt beperkt tot de nacht, brandbare vloeistoffen
zakkingen voorkomen.
kunnen ook overdag vervoerd blijven worden. Om de living bridge te beschermen tegen aanvaringen is een
Dit afstudeerproject laat zien dat er harde randvoor-
systeem ontwikkeld van geleidewerken, dat schepen
waarden gelden ten aanzien van de scheepvaart en
veilig langs de brug geleidt.
de veiligheid. Maar ook met deze randvoorwaarden is een brug over het IJ wel degelijk mogelijk. De living bridge als geheel, met de bruggen, eilanden en torens is een interessante en waardevolle toevoeging aan de stad Amsterdam.
Student:
L. Dietz
Committee:
Prof. ir. L.A.G. Wagemans, Prof. dipl-ing. J.N.J.A. Vamberský, Prof. ir. A.P.J.M. Verheijen (Faculteit Bouwkunde, afdeling Bouwtechnologie)
For more information you can contact the section Structural and Building Engineering, tel. 015-2783990
0307
HydraulicEngineering Building & Geotechnical Engineering
Waarde van het ontwerp in relatie tot de waarde van het proces Een studie naar de verbeterpunten in het ontwerpproces van technisch complexe projecten in de Utiliteitsbouw voor een betere afstemming tussen vraag en aanbod, uitgevoerd bij Royal Haskoning. Achtergrond
Het ontwerpproces speelt een belangrijke rol in de totstandkoming van gebouwen. Gedurende het ontwerpproces worden belangrijke keuzes gemaakt ten aanzien van de uiteindelijke waarde en de uiteindelijke kosten van het gebouw. De waarde refereert hier aan de mate waarin het ontwerp van het gebouw ‘het aanbod’ voldoet aan de behoeften van opdrachtgever en eindgebruiker ‘de vraag’. Een succesvol ontwerpproces is een proces dat leidt tot
Resultaten
een ontwerp, dat voldoet aan deze behoeften, op het
De onvoldoende kwaliteit van het PVE is door de
juiste moment gereed is en waarvan de onnodige
participanten gewaardeerd als een primair knelpunt.
kosten tot een minimum beperkt zijn. Echter, in de
Een oplossingsrichting is ontwikkeld met betrekking
praktijk blijkt niet altijd sprake te zijn van een dusda-
tot het PVE tezamen met de inrichting van het vroege
nige effectiviteit en efficiency van het ontwerppro-
ontwerpproces, omdat daar de beïnvloeding op de
ces, aangeduid als ‘waarde’ van het ontwerpproces,
waarde en kosten het grootst is.
dat dit leidt tot de genoemde resultaten. Dit speelt
De belangrijkste aanpassingen in de voorgestelde
binnen de Utiliteitsbouw bij technisch complexe
oplossingsrichting inzake het PVE en de inrichting van
projecten in het bijzonder een rol. De adviesgroep
het vroege ontwerpproces zijn:
project Management van Royal Haskoning wil inzicht
- Van aftrap met architect naar aftrap met ontwerp-
krijgen in de invloedsfactoren c.q. knelpunten in het ontwerpproces van technisch complexe projecten in de Utiliteitsbouw én in de bijbehorende sturingsmogelijkheden vóór de projectmanager.
team - Van samen ontwerpen naar gezamenlijk ontwerpen én programmeren - Van Programma van Eisen & Wensen naar Programma van Eisen & Programma van Wensen
Onderzoeksopzet
Om inzicht te verkrijgen in de knelpunten is gebruik gemaakt van een literatuurstudie en van het houden van interviews. Voor de praktijkstudie is een bouwproject als case genomen en is gesproken met alle bij het ontwerpproces betrokken partijen. Deze inzichten hebben geleid tot de keuze van een primair knelpunt. Hiervoor is intern bij Royal Haskoning in samenwerking met een multidisciplinaire vertegenwoordiging, door het houden van oplossingsgerichte interviews een oplossingrichting ontwikkeld.
Student:
T.J. Duvivier
Committee:
Prof. Dr. Ir. H.A.J. de Ridder, Dr. Ir. G.A. van Nederveen, Ir. F.A.M. Soons, Ir. K. Th. Veenvliet (UTwente), Ir. P.C.M. Zwinkels (Royal Haskoning)
For more information you can contact the section Building Engineering, tel. 015-2786636
23
24
HydraulicEngineering & Geotechnical Engineering Building
0307
Ondergrondse kleine infrastructuur Nut en noodzaak van ordening
In stedelijke gebieden doen zich steeds vaker compli-
moment kan bijvoorbeeld in de grondexploitatie-
caties voor in samenhang met ondergrondse kleine
begroting ook nog budget vrijgemaakt worden om
infrastructuur (netwerken voor het transport en de
voor ordening in een ordeningssysteem (integrale
distributie van signalen, elektriciteit, vloeistoffen of
leidingen tunnels (ILT’s), utility ducts, bundeling van
gassen). Deze complicaties lijken voort te komen
kabel en/of leidingen en kabel- en/of leidinggoten) te
uit de explosieve toename van het aantal verschil-
kiezen.
lende netwerken en de trend tot het verdichten van steden enerzijds en de traditionele wijze waarop
Van de drie te onderscheiden actoren op het gebied
deze netwerken in de ondergrond zijn aangebracht
van ondergrondse kleine infrastructuur (gemeente,
anderzijds. Het onderzoek geeft ter onderbouwing
kabel- en leidingbeheerders en gebruikers) is de
hiervan een aantal trends aan en geeft de achter-
gemeente de meest aangewezen actor om als regie-
grondinformatie bij de verschillende netwerken. Het
voerder op te treden. De gemeente dient namelijk te
onderzoek richt zich op de vraag waarom er bij het
waken over het maatschappelijk belang en beschikt
(her)ontwikkelen van gebieden ondanks de ervaring
over voldoende sturingsmogelijkheden om grip op
met het optreden van dergelijke complicaties zelden
het proces te kunnen houden.
wordt gekeken naar de mogelijkheid om de ondergrondse kleine infrastructuur op een andere manier
Bij het bestuderen van knelpunt 2 kwam naar voren
aan te brengen.
dat de maatschappelijke kosten en baten vaak buiten beschouwing gelaten worden, wanneer de kosten
Hiervoor is IJburg 1e fase als casus uitgewerkt.
behorend bij verschillende manieren van aanbren-
Hieruit kwamen twee knelpunten naar voren, name-
gen (traditioneel of in een ordeningssysteem) van
lijk: de manier waarop ondergrondse kleine infra-
ondergrondse kleine infrastructuur gekwantificeerd
structuur in het ontwerp- en besluitvormingsproces
worden. Hierdoor is het onwaarschijnlijk dat er geko-
van IJburg
1e
fase meegenomen is (knelpunt 1) en
de manier waarop de kosten die voortkomen uit de
zen wordt voor een oplossing waar de samenleving als geheel het meest baat bij heeft.
verschillende manieren van aanbrengen van kleine infrastructuur gekwantificeerd kunnen worden (knel-
Om die reden is er tijdens het onderzoek een
punt 2).
omvangrijk rekenmodel ontwikkeld waarin alle verschillende (maatschappelijke) kosten aan de hand
Bij uitwerking van knelpunt 1 blijkt dat ondergrondse
van parameters zijn opgenomen. Dit model geeft
kleine infrastructuur op dit moment erg laat in het
daardoor alle factoren weer die het besluit hoe de
ontwerp- en besluitvormingsproces van te ontwik-
ondergrondse kleine infrastructuur het best geordend
kelen gebieden betrokken wordt. Hierdoor komen
kan worden beïnvloeden, zodanig dat de maatschap-
conflicterende situaties of belangen (ook tussen
pelijke kosten en baten het positiefst uitvallen. Het
boven- en ondergrond) pas tijdens de uitvoeringsfase
model is daardoor goed geschikt om deze kosten op
naar voren. Ook ontbreekt een regievoerder die de
een hoger (politiek) abstractieniveau inzichtelijk te
verschillende belangen onderling kan afwegen en
maken.
sturing geeft. Uit het onderzoek komt naar voren dat de bovenen ondergrond op elkaar dienen te worden afgestemd voordat de bovengrondse inrichting in een Stedenbouwkundig Plan wordt vastgelegd. Op dat Student:
M.P. Franken
Committee:
Prof.dr.ir. H.A.J. de Ridder, Ir. G. Arends, Prof.ir. J.W. Bosch, K.B. Braat, MSc, BSc, Drs. F.M. Taselaar (Ingenieursbureau Amsterdam)
For more information you can contact the section Building Engineering, tel. 015-2786636
0307
HydraulicEngineering Building & Geotechnical Engineering
Research of the functional and technical feasibility of a floating football stadium Introduction
Caused by the media and new sources of income increasing demands are made on new stadiums. They have to be more flexible, tailor-made for one function and need an increasing capacity. At the same time for events like Olympic Games or football Championships the demanded capacity exceeds the after-event demand for sports venues leading to misinvestments. Results Problem Definition
The maximum
A moveable floating stadium could be a solution.
dimensions for possible
Such a stadium could be moved to the location
berthing locations
where temporary a high capacity is needed. In
together with the
coastal cities or cities next to navigable rivers a
functional requirements
floating stadium could be moved to very attractive
resulted in a stadium that is split
inner city locations. In the past years a lot of
up into six elements; two playing field elements and
research on floating structures like houses or even
four surrounding grandstand elements. A design tool
airports has been done but never the feasibility
was made that linked the structural design with its
of a floating stadium was analysed. The problem
hydro-mechanical properties.
of this report can be defined as follows: There
In the preliminary design the results of the design
is not enough information about the design,
research were implemented into a structural
the construction and functional and economical
context. The main structure of the floating stadium
consequences of a floating stadium.
elements were designed and the attention points regarding the floating character of the stadium like the construction and the connection of the floating
Objective
The goal of this thesis is a research of the
stadium elements, were highlighted.
requirements and the technical and functional major problems of a floating stadium followed by the implementation of the derived solutions into a preliminary design.
Conclusions and recommendations
• A floating stadium that during operation berths in a port of a river quay is technically and functionally feasible. • The capacity of the stadium is limited to a
Research
The main bottle necks for the realisation of a floating stadium that resulted from an extensive literature research were analysed and solved in an iterative way.
maximum of 50.000 spectators. • A stabilizing system is necessary to maintain a zero degree angle of the stadium during operation. • It should be analyzed which standards and regulations have to be suited for a floating stadium.
Student:
N.T.N. Groenendijk
Committee:
Prof. ir. L.A.G. Wagemans, Prof. Dr. Dipl. Ing. J.N.J.A. Vamberský, Ir. H. Mihl, R. Jansma (Zwarts & Jansma Architecten)
For more information you can contact the section Structural and Building Engineering, tel. 015-2783990
25
26
HydraulicEngineering & Geotechnical Engineering Building
0307
Optimization of Dome Housing in Sri Lanka
The Solid House Foundation aims at contributing
Currently half of the material turns out to be
to an enduring development of housing projects
used for the foundation of the dome. After some
in poor communities. The intention is to enable
calculations could be concluded that this heavy
local inhabitants to independently prepare and
foundation is required to anchor the uplifting forces
build successful housing projects. The Solid House
of the inflatable formwork. Consequently research
Foundation uses re-usable inflatable hemispherical
has been done on alternative anchorage of the form,
formwork to build reinforced concrete dome
resulting in ideas for formwork that does not need
dwellings. In this thesis a study is made of possible
anchorage at all. The research phase was rounded
optimization of costs, simplicity and durability of this
off with a study of the climatic circumstances in Sri
building concept. Main occasion is the increasing
Lanka. Matching building responses to the climate
price of rebar and the bad availability of rebar in
were studied and applied on dome designs.
most regions where the SHF is active. As SHF is now involved in a large housing project in Sri Lanka, a
The conclusions drawn from structural analyses in
first focus is on this region.
the finite element program ANSYS have resulted in a proposal for alternative material use in
To have an idea of threads and opportunities in
combination with the currently applied formwork.
dome building a literature study was made on
A design for a ferrocement shell has been made
dome shapes in nature, domes in other cultures,
and an experiment is carried out. This has resulted
the history of concrete shells built with inflatable
in a construction manual for application of the
formwork and of domes in general. As a result
current inflatable formwork in combination with the
several form-related possibilities were identified that
material ferrocement. Costs of raw materials for this
could reduce the tension stress in the shell and thus
alternative turn out to be considerably lower than
the amount of reinforcement needed.
for the reinforced concrete shells that have been built so far.
Also, research on alternative materials for dome building was done. This resulted in several options
However to improve issues such as the heavy
of which ferrocement was considered the most
foundation and the dependency on electricity,
suitable. The latter from both a cost point of view as
a different design of the formwork is required.
from the fact that there is a lot of experience with
Therefore possibilities for an alternative design of
this easy applicable material in Asia.
the formwork are studied and evaluated.
Student: C. Hammer Committee: Prof.ir.L.A.G.Wagemans, Dr.ir.P.C.J.Hoogenboom, Dr.ir.E.Schlangen,
Ing W.J.H.Stroecken (Solid House Foundation) For more information you can contact the section Structural and Building Engineering, tel. 015-2783990
0307
HydraulicEngineering Building & Geotechnical Engineering
Design tools for the Virtual Wind Tunnel Setting up the geometry for CFD calculations
Momenteel kan de windbelasting op gebouwen op
Met deze toolbox kan de windbelasting op een
twee manieren worden bepaald: met behulp van de
gebouw of constructie worden bepaald en verschil-
norm (NEN 6702, Eurocode) of door middel van wind-
lende ontwerpen worden vergeleken in een relatief
tunnelproeven. De norm is echter alleen bruikbaar
korte tijd zonder veel tussenkomst van de gebruiker.
voor eenvoudige vormen; complexe gebouwvormen
Optimalisatie van vorm en constructie wordt hiermee
vereisen windtunnelonderzoek. Dit onderzoek is
mogelijk. Om de windbelasting te bepalen op een
echter erg duur en zeer tijdrovend, waardoor het
gebouw dat is geplaatst in een bebouwde omge-
nauwelijks gebruikt wordt in het vroege ontwerp-
ving, is een ontwerptool ontwikkeld waarmee een
proces. Toch is het juist deze fase waarin belangrijke
3D model van de omgeving kan worden gecreëerd,
ontwerpbeslissingen worden genomen en meer
gebruik makend van GIS technologie. Een andere tool
inzicht in de effecten als gevolg van wind is dan
is ontwikkeld waarmee het centrale gebouw-model
ook wenselijk. Numerieke methoden zijn geïntro-
kan worden vereenvoudigd door het verwijderen
duceerd om de windeffecten te bepalen middels
van niet-relevante elementen en kleine details. De
Computational Fluid Dynamics (CFD).
rekentijd van de CFD software kan hiermee aanzienlijk worden verkort. Omdat de afmetingen van het
In recent afstudeeronderzoek aan het Structural
domein waarin de berekeningen worden uitgevoerd
Design Lab is een Virtuele Windtunnel voorgesteld
afhangen van de dimensies van het onderzoeksge-
waarmee constructieve ingenieurs de windbelasting
bied, is een laatste tool ontwikkeld waarmee het
in een vroeg stadium van het ontwerpproces kunnen
domein kan worden gegenereerd, afhankelijk van de
bepalen door gebruik te maken van CFD. Dit onder-
afmetingen van het onderzoeksgebied.
zoek heeft geleid tot een algemene aanpak voor het uitvoeren van CFD berekeningen en een domein
Er is geconcludeerd dat de ontwerptools goed werken
waarin de berekeningen kunnen worden uitgevoerd.
voor CFD toepassingen. In de meeste gevallen
Het zogenoemde Van Nalta domein geeft veelbe-
worden veelbelovende resultaten verkregen en de
lovende resultaten voor eenvoudige vormen, zoals
gegenereerde geometrie blijkt zeer goed bruikbaar
kubussen en cilinders. De eisen aan de geometrie
voor CFD simulaties. Voor enkele test cases zijn bere-
voor CFD berekeningen zijn echter zeer hoog en het
keningen uitgevoerd in het Van Nalta domein. Het
genereren van bruikbare modellen van met name
blijkt momenteel erg lastig om nauwkeurige resulta-
complexe gebouwvormen blijkt zeer lastig.
ten te verkrijgen van de berekeningen, mede door de geringe capaciteit van de huidige computers. Echter, rekening houdend met de continue ontwikkeling van
Tijdens dit afstudeeronderzoek zijn verschillende
de computer hardware, is het de verwachting dat het
ontwerptools ontwikkeld waarmee de geometrie
in de nabije toekomst mogelijk zal zijn de windeffec-
voor CFD berekeningen kan worden gegenereerd.
ten op complexe gebouwmodellen, die zijn geplaatst in een bebouwde omgeving, nauwkeurig te voorspellen.
Student:
R.A.G. Kerklaan
Committee:
Prof.dipl.-ing. J.N.J.A. Vamberský, prof.ir. L.A.G. Wagemans, ir. J.L. Coenders, dr. dipl-ing. S. Zlatanova (OTB onderzoeksinstituut, GIS), dr. ir. L.L.M. Veldhuis (Lucht- en Ruimtevaarttechniek, Aerodynamica)
For information on the report of the Master’s thesis please contact the Building Engineering section, telephone: 015-2783174
27
28
HydraulicEngineering & Geotechnical Engineering Building
0307
Functioneel Specificeren bij projecten van Rijkswaterstaat Ontwikkeling van een kader voor evaluatie en advisering Achtergrond
Onderzoeksopzet
Rijkswaterstaat is in Nederland verantwoordelijk voor
Het ontbreekt op dit moment aan inzicht in de
beheer, onderhoud en aanleg van een groot deel
toepassing van de werkwijze in de praktijk. Dit zou
van de infrastructurele bouwwerken. De aanbeste-
kunnen worden gebruikt om de werkwijze beter te
ding van werkzaamheden werd tot voor kort gedaan
implementeren. De doelstelling van dit afstudeer-
door het opstellen van een bestek aan de hand van
onderzoek luidt dan ook als volgt: “Het ontwikkelen
een ontwerp. Sinds enkele jaren bestaat de tendens
van een kader voor het evalueren van en adviseren
meer werkzaamheden aan de markt uit te besteden,
over het “Functioneel Specificeren” bij projecten van
bijvoorbeeld door Design & Construct contracten.
Rijkswaterstaat, ten behoeve van het verbeteren van
Het gebruiken van de kennis van de markt, bijvoor-
de toepassing ervan tijdens individuele projecten en
beeld op het gebied van uitvoering van projecten of
mogelijk de uniforme werkwijze van Rijkswaterstaat.”
van een specifiek product, door het uitbesteden van
Het dient hierbij te gaan om een quick-scan die
(delen van) het ontwerpproces kan leiden tot betere
toepasbaar is op verschillende soorten projecten en
en/of goedkopere oplossingen.
snel duidelijk kan maken hoe het binnen een project
met het “Functioneel Specificeren” gaat.
Het gebruik van geïntegreerde contractvormen vraagt een andere wijze van het opstellen van de
Het onderzoek bestaat uit een studie naar theorieën
vraag door de opdrachtgever. Binnen Rijkswaterstaat
en achtergronden van de werkwijze “Functioneel
is hier de werkwijze “Functioneel Specificeren” voor
Specificeren”, een korte studie naar evaluatieme-
ontwikkeld, die steeds vaker wordt toegepast. Hierbij
thoden en een praktijkonderzoek door middel van
is Rijkswaterstaat vooral betrokken bij de voorkant
interviews en een enquête naar toepassing van de
van het ontwerpproces en wordt het verdere verloop
werkwijze in projecten.
hiervan gemonitord. De specificatie van eisen bestaat zoveel mogelijk uit functionele eisen en er worden zo
Resultaten
min mogelijk eisen gesteld, zodat een zo groot moge-
Het onderzoek heeft geleid tot de basis voor een
lijke oplossingsruimte voor marktpartijen overblijft
kader voor evaluatie van de werkwijze “Functioneel
om binnen te ontwerpen.
Specificeren”. Bij gebrek aan een duidelijke praktijkhandleiding is een overzicht gemaakt van de activiteiten die bij de werkwijze (kunnen) worden uitgevoerd. Daarnaast zijn er diverse factoren onderscheiden die van belang zijn voor het succesvol toepassen van de werkwijze, resulterend in een check-list en een aantal Kritieke Succes Factoren. Naast het opstellen van het kader voor evaluatie in projecten bleek het goed mogelijk in het onderzoek ook een evaluatie van toepassing van de werkwijze zelf uit te voeren. Dit heeft geresulteerd in een duidelijk beeld over de stand van zaken wat betreft de ontwikkeling van “Functioneel Specificeren” en adviezen over mogelijke verbeteringen.
Student:
A.W. Lever
Committee:
Prof.dr.ir. H.A.J. de Ridder, Ir. R.M. Bosch (Rijkswaterstaat), Ir. A. van der Kuilen, Ir. G. Arends
For information on the report of the Master’s thesis please contact the Building Engineering section, telephone: 015-2783174
0307
HydraulicEngineering Building & Geotechnical Engineering
Variantenonderzoek Onderbouw Parkhaventoren
Eind 2001 presenteerde een consortium van twee
Alle drie de vragen afzonderlijk kennen een groot
ontwikkelingsmaatschappijen het “Masterplan
aantal oplossingsrichtingen. Door het vraagstuk inte-
Parkhaven”. Het plan voorziet in de herontwikke-
graal te benaderen wordt dat aantal verkleind. Daarin
ling van het Parkhavengebied in Rotterdam door
blijkt vooral de laatste vraag over de functie-uitvoe-
uitbreiding van het Park, de bouw van kantoren
ring van bepaalde ruimtes bepalend te zien. Vanuit
en woningen en de realisatie van een entertain-
de mogelijke oplossingsrichtingen zijn twee vooront-
mentcenter. Hoogtepunt vormt de 392 meter
werpen voor de onderbouw van de Parkhaventoren
hoge Parkhaventoren; een nieuwe blikvanger voor
ontwikkeld. De bovenbouw is daarbij geïnventari-
Rotterdam met een recordhoogte in Europa.
seerd en als een gegeven beschouwd.
Het Masterplan Parkhaven werd door de gemeen-
Om de voorkeur te geven aan één van de twee
teraad van Rotterdam verworpen en de ontwikke-
voorontwerpen voor verder uitwerking tot definitief
ling van de Parkhaventoren werd bij het bouwkun-
ontwerp zijn beide beoordeeld. Een beoordeling van
dig ontwerp stopgezet. Het verrichte onderzoek
de voorontwerpen op alleen het constructieve vlak is
beschrijft het proces van bouwkundig ontwerp naar
een te krappe benadering. Wanneer er verschillende
voorontwerp en richt zich daarbij op de onderbouw
oogpunten ingenomen worden, worden er verschei-
van de Parkhaventoren.
dene belangen zichtbaar die tegenstrijdig met elkaar kunnen zijn. Door de belangen goed af te wegen
De onderbouw vormt de ondersteuning voor de
wordt tot een evenwichtige beoordeling gekomen die
bovenbouw en draagt zorg voor de afdracht van
de basis vormt voor een keuze voor één van de twee
krachten naar het fundament. In het onderzoek
voorontwerpen.
zijn een drietal vragen gesteld; hoe wordt de Parkhaventoren gefundeerd, hoe worden de krachten uit de bovenbouw geïntroduceerd in het fundament en op welke wijze kan dit gedaan worden opdat de functie van gebruiksruimtes niet belemmerd wordt?
Student:
O. Los
Committee:
Prof. dipl.-ing. J.N.J.A. Vamberský, Ing. H.J. Everts, Ir. G. Arends
For information on the report of the Master’s thesis please contact the Building Engineering section, telephone: 015-2783174
29
30
HydraulicEngineering & Geotechnical Engineering Building
0307
Progressive Collapse Assessment Non-linear behaviour of concrete structures in damaged state
Progressive collapse is a collapse where local failure leads to a disproportionate collapse (Fig. 1). Due to a focus on ease of erection in the construction process and more and more optimisation of design through advanced analysis techniques, buildings are believed to have become more vulnerable to progressive collapse over the past decades. To design a building resistant to progressive collapse in a cost efficient and aesthetically attractive way, consideration of non-linear effects is required. The purpose of this research is to investigate structural non-linear behaviour of building structures and develop design rules or strategies to economically design building structures resistant to progressive collapse. Focus is on reinforced concrete structures
To assess the influence of non-linear effects,
in static loading conditions.
numerical determination of limit loads upon column removal through advanced non-linear
First the progressive collapse phenomenon itself
EEM calculation was performed for a simple office
was considered. Three design approaches were
building. Three non-linear effects creating an
distinguished: the event control approach aimed
overcapacity compared to linear assessment were
at improving the level of protection of a building,
distinguished in this case study: strain hardening of
the specific local resistance approach aimed at
the reinforcement steel, moment redistribution and
increasing the hardness of a building and the
a load bearing floor slab contribution.
alternate load path approach which aims at improving the robustness of building (Fig. 2). The
The magnitude of these effects depends on the
latter approach has been elaborated.
actual amount of reinforcement and its lay-out and the structural geometry. For three investigated
Alternate load paths can be developed in roughly
cases of column removal the available non-linear
four manners: by arch action, suspension action,
overcapacity was in the order of magnitude of 1.8.
Vierendeel action and catenary action. Ductility of
A linear procedure of notional element removal was
the structure and its connections is important to
performed for the entire building. Each column was
enable these alternate load paths. For arch and
removed one by one, one at a time and the required
catenary action special detailing of structural ties is
strength was assessed through the calculated
needed, especially catenary action depends highly
overcapacity-factor.
on the elongation capacity of these ties. It was concluded that via this approach the design of the studied building can be adjusted adequately and economically to enhance the robustness. The right detailing is of primary importance in enhancement of robustness.
Student:
M. Smith
Committee:
Prof. dipl.-ing. J.N.J.A. Vamberský, ir. J.L. Coenders, ir. A.M. de Roo (Arcadis Bouw & Vastgoed), prof. ir. A.C.W.M. Vrouwenvelder, ir. J.W. Welleman
For more information about this thesis project please contact the department, tel. (+31) 15-2783174
0307
HydraulicEngineering Building & Geotechnical Engineering
Optimisation of structural transfer zones in multiuse buildings Introduction One of the main problems of designing multi-use
process, including several other genetic algorithm
buildings is the transfer of loads between the
operators, will be repeated until the fittest or best
structural grid systems of the different functions. In
solution per population remains unaltered during a
lieu of making compromises in the design of these
number of generations.
systems per function in order to vertically align the grid lines or grid bands, a structural transfer zone in
generations.jpg ?????
an intervening floor can be designed. By designing an optimal allocation of vertical oriented structural elements, loads can be transferred between the different structural grid systems, without adversely
Concluding remarks
affecting the functionality and usability of the
This Master’s thesis shows the capability of an
intervening floor.
artificial based design optimisation tool in a predefined setting of the allocation problem of
Structural design tool
columns in a structural transfer zone. At the same
The Master’s thesis ‘Optimisation of structural
moment, it is made clear that progress can be made
transfer zones in multi-use buildings’ deals with the
for the presented design tool and in scripting design
development of a computational structural design
tools for the building practise in general. This also
tool based on the artificial intelligence method
means that it can be expected that tools similar
genetic algorithms, that can determine the optimal
to the tool presented in the Master’s thesis will be
solution for the allocation of columns between two
used more often in the near future. This, however,
structural grid systems. This tool, implemented
does not mean that the structural engineer will lose
in VBA and using AutoCAD as a visualisation tool,
his or her position, as hand calculations and logical
allows the user to generate and optimise the
interpretations of the result of the design tools will
configuration of the load bearing elements for an
always have to be made.
arbitrary design, with the rules following from the demands of several aspects of a structural and functional design. Features of the design tool
In the AutoCAD environment, the user needs to give the starting and end point of the structural grid line graphically in both the bottom and top layer of the intervening floor to determine the possible location of the columns. Subsequently, the vertical point load, the horizontal point loads, and the moments in the centre of gravity acting on the load transferring structure need to be given numerically. Based on the user input, the tool then randomly generates several solutions in what is called the first generation. By determining the fitness, or in other words the overall compliance with the prescribed desired conditions, the genetic algorithm will use the best solutions to create a new population. This Student:
R. van de Straat
Committee:
Prof. dipl.-ing. J.N.J.A. Vamberský, Ir. J.W. Welleman, Ir. J.L. Coenders, Ir. S. Boer (Mecanoo Architecten)
For more information about this thesis project please contact the department, tel. (+31) 15-2783174
31
32
HydraulicEngineering & Geotechnical Engineering Building
0307
Parametric Associative Design for Free Form Architecture Over the last decade, the computer has become a
of parametric associative tools. Where a parametric
tool a structural designer cannot do without. For
associative design process differs from a traditional
an efficient structural design processes however,
design process is that with a design process
computational power is not yet being used in the
according to the Structural Design Tools approach,
most efficient manner. Structural engineers still
the quantitative characteristics of the design can
have difficulties with using available software in an
change in the end of the process. The design logic
efficient structural design process. Coenders and
behind the generation algorithms defines the range
Wagemans [2005] have proposed a new approach
in which the design can be varied in the end of
toward use of computers in the structural design
the generation process. This logic cannot easily be
process: the Structural Design Tools approach.
changed in the end of the process. With setting an
The Structural Design Tools concept doesn’t strive
accurate design direction in the beginning of the
to be an all-comprising model, but a collection of
process, the freedom of the final design is restricted
simple tools that can be chosen by the designer to
soon in the development process. Like a traditional
build his design. Instead of using the computer for
design process, the discrepancy between having no
engineering purposes, the computer can be used for
design knowledge and having to make governing
design purposes.
design decisions still is present in a parametric associative design process. With a system of
An important aspect of the Structural Design Tools
parametric associative design tools however, the
concept is the parametric associative character
structural designer is able to generate a range of
of the design tools. Parametric design is used
possible design representations in a fast way. By
for the rapid generation of computable design
a combination of a qualitative and quantitative
representations describing design alternatives.
comparison of the generated designs, insight into
Potential design alternatives are generated and
the consequences of parameter variation can be
evaluated in order to obtain insight into the impact
obtained.
of the structural parameters on the final integral design. With adding associativity to the structural
In a real life design process, a large benefit
design process, design steps are linked and the
of using parametric associative design tools is
possibility of adjusting the parameters in the end
the fact that interaction between architect and
of the design process is reached. With designing
structural engineer is stimulated. A structural
structures for Free Form Architecture, this ability is
engineer can, without losing a lot of time doing
very valuable. Since there is little design experience
repetitive calculations, show the architect what
with these kind of structures, it is hard to predict
consequences of design choices are. When a
what the impact of a design decision on the final
common understanding on all design relations
design is. The ability of defining the values of the
is reached, the total design team can come to a
structural parameters at the end of the design
well considered, well founded set of values for the
process leads to a more efficient structural design
design parameters. Instead of delivering the optimal
process.
design object, a system of parametric associative design tools offers the possibility for an optimal
The goal of the graduation project was to research
design process in which interaction between the
methods for developing structural design for Free
architect and the structural designer is put central.
Form Architecture in a parametric associative process, whereby elaborating one specific combination of researched methods into one system Student:
P. Vermeij
Committee:
Prof. dipl-ing. J.N.J.A. Vamberský, Ir. J.L. Coenders, Ir. J.W. Welleman, Ir. M. Veltkamp (Faculty of Architecture)
For more information you can contact the section Building Engineering, tel. 015-2783174
0307
Hydraulic & Geotechnical Engineering
Civil Engineering Theses
Hydraulic & Geo Engineering
33
34
Hydraulic & Geotechnical Engineering
0307
Gabion Stability
In 1932 the Dutch ‘Afsluitdijk’, stretching over
stable these sack gabions are exactly. The objective
30 kilometres, was completed. This made it
of this report is to make a preliminary study on the
possible to reclaim land in the former ‘Zuiderzee’
stability of sack gabions.
by means of constructing the ‘Flevopolder’ and the ‘Noordoostpolder’. Since then technological
In 2006, after a 20 year preparation, the
developments have made it possible to build even
Saemangeum estuary in South Korea was closed
larger dams in more difficult circumstances.
with a dam. During the closure sack gabions were used in the bed protection, sill construction and
One of the countries that is also reclaiming land
dam heads. In corporation with Delft University of
by constructing dams and polders is South Korea.
Technology, Rijkswaterstaat and the Korea Rural
Because of the large mountainous areas and
Community & Agriculture Corporation a field trip
the growing population in this country, arable
to the Saemangeum project was made, in order
land is becoming rare and land reclamation may
to collect useful data on the stability of gabions.
offer a solution. The large tidal differences along
Also the experimental data of RRI (Korean Rural
the Korean coast make building these dams a
Research Institute) on model tests on the stability
challenging job.
of gabions was obtained. As an addition to the data from the Saemangeum project and the model
One of the solutions in South Korea to cope with the
tests performed by RRI, also model tests in Delft
high flow velocities in closure projects is to apply
were done. All this information combined leads to a
sack gabions. These are steel nets with rocks inside
stability relation for the applied sack gabions.
them that weigh up to 3 tons. It is not clear how
Student:
R.H.P.A. Beekx
Committee:
Prof.drs.ir. J.K. Vrijling, ir. H.J. Verhagen, drs. R. Booij, ir. K. Dorst
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
0307
Hydraulic & Geotechnical Engineering
Veldproeven op steenzettingen
Uitvoering en resultatenanalyse van onderzoek
Met het model en de meetresultaten als input is het
naar de klemming van gazette stenen op dijken
mogelijk de materiaaleigenschappen van de zetting
Steenzettingen worden van oudsher gebruikt om het
te berekenen. Deze eigenschappen kunnen in het
aangevallen front van dijken te bekleden. De mecha-
vervolg worden gebruikt om het gedrag van de
nische achtergronden en de materiaaleigenschappen
zetting onder natuurlijke omstandigheden te beschrij-
van deze constructie zijn nog niet volledig beschre-
ven.
ven. In dit afstudeeronderzoek is met name de klemming van de stenen door de zwaartekracht in de rich-
De belangrijkste conclusies uit het onderzoek zijn:
ting van het talud onderzocht. Deze inklemming kan
1. De zetting reageert altijd als een plaat op de
ervoor zorgen dat de losse elementen als een plaat gaan samenwerken en dus als zodanig beschreven kunnen worden.
belasting. Dit geldt voor de trekproeven en bij loklale verschildrukken bij golfbelasting 2. Alle beproefde stenen zijn visueel geselecteerd als geklemd en dit bleek bij beproeving in alle geval-
Op drie lokaties in Zeeland zijn veldproeven uitgevoerd om data te verzamelen over de plaatwerking
len grote sterkte op te leveren. 3. Er is meestal op twee peilniveau`s gemeten.
van de zettingen. De zettingen waren opgebouwd
Tussen deze niveau`s is geen significant verschil
met Basalton en Hydroblock zuilen en allemaal onge-
in sterkte of stijfheid gemeten en berekend. Er is
veer 1:3 steil. Er is op verschillende manieren een
een reductie van de sterkte nabij de teen vastge-
belasting loodrecht op de zetting opgelegd (trekproeven). Tegelijkertijd is met verplaatsingssensoren de responsie van het omliggende veld gemeten. Ook zijn er schuifproeven uitgevoerd, waarbij een stuk zetting tegen het talud op werd gedrukt.
steld. 4. De geometrie van de stenen heeft geen invloed op de vorm van het verplaatsingsgebied. 5. Een slecht ingewassen zetting scoort lager op verschillende sterkte criteria. 6. Indien wordt voldaan aan een aantal criteria levert
De analyse van de gegevens is aan de hand van de
dit onderzoek een belangrijke onderbouwing voor
veronderstelde plaatanalogie gedaan. Hiervoor is een
het rekenen op enige klemming bij toetsing en
model noodzakelijk dat de elastische responsie van
ontwerp.
een homogeen orthotroop materiaal kan beschrijven. Het plaatgedrag van de zetting vertoont verschillende eigenschappen in de onderling loodrechte richtingen (de zwaartekracht werkt maar in één richting).
Student:
J.A.H. Blom
Committee:
Prof.ir.drs. J.K. Vrijling, ir. DJ Peters, ir. H.J. Verhagen, ir. J.A. den Uijl, ir. R. ’t Hart (DWW, RWS), ir. A.J.E.J. van Casteren (BAS bv)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
35
36
Hydraulic & Geotechnical Engineering
0307
“Sandwich wall as the quay wall for the future”
In this report an attempt is made to develop a
The sandwich wall consists of two rows of steel
new design method for quay walls. Previous quay
piles and a jet grout mass between these two pile
walls designs are being analysed and an attempt is
rows. The steel piles are equipped with steel rings
made to find relations between external conditions
to be able to transfer a certain shear force from the
and design parameter of the structure. When such
piles into the grout. These steel rings facilitate a
relations exist they can be used as design graphs.
shear connection, which causes the wall to behave
The new design method will be called reference
as a composite structure. This composite action
based design. In this thesis this new method has
has a favourable effect on both the strength and
been applied to block walls and to sheet pile walls.
the stiffness of the wall. On top of the sandwich
The discovered relations can be used to make an
wall a relieving floor structure will be constructed;
estimate of the material quantities in a very short
this is very common for large wall structures. An
time.
impression of the sandwich quay wall can be seen in the figure below.
The block wall designs have been examined for the following relations: • Retaining height vs. number of blocks in a cross section; • Retaining height vs. concrete volume per meter wall; • Dimensions of the separate blocks vs. elevation of the blocks; The designed configuration of the sandwich wall has The sheet pile wall designs have been investigated
been compared to a reference design to investigate
for the following relations.
the economic potential of the sandwich wall. A combi
• Retaining height vs. embedded length;
wall has been selected for the reference design,
• Retaining height vs. steel volume per meter wall;
as this type of quay wall is generally the cheapest solution for wall structures in sandy soil with a large
The second part of this thesis focuses on the
retaining height. The combi wall is designed for equal
development of a new type of quay wall, which
load conditions.
will be designed for the expected future situation. In the last couple of decades ship sizes have been
The costs of both the combi wall and the sandwich
increasing and the loads on quay walls have also
wall have been estimated. Although the sandwich
become larger. These changes have an effect on
wall requires a much smaller amount of steel than
the quay walls at which these ships can be moored.
the combi wall the sandwich wall proves to be more
When these two trends continue container ships
expensive. The largest contribution in the costs of the
will have to become very large and very strong in
sandwich wall results from the welding of the steel
the future. A new quay wall concept may be more
rings around the piles. It may be possible that in the
economical in case of this extreme situation. Several
future the sandwich wall becomes more attractive. As
new types of
the amount of steel in the sandwich wall is relatively
quay walls have been considered of which a
small an increase in the price of steel makes the
sandwich quay wall is the most promising.
sandwich wall economically more attractive.
Student:
P. Bonte
Committee:
Prof. drs. ir. J.K. Vrijling, ir. W.F. Molenaar, ir. W.J.M. Peperkamp, ir. L.A.M. Groenewegen (Delta Marine consultants)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
0307
Hydraulic & Geotechnical Engineering
“Dynamic behaviour of jetty structures under seismic conditions“ Jetty structures are relatively long structures.
This research investigates the effect of uneven
Codes applied to seismic engineering, e.g. eurocode
excitation on a jetty structure by the time history
8, do not make a differentiation to relatively
method. A model has been set up according the
long structures. So, what is the effect of uneven
Euler- Bernoulli beam model. The calculation is done
excitation on relatively long structures? Is there an
for the Alkion earthquake for variable angles of
effect at all? Do the structural stresses increase/
incidence. For particular angles of incidence does
decrease?
the maximum bending moment peak. The cause of this response amplification is discovered in the
The earthquake load, according to the eurocode
transfer functions.
8, is modelled by a modal analysis spectrum. Consequently, this modal response spectrum is
Time delay in excitation turns out to be important
applied on a modal analysis. The only information
for the occurring maximum forces/ bending
a modal response spectrum contains, is the
moments. Building codes should contain this
information about the maximum response of a
information.
single degree of freedom model during a design earthquake event. The modal response spectrum does not contain information about the time delay in excitation. Therefore it is not possible to implement the effect of uneven excitation when applying the modal analysis.
Studente:
H. de Brabander
Committee:
Prof. Drs. Ir. J.K. Vrijling, Dr. Sc. A. Metrikine, Ir. W.F. Molenaar, Ir. L.A.M. Groenewegen (Delta Marine Consultants B.V.)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
37
38
Hydraulic & Geotechnical Engineering
0307
Effects of softwood vegetation within groyne fields
Softwood vegetation can be found within a
The data obtained from elevation measurements
significant number of groyne fields along the River
has been used to create detailed Digital Elevation
Waal. Vegetation is commonly known to decrease
Models to describe the morphological situation at
flow, attenuate waves, alter sediment properties
the time of measuring. In order to create these
and trap sediment. The total effect of these
models, several interpolation methods have been
characteristics on groyne field morphology however
assessed to determine which technique would be
is still unknown.
best suited for this study. Elevation Difference Maps and series of Riverbank Profiles were derived
Within this thesis the effect of softwood vegetation
from the Digital Elevation Models. These were used
on groyne field morphology is described. The
to describe the morphological development per
morphological development of three test locations
location over time. Volumetric calculations were also
along the River Waal have been determined based
made to determine the effect on the total sediment
on elevation measurements from 1990 until 1995
balance within each groyne field.
and newly conducted measurements from 2005 and 2006. At each of the test locations one groyne field
At each of the three test locations, the presence
has been used for the plantation of willows while
of softwood vegetation has caused erosion of
the upstream and downstream groyne field has
the lower bank and accretion at the upper bank.
been used as reference.
The morphological development within the corresponding reference groyne fields differ from
At each location the species, common osier (Salix
the test groyne field but are consistent with each
viminalis), purple willow (Salix purpurea) and gray
other. It can therefore be concluded that the
willow (Salix cinerea) were planted in an alternating
found effect at the test locations is induced by
pattern on the upper bank of the study groyne
the presence of softwood vegetation. From the
field. From these species the survival percentages
calculated volumetric differences, it can be seen
and yearly averaged mortality rates have been
that at locations were erosion has taken place at the
determined.
reference groyne fields the presence of vegetation at the test groyne field has caused less erosion
Furthermore, hydraulic conditions (water level and
compared to the reference fields. At the locations
discharge) have been determined at each location
were sedimentation has taken place at the reference
from 1990 until 2005 at each location. These
groyne fields, the presence of softwood vegetation
conditions have been determined by using a 1D-
within the study groyne field has caused erosion.
model, SOBEK. The total of the processes and factors, which are mentioned throughout this report to have an effect on groyne field morphology, are bundled into a conceptual riverbank model for groyne fields with the presence of softwood vegetation. From this model a list of desired improvements for future riverbank models has been derived.
Student:
M.T.B. van den Broek
Committee:
Prof.dr.ir. H.J. de Vriend, Dr.ir. M.J. Baptist, Dr.ir. E. Mosselman, Drs. M.M. Schoor
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
0307
Hydraulic & Geotechnical Engineering
Floating Breakwater A Theoretical study of a dynamic wave attenuating system
Ever since progressive engineers came up with the
thesis work. Therefore, a rectangular floating
idea of creating floating structures in the sea, many
body with varying width, draft and mass has
studies and models tests were performed in order to
been assumed as the basic shape of the floating
develop the optimal floating breakwater. Although
breakwater. Hydrodynamic behavior as calculated
the advantages of a floating structure seem to be
by the ReFBreak-model has been checked with
rather obvious, the use of these structures is limited,
the three dimensional potential-theory computer
mainly due to the complex hydrodynamic behavior,
model DELFRAC to determine the reliability of the
the reliability and the costs of these structures.
calculations. Wave transmission to the harbour side of the floating breakwater has been calculated for
International container shipping is one of the most
several floating breakwater layouts as is shown in
dynamic economic sectors of the past years. Higher
the figure for a floating breakwater with a variable
efficiency of the loading and unloading processes
width, draft and screen draft.
and the increase in size of container vessels contributed to the development of the Floating Transhipment Container Terminal (FTCT). The objective of this thesis was to analyse the hydrodynamic behavior of the floating breakwater and to improve the performance of the floating breakwater. A model, the so-called Rectangular Floating Breakwater Design Model (ReFBreak-Model), had to be developed that served as a general design tool to determine the dimensions of the floating breakwater. First of all, the calculation parameters, requirements and boundary conditions had to be determined.
The theoretical study proves that a floating
The harbour efficiency puts demands on the
breakwater is able to attenuate waves when the
performance of the floating breakwater and is an
structural layout is optimal.
important factor to determine whether the floating breakwater concept is successful or not. The
-
The floating breakwater is able to attenuate
hydrodynamic coefficients for rectangular floating
regular beam waves with 17 second periods
bodies, measured by Vugts (1970) are used in the
-
calculations and were extrapolated to a wider wave
to adapt its structural appearance on the prevalent
frequency range. Two-dimensional calculations were
wave periods.
performed to determine the influence of several
-
structural variables on the hydrodynamic behavior
factor for the performance of the breakwater.
This kind of floating breakwater must be able
The draft-width relation is the most important
of the floating breakwater. The calculations were performed in regular, sinus-shaped beam-on waves.
Since the results of this model are based on pure theoretical calculations, further research is
The hydrodynamic behavior of floating breakwaters
necessary to investigate the influence of irregular,
is influenced by many factors. However, only a
oblique (Ocean) waves on the performance of the
limited number could be analyzed in the underlying
adaptable floating breakwater.
Student:
M.W. Fousert
Committee:
Prof.drs.ir. J.K.Vrijling, ir. W.F.Molenaar, ir. J.L.F. van Kessel
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
39
40
Hydraulic & Geotechnical Engineering
0307
Feasibility Study on Tidal Power Barrages Including plant design and site selection Tidal power is a proven technology to produce
with the required head difference for generating.
electricity and has the potential to generate
As little was known about the effect of pumping
significant amounts of electricity at certain sites
at tidal power barrages, this has been worked
around the world. However, only limited guidance
out. Pumping water out or into the basin is shown
is available for a cost efficient tidal power plant
to be not profitable at constant electricity costs
design and the selection of a suitable site. Both
over a day as it consumes more power than it
items are addressed in this study, together with a
produces, but gains potential when electricity rates
comparison of the tidal power costs to the costs of
are lower (i.e. at night). After the general tidal
other (renewable) energy sources. Within this study
power plant and turbine design were defined, the
the possible concepts for tidal barrages have been
site selection process could be worked out. The
analysed, from which a single basin layout showed
essential parameters resulting in a valuable site
to be the most attractive plant layout. This layout
selection were determined. With this, a method
could be combined with three generation modes;
was introduced to define the attractiveness of a
One-way generation, Two-way generation and
site. A site that does not meet the required mean
generation with additional pumping.
tidal range criterion of 7 m, can not reach the most economic design for tidal power barrages and will
For these concepts, a general plant design has been
lose attractiveness.
analyzed, to determine the general dimension of the essential plant components, including; powerhouse,
To define the economical position of tidal power
sluice gates, barrage dam, bed protection and
in relation to other electricity sources, the costs
transmission lines. Aspects like cavitation and
of tidal power were determined. This included the
required excavation are taken into account. The
investment costs as well as the operational and
construction costs for these components are mainly
maintenance costs during its life time. Compared to
estimated by multiplying the defined volume of
the other electricity sources, tidal power showed to
material by the unit costs.
have high investment costs and low operational and maintenance costs. From this it can be concluded
As the turbines and further electromechanical
that tidal power has the potential to compete with
equipment required further detailed study, this is
other electricity sources.
studied separately from the general plant design. From this, a turbine diameter of 5-8 m is suggested
One of the most important recommendations which
for all sites and a method is introduced to determine
can be made on the basis of this study is further
the optimum number of turbines and sluice gates.
research in the possible environmental aspects
By studying the efficiencies and costs, for One-
of tidal power barrages regarding morphology,
way generation the single regulated Bulb turbine
water level changes and impact on fish habitats. In
was proven to be the most attractive turbine type.
addition, this thesis shows that this subject should
For Two-way generation the double regulated Bulb
be further elaborated as this could increase the total
turbine is suggested. This study showed that Two-
feasibility.
way generation is the most attractive generation mode. With the use of the Dynamic Tidal Power Model the optimum plant capacity is defined together,
Student:
J.J. van Harn
Committee:
Prof.dr.ir. M.J.F. Stive, Ir. J. van Duivendijk, Ir. H.J. Verhagen, Dr.ir. P.J.A.T.M. van Overloop, Ir. E. ten Oever (Delta Marine Consultancy)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
0307
Hydraulic & Geotechnical Engineering
The sandhunger of the Oosterschelde Case study: The development of the morphology of the Galgeplaat
After the realisation of the Deltaworks, the
realise a net sedimentation. The data-analysis gives
morphologic balance of the Oosterschelde (see
a lot of information about the deciding factors of
picture) has severely been disrupted. Due to the
the erosion of de Galgeplaat. Besides that we look
Deltaworks the tidal prism in the basin has been
at the influence of a closed barrier on the erosion
reduced sharply. The tidal trenches became to wide
of de Galgeplaat. The data-analysis together with
and need sand to get to a new morphologic balance.
several computer simulations, makes it possible to
The stormflood barrier stops sediment entering the
give a prediction of the lowering of the sandbar de
basin from sea, a redistribution of sand from the
Galgeplaat in the future.
sandbars takes place. This explains the lowering of the sandbar de Galgeplaat.
The goal of this research is to get more understanding of the loweringproces of the sandbar. In the period 1983-2001 the changing in height of the sandbar de Galgeplaat was measured at 43 locations. In combination with the wind data collected in that period, a data-analysis has been carried out. This analysis learns us that after the realisation of the Deltaworks there is still sedimentation at de Galgeplaat, but to small to
Student:
M.L.E.B. van der Hoeven
Committee:
Prof Dr. Ir. M.J.F. Stive, Dr. Ir. Z.B. Wang, Dr. Ir. M. Zijlema, Drs. E. van Zanten.
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
41
42
Hydraulic & Geotechnical Engineering
0307
The influence of flow acceleration on the stability of stones Bed protections are often made of granular material
An attempt is made to quantify the difference
and are used to prevent erosion of the bottom or
in velocity of the accelerated situation with the
to prevent the development of scour holes near
velocity of a uniform situation for which the same
hydraulic structures. Failure of the bed protection
amount of stone movement would occur.
can undermine the foundations of a hydraulic
With the help of the 7 stages of transport defined
structure and in the worst case lead to total failure
by Breusers (DHL, 1969) a translation can be
of the hydraulic structure.
made from the amount of stones, that moved in the experiments, to a Shields parameter. With this
In situations where the uniform flow is interrupted,
Shields (1936) parameter the critical velocity can be
velocity gradients develop. It is found in
calculated for which this amount of stone movement
experiments and in practice that when a flow is
occurs under uniform flow conditions.
accelerated stones start to move before the critical velocity has been reached. This movement is ascribed to the existence of flow accelerations. To find out more about this phenomenon experiments were carried out in a flume containing a locally tapered section in the labortatory for Fluid Dynamics of the Department of Hydraulic and Geotechnical Engineering.
In the tapered section the flow is accelerated and flow conditions can be created, so that the threshold of motion is reached. If the assumptions are correct the stones should move before the critical flow velocity is reached.
Student:
M. Huijsmans
Committee:
Prof. dr. ir. M.J.F. Stive, Ir. H.J. Verhagen, Dr. Ir. H.L. Fontijn
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
0307
Hydraulic & Geotechnical Engineering
Scour around an offshore wind turbine
During the construction of the first near-shore wind
The filter stones have a size of Dn50F = 0.05 m,
farm in the Netherlands near Egmond aan Zee,
with a layer thickness of 0.4 m to 0.7 m directly
prototype measurements are performed with the
on top of the sand of the sea bed (Dn = 250 μm).
aim to monitor the behaviour of the scour protection
Local conditions during the measurement are a tidal
around the mono-pile foundation of the wind
current velocity of about 0.7 m/s and a wave height
turbines (Dpile=4.6 m).
of order Hs < 3.6 meter.
The sea bed around the monopile is protected
Near the pile a lowering of the filter material is
with a two-layer rock protection. Interest
found of 0.4 m until a distance of 2 meter from
goes to the scour process on the first layer,
the mono-pile. For the whole filter construction an
the filter construction, under influence of the
evenly distributed average lowering of about 0.07
surrounding environment. For this purpose velocity
meter was observed, mainly influenced by tidal
measurements, wave characteristics and multi-beam
current and waves. The lowering that followed by
depth soundings are gathered to give an overall
the design formulas show a comparative lowering,
impression of both the acting forces on as well as
depending on the assumption for the addition of
the strength of the structure.
shear stress accounts by currents and waves.
In the design phase unfamiliarity with the exact scour process influenced by the interaction of waves and currents was reason to carryout scale model tests at WL|Delft Hydraulics laboratory. The present prototype measurements serve as a reference, verification and calibration of the scale model tests.
Student:
W.F. Louwersheimer
Committee:
Prof. dr. ir. M.J.F. Stive, ing. H.T. Van Lieshout, ir. J. Olthof, ir. H.J. Verhagen, dr.ir. A.J.H.M. Reniers
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
43
44
Hydraulic & Geotechnical Engineering
0307
Dealing with uncertainties in the design of bottom protection near quay walls During a design of bottom protection near a quay wall a civil engineer has to deal with several uncertainties. Therefore practical experience and insight in the consequences of the choice of the input variables in the present design formulas is a condition to guaranty an optimal design. To enlarge this insight in the present design formulas several bottom protections in the port of Rotterdam have been investigated. Because one of the bottom protections did not satisfy the demands of stability required to guarantee a stable bottom protection,
The probabilistic model is calibrated by the
this bottom protection is studied with soundings.
sounding results and by registrations of mooring
Using these soundings the actual level of stability
and unmooring vessels. Out of these probabilistic
can be compared with the present design formulas.
approaches insight in the influence of each input
The loads on this bottom protection differ, because
variable can be derived. By using a combination of ◊
of diversity in shipping and tidal motion. Therefore
probabilistic results and a fault-tree the probability
a better comparison can be made by resembling
of a scour hole near a quay wall can be calculated.
the results of the soundings with a probabilistic
With these results it is still not possible to choose
approach.
one strategy for designing bottom protections. The impact of a scour hole on the environment of a quay wall needs to be investigated. Therefore a study to the interaction between a scour hole and the quay wall is enclosed. With these results a risk based analysis is made to evaluate the different strategies and their consequences.
Student:
A.A.Roubos
Committee:
Ir. T. Blokland, Drs. R. Booij, Ir. J.G. de Gijt, Ir. H.J. Verhagen, Prof.drs.ir J.K. Vrijling
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
0307
Hydraulic & Geotechnical Engineering
“Computational modelling on the final closure gaps in the Saemangeum dam, South Korea” The flow velocities through a closure gap in the
area in EFD.lab may not exceed 1 by 1 km. Because
final construction stage can be relatively high
the EFD.lab model does not calculate the water
because the total basin fills and empties through
level, a water level had to be imposed beforehand.
this closure gap. The flow velocities in this final
After every calculation, this imposed water level has
stage are often normative for the design of the
to be adapted to the results. The flow above the
construction and the closing method. The stability
sill appeared to be super critical and this instigated
of the bottom protection is of main importance
problems in modelling the flowThe changing of
during the last construction phase because scour
the gravitational acceleration did not influence
holes that develop too close to the construction may
the results of the calculation. To investigate the
cause the total construction to fail. The stability of
turbulence in the model calculation, the turbulent
a bottom protection not only depends on the mean
parameters at the boundary of the model have been
flow velocity but on the turbulent properties of the
changed. Changing the turbulent parameters at the
flow as well.
boundary of the model did influence the results. Lowering the turbulent values at the boundaries
EFD.lab is a three-dimensional fluid flow model that
of the model implied less turbulence in the fluid
calculates a detailed pattern of the flow through a
flow. By adapting the turbulence parameters at
closed system, like a tube or a pipeline. EFD.lab is
the boundary of the model as well as in initial
capable of calculating the turbulent properties in a
values in the general settings, the results were
flow. A free water surface cannot be calculated with
influenced in such a way that the results were no
this model but by using a pressure ceiling, a free
longer plausible. Finally, the influence of changing
surface flow can be modelled. To investigate the
the roughness of the bottom surface has been
suitability of the EFD.lab model for situations with
investigated. The results of the calculation with an
a free water surface like a closure gap, one of the
extra bottom roughness showed a higher maximum
final closure gaps in the Saemangeum dam has been
mean flow velocity above the sill and higher
modelled with the EFD.lab model.
turbulence fluctuations.
Because no measurements could be executed during
The EFD.lab model appeared to be not very suitable
the closure of the dam, data about water levels at
for the modelling of fluid flows with free surfaces.
both sides of the dam, which are needed for the
Adapting the water level was time consuming and
input of the EFD.lab model, needed to be estimated.
when the flow became super critical, problems
With a storage area approach, a first estimate of the
arose. The parameters for the turbulent kinetic
varying water level inside the basin has been made.
energy and the turbulent dissipation in the general
Subsequently the water level variation during the
settings are start values for the calculation and
closing period has been calculated in more detail
therefore it had not been expected that changing
with a two-dimensional model called Waqua. The
them would influence the results as much as
predicted water levels have been used as input data
they were. Before the EFD.lab model is used for
for the three-dimensional EFD.lab model.
turbulent calculations in a free surface flow, further investigations are recommended.
Closure gap number 1 has been modelled with the EFD.lab model. The geometry of the closure gap has been scaled with a factor 2.5 in both the vertical as the horizontal direction, because the computational
Student:
M. van der Sande
Committee:
Prof.drs.ir. J.K. Vrijling, Ir. H.J. Verhagen, Drs. R. Booij, Dr.ir. A. Vrijburcht (Rijkswaterstaat), Ir. T.J. Zitman
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
45
46
Hydraulic & Geotechnical Engineering
0307
Hydraulic fracture grouting Laboratory experiments in sand Introduction and objectives
When a tunnel is bored under buildings, those buildings may settle because of an over cut of soil under the foundations by the tunnel bore machine (TBM). A mitigation measure to reduce these settlements is compensation grouting, which means compensating the settlements by injection of grout under the settled foundations. Compensation grouting occurs in two types, compaction grouting and fracture grouting. Fracture grouting is preferred when settlements over a larger area have to be compensated. Especially under a piled foundation, fracturing is more advantageous than compaction, because of the lower occurring local stresses with the method of fracture grouting. Research has shown that fractures occurred in clay and silty soils, but the realization of fractures in sand is more difficult. This research is meant to create fractures in sand by grout injection, if necessary with different grout properties. Further it is meant to gain more insight in fracturing in sand, especially for the implementation of the tunnelling project in Amsterdam, where this technique has to be used in sand. Besides those two objectives it is tried to give insight in the efficiency and processibility of the grout mortar. Implementation
The test series is carried out with the same set-up as used in the test series of Kleinlugtenbelt, 2005.
Results
The set-up simulates the fracture grouting technique
The results show that grout can fracture sand. It
in the field. The grout injections are carried out with
appears that there is an optimum of grout efficiency
changing grout properties. Pressures, efficiency,
and fracture geometry using various cement
drainage and shape of the fractures are measured
entities. There are three conflicting grout properties
and examined to find relations between these
which occur during hydraulic fracture grouting:
results and various grout properties.
-
The amount of leak off
-
The bleeding capacity
-
The amount of particles
Between those properties there has to be found a balance to make fracture grouting in sand possible and most effective.
Student:
M.P.M.Sanders
Committee:
prof. ir. A.F. van Tol, prof. ir. J.W. Bosch, ing. H.J.Everts, ir. A.Bezuijen (GeoDelft), Dr.ir. A. Fraaij and ir. F. Kaalberg (Witteveen+Bos)
For more information about this thesis project, please contact the department, tel. (+31) 15 27 81880.
0307
Hydraulic & Geotechnical Engineering
The influence of flow acceleration on the stability of stones There is a trend in the development of safety
The combination of advanced models and relatively
concepts as well as in economical approaches
high parameter uncertainty make the use of
to structural design to imply more probabilistic
uncertainty respectively reliability analysis methods
concepts. In this thesis work an attempt is made
in combination with the Finite Element method
to contribute to this development by describing
very attractive. It is a way of dealing with the
how structural reliability analysis can be carried out
present uncertainties in a rational manner and using
in Geotechnics, a discipline that deals with large
advanced modeling techniques at the same time.
uncertainties in the properties of its most important building material - the soil. As specific subject
For this thesis work special attention was paid to
the structural reliability of deep excavations was
the use of Finite Element Analysis in structural
chosen, for which several examples will demonstrate
reliability concepts. It is demonstrated that, in
the applicability of the presented theoretical
contrast to the common opinion, probabilistic
framework. Furthermore, the Finite Element Method,
analyses can be carried out with an acceptable
as state of the art structural analysis tool, will be
number of calculations and that not always 100.000
applied for the reliability assessment.
samples from a Monte Carlo simulation are needed to obtain reasonable estimates of the reliability of a structure. The application of advanced and more efficient concepts was part of the research.
Student:
T. Schweckendieck
Committee:
Prof. drs. ir. JK Vrijling, Dr.ir. PHAJM. van Gelder, Dr.ir. RBJ Brinkgreve, Ir. Ed Calle (GeoDelft), Dr.ir. Paul Waarts (TNO)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
47
48
Hydraulic & Geotechnical Engineering
0307
An analysis of friction by microtunneling Characteristic of microtunnelling is that the TBM
the weight above the tunnel is limited.
(Tunnel Boring Machine) and the tunnel are pushed
Another boring of WRK II revealed the importance
through the ground from the starting shaft to the
of lubrication. During a problem with the lubrication
receiving shaft. Inherent to this technique is that
injection system a very significant increase in wall
the friction forces grow with an increasing length of
friction is recorded. The influence of the lubrication is
the tunnel. In current practice it is not possible to
far larger then the influence of the increase in weight
accurately predict the friction by microtunnelling. The
of the ground column.
objective of this research is to improve the prediction of wall friction by microtunnelling in common Dutch
In segmented microtunnels misalignment has a large
soils.
influence. This is explained as follows: • C onstant steering actions are necessary to correct
The primary factor for higher jacking loads after a standstill is the dissipation of water overpressures in the layers surrounding the tunnel. Due to the
small deviations in the obtained alignment of the boring, even at straight borings. • Small rotations (< 0.3°) could give rise to high
existence of arching mechanisms, the weight of the
stresses in the soil-tunnel interface. Theoretically
soil layers above the tunnel is less important for the
this is explained in this report by considering the
encountered friction.
segments as blocks. In normal curves up to 50 % of the friction can be attributed to curved boring. In misaligned curves this percentage is higher. • Jamming of segments which are longer then the longest part of the TBM may occur under certain conditions. Borings in very stiff soils (compacted sand) and with a small overcut are vulnerable for jamming. The most important conclusion of this report is that construction related factors, such as standstills, poor lubricant injection and misalignments have a large
In a case project (WRK II) the influence of arching
influence on the friction. Especially in stiff soils, in
mechanisms and lubrication is shown. Ten borings
which the TBM reacts very well onto steering actions,
under almost similar boundary conditions are inves-
the influence of misalignment and steer corrections
tigated. The borings are constructed in a sand layer
on the friction can be significant.
covered by approximately 8 meters of peat. The borings consist of a welded continuous steel pipe.
The regular friction in a microtunnel varies between
Two of these borings crossed a highway. Locally the
1 to 5 kN/m2. Steering actions can cause locally 150
peat is replaced by sand and here the weight of the
kN/m2 or more of extra friction. Depending on the
ground column has increased. These two borings
amount of steer corrections, this leads to an increase
started and ended under the peat layer. Under the
of several kN/m2’s averaged over the entire tunnel.
highway the wall friction was twice as high as under the peat layers, while the weight of the ground column was four times larger. This indicates that arching mechanisms do occur and the influence of
Student:
N. Verburg
Committee:
Prof.ir A.F. van Tol, e.a
For more information about this thesis project, please contact the department, tel. (+31) 15 27 81880.
0307
Watermanagement
Civil Engineering Theses
Watermanagement
49
50
Watermanagement
0307
Probabilistic modeling of sewer deterioration
Traditionally, Dutch municipalities apply theoretical
when inspecting sewers. It was further found that
deterioration models without any form of validation
numerous models are developed for deterioration
or calibration. This practice may result in incorrect
modeling. However, most models were not
decisions and a cost ineffective sewer management
confronted with field data. In this research a first
policy. The focus of my research was the application
step is made towards the application of such models
of sewer inspection data for the development of a
to the Dutch sewer system using field data.
sewer deterioration model. Sewer inspections of the municipality of Goirle, Since the mid 1990s sewer inspections in
the Netherlands, were assessed on suitability for
the Netherlands are daily practice for most
sewer deterioration modeling. It was found that
municipalities. Most inspections are carried out by
most aspects, on which the sewer is assessed when
CCTV (closed circuit television) camera, the footage
inspected, are not of interest for deterioration
is consequently interpreted by qualified/certified
modeling because:
inspectors. Regulations determine the aspects
- some aspects are hardly present in the sewer
on which the condition of the inspected pipes is
inspection files, these aspect depends on the case
rated. For this particular research only inspection
study at hand (e.g. intruding sealing material);
data till 2004 is used. After 2004 a new European
- some aspects do not solely assign to the structural
sewer inspection regulation was imposed. Despite the fact that this new regulation shows great similarities with the ‘old’ Dutch sewer inspection
condition and therefore do not necessary deteriorate over time (e.g. intruding connection); - some aspects have a very large probability
regulation, combining the two distinct datasets was
(>50%) of not being identified when inspecting a
not feasible. Although inspections based on the two
pipe, these aspects are longitudinal displacement
regulations are not alike, the results of the research
and radial displacement.
are indicative for the application of inspection data
Two aspects remain, these are, ‘surface damage by
based on European regulations for deterioration
corrosion or mechanical action’ and ‘fissure’.
modeling. A case study was performed on the modeling of the A literature study on probabilistic deterioration
aspect ‘surface damage by corrosion or mechanical
models learned that the failure rate model, the
action’ using a Markov model. The results show
Markov model and the semi-Markov model reflect
that the Markov model is a good starting point for
the non-continuous classification system as applied
modeling sewer deterioration.
Student:
J. Dirksen
Committee:
prof. dr. ir. F.H.L.R. Clemens, dr. ir. J.L. Korving, ir. W.M.J. Luxemburg, ir. M.J. Kallen (TU Delft, faculty of Electrical Engineering, Mathematics and Computer Science), drs. ir. E.C. Ottenhoff (Witteveen+Bos)
For further information please contact the secretary of the section Water management: (+31) 15 2781646
0307
Watermanagement
Risk Assessment for Floods Due to Precipitation Exceeding Drainage Capacity Studies on flood protection and flood damage
This study aims to investigate and improve current
modeling were mostly concentrated on the floods
situation in risk assessment of floods due to rainfall
caused by breaches of dunes and levees since a
exceeding capacity of the drainage system of
flood resulting from these would be sudden and
polders by working on following objectives.
extensive and combined effects may be catastrophic but recently attention was also given to floods
- To figure out if any of the commercially available
due to precipitation exceeding capacity of the
models are capable of solving this problem
drainage canals and pumping stations of polders.
considering the different nature of rainfall induced
This kind of flood is neither life threatening nor as catastrophic as the floods due to breaches of dunes
floods in low lands. - To prove the correlation between flood depth and
and levees but as a result of the increase in the
flood duration. This correlation is rather important
extreme precipitation events due to climate change
because proof of such a correlation will allow us to
and increased land value, the risk due to this kind
eliminate one of these parameters, reducing the
of floods increased considerably, and must be calculated.
vast workload and enabling us to calculate risk. - To investigate the applicability of a new risk analysis tool for calculation of risk for rainfall induced regional floods in low lands. Results of an extensive study on the subject showed that none of the existing models were capable of solving this problem. Yet due to the correlation between flood depth and duration, it was possible to calculate the risk. And the “risk analysis method” was an applicable approach to this case but it requires further improvement.
Student:
U. Karamahmut
Committee:
Prof.dr.ir. N.C. van de Giesen, Dr.ir. P.E.R.M. van Leeuwen, Ir. O.A.C. Hoes
For more information you can contact the section Water Management, tel. 015-2781646
51
52
Watermanagement
0307
The impact of the deep water extraction at the position of the fresh-salt interface The ground surface above sea level and a
Because Triwaco lacks facilities to automatically
precipitation surplus are the main conditions for
move the interface; this would have to be done by
the formation of a fresh water lens under the dune
hand. To automate this otherwise very cumbersome
area. Because fresh water is lighter than salt water,
process, in this study a batch-file script was
the fresh water lens is in a dynamic equilibrium with
developed. This DOS script runs the program
the surrounded brackish and salt water. (Figure
automatically and adapts the interface elevations
1) The dune water company South-Holland (DZH)
and all effected parameters after each time step.
extracts fresh water from the dunes for drinking
Furthermore the effect of the extra resistance layers
water. With artificial recharge DZH tries to maintain
in Triwaco, the density distribution and the effect
a dynamical equilibrium of the fresh water lens. DZH
on fully penetrating wells is studied to improve the
wants to extract as many water as possible from
model.
the deeper aquifers without reducing the size of the fresh water. However, there is still little knowledge
After running the model for a period of 20 years,
about the flows and displacement of the water in
the conclusion was drawn that the model did not
the deeper aquifers, nor is there an accurate model
give the desired results. For instance at the well
of the interface and its brackish transition zone. The
locations Waalsdorp the interface moved to an
research objective is to determine the sustainable
unrealistic high position. One reason for this is the
extraction capacity for the deep wells in the region
absence of clay layers in the Triwaco model. To
Meijendel preventing intrusion and upconing of salt
determine the reliability of the model predictions
water in the wells. A second objective is to establish
the model is calibrated on the interface position.
the reliability of the predictions to determine the
The uncertainty of the newly calculated interface
extraction capacity.
depth is too large to give a plausible estimation of the change of the interface. The predictions of the
The software that was used in order to simulate this
model are unreliable due to the large error in the
complex three-dimensional groundwater system is
calculated head and due to the low sensitivity of
Triwaco. This software programme was chosen out
the parameters, which are used to carry out the
of a comparison of available models. The advantage
calibration.
of using Triwaco is that a good working model is available and that there is experience with this
The conclusion is drawn that this model can not be
model at DZH. The disadvantage is that it does not
used for calculation of the interface displacement.
take into account displacement of the fresh-salt
A better solution is to use the Triwaco model only
interface.
for calculation in the shallow aquifer. The data can
In this study, the fresh-salt interface is represented
be transferred into Modflow for making calculations
by two interfaces, the 300 mg Clˉ/l and 10.000
in the deeper aquifers. The advantage of Modflow
mg Clˉ/l. These iso-concentration layers are
is that all model layers can easily be included and it
implemented in the model as resistance layers. The
takes into account automatic interface displacement
level of 300 mg/l was chosen from the perspective
in time and the transition zone for the density
of maximum tolerable chloride for drinking water
distribution.
production. To determine the overall behaviour of the fresh water lens a 10.000 mg Clˉ/l interface was defined by DZH. Nine model layers and 8 resistance layers are necessary to model the interface and all presented aquifers and aquitards (Figure 2) Student:
N.L.Kramer
Committee:
Prof.Dr.ir.T.N.Olsthoorn, Dr.ir.C.Maas, Dr.ir.G.J.M.Uffink, J.B.Fritz
For more information you can contact the section Water Management, tel. 015-2781646
0307
Watermanagement
Integrated water quantity and water quality control of lowland water systems Water systems are continuously charged by a
methods generates several control principles, which
diversity of loads. These loads differ from water
can be used for combined water quantity and
that flows into the system, like precipitation and
quality control.
infiltration, to water that flows out of the system,
A theoretical case has been created to test the
like drainage and evapotranspiration. To maintain
developed control principles and compare these
the water level and prevent inundation these
principles with standard control. In several cases
systems are equipped with pumps and inlets, which
the developed control outperformed standard
are mainly controlled, based on the knowledge and
control. The best control principles was tested on a
experience of the supervisor. This is a very effective
model of the Haarlemmermeerpolder, since real life
way to manage water systems. When these water
testing was not possible. The model was created
systems are in the Western part of the Netherlands
with data of the Hoogheemraadschap Rijnland and
they may suffer from salt intrusion. As a result
Sobek, which is software from WL|Delft Hydraulics.
of salt intrusion the surface water may become brackish. To prevent this, the system is flushed
Advanced control works very well on the
continuously with large amounts of water, which are
Haarlemmermeer polder, although not as good
larger than necessary. The salinity of the inlet water
as was the case with the theoretical case. The
varies continuously. These variations combined with
quantitative control performed as well as standard
the constant flush rate and varying precipitation,
management. Water quality levels at measuring
cause the systems salinity levels to vary over
points were the roughly the same with advanced
time. Because the salinity in the water system has
control and standard management. Some
to remain lower than an absolute maximum, the
improvement were evident. There was a reduction
amount of water that is let in, is on the safe side,
of flushing water and salinity level in the system
meaning larger than necessary. This conservative
lowered as a result of redirections of saline water.
control is based on steady state calculations of
Concluding it can be noted that Model Predictive
the water systems behavior. It is a low-tech, but
Control performs much better than standard
cheap and effective way to solve the water quality
management in the theoretical case on quantitative
problem. Increasing the efficiency of these system
as well as qualitative demands and shows good
and maintaining the effectiveness should be
salinity predictions. Some additional fine tuning of
possible with advanced control systems.
Model Predictive Control will allow this system to
Therefore the objective of this master thesis is to
operate on its maximum. It may be concluded that
‘Develop a generic control system that can fulfill
Model Predictive Control works very well in theory.
the water quantity requirements of a water system
In the Haarlemmermeerpolder, Model Predictive
in combination with the water quality requirements
Control performs as good as or even better than
and minimizes the effort required to fulfill these
standard management in terms of quantitative and
requirements.’
qualitative demands with 10% less inlet water for
Several steps are taken to develop this control
MPC. The goal of this master thesis has been partly
system. The two most important factors, water
achieved. Unfortunately, Model Predictive Control
quality and water quality, are quite different.
cannot fully fulfill the water quality requirements as
Therefore water quantity and quality are separated.
a result of model inaccuracies in some basins, but
For both factors the relevant processes are
still improves the salinity control of the system.
described, then these processes are modeled and at last the control methodology is being described for the separate factors. Combining the control Student:
B. van Rossum
Committee:
Prof.dr.ir. N.C. van de Giesen, Dr.ir. P.J. van Overloop, Dr. B. van der Wateren – De Hoog (Hoogheemraadschap Rijnland)
For more information you can contact the section Water Management, tel. 015-2781646
53
54
Watermanagement
0307
A distributed stream temperature model using high resolution temperature observations Highly distributed temperature data are used as
The four sources are used as input for a distributed
input and as calibration data for a
physical based temperature model. In
temperature model of a subcatchment of the
the model the total energy balance including solar
Maisbich, a first order stream in
radiation (with shading effects),
Luxembourg. A DTS (Distributed Temperature
longwave radiation, latent heat, sensible heat and
Sensing) fiber optic cable with a length
river bed conduction is calculated.
of 1500m is used to measure stream water
The simulated temperature along the whole stream
temperature with a spatial resolution of 0.5
is compared with the measured
meter and a temporal resolution of 2 minutes. The
temperature at all points along the stream. It shows
measurements are done during one
that proper knowledge of the lateral
week in April 2006. In the measured temperature
inflow is crucial to simulate the temperature
profile four jumps in temperature are
distribution along the stream, and, the other
seen (see Fig 1). This is caused by groundwater
way around stream temperature can be used
sources. Using two profiles and the
successfully to identify runoff components.
assumption that the discharge and temperature of a
The DTS fiber optic is an excellent tool to provide
groundwater source is constant, these
this knowledge.
sources can be quantified.
Student:
M. Westhoff
Committee:
Prof.dr.ir. H.H.G. Savenije e.a.
For more information you can contact the section Water Management, tel. 015-2781646
0307
Transport & Planning
Civil Engineering Theses
Transport & Planning
55
56
Transport & Planning
0307
Dynamisch Railverkeersmanagement op knelpunten Dynamisch Railverkeersmanagement (DVM) is
Voor één knelpunttype, een meersporig baanvak met
bedoeld om op het spoorwegnet effectief om te
inhaalmogelijkheden, is voor de case Utrecht – ’s-
gaan met variaties in de uitvoering. Met een groei
Hertogenbosch onderzocht wat de effecten van DVM
van het aantal treinen en hogere kwaliteitseisen die
zijn. In verschillende scenario’s is gevarieerd met het
worden gesteld biedt DVM mogelijkheden voor een
aantal inhaalmogelijkheden, het aantal treinen en
betere benutting van de bestaande infrastructuur. Dit
DVM maatregelen voor de keuze van plan- en regel-
gebeurt door het opstellen van een beter betrouw-
strategie.
baar plan of door meer vrijheden voor het regelen van treinverkeer in de uitvoering te bieden. DVM
Uit de simulatieresultaten is gebleken dat in de
biedt mogelijkheden om flexibeler om te gaan met
huidige situatie een uitbreiding van de infrastructuur
variaties in vertrektijden en volgordewisselingen en
niet noodzakelijk is. Slechts wijziging van de plans-
desondanks toch meer betrouwbaarheid biedt in de
trategie zorgt voor aanzienlijke verbetering. Dit geldt
rijtijden en aankomsttijden, en daarmee een betere
voor zowel stoptreinen als intercity’s.
afhandeling van het treinverkeer. Bij toename van het aantal treinen blijkt dat uitbreiTot nu toe werd DVM alleen situationeel toegepast,
ding van de infrastructuur onafwendbaar is. De keuze
waardoor veel aandacht werd geschonken aan de
van regelstrategie wordt daarin ook steeds belangrij-
lokale omstandigheden en de plaatselijke mogelijk-
ker, terwijl ook de gekozen planstrategie nog steeds
heden van DVM. Bij wijziging van deze omstandig-
een grote invloed heeft. Uit de simulatieresultaten
heden tijdens het onderzoek gaat een deel van het
blijkt dat juist in deze situatie DVM maatregelen
onderzoek naar de mogelijkheden van DVM verloren.
een effectieve bijdrage kunnen leveren om de rij-
Een typologie van knelpunten zorgt ervoor dat knel-
en aankomsttijden te verbeteren. Bij een groeiend
punten van een zelfde type sneller kunnen worden
aantal treinen zullen de planstrategie, regelstrategie
onderzocht, omdat onderzoek van naar de effecten
en het aantal inhaalmogelijkheden dus steeds meer
van DVM voor vergelijkbare situaties kunnen worden
moeten worden geoptimaliseerd.
gebruikt.
Student:
M. van Dijk
Committee:
Prof.dr.ing. I.A. Hansen, dr.ir. T.J.J. van den Boom, dr. R.M.P. Goverde, ir. R. Hemelrijk (ProRail), Ir. J. van den Top
For more information please contact the department of Transport & Planning: (+31) 15 2781681
0307
Transport & Planning
De oorzaken van de verslechterde doorstroming bij 80 km zones In november 2005 is ter verbetering van de luchtkwaliteit op vier trajecten op de snelwegen rond de grote steden in de Randstad de snelheid verlaagd naar 80 km/u in combinatie met trajectcontrole. Gebleken is dat na invoering van de 80 km/u maatregel de filezwaarte op drie van deze vier trajecten is toegenomen. Als gevolg van deze toename is de vraag gerezen waarom de doorstroming op deze trajecten is veranderd na invoering van de maatregel. Het afstudeeronderzoek was erop gericht om te onderzoeken welke aspecten van het rijgedrag na de invoering van de 80 km/u maatregel zijn veranderd en wat voor effect dit heeft gehad op de doorstroming. Voor het onderzoek is gebruik gemaakt van
De belangrijkste oorzaken van de geconstateerde
geaggregeerde lusdata (1 en 15 minuten gemiddel-
capaciteitsdaling zijn:
den), lusdata op voertuigniveau en gedigitaliseerde
• De snelheid op de wegvakken ligt als gevolg van
videobeelden opgenomen vanuit een helikopter. Alle
de invoering van de trajectcontrole onder de 80
vier de (nieuwe) 80 km locaties zijn onderzocht.
km/h. De capaciteitssnelheid van de bottlenecks liggen in de voorsituatie echter allemaal boven de
In de eerste fase van het onderzoek is de capaciteit
80 km/h, waardoor de capaciteitswaarde van de
voor en na invoering van de 80 km zones bepaald.
voorsituatie niet meer kan worden bereikt.
Hiervoor zijn verschillende methodes toegepast en
• Door de geringere snelheidsverschillen tussen
vergeleken, waaronder de empirische distributie-
de verschillende rijstroken en de (wettelijke)
methode, de productlimietmethode en het funda-
verplichting om rechts te houden, is het percen-
menteeldiagram. Hieruit blijkt dat de capaciteit van
tage verkeer op de rechterrijstrook toegenomen
de bestaande knelpunten op de trajecten significant
en wordt de linkerrijstrook minder optimaal benut
is gedaald na invoering van de verlaagde maximum snelheid in combinatie met de trajectcontrole. Op
dan in de situatie zonder de 80 km/u maatregel. • Het is voor het verkeer dat de hoofdrijbaan wil
basis van de individuele voertuigdata uit de induc-
betreden moeilijker geworden om in te voegen,
tielussen en de helikopterdata is vervolgens het
omdat de gemiddelde lengte van een voertuigco-
rijgedrag op de 80 km zones onderzocht. Hierbij is
lonne is toegenomen.
gekeken naar de snelheid, het rijstrookgebruik, het volggedrag en het rijstrookwisselgedrag.
• Vanwege de strenge handhaving van de snelheid remmen bestuurders eerder af bij het zoeken van een geschikt hiaat dan dat ze gas geven voordat
Uit het onderzoek is naar voren gekomen dat de
de van rijstrook (kunnen) wisselen. Ook de door-
verlaging van de maximumsnelheid van 100 km/u
gaande bestuurders voeren voornamelijk rembe-
naar 80 km/u op zichzelf niet de grootste oorzaak
wegingen uit om een geschikt hiaat te creëren
is van de veranderingen in de verkeerssituatie. De
Op basis van de resultaten van het onderzoek zijn
daling van de capaciteit wordt juist vroorzaakt door
aanbevelingen gedaan voor de verbetering van de
de veranderingen van het rijgedrag van de wegge-
doorstroming op de huidige 80 km zones en ter
bruikers als gevolg van de snelheidsverlaging in
verbetering van de besluitvorming omtrent nieuwe
combinatie met trajectcontrole.
locaties voor de 80 km/ maatregel.
Student:
H.J. Harms
Committee:
prof. dr. H.J. van Zuylen, prof.dr.ir. S.P. Hoogendoorn, prof.ir. F.M. Sanders, ir. J.W. Goemans (Witteveen+Bos), drs. O.G.P. Tool (RWS Adviesdienst Verkeer en Vervoer), drs. R. Dekker (Faculteit TBM)
For more information please contact the department of Transport & Planning: (+31) 15 2781681
57
58
Transport & Planning
0307
Systematische herinrichting van zwarte punten in Vlaanderen Een beslisboom en een kosten-batenanalyse
De Vlaamse overheid investeert 500 miljoen euro
Ten tweede werd een maatschappelijke kosten-baten-
voor de herinrichting van 800 zwarte punten. Dat
analyse uitgevoerd voor de herinrichting van een zwart
zijn kruispunten en wegvakken waar veel verkeers-
punt. Als voorbeeldproject is een lichtengeregeld
slachtoffers zijn geregistreerd. In dit MSc-eindwerk
kruispunt in Lier gekozen, waar een Haarlemmermeer-
zijn twee aspecten van de herinrichting van zwarte
aansluiting aangelegd zal worden. De belangrijkste
punten in Vlaanderen beschouwd.
baten bestaan uit de in geld uitgedrukte waarde van vermeden verkeersslachtoffers. Op basis van histori-
Ten eerste werd een beslisboom samengesteld waar-
sche ongevalgegevens is een prognose gemaakt van
mee systematisch bepaald kan worden wat het meest
het aantal ongevallen en slachtoffers dat geregistreerd
geschikte kruispunttype op een bepaalde locatie
zal worden als het zwarte punt niet heringericht wordt.
is. Deze beslisboom bestaat uit een tabel en negen
Ook werd beredeneerd met hoeveel procent het aantal
stroomschema’s. Met de tabel kan bepaald worden
ongevallen en slachtoffers zal afnemen door de herin-
welk stroomschema gevolgd moet worden om het
richting. Vervolgens is voor elk jaar berekend hoeveel
meest geschikte kruispunttype te vinden. Welk
ongevallen, doden, zwaargewonden en lichtgewon-
stroomschema dat is, hangt af van de functies (of
den er vermeden worden door de herinrichting. Deze
de daarvan afgeleide categorieën) van de wegen die
baten worden in geld uitgedrukt, net als het vermeden
elkaar op het kruispunt ontmoeten. In het te volgen
brandstofverbruik. De contante waarde van de totale
stroomschema worden vervolgens ja/nee-vragen
baten blijkt ongeveer tweemaal zo hoog te zijn als de
gesteld over de intensiteit op die wegen en over de
contante waarde van de kosten, dus het voorbeeldpro-
ruimtelijke inpasbaarheid van de mogelijke kruis-
ject wordt maatschappelijk rendabel geacht.
punttypen. Aan het eind van het stroomschema is bepaald wat het meest geschikte kruispunttype is.
Student:
M. van ‘t Hof
Commissie:
Prof.Dr.-Ing. I.A. Hansen, Prof.ir. L.H. Immers(K.U.Leuven), Dr.ir. J.A.A. Stoop, Ir. J. Van Den Bossche (TV 3V), Ir. P.B.L. Wiggenraad
For more information please contact the department of Transport & Planning: (+31) 15 2781681
0307
Transport & Planning
Modeling interaction between pedestrians and revolving doors This research implements a submodel in the microscopic pedestrian simulation model NOMAD, with which the functioning of revolving doors can be analysed. Based on laboratory experiments the model has been validated and calibrated. Two conclusions can be drawn: firstly, a simple physical model fits well the observed performance of the door. Secondly, the capacity is not constant but shown to be dependent on the flow.
Analysis To analyse the performance of the different
Laboratory experiments
scenarios, arrival-departure curves are made,
For the validation and calibration of the model, data
describing the in and outflow from the walking area.
on pedestrian behaviour is essential. To get this
This gives a first impression of travel times and
data, laboratory experiments have been performed.
travel time losses.
The influence on the system performance was considered by systematically changing the
By slanting the curves, information concerning
experimental variables: initial revolving door speed,
the capacity of the door and intensities of the
flow composition, obstacles and walking direction.
flow become visible. The derivative of the slanted departure curve describes the throughput of
By means of software that can recognize and follow
the entrance. Kinks in the curves reveal that the
the different coloured caps, pedestrians inside the
capacity of a revolving door is not a constant
walking area are automatically tracked. In this way
value. In other words, revolving doors do interact
trajectories are gathered containing microscopic
with pedestrian behaviour, because of the safety
walking characteristics of all observed pedestrians
sensors. In order to describe the interaction
like speeds, accelerations and headways.
between pedestrians and revolving door, a logistic relation was found between the number of
The video images of the revolving door are used to
pedestrians in the walking area and the speed of the
gather information concerning segment occupancy
revolving door.
and the actual revolving door speed due to breakdowns, caused by pedestrians activating the
Vrotation = Vmin + (Vmax - Vmin) * (1 / (1 + exp((-
safety sensors.
Nped + mu) / s))) Results After the implementation of the behavioural parameters and relations, the interaction can be simulated. One of the means by which entrances can be assessed is the level-of-service plot.
Student:
R. Landman
Committee:
Prof.dr.ir. P.H.L. Bovy, Prof.dr.ir. S.P. Hoogendoorn, Ir. P. Wiggenraad, Dr.ir. W. Daamen, Dr.ir. S. Silvester(Industrial Design, DDI), H. v. Wijngaarden (Boon Edam Nederland B.V.)
For more information please contact the department of Transport & Planning: (+31) 15 2781681
59
60
Transport & Planning
0307
0307
Resource Engineering
Applied Earth Sciences Theses Resource Engineering
61
62
Resource Engineering
0307
The recyclability of ultra light car designs
European Union legislation (Directive 2000/53/
All objectives were related to recyclability of future
EC) introduces high recycling targets (95% reuse
car designs and use of exergy concept and exergy
and recovery plus 85% reuse and recycling in
analysis to fully describe car recycling as a dynamic
2015) on automotive industry especially car
system. By applying exergy concept to each unit
recyclers. For that reason automotive engineers
operation existing in one of five main parts of a
and environmental specialists are looking for
flowsheet of the recycling system optimization
technological solutions to fulfill recycling targets.
model (M.A. Reuter et al. 2006) it is possible
It became clear that automotive plastic recycling
to perform exergy balance over one of the five
need to be investigated to find out new technologies
main parts. At the end general exergy losses over
where as much as possible different plastics can be
whole car recycling system can be calculated. This
recovered and therefore increase total car recycling
approach allows identifying and quantifying quality
rate (if possible). Plastics and composites applied
losses in the system what became crucial to truly
in a car and expanding car recycling model with
understand car recycling system and improve future
new recycling options where exergy analysis can be
ultra light car designs from recycling point of view.
calculated was the subjects in this thesis work. Next aim of this thesis was to minimize recycling losses occurring in car recycling system during metallurgical processing of metals by applying exergy concept (Chapter 6) as new tool which can be used in design phase to avoid incompatible material combination according to thermodynamic constraints crucial for metallurgical treatment of car scrap. Car recycling system was discussed not only due to recoveries of parts or materials using car recycling model (M.A. Reuter et al. 2006) but also due to exergy concept and its application to calculate quality losses within the system. Exergy concept application within all end-of-life recycling system was a main objective in this thesis work. It was considered due to metallurgical processes, physical separation unit operations and plastic recycling options.
Student:
M. Gadziala
Supervisors:
Prof.dr. M.A. Reuter, Dr.ir. A. van Schaik
For further information about this master theses report you can contact the faculty of Resource Engineering: + 31 15 27 81328
0307
Petroleum Engineering and Geosciences
Applied Earth Sciences Theses Petroleum Engineering and Geosciences
63
64
Petroleum Engineering and Geosciences
0307
Using Real Data to test Reservoir Model Updating with the Ensemble Kalman Filter On average only one third of the oil in a reservoir
The main conclusion is that updating reservoir
is recovered, the majority is left behind in the
models with the EnKF on the basis of real data can
subsurface. A promising method for increasing the
improve the match of the model to the historical
recovery from a reservoir is by applying a closed-
production data. Updating the skin for every
loop reservoir management strategy [13]. This
interval while assimilating well test and production
strategy uses an optimisation procedure and a
log test data is an example of a case where the
model updating procedure (updating the reservoir
EnKF perform well. When too many parameters are
model on the basis of measurements to improve its
updated the performance of the EnKF weakens due
predictive capacity).
to poor statistics from the ensemble. An example
In previous research the Ensemble Kalman Filter, a
is updating the permeability in every gridblock in
model updating method, is used to update reservoir
addition to the skin.
models on the basis of synthetic data. The objective of this research is to assess the performance of the
The definitions of the initial ensemble and of the
Ensemble Kalman Filter when it is used for reservoir
output uncertainty are critical in the set up of the
model updating on the basis of real production
experiments. The definition of the initial ensemble
data. The source of this real data is the X field. In
includes the choices of the parameters to update,
this field three out of four wells are equipped with
their range of uncertainty and the number of
permanent downhole pressure gauges. The X field
ensemble members. The output uncertainty is a new
data includes well tests, interference tests and
defined parameter in the EnKF that combines the
production log tests.
effect of the measurement error, the model error and the non-linear terms in the relation between
Specific goals are: to identify what kind of
model parameters and measurements.
performance can be expected based on the
Reducing the model error in the prior model by
theoretical formulation of the EnKF, to identify
including more physics and by modelling in more
what preparation the data and the reservoir model
detail will result in a different and likely better
require before it can be used in a data assimilation
parameter update.
experiment, to identify what settings and choices are critical in a data assimilation experiment with
The recommendations for further research are to
the EnKF and to identify problem areas and to come
look for techniques of improving the quality of the
up with possible solutions.
initial ensemble and to look for ways of reducing
In this research two experiments are conducted in
(the effect of) non-linearity in the relation between
which the EnKF is used to update reservoir models
a model parameter and a measurement.
on the basis of real data. Based on the procedure of setting up these experiments and on the results that were generated, conclusions on the goals and objective of this research are formulated.
Student:
H.J. de Boer
Supervisor:
Prof.dr.ir. J.D. Jansen
For further information please contact the secretary of the section Petroleum Engineering: (+31) 15 2781328
0307
Petroleum Engineering and Geosciences
Sediment Mass Balance Study of the late-Holocene Prodelta on the Northern Adriatic Shelf The late Holocene stratigraphic record in the
Within the range of uncertainties, the sediment
Adriatic Basin developed during a relatively stable
supply matches the mass of the prodelta and Po
highstand of the sea level. Among the highstand
delta. This match implies that for the past 5.500
deposits, preserved in the stratigraphic record, are
years, virtually all of the delivered sediments are
the modern Po delta and an elongated prodelta
preserved in the stratigraphic record. The Adriatic
on the Adriatic shelf. The base of these deposits is
Basin can therefore be considered as a semi-
dated at 5.500 years BP.
enclosed basin.
This study demonstrates a stochastic simulation that derives sediment mass estimates from seismic travel time data of the prodelta. The simulation shows that data density and porosity are the main factors contributing to uncertainty in the estimates. This study shows a match between the mass of the stratigraphic record and calculated sediment flux into the basin. Sediment flux simulations of rivers, draining Alpine and Apennine source areas, result in an estimated 3.2 x 105 Mt. (with uncertainty, σ = 0.64 x 105 Mt.) of sediment delivered to the Adriatic Basin for the past 5.500 years. The mass of the prodelta is estimated at 2.0 x 105 Mt. (σ = 0.1441 x 105 Mt.) and the calculated mass of the Po delta is 0.7 x 105 Mt. (σ = 0.1441 x 105 Mt.)
Student:
W. Bron
Supervisors:
Dr. G.J. Weltje, Drs. M. Brommer
For further information please contact the secretary of the section Reservoir Geology: (+31) 15 2781328
65
66
Petroleum Engineering and Geosciences
0307
An Integrated Study into the Reservoir Characteristics of Miocene Mangrove Deposits of Mallorca Several oil reservoirs around the world are
The outcrop data were used as a framework to build
producing from carbonate mangrove deposits.
a three-dimensional static reservoir model using the
Little previous research has been undertaken on
software package Petrel. Rock properties measured
fossil mangroves, especially regarding their lateral
from the rock samples were used to populate the
heterogeneity, structure, permeability and porosity.
facies model with porosity and permeability data.
This has resulted in a relatively poor understanding
The Petrel model was then imported into Eclipse in
of reservoir mechanisms and consequent reservoir
order to make a dynamic model. In this software
performance of such reservoirs. This integrated
package several well placement scenarios were
study on outcropping mangrove deposits provides
simulated as if the Santanyi Limestone and
insight into the properties of mangrove carbonate
surrounding facies would have been a reservoir.
reservoirs.
The main outcome of the study was that the low horizontal and high vertical permeabilities of the
A series of Miocene carbonate outcrops along
mangrove facies strongly favour field development
the south eastern coast of Mallorca include fossil
using horizontal wells.
mangrove deposits. These rooted intervals are part of the Santanyi Limestone and subject of this integrated study. First, a literature study was done on the geology of Mallorca. This was followed by a literature study on mangrove environments in order to understand the depositional environment of the Santanyi Limestone and its resulting specific reservoir characteristics. Three weeks of fieldwork were undertaken during which sedimentological and petrographical data were collected from 12 logged outcrops in order to examine petrophysical properties and lateral heterogeneities. Rock samples were taken and were analysed to elucidate their porosity, permeability and petrophysic characteristics. From these data, a sedimentological model was established.
Student:
H. Coppes
Supervisors:
Dr. J. Noad, Prof.dr. S.M. Luthi
For further information please contact the secretary of the section Reservoir Geology: (+31) 15 2781328
0307
Petroleum Engineering and Geosciences
Enhanced mass transfer of CO2 gas into water by density driven natural convection Global warming has increased interest in
A theoretical interpretation of the observed effects
quantification of the dissolution of CO2 in (sub)-
has been proposed, based on diffusion and
surface water. In all cases of practical interest CO2
natural convection phenomena. The ensuing
is present above the water. Dissolution of CO2
equations have been solved for the steady state case.
into water causes a density increase, with respect to pure water. This density effect causes natural
Convection effects are no longer dominant in the
convection, which enhances the mass transfer rate
long term and the mass transfer rate becomes a
across the interface. To our knowledge, only a few
diffusion process. The experimental data allow the
studies have been carried out to experimentally
determination of the diffusion coefficient. Its value
investigate this mechanism.
agrees with values presented in the literature.
This article describes, a series of experiments done in a cylindrical PVT-cell, where an over pressured volume of CO2 gas was brought into contact with a column of distilled water. The Rayleigh number is of the order of one million whereas the Schmidt number is of the order of five hundred. The results show that the mass transfer rate across the interface is much faster than predicted by Fick’s second law. This mass transfer rate turned out to increase with increasing gas pressure.
Student:
H.A. Delil
Supervisors:
Dr. J. Bruining
For further information please contact the secretary of the section Petroleum Engineering: (+31) 15 2781328
67
68
Petroleum Engineering and Geosciences
0307
Simultaneous Measurements of Capillary Pressure and Dielectric Constant in Porous Media from 50 Hz to 3 MHz An experimental procedure is presented with which the capillary pressure (P¬¬c) and the dielectric constant (ε) of a porous medium can be measured simultaneously. The equipment is designed to conduct measurements under constant pressures (up to 20 bar) and constant temperature conditions for the unconsolidated sand- water-gas (N2 and CO2) system. Pc is defined as the averaged pressure difference between the bulk gas and water pressures within the system and ε is obtained utilizing an impedance tool. The tool design consists of a porous medium sample holder acting as a parallel plate capacitor. A precision component analyzer measures the complex impedance and phase angle as function of frequency during displacement processes and its value is directly related to the effective dielectric constant of the mixture of grains, water and gas phase. We have validated the set-up for reproducible capillary pressure curves with the different gases injected. Moreover, the accuracy of the dielectric measurements is higher than 96% using calibration substances with known dielectric properties. The aim of this study is to get an understanding of the hysteresis in Pc and ε between the drainage and imbibition processes in terms of phase distributions, frequency dependence, and interfacial area factors which may exert influence on it. We propose that there is a direct relationship between the interfacial interactions within the systems and ε. The capillary pressure and the dielectric constant are functions of the water saturation therefore there is a direct relation between both physical properties and their hysteretic behavior is the evidence of this.
Student:
L.M. Moreno Tirado
Supervisors:
Dr. J. Bruining, Dr.ir. E.C. Slob, Ir. W.J. Plug
For further information please contact the secretary of the section Petroleum Engineering: (+31) 15 2781328
0307
Petroleum Engineering and Geosciences
Recovery Enhancement by Injection of Low Quality Steam with Volatile Oil It is generally expected that consideration of non-
In this study, steam drive recoveries of oil with
conventional oil resources and new technologies
and without volatile oil (alkanes) are compared.
in exploitation and exploration will enhance the
As opposed to previous studies where high quality
future oil reserves. Different sources quote different
steam is used, this study is focused on the low
values for these increased reserves. However,
quality steam injection. The most interesting result
it is generally agreed that the same order of
of this study is that the recovery enhancement due
recoverable heavy oil exists as remaining reserves
to volatile oil, which is clear for high quality steam,
of conventional oil.
is much less for low quality steam. For the modeling of the experiments the STARS simulator is used.
Several methods are used in the production of heavy oil, such as hydrocarbon gas injection and thermal methods, e.g., hot water, steam and in-situ combustion. Steam injection into heavy oils has been applied over the last 40 years; however, the mechanisms and effectiveness of this process are poorly understood. It is possible to improve the efficiency of the steam recovery process by adding distillable oil to the injected steam and tested in the field successfully in 2005.
Student:
M.N. Guy
Supervisors:
Dr. J. Bruining
For further information please contact the secretary of the section Petroleum Engineering: (+31) 15 2781328
69
70
Petroleum Engineering and Geosciences
0307
Stress estimation and gas detection from seismic reflection coefficients at a non-welded interface We investigate the possibility to estimate effective
stress-compliance relation is available. Both
stress and detect gas from seismic reflection
estimations yield best results at normal incidence,
coefficients at a non-welded interface. The
where the inversion can be approximated by a
interface is represented by a planar distribution
simple linear expression, relating the imaginary part
of penny-shaped cracks, resulting in a linear slip
of the AVO intercept directly to the compliance.
boundary condition with a normal and a tangential
Realistic changes in crack infill have more influence
compliance. These compliances change as the
than realistic changes in effective stress; thus the
planar crack density decreases exponentially (due
suggested approach has more potential for gas
to crack closure) with increasing effective stress.
detection than for stress estimation.
The media above and below the interface are vertical transverse isotropic (due to horizontal inclusions, fractures or fine layering) and their elastic coefficients are taken from empirical data (dependent on effective stress and pore infill). We compute quasi-PP, -SvP, -SvSv and -PSv reflection coefficients for several realistic scenarios with varying angles of incidence at different stress states with different pore infill (brine or gas). Both effective stress and pore infill affect the model in two ways: a) through the elastic coefficients of the upper and lower media, and b) through the interface compliances. Both effects have significant impact on the computed reflection coefficients and their interplay can easily cause misinterpretations. We show how the slip induced effects can approximately be separated by taking the imaginary part of the reflection coefficients. Alternatively, taking the real part of reflection coefficients can correct for slip effects in AVO. We invert the synthetic reflection coefficient data as generated by the forward model for the vertical effective stress component and for the compliance ratio, being an indicator for crack infill properties. Our analysis reveals that the inversion requires a priori measurements of the vertical wave velocities at each stress state, an estimation of anisotropy and some (theoretical or empirical) relation between fracture compliance and effective stress. We introduce error bars in the estimated stress considering errors in the input wave velocities. Our inversion results demonstrate that we are able to estimate both compliance ratio and effective stress, assuming that an accurate
Student:
J. van der Neut
Supervisors:
prof. dr. ir. C.P.A. Wapenaar and prof. M.K. Sen, PhD
For further information please contact the secretary of the section Applied Geophysics and Petrophysics: (+31) 15 2781328
0307
Petroleum Engineering and Geosciences
Produced Water Re-Injection Experimental Investigation of the Effect of Flow Rate on Filter Cake Build-up in Fractures
Attempt has been made by means of laboratory
Five experiments were conducted with different
investigation to quantify the effect of standard flow
combinations of crossflow and permeate velocity.
parameters on the formation of external filter cake
Results indicate that at regions in the fracture close
in water-injection fractures. The approach was to
to the wellbore, decrease in injectivity could be
simulate three flow regimes in fractures during
dominated by external filter cake formation. The
produced water re-injection. The simulated zones
low permeate rate relative to the crossflow flow
are the entrance to the fracture adjacent to the
rate ensures that formation damage is gradual. A
wellbore; a region in between the wellbore and the
comparison of the result of the last two experiments
fracture tip; and finally the region at the fracture tip
underscores the relevance of crossflow flow on
where leak-off is least. All the parameters of interest
external cake formation and the associated erosion.
were kept more or less constant except for the
Based on the experimental conditions, it was
permeate and crossflow velocity that were varied
concluded that a relatively high crossflow flow rate
to see what the impact would be on the process of
will result in accelerated external filter cake erosion.
cake formation.
Student:
C.C. Obeta
Supervisors:
Prof.dr. P.K. Currie, Ir. A.H. de Zwart
For further information please contact the secretary of the section Petroleum Engineering: (31) 15 2781328
71
72
Petroleum Engineering and Geosciences
0307
Modeling sediment storage in a tidal dominated delta, the Fly River, Papua New Guinea Tide dominated deltas are not studied so
result of only sediment deposition at the delta
extensively as river-dominated and wave-dominated
apex, due to low velocity and low river discharge,
deltas. Through modeling of a tide dominated delta,
sediment has not been transported towards
insight will be achieved about the influences of tidal
downstream area. With tide and without tide
and fluvial processes on sediment transport and
scenarios, resulted into differences in sedimentation
deposition in these tide dominated environments.
patterns, based on grainsize characteristics. The
Process based modeling of tide dominated deposits
morphological development shows that changes
makes it possible to distinguish the controls of
around a specific island has resulted scouring of the
tidal depositional processes on the depositional
channel bottom at tidal conditions and deposition
architecture in terms of reservoir properties. Due
of coarse grained sediments along the sides of
to the fact that tide-dominated deposits are very
the channel. Further it was distinguished that the
heterogeneous, process based modeling of these
highest sand accumulation has been occurred at
deposits could support high resolution correlation
the upstream part of the island and the highest clay
and delineation of reservoir flow units.
sedimentation at the downstream part of the island. This characterizes an important difference between
The objective of this research was to model the
more fluvial-dominated deltas and tide-dominated
sediment storage in the tide dominated delta and to
deltas. The main problem during modeling was
study morphological changes in the delta at annual
related to the scaling of the model according to
conditions and due to variable river discharge and
the Fly delta geometry and flow conditions. This
sediment load.
was caused by the Delft3D model limitations, for size and resolution of the model grid. Overall we
The research method involves process based
conclude that longer-term simulations create the
modeling with the Delft3D modeling software.
possibility to study the morphological development
Here several scenarios have been executed while
within the delta in more detail.
varying parameters, which control river and tidal influences. The simulation results were used to study the sedimentation pattern development and morphological changes within a tide dominated delta. This research uses the Fly delta, in Papua New Guinea as case study area, with the focus on the area between the apex and the mouth of the delta. Depth average velocity and yearly sedimentation rates were used as criteria to select the most suitable scaled sediment load scenario for the simulations. Bed level study shows that the sedimentation rates varies within the delta, with highest sedimentation in the mid-delta area, and lowest at the channel mouth. Decrease in sediment deposition during low flow conditions was relatively larger, while the high flow conditions causes a smaller increase in sediment deposition. The El Niño extreme low flow scenario shows a predictable
Student:
N.R. Sheombarsing
Supervisors:
Prof.dr. S.B. Kroonenberg, Dr.ir. I. Overeem, Dr. J. Storms, Dr. G.J. Weltje
For further information please contact the secretary of the section Applied Geology: (+31) 15 2781328
0307
Engineering Geology
Applied Earth Sciences Theses
Engineering Geology
73
74
0307
Engineering Geology
The investigation on the formulation of a new design code for MV-piles This thesis investigates, whether the current
This formula differs from the old one on the
design code for MV-piles is still valid or needs to
following two aspects:
be updated, because these days the used piles are
• CV = Calculation value for the circumference of
much larger, than the time when the current code
the pile
was formulated. In order to check if the current
• W = width of the pile
code is still valid, the t-factor in the formula below
• H = height of the pile
was calculated for forty-seven piles, using the
• t = 2.5 %
bearing capacity derived from the pile load-tests. The final conclusion of this thesis is to use the
F
Pile
qc ⋅ L⋅ O⋅ α t
lowest value for the bearing capacity that is
av
predicted with either the formula above or the
In which:
existing formula. The differences in correctly
• Fpile = Bearing capacity
predicted bearing capacities between both methods
• qav = Average cone resistance over the length
where too small to replace the current formula by
where shaft resistance is mobilised
the new one. But since the new formula does not
• L = The active length of the pile
overpredict the bearing capacity of the larger piles,
• O = Circumference of the pile
this will lead to safer design of MV-piles.
• αt = coefficient for the shaft friction = 1.4 % From the analysis of the dataset it followed that the current design code does not fit this dataset, since no constant value of 1.4% for the αt-factor was found. In stead of a constant value for the αt-factor a negative relation between the circumference and the αt-factor found. This leads to an overestimation for the piles with large circumferences and thus to dangerous situations. Therefore various modifications of the current design code where investigated in order to give a better prediction for also the larger piles. The following method gave the best predictions for the dataset:
F
Pile
qc ⋅ L⋅ CV⋅ α t av
qc ⋅ L⋅ ( 2 ⋅ W + 0.38 ⋅ H) ⋅ 0.025 av
Student:
R.L. van Hof
Supervisors:
Prof.ir. A.F. van Tol
For further information please contact the secretary of the section Engineering Geology: (+31) 15 2781328
0307
Engineering Geology
Influence of spatial correlation length on predicted settlements of a road embankment In the common geotechnical engineering practice
road axis for three representative locations. The
the shallow subsurface is often modelled in several
methodology of creating a lithological random
layers by assigning to each of these average
field is followed. Furthermore the outcomes of
material properties. However the reality is quite
the realization technique are compared with the
different. The soil properties are characterized
outcomes of the classical approach which is used in
by spatial variability within each homogeneous
the common Civil/Geotechnical Engineering practice.
lithological unit. This variability can be taken into
(This work was supported by TUDelft and TNO-
account by incorporating the value of the spatial
NITG/Nederland’s Institute for Applied Geosciences)
correlation length on the simulation results. The spatial correlation length describes the distance over which a random variable tends to be correlated in the underlying Gaussian field. A large value of spatial correlation length describes a smoothly varying field, while a small value implies a ragged field. The objectives of this Graduation project are to extract the value of the spatial correlation length for a specific case study and to investigate its influence in the settlement calculations of a road embankment. The study area deals with the A2 highway connecting Amsterdam and Utrecht. A representative section of 8,5Km was analyzed and data were gathered from 248 Cone Penetration Tests, 35 Boreholes and a Geophysical survey of 2,5Km length (Consoli Test). The project consists of 4 major sections. Firstly the methodology used for the processing of the data set is given (CPT, Borelogs and Geophysical outcomes). In the second section a literature review is performed and three different techniques for the quantification of the spatial variability are presented (Moving Average Window Technique, Autocorrelation Function, and Semivariogram Function). Based on the evaluation of these techniques the Semivariogram technique was the one selected for the extraction of the spatial correlation length. By implementing the semivariogram function in every lithological unit 50 different three dimensional lithological maps of the Holocene deposits were made. By importing that lithological information in the settlements calculations (Finite Element Method) 300 hundred simulations were performed along and across the Student:
S. Kalamatas
Supervisors:
Prof.dr.ir. F. Molenkamp, Dr.ir. D.J.M. Ngan Tillard
For further information please contact the secretary of the section Engineering Geology: (+31) 15 2781328
75
76
Engineering Geology
0307
Plaxis Soft Soil Creep: de toepassing van een isotroop kruipmodel op de anisotrope ondergrond In met name West-Nederland bestaat de ondergrond
2D vervormingen blijkt de K0nc-afhankelijke
voornamelijk uit slappe klei- en veenlagen. Bij het
M parameter een belangrijke modelparameter.
aanbrengen van een maaiveld belasting zullen er in
Aandacht is daarom besteed aan de bepaling
deze slappe grondsoorten verticale en horizontale
van deze parameter. Een K0-C.R.S. proef geeft
vervormingen optreden. Voor het berekenen
realistischere waarden voor M(K0nc) dan de
van de vervormingen zijn verschillende modellen
vuistregel van Jaky. Verder heeft de geometriekeuze
beschikbaar. Het 3-dimensionale SSC model is
(axisymmetrisch of plane strain) en de bepaling
echter het eerste materiaalmodel in Plaxis waarin
van de doorlatendheid significante invloed op de
kruip is geïntroduceerd. Dit model is gebaseerd op
resultaten.
het 1-dimensionale a,b,c-Isotachenmodel. Bij de No-Recess case is de anisotrope ondergrond Uit praktijk ervaring blijkt dat bij de aanbevolen
gemodelleerd met het isotrope SSC model. De
omrekening van de a,b,c-Isotachen in SSC
gevonden horizontale vervormingen sluiten bij
samendrukkingsparameters de zetting van het a,b,c-
een juiste parameter- (doorlatendheid en M) en
Isotachenmodel niet in overeenstemming is met de
geometriekeuze (axisymmetrisch of plane strain)
zetting volgend uit een 1D SSC berekening. Dit is de
goed aan bij de gemeten vervormingen. Voor
belangrijkste rede dat dit onderzoek is opgesteld.
de zettingen geldt dit echter niet. Het model
Er is onderzoek gedaan naar de oorzaak van dit
overschat de zettingen vooral in het begin van de
verschil, hetgeen vervolgens is gevalideerd a.d.h.v.
ophoogfase. Niettemin lijkt het model de horizontale
een samendrukkingsproef en een case. Verder is
en verticale kruip én horizontale / verticale
het SSC model beschreven en gevalideerd aan 2D
vervormingsverhouding goed in te schatten. Bij de
vervormingen. Het algemene doel van dit onderzoek
gekozen parameters is de anisotrope ondergrond
is het verbeteren van de praktische toepasbaarheid
daarmee goed met het isotrope SSC model te
van het SSC model.
simuleren.
Uit modeltechnisch onderzoek blijkt dat de zetting van het SSC- en a,b,c-Isotachenmodel bij een 1D berekening exact met elkaar overeen moeten komen onder de voorwaarde dat de verhouding horizontale / verticale spanning constant is. Bij een niet constante verhouding ontstaan er verschillen die normaliter te verwaarlozen zijn. De simulatie van een samendrukkingsproef bevestigt dit, de No-Recess case echter niet. De oorzaak hiervan is het op een andere wijze in rekening brengen van onderwaterzakken (bij de samendrukkingsproef speelt onderwaterzakken geen rol). In Plaxis (SSC) is onderwaterzakken correct geïmplementeerd, MSettle (a,b,c-Isotachenmodel) benadert onderwaterzakken. De verschillen tussen de modellen ontstaan dus t.g.v. de implementatie in verschillende rekenprogramma’s. Bij het beschrijven van het SSC model voor Student:
R. Servais
Supervisors:
Prof. ir. A.F. van Tol, Ing. H.J. Everts, Dr. ir. R.B.J. Brinkgreve, Ir. H. L. Jansen (Fugro), Ir. W.H.J. van der Velden (Fugro), Dr. ir. D. J. M. Ngan-Tillard (coördinator Ingenieursgeologie)
For further information please contact the secretary of the section Engineering Geology: (31) 15 2781328
0307
Offshore Engineering
Offshore Engineering Theses
77
78
Offshore Engineering
0307
Conceptual Design of a Tension Leg Platform Optimized for the Heerema Group capabilities In the search for offshore hydrocarbons many
Equatorial Guinea, an integrated TLP which has been
platform concepts have been developed over the
self-installed. Finally a conceptual design for the
years. One of those concepts is the Tension Leg
Heerema Tension Leg Platform (HTLP) is presented.
Platform (TLP), a floating platform connected to
The installation of HTLP has been investigated
the seabed by vertical tubulars, called tendons,
for sea states with a probability of exceedence
which are under permanent tension using excess
around 50% in both Equatorial Guinea and Angola.
buoyancy of the platform. The three companies
The dynamic hook load fluctuations in the cranes
within the Heerema Group have been involved in
have
the engineering, fabrication, transportation and/or
configurations of the HTLP and the SSCV Thialf. A
installation of more than 70% of all TLP projects
dual crane installation proved to be preferable over
since the installation of the first TLP by the Semi-
a single crane installation.
Submersible Crane Vessels (SSCVs) Balder and
jpg
been
investigated
for
several
installation
Brinkhuis.
Hermod. Both the hull and the transportation and installation In general, two different installation methods for
process of the HTLP have been compared to
TLPs can be distinguished: self-installation and
competitive TLP designs. Compared to the reference
installation assisted by a crane vessel. Self-installable
TLP, the hull efficiency can be increased, which can
TLPs are usually considered to be integrated TLPs,
result in a decrease in the hull mass of 11%. The
i.e. the mating of the hull and the topsides has been
total time of transportation and installation can be
completed in the yard and the integrated TLP is
reduced by 16% compared to separate hull and
transported to the installation site. The impact of
topsides installation. This can result in a reduction
stability requirements on the hulls of self-installable
of 23% on the installation and transportation costs.
TLPs during the installation can be significant and
For water depths ranging from 500m to 2000m the
may result in a hull design which is not optimal for
HTLP can compete with existing TLP designs, with
in-place conditions. By suspending the TLP in a crane
respect to displacement. The influence of composite
during the installation, i.e. crane-assisted installation,
tendons on the displacement of the HTLP has also
the impact of the stability requirements on the hull
been investigated. For depths exceeding 1200m,
can be reduced and more optimised hull designs can
composite
be achieved. As a consequence, these optimised
decrease of the displacement of the HTLP.
tendons
can
result
in
a
significant
hull designs have insufficient stability for a freely floating hull with integrated topsides. Therefore the
Although the conceptual design presented in this
installation is split into two phases: first the hull is
study is by no means an optimal design for the given
installed, followed by the offshore installation of
environmental conditions, it does provide insight in
the topsides. This leads to a considerable increase
the potential of a TLP optimised for both in-place
in installation time. A combination of these two
conditions and the capabilities of the Heerema
installation methods is presented in this study as
Group. It is concluded that such a TLP can be
the preferred installation method for the Heerema
advantageous compared to competitive TLP designs
Group: crane assisted installation of an integrated
and it is recommended that more research will be
TLP.
conducted in the feasibility of a Heerema Tension Leg Platform.
A basis of design has been developed for a TLP in West-Africa in 500m water depth. The boundary conditions have been based on a reference TLP in Student:
H.T. Brinkhuis
Sponsor:
Heerema Marine Contractors
Committee:
prof.ir. J. Meek, ir. G.H.G. Lagers, ir. H. Boonstra, ir. R. Zoontjes
For more information please contact the department of Offshore Engineering: (31) 15 2781328
0307
Offshore Engineering
Development of the Yoke Quay Mooring Concept (YQM) Weathervaning LNG Terminal in Shallow Water
Introduction
Yoke Quay Mooring Concept
The objective is of the thesis study was to develop
Three terminal concepts have been developed
a concept design for a freely weathervaning LNG
and analyzed using the AQWA software for
terminal in a water depth of 16 meters, in a West-
hydrodynamic calculations. The selected concept is
African environment (Nigeria), which survives the
Yoke Quay Mooring (YQM) Concept 1 (see figure 1).
100-year conditions and which is operable up to the 1-year extreme conditions.
The concept consists of three main elements; the
The terminal must be suitable for non-dedicated
floating quay structure, the connection method of
LNG carriers with a mid-ship manifold and
the quay to a fixed tower and the mooring system
conventional mooring line facilities. The LNG carrier
for LNG carriers.
has a capacity of 135000 cubic meters. Submerged
A semi-submersible structure was selected as
cryogenic swivels or flexible cryogenic hoses are
a quay structure. The quay has a limited width
not permitted in the terminal design. Proven LNG
in order to make the loading arms suitable for
loading arms are to be used.
operation at both sides. Eight quay designs have
In operational conditions, the relative motions
been analyzed. The seventh quay design has the
between the mid-ship manifold on the LNG carrier
best motion behavior in survival conditions and the
and the LNG loading arms on the terminal must
smallest loads in the mooring lines in operational
remain below the allowable limits. The loads in the
conditions. This quay design is shown in figure 2.
mooring lines may not exceed the maximum safe
The Soft Yoke Mooring and Offloading system
working load. In survival conditions the minimum
(SYMO) developed by SBM for the application of
allowable keel clearance is 1 meter.
LNG offloading, was selected as the most suitable method to moor the quay to the fixed tower. The SYMO allows a “soft” response and consequently the quay follows the motions of the LNG carrier. In this way the motions of the loading arms under operation and the loads in the mooring lines are limited. The solution of a side-by-side mooring arrangement was selected to moor the LNG carrier to the quay. No adjustments to the carriers are required. Conclusion
The technical feasibility of the Yoke Quay Mooring Concept has been established. However the operability in 1-year extreme conditions is limited in case of cross environments. The results of the operability study will be improved by including damping coefficients and shielding effects in the AQWA calculations.
Student:
E.W. Heerema
Sponsor:
GustoMSC
Committee:
prof.dr.ir. J.A. Pinkster, A. Metrikine PhD MSc, ir. G.H.G. Lagers, ir. A.J. van der Spek
For more information please contact the department of Offshore Engineering: (31) 15 2781328
79
80
Offshore Engineering
0307
A Practical Assessment of Lateral Buckling Sensitivity of Subsea Pipelines Increasing numbers of subsea pipelines are required
lateral buckling are described by the axial stiffness
to operate at very high pressures and temperatures.
(EA) and bending stiffness (EI). Combining the key
A subsea pipeline operated at temperatures and
parameters with the key properties by means of
pressures above ambient will expand. If the pipeline
dimensional analysis, leads to four dimensionless
is restrained, e.g. by soil friction, axial compressive
parameters. They are: πforce, πlateral_friction,
stresses will develop as temperatures and pressures
πaxial_friction and πOOS. These dimensionless
increase. In case these axial compressive stresses
parameters characterise the initiation of buckling
reach a critical value and the pipeline is not buried,
and are called Buckle Indices.
they may lead to lateral movement of the pipeline. This phenomenon is called lateral buckling and
Finite Element Modelling (FEM) has been used to
may be a problem if the stresses and strains in
analyse the relationships between the different
the pipeline exceed the design criteria. As a result
Buckle Indices. This analysis demonstrated that the
lateral buckling has to be considered during the
force at which buckling is initiated is independent
design of subsea pipelines where high pressures and
of the axial resistance. Therefore the initiation
temperatures occur.
of buckling can be described by means of three Buckle Indices. Combining these Buckle Indices in a graph enables identification of the following areas : no buckling, buckling possible and buckling taking place. The combination of Buckle Indices has been chosen such that the area “buckling possible” is reduced to a minimum. This has been done by
Buckling theories have produced several methods
plotting πforce / πlateral_friction as a function of
and models to assess the susceptibility of
πOOS.
pipelines to lateral buckling. However, results of
The operational data of the pipelines used in this
these methods and models are felt to be very
study have been provided by NAM or Shell Expro.
conservative. If a discrepancy between theory and
Predetermined criteria have been used to select
reality does indeed exist, unnecessary costs deriving
pipelines which were thought to be most susceptible
from conservative designs are incurred during
to lateral buckling. From this selection of eight
construction of pipelines. The objective of this
pipelines, only one was reported to have actually
study is to develop a tool, which is able to compare
buckled laterally. Part of the operational data needed
theoretical results with actual operational data
to calculate the input parameters of the BIM was not
with respect to the initiation of lateral buckling, to
available. Therefore the results of the BIM based on
confirm the theoretical discrepancy (if any) and help
operational data, should be treated with care.
to identify the causes. This tool has been called the Buckle Indices – Method (BIM).
By comparing the results of the BIM based on FEM
Based on literature studies a number of key
and based on operational data, a discrepancy has
parameters has been identified that influence the
been shown, indicating that FEM is conservative.
initiation of lateral buckling. These are: effective
Reasons for this may be an incomplete soil model
axial force at which buckling occurs (Sbuckle), lateral
in FEM, errors in the results of the BIM based on
resistance (Rl_breakout), axial resistance (Ra_
operational data due to lack of accurate actual soil
breakout) and the actual out of straightness (O0).
data or an overestimation of the actual effective
All key properties of the pipeline with respect to
axial force in a pipeline due to free spanning.
Student:
M. van Heel
Sponsor:
Shell Int. Exploration & Production
Committee:
prof.ir. J. Meek, dr.ir. S. van Baars, ir. G.H.G. Lagers, ir. S. Draaisma
For more information please contact the department of Offshore Engineering: (31) 15 2781328
0307
81
Offshore Engineering
Feasibility study of the use of the Ampelmann in Shell
For the winter production of hydrocarbons at sub-
With respect
arctic Sakhalin Island (Russia), Shell has applied
to deviating
a dedicated vertical chute system for the use as
ice-drift
emergency evacuation method to escape directly
directions and
from the top deck of the offshore installations down
the presence
to the deck of an Ice Breaking Standby Vessel. This
of ice-rubble
chute, named Skyscape (left figure), is a set of nets
formations
and rings that folds-up at the deck of the vessel
around the
to compensate for the wave-induced motions of
legs, the
the vessel. By the nets, the personnel encounter a
chute is finally
decelerated fall to the vessel underneath.
substituted by a suspended
In this thesis study, the reliability of this Skyscape
gangway design
is investigated with respect to several (sub arctic)
(concept 4:
environmental conditions: swell-in-ice events, wind
see figure
affecting the alignment of the chute, deviating
above). This
ice-drift directions and the formation of ice-rubble
gangway design
around the offshore structure. The findings of
leads over
this reliability review is that the environmental
the ice-rubble
conditions will limit the safe operation of this chute
formations and
significantly, resulting in an unavailable evacuation
can be directed into any likely wake direction behind
method for over 12 days per winter.
the platform. As a result, the use of this suspended gangway design in combination with an Ampelmann system improves the workability from 12 days lost due to environmental conditions (Skyscape) down to only 2 days of unavailability (extreme swell in ice conditions) per winter. In order to compare the effectiveness of all concepts, the risks and the related costs of each concept are assessed and compared in an ALARP demonstration. As a systematical approach for this demonstration, the EER-triangle suggested by the
To improve the availability of this Skyscape (concept
ISO standards has been applied. In this triangular
1), the use of an Ampelmann system in between the
approach, the ‘hardware integrity’, ‘procedures
vessel and the chute is studied. By canceling out all
and controls’ and the ‘personnel competences’ of
wave-induced motions of the vessel, the Ampelmann
each concept are valued. It is concluded by this
eliminates the risks encountered by the hazardous
ALARP demonstration that the suspended gangway,
folding characteristics of the Skyscape chute (concept
supported by the Ampelmann, demonstrates to be
2). To prevent misalignment of the chute, a guidance
ALARP for sub arctic conditions: concept 4 meets
line in between the vessel and the suspension point
the lowest risks that are reasonably practicable in
of the chute is suggested (concept 3).
terms of costs.
Student:
J.M.L. Koch
Sponsor:
Shell E&P
Committee:
prof.ir. J. Meek, ir. G.H.G. Lagers, dr. ir. J. van der Tempel, ir. C. Brummelkamp
For more information please contact the department of Offshore Engineering: (31) 15 2781328
82
0307
Offshore Engineering
Fsru processes
The liquefaction and regasification terminals for
the ‘best value’ BOG management solution. The jet
natural gas are traditionally located onshore.
pump system does not require any compression of
With the increasing demand for natural gas, new
the BOG, which makes it attractive in view of the
locations could be located offshore for various
safety, environmental impact and operating costs.
reasons (e.g. safety, financial). One alternative of an
The main disadvantage is that the solution is not
onshore liquefied natural gas (LNG) import terminal
yet proven technology and that a pilot plant will be
is called a Floating Storage Regasification Unit
required to test and validate its capability to deal
(FSRU) and is a permanently moored offshore LNG
with BOG.
import terminal. Regasification systems
The two main activities on board an FSRU are
The vaporization of LNG requires a substantial
storage and vaporization of LNG. These activities
amount of heat that can be withdrawn from three
introduce the following challenges:
main sources (directly or indirectly): (i) Combustion;
Boil-off gas (BOG) has to be removed from the
(ii) Sea water; (iii) Air.
cargo storage tanks in order to avoid overpressure.
In the best value system natural draught ambient
Except for in emergency situations, the BOG should
air vaporizers (AAV) use air to vaporize LNG. They
not be wasted for environmental and commercial
can provide a large percentage of the required heat
reasons.
without power consumption. This aspect makes the AAV attractive in view of the safety, environmental impact and operating costs. AAV’s have been used before in small scale applications, but never in the quantities required on an FSRU or grouped together as on the deck of vessel. Some additional source of heat will be required to bring the NG up to the required sendout temperature. Conclusions & Recommendations
An FSRU has to
The preferred solution will depend on project
reliably vaporize
specific data. The study report presents an overview
LNG at a constant
of the feasible options and discusses the main
rate after it has
features, pros and cons for different scenarios. (See
been boosted to
chapter 2 for the overview.)
send-out pressure.
Each FSRU project should start with an identification
Boil-off gas handling systems
of possible alternatives in order to continue with a
Three different methods exist to handle the BOG
systematic comparison, in which the project specific
that is in excess of the fuel gas requirement: (i) Mix
data are taken into consideration to select the
the BOG with regasified send-out gas; (ii) Mix the
preferred solution(s).
BOG with subcooled LNG in order to dissolve the
The conclusions and recommendations of the study
gas into the liquid phase; (iii) Reliquefy the BOG
report can be used in the initial phase of FSRU
by cooling it down and send it back into the cargo
design development in order to aid the selection
tanks.
process for the preferred BOG management and
This study has identified the use of jet pumps as
vaporization systems.
Student:
R.C.J. Lagers
Sponsor:
SBM Inc
Committee:
prof.ir. J. Meek, prof.dr. J.A. Moulijn, dr.ir. S.A. Miedema, ir. K. Hoving, ir. M. Ubas
For more information please contact the department of Offshore Engineering: (31) 15 2781328
0307
Offshore Engineering
Structural analysis of impact on guides and bumpers
To provide for accurate positioning, during offshore
time domain solver LS-DYNA. The resulting contact-
lift-operations, generally use is being made of guides
model was then incorporated in the user-defined part
on the receiving support structure and bumpers on the
of LiFSiM and a comparison was made with the results
topsides that is being installed. During a certain stage
obtained with a contact-model constructed in the
of the lift process, in which initial contact between
conventional way. The LS-Dyna analyses learned that
topside and support structure takes place, impact
the impact velocity hardly has any influence on the
loads are a common phenomenon, which makes this
development of the impact force, only on the eventual
stage the most critical with respect to damage to both
maximum magnitude of the impact force; the higher
structures.
the velocity, the higher the maximum impact force will be. The results also showed that during an impact
Therefore an analysis has been performed in order
no velocity dependent viscous damping is present,
to asses the risk of possible impact loads and the
but only elastic-plastic damping through plastic
magnitude thereof. Normally this is done with a
deformation. Implementing both contact-models in a
multibody dynamics program (LiFSiM) which can
LiFSiM model resulted in simulations which revealed
accurately predict motions of a floating support
that the conventional contact model resulted in highly
structure and of a crane vessel with a deck hanging
unstable simulations, whereas the new contact-model
from its crane(s). The modeling of the contact stage
resulted in more stable simulations. However, both
between guides and bumpers during impact may
types of LiFSiM simulations required an extra velocity
be adequate to derive realistic motion behaviour
dependent viscous damping force in the contact
of the system but is considered inadequate for the
model, in order to be able to complete simulations
assessment of the magnitude of impact forces.
without them becoming numerically unstable.
Furthermore, modeling of the impact process itself is completely dependent on the choices made by the
As a result of uncertainties introduced when
responsible engineer. The linear single-spring model
considering damping as a part of both contact-
which is generally being used seems not sophisticated
models, two more LiFSiM simulations (2BODY), with
enough to fully describe the structural behaviour
and without damping, have been conducted. Now
of “guide & bumper” during impact. Refining this
a direct comparison could be made between the
(structural) model, describing the contact stage, is
performance of LiFSiM and LS-Dyna. This learned that
expected to be necessary to achieve more accurate
LiFSiM correctly calculates the impact forces when
predictions of the magnitude of impact loads.
no damping is applied and can underestimate the impact force and displacement when (for numerical reasons) extra damping is applied. Thus, at this point a relatively simple 2BODY impact analysis can be performed, but a more complex LiFSiM simulation can not yet be conducted. It can therefore be concluded that a new analysis method to calculate impact loads is not yet available. This research also showed that guides & bumpers designed on the basis of standard
Based on a finite element model of a typical guide and
guidelines appear to be very stiff and only utilize their
bumper design which was previously used by HMC
elastic capacity, which results in relatively high impact
on an offshore removal project, a different and more
loads. Less stiff guide design and allowing for plastic
accurate contact-stage model has been created. This
deformations can lead to lower impact loads and
was done by analysing the FEM model with the explicit
subsequently more cost efficient solutions.
Student:
P.J. Maas
Sponsor:
Heerema Marine Contractors
Committee:
prof.ir. J. Meek, ir. G.H.G. Lagers, ir. G. Hommel, ir. A.W. Vredeveldt, ir. R. Zoontjes
For more information please contact the department of Offshore Engineering: (31) 15 2781328
83
84
Offshore Engineering
0307
Basic design of hydrate mining equipment
The growing demand for oil and gas leads to an increase of exploration and exploitation as well as to research in alternative ways of hydrocarbon production out of natural resources. The predictions of huge amounts of gas hydrate dispersed in artic and ocean sediments make this a potential future energy source. Recent studies and experiments to retrieve gas from gas hydrates focussed on depressurization and/or thermal stimulation of the hydrate bearing sediments. The drawbacks of these methods are low reservoir permeability and dissociation of gas hydrates during production.
The proposed design of hydrate mining equipment
This causes production rates to stagnate and
is driven and controlled by a pressurized fluid. The
induces bore hole instability. A combination of
fluid is circulated through the mining equipment
excavation and pressurization during the production
by a pressure difference over the injection and
of hydrate bearing sediments is proposed to avoid
export means of the mining tool. The driving of
these problems. The generation, basic design and
the cutterarms is achieved by a set of Positive
challenges of gas hydrate mining equipment are
Displacement Motors (PDM), The PDM’s are driven
presented in this study.
by a pressure difference over their inflow and outflow channels. Pressure release valves control
The generation of hydrate mining concept designs
the production rate, and an actuation cylinder
has been executed by using a morphological
determines the position of the cutterarms.
matrix. The most promising concept design has been worked out in more detail. A computational
The simulation demonstrates the importance of
simulation and analysis of the selected concept
pressure release valves for maintaining a constant
design has been executed for various reservoir
production rate under irregular reservoir conditions.
conditions. Based on different production and
The energy balance showed a positive net
reservoir scenarios, energetic and economic
production of energy for each reservoir scenario and
analyses were executed to provide first insight in
production sequence. The economic balance showed
the feasibility of hydrate mining.
a negative net profit for all scenarios at the current gas price. The current day rate of a drill rig has
This concept design of a hydrate mining tool
major impact on the net profit. The net profit will
exists of two rotating cutterarms. The mining
become positive for a gas price that equals three
tool is lowered from an ordinary drill rig by a drill
times the current gas price. The layout and working
string until it hits the ocean floor. From there, it
method of this concept mining equipment creates
bores itself to the hydrate bearing sediment and
the possibility of mining other valuable minerals
production is started. Upon termination of the
from ocean sediments.
production, the mining tool is able to excavate itself out of the ocean floor from where it is lifted to the drill rig.
Student;
W.J. Overes
Sponsor:
Huisman-Itrec
Committee:
Prof.dr.ir. J. Meek, Prof.ir. W.J. Vlasblom, ir. G.H.G. Lagers, ir. J.J. De Ruiter, ir. R.F. Van Kuilenburg
For more information please contact the department of Offshore Engineering: (31) 15 2781328
0307
Offshore Engineering
The upgrade of “Noble to Van Langeveld” to 1500 m water depth capacity The drilling semi-submersible “Noble Ton van Langeveld” (NTvL) currently works in the UK sector of the North Sea. As future work is limited due to the shift towards deeper water, a study of the upgrade of the NTvL to deeper water to ensure work in the (near) future has been carried out. From the current main deepwater areas, West
The mooring design is based on the design loads
Africa and South East Asia are selected as the most
in both areas and is analysed using the mooring
promising locations to upgrade the NTvL for.
program Seamoor. The modifications to the mooring
The environmental loads in both areas (West Africa
system currently installed are minimized, resulting in
and South East Asia) are formulated, resulting
an additional 200 m of anchor chain to be added to
in a set of design loads, which the NTvL should
each winch. This adds up to a total of 280 tons. The
be capable of withstanding. The environmental
design mooring system for each winch consists of a
conditions in West Africa are benign, compared to
chain-wire-chain connection as follows :
South East Asia. In South East Asia tropical storms
• 1280 m bottom chain length
(typhoons) are present. These occur throughout
• 2020 m wire insert length
most of the year and impose especially large wind
• 200 m top chain length
loads on the platform. In case of a typhoon the rig
• The chain-wire-chain connection is subject to a
is abandoned as safe work is not possible anymore.
top tension of 150 tons.
The environmental loads are divided into wind, wave
On the NTvL, the Noble Drilling aluminum alloy
drift and current loads. The wave drift loads are
riser (AAR) will be used. This greatly reduces the
composed of potential wave drift loads and viscous
suspended weight of the riser. Therefore, only minor
wave drift loads. The potential wave drift loads
modifications to the riser tensioner system are
are computed using DELFRAC. The viscous wave
required. The required number of riser tensioners
drift loads are computed using the model created
can be reduced by installing more buoyancy on the
by A.K. Dev in his PhD-thesis and are caused by
riser.
the presence of a wake behind a cylinder in a flow.
The riser motions result from the mooring system
Viscous wave
characteristics and the environmental conditions as
drift loads
well as the wave and current loads on the riser. The
are found by
resulting bending and tensile stresses in the riser do
integrating
not exceed the yield stress of the aluminum.
the drag
In conclusion, the upgrade of the NTvL to West
component of
Africa and SE Asia conditions is well possible with
the Morison
relatively minor modifications to the mooring and
equation over
riser systems.
the structure height and averaging this over one wave period.
Student:
A. Smit
Sponsor:
Noble Drilling
Committee:
prof.dr.ir. J.A. Pinkster, dr.ir. S.A. Miedema, ir. G.H.G. Lagers, dr.sc. A. Metrikine, G.J. Windhorst
For more information please contact the department of Offshore Engineering: (31) 15 2781328
85
86
Offshore Engineering
0307
Structural optimization of monopile foundations for offshore windturbines handled by integrated analysis Wind energy is a clean renewable source of
In the design process for monopile foundations
energy and currently undergoing major growth in
for the Kentish Flats wind park Rambøll made the
application. Although the vast majority of newly
decision to deviate from the approach of using
installed wind farms are still onshore, offshore wind
standardised foundation structures throughout
energy has the advantage of greater average wind
the wind farm. Using advanced analyses, detailed
speeds and lacks the nuisance problems associated
data and individually designed monopiles resulted
with implementation of wind energy nearby people’s
in a significant weight and cost reduction for the
homes. The higher cost of offshore wind energy
foundation structures. Ever increasing size of wind
is the major barrier for larger implementation;
farms increases potential gains from individualised
increased cost of the foundation structure of
design, but the manual work involved rises as
offshore wind turbines is the main reason for the
well. Development of automated tools will thus
higher investment cost. Consequently lowering
be necessary. The development of an automated
these costs has a high priority to increase the
optimization procedure for this purpose has been
competitiveness of offshore wind energy.
the subject of this thesis.
Student:
R. Swinkels
Sponsor:
Rambøll Denmark
Committee:
Prof.ir. Meek, dr.ir. J. van der Tempel, ir. G.H.G. Lagers, dr. A. Romeijn, Henrik Carstens (Rambøll)
For more information please contact the department of Offshore Engineering: (31) 15 2781328
0307
Offshore Engineering
A probabilistic approach to jack-up leg penetration in stratified soils When jack-up platforms are installed at their
Predicting the leg penetration and punch-through
temporary site of operation, geotechnical engineers
risk is complicated due to three areas of uncertainty.
gather soil samples in order to determine the soil
They are the spatial variability in both vertical
property values. If the soil property values indicate
and horizontal direction as well as the uncertainty
a soil profile with sufficient bearing capacity,
incorporated in the models used to predict the soil
preloading of the jack-up can start by filling the hull
bearing capacity. The models consider three main
compartments with seawater. The preload forces
failure mechanisms. They are general shear of both
the leg footings, or spudcans as they are called,
sand and clay, squeezing of clay and punch-through
to penetrate the soil to a depth where adequate
of both sand-over-clay as clay-over-clay soil profiles.
bearing capacity is encountered. It is the preloading
By using probabilistic methods, the spatial variability
phase in which a hazard known as punch-through
as the model uncertainties can be taken into
is present. If the soil profile consists of a strong
account. Due to the non-linear behaviour of soils,
layer overlying a weaker layer (e.g. sand on clay),
the probabilistic method of Monte Carlo simulation
a spudcan can punch through the strong layer and
has been used to predict the probability of punch-
plunge into the weaker layer before the intended
through failure.
preload is reached. This may lead to damage to the legs and/or platform.
Although this study provides an effective probabilistic tool for the geotechnical assessment of jack-up platforms, one of the conclusions was that the models used in the prediction of the bearing capacity of stratified soils, should be improved if possible.
Student:
T. van der Wal
Sponsor:
Fugro
Committee:
prof.ir. A.C.W.M. Vrouwenvelder, dr.ir. S. van Baars, ir. G.H.G. Lagers, ir. J. Peuchen, ir. D. Bouwmeester
For more information please contact the department of Offshore Engineering: (31) 15 2781328
87
88
Last year’s Theses
0307
0307
Last year’s Theses
Last year’s Theses
89
90
Last year’s Theses
0307
Master’s Theses October 2006 Civil Engineering Theses
Predicting time dependent reinforcement corrosion due to chloride ingress
Structural Engineering
Student: I. Mele
Amsterdam ArenA Ontwerp en constructieve uitwerking veld ophangen aan dakconstructie. Student: J.M.G. Huijbregts
Building Engineering
Deuvelwerking van randbalken als onderdeel van vloeren in prefabbouw
Non-linear FEM modelling of steel fibre reinforced
Student: E.A. Pieterse
concrete for the analysis of tunnel segments in the thrust jack phase
CO2 emissie modelering van de gebouwschil
Student: R.A. Burgers
Student: H. Staal
Drijvende achterlandverbinding in zeer hoge sterkte
Lightweight cold rolled steel construction systems
beton
Student: C. van Zandwijk
Student: E.D. Pinas Bouworganisatievormen voor infrastructuur Zettingsgedrag van blokkenmuren bij een variabele
projecten voor gemeente Den Haag
grindlaag
Student: H.J. de Graaf
Student: P.J.H. Renders Ontwikkeling Life Cycle Management Model voor Comparison between the VBC/VBB and the Euro
Kademuurconstructies
code Design of incremental launching Box Girder
Student: G.H.S. Weisz
Bridge using high strength of concrete Student: K. Sinnadurai
Energie uit afvalwater Student: J.D. Spronk
Onderzoek naar autogene vervorming van cementpasta en beton.
De samenwerking tussen uitvinder en ondernemer
Student: G.A. Leegwater
bij technologische Start Ups met een patent Student: O.J. Meijer
Sea Ice – Offshore Structure Interaction: Steady State Downward Bending
Adaptieve Temperatuurgrenswaarden
Student: P. van der Male
Student: M. van Beek
Ground vibrations induced by a high-speed train
Hydraulic & Geo Engineering
running over inhomogeneous subsoil
Abstract
Student: K.N. van Dalen
Student: T.M. Caus
Gedrag Staal-beton kokerliggerbrug met
Comparative analysis of design recommendations for
geprofileerde lijven
quay walls
Student: A. El Hadji
Student: E.Meijer
Ontwikkeling van een methode om het mechanische
Summary
gedrag van ASR gels te meten.
Student: E.A. van Blaaderen
Student: P.C. Crucq Wave characteristics derived from video Effects of nano-clay modification on rheology of
Student: C. Bos
bitumen and performance of asphalt mixes Student: D.B. Ghile
Influence of foreshore steepness on wave velocity
0307
Last year’s Theses
and acceleration at the breakwater interface
MeteoLook – a physically based regional distribution
Student: N.J.Oortman
model for measured meteorological variables Student: M.P. Voogt
Surfability of an ASR in irregular waves Student: R.W.J. Over
Flood Control? An Evaluation of the Impacts of Flood Control and Drainage Projects in Bangladesh
Morphodynamic modeling of a schematic barrier
Student: M.L. Drost
island Student: B. de Sonneville
Nalevingsmetingen in het waterbeheer Een casestudy naar de Wet beheer
Het effect van erosie en grondeigenschappen op het
rijkswaterstaatswerken
dynamische gedrag van offshore windturbines
Student: M. Hofstra
Betreffende stalen en betonnen mono paal funderingen
Risicoanalyse binnen het regionale waterbeheer
Student: J. Van Ginhoven
Student: G.F. Verhoeven
Cost-Estimating of Heineken Breweries Worldwide
“Vasthouden, bergen, afvoeren” onder de loep;
A Probabilistic Framework
Onderzoek van de effectiviteit van maatregelen
Student: M. Groeneveld
tegen wateroverlast door neerslag, toegepast op polder Eijerland
Uretek Deep Injection Method. Lifting of settled
Student: G.J. Zegwaard
foundations Analysis of full scale test results Student: R. van Reenen
UV/H2O2 behandeling bij drinkwaterbereiding: Onderzoek en ontwerp
Verticaal evenwicht van damwandconstructies
Student: D. de Ridder
Student: M. de Koning Treatment Techniques for Combined Sewer a,b,c- Isotachenmodel (van a,b,c tot zetting)
Overflows
Student: D. Sipkema
Student: S.M. Scherrenberg
Masterplan for the Port of Azzawiya, Libya
New process of drinking water production in 21st
Student: P.J.J. Groenewegen
century Student: S. Li
“De In- en Uitbreiding van het Haven- en Industriegebied Moerdijk”
Sediment Resuspension Effect on Water Quality in
Student: D.B. de Bondt
Drinking Water Distribution System Student: Q. Wang
Samenvatting Student: E. van der Maaten
Transport & Planning
Rijgedrag bij werkzaamheden Zicht op versmalde Watermanagement
‘Measurability of hydrological processes by means of
stroken vanuit de helikopter Student: R.J. ter Kuile
gravimetrical measurements’ Student: J.E.J. de Goffau
Systematische herinrichting van zwarte punten in Vlaanderen Een beslisboom en een kosten-
Predicting Ulva growth in a saline Volkerak-
batenanalyse
Zoomlake
Student: M. van ‘t Hof
Student: R.P. Hulsbergen
91
92
Last year’s Theses
0307
Paramaribo op orde; Structuurvisie Groot-
Screening of Reservoir Characteristics for the
Paramaribo 2020
Applicability of Smart Field Technology to Dynamic
Student: Y. Blufpand
Water Flood Optimisation Student: A. Altintas
Werken aan vitale wijken Student: E. Martens
Fluid front detection from time-lapse pressure propagation test
Applied Earth Sciences Theses
Student: R. Formoso-Rafferty Castilla
Resource Engineering
Feasibility Study of WAG Injection in Naturally
Experimental study on the vitrification of bottom
Fractured Reservoirs
ash from municipal waste incinrators
Student: J. Heeremans
Student: M. Oorsprong Trapping Sequence Determination in Deep-bed Prediction of ore mixture grinding behavior
Filtration using Colored Particles during Produced
Student: A. Scheltema Beduin
Water Reinjection Student: B. Turekhanov
An Experimental study on the thermal behavior of heavy metals and minor elements in fly ash from a
Engineering Geology
municipal solid waste incinerator
Massive Flank Collapse at La Palma Numerical slope
Student: N.R. Wilson
stability models of the Cumbre Vieja Volcano Student: J.M.C. van Berlo
Petroleum Engineering and Geosciences
Analysis of Geochemical data from Wells and
The accuracy of the interpretation of CPT-based soil
Outcrops, in the Permian Tanqua subbasin fan
classification methods for soft soils.
complex, southwestern Karoo, South Africa
Student: J. Mollé
Student: R. van den Brink Swelling and shrinkage characteristics of soils in Turbidite Slope Channel deposits, a Reservoir
the northern Netherlands and Restrained clay ring
Simulation Study based on Field Data
shrinkage
Student: R. van den Ham
Student: M. Zandbergen
The use of modern analogues in shared earth
Offshore Engineering Theses
modeling (Case study of the Cook Formation,
Motion compensated float-over installation with the
Oseberg Field, offshore Norway)
use of the Ampelmann
Student R. Thomassen
Student: F.W.B. Gerner
Analysis of Salt-Induced Stress Anomalies
Simulation of ship motions and probalistic design of
Student: A. Vogelaar
Ampelmann platforms Student: A.J. Göbel
Temperature Dependent Sorption of Carbon dioxide on coal
Safety and Reliability of Partly Jacked Vessels
Student: R.M.S. van Lier
Student: P.A. van der Graaf
Effect of sorption induced swelling on coal cleat
Calibration of SQM model tests
permeability
Student: N.P. Haakman
Student: I.J.P. Moors
0307
Last year’s Theses
Cryogenic Floating Hoses for Liquefied Natural Gas
Lifespan enlargement of deck plates of movable
Transfer
steel bridges
Student: T. Klieverik
Student: M.C. Schrieks
Numerical approach for predicting heave motion
Technische haalbaarheidsstudie van een ultra-hoge-
coefficients for a Tophat Design
sterkte betonnen boogbrug
Student: A. de Leeuw
Student: J. den Hollander
Ships going semi?
Connections Pile with Upper Structure for Concrete
Student: D.A. Manschot
Jetty Numerical analysis and design proposal
Environmental Load Calculations on Space Frame
Student: W. Xia
Support Structures for Offshore Wind Turbines Student: A.H. van der Pol
Flexvloer – Onderzoek naar de constructieve aspecten van een nieuw vloersysteem
Deep water riser concepts offshore Angola
Student: H.G. Burggraaf
Student: S. van der Puttem On Isogeometric Analysis for Crack Modelling LNG export and shipping in Arctic seas – a new way
Student: W.M. Swolfs
of LNG shipping in Arctic seas Student: Y. Shu
A Very Large Floating Container Terminal Student: G.V.P. de Rooij
Operability of a floating LNG Terminal Development of a new approach and berthing
Laser welded steel bridge decks
concept for an exposed location
Student: H. Stam
Student: J. Wolff Haalbaarheidsonderzoek vervanging verslechterde Implementing a frequency domain approach for the
houten brugdekken door middel van VVK
fatigue analysis of offshore wind turbine support
Brugdekken
structures
Student: D. Leliveld
Student: W.E. de Vries Design of an integral bridge by FE modelling Master’s Theses June 2006
Student: J.E. Göttgens
Civil Engineering Theses
Larch Round Wood and its applications Student: R. Schuch
Structural engineering
Possible use of C-Fix in Porous Asphalt
Adaptive Anticlastic Membrane Structures
Student: R.N. Khedoe
Prestressed by Edge Cables and Actuators Student: P.C. Oltheten
Spoorvernieuwing in de London Underground Student: A.M.P. van Rossum
Building Engineering
Gekromde Hoogbouw Damping of vibrations in slender tubes of arch bridges Student: R. Gerbranda
Student: M. Wiersma
93
94
Last year’s Theses
0307
Optimizing future risk management at Fluor based
Vetiver grass as bank protection against vessel-
on historical project data
induced loads
Background
Student: D.J. Jaspers Focks
Student: F.C.P. van Roij Design of granular near-bed structures in waves and Verhoging van de haalbaarheid van
currents
weginfrastructurele projecten door toepassing van
Student: J. van den Bos
een publiek privaat samenwerkingsmodel Student: R.M. Schunck
Run-up Reduction through Vetiver grass
Shaping the Virtual Wind Tunnel
Student: A. Algera
Student: D.P.Snijders Equilibrium and stability of a double inlet system Construction of Prefab Concrete Shells
Student: R. Brouwer
Student: M. van Roosbroeck Siltation of Incheon Terminal basin and the Kinetic Space Frames
Approach Channel
Student: P.A. van de Rotten
Student: J.J.M. van der Lans Uncertainty in the application of Bay Shape
Hydraulic & Geo Engineering
Smoothed Particle Hydrodynamics Student: L. de Wit
Equations
Student: R. Lausman
Feasibility of IGW technology in offloading hoses
Verbetering Zeetoegang IJmuiden: Systeem met
Student: S. Nooij
keersluis, open tijdens laagwater Student: N. van der Zwan
“3D numerical simulation of a harbour flow, applied to Waalhaven, Port of Rotterdam”.
Stormvloedkering in de Westerschelde
Student: H.H.Schonewille
Student: J.M. van der Meer
Estimating Freak Wave Occurrence Probability in the
Door grond horizontaal belaste palen
Agulhas Current
Student: Is. Cherqaoui
Student: A.J. Lansen Capacity study for the port of Buenos Aires, Influence of a secondary channel on bed
Argentina
morphology and sediment distribution at a river
Student: R. Smits
bifurcation Student: J.J. de Nooijer
Dynamic Response of a Transatlantic Tunnel to a Hypersonic Train
Smart Nourishment of the Frisian Inlet
Student: W. Verdouw
Student: T.M. Kluyver Watermanagement
Sand Balance “Loswal Noord” - The Net Contribution
Studie naar de bandbreedte van een Q(h)-relatie bij
of “Loswal Noord” to the Sand Budget of the Dutch
de koppeling tussen SOBEK en SIMGRO
Coastal Foundation
Student: J. Hornschuh
Student: M. Slee The influence of compartmentalisation on flooding Geomatrically open filters in breakwaters
in Central Holland
Student: E.F. Uelman
Student: E.P. de Bruine
0307
Last year’s Theses
Offshore Engineering Theses
Suitability of natural tracers for determination of
Concrete LNG FPSO
runoff generation
Student: K. Loijen
A study in the Maisbich catchment (Luxembourg) Student: M. Jasperse
Availability of a weathervaning LNG import import terminal
Land Subsidence and Water Management in
Student: A. van der Pijl
Shanghai A study into the reason, prevention methods and
Extension of pipelay capacity on Allseas’ Solitaire by
future development of land subsidence in Shanghai.
S-lift implementation
Student: Q. Wei
Student: M.Dikkers
Hergebruik van Afvalwater: Duurzame bron of
Master’s Theses March 2006
onnodig risico? Student: L. Meijer
Samenvattingen Civiele Techniek
Substandard Supply Minutes in relation to risk
Structural Engineering
management for water supply
Voorontwerp en dynamische analyse van een
Student: S.C.Alberga
hardhouten tuibrug voor langzaam verkeer Student: J.J.M. van der Asdonk
Development of Indirect Potable Reuse in impacted areas of the United States
BOUW - Software voor bepaling tuikabel-
Student: H.P. Jansen
voorspankrachten Student: P.A. Brongers
Transport & planning
Netwerkconcepten in Ruimtelijke Planning
Bouw - Voorgespannen Spoorbrug in Hogere Sterkte
Student: M.C. van Breukelen
Beton Student: H.J. de Bruijn
Machine Learning en het voorspellen van de individuele schadekans
Experimenteel onderzoek naar de RCM-methode
Student: C.P.J. van Hinsbergen
Student: S.M. van Dalen
Openbaar Vervoer Paramaribo:
Phenomenological Modelling of Vortex-Induced
Een netwerk en lijnennet ontwerp
Vibrations of Deep-Water Risers
Student: S. Ferrier
Student: W. Hoogkamer
Verkeerscirculatieplan voor Hoek van Holland op
BOUW - Minimum wapening in gewapend betonnen
drukke stranddagen.
platen
Student: A. Meurs
Student: J. Keijnemans
Verkenning naar de toepasbaarheid van
Bouw - IJmeerverbinding
microsimulatie bij beslissingsondersteuning
Student: R.L.J. Maes
Student: J.R. de Vos Joint behaviour in microtunnelling processes Applied Earth Sciences Theses
Student: Mohammed Abdelkarim Taher
This publication there were no Applied Earth Sciences theses available
Innovation of stress and damage reduction in bored tunnels during construction, based on a shield equilibrium model Student: Q.C. de Rijke
95
96
Last year’s Theses
Discontinuous Galerkin methods for elastoplasticity Student: D. Romagosa Sanchez-Monge
0307
Hydraulic & Geo Engineering
Large-scale coherent structures in turbulent shallow flows
Building Engineering
Student: W. van Balen
Hoogbouw op ‘Stapeldok’ Student: M. Bahri
The evaluation of piping at existing flood defence constructions
De “Rotonde”
Student: A.J. Boer
Student: J.M. Brouns Erosion resistance of a grass top layer against wave Waardevol verleden...
overtopping
Student: R. M. Burer
Student: W. van den Bos
Koelkast of broeikas?
Klimaatverandering en Binnenvaart
Student: M.D. van Donselaar
Student: C.G. Bosschieter
Deployable Structures based on Mechanisms in
Admittance policy tidal bound ships
Nature
Student: R. Bouw
Student: W.L. Dumans Side channels to improve navigability on the river Constructief ontwerp van het nieuwe stadhuis van
Waal
Gouda
Student: C.A.J. van Dam
Student: T.E. de Graaff Design of a cooling water outfall system Constructief glazen element
Student: V.N. van Dijk
Student: J.F. van Heusden Nourishment Behaviour Delray Beach Constructief Ontwerp ‘VandenEnde Musicaltheater’
Student: W.M. Hartog
Student: S.T. Kiefte Probabilistic analysis of typhoon induced hydraulic “Bridge to China”
boundary conditions for Suo-nada Bay, Japan
Student: K.T. Lee
Student: E.N. Klaver
Lightness in glass constructions
Compensation Grouting Experiments in Sand
Student: J. Luttmer
Student: R.M. Kleinlugtenbelt
De Haagsche Zwaan
Humplike nourishing of the shoreface
Student: G.J. Roos
Student: L. Koster
Een snel wegneembare overkapping van tentdoek
The Irrigation System as an Open System; Proyecto
Student: N. Roovers
Rio Dulce and the Rio Dulce Basin Student: C.N. Lieveld
Techniek in Mijnbouwkunde Student: R. Sanders
Jetgrouten Student: R.M. Loeffen Theoretical and Experimental study on the placement of Xbloc Student: E. ten Oever
0307
Itapocú Inlet, Brazil Student: L.M. Perk
Last year’s Theses
Transport & Planning
Functionele eisen voor beweegbare bruggen Student: C. Hofma
Planning and technical feasibility study deepwater port ‘Zona Portuaria Simon Bolivar’, Venezuela
Financieel-economische haalbaarheid van
Student: S. van Poeteren
ontwikkeling van meervoudig ruimtegebruik bij railinfrastructuur in stedelijk gebied
Transverse slope effects on widely graded sediment
Student: M. Kokshoorn
Student: P.E.M. Schoonen Woonmilieus aan de Zuiderzeelijn Drifting Sea Ice
Student: H.N. Vuong
Student: T.J. Segboer Optimal utilization of capacity A probabilistic flood risk assessment and the impact
Student: H.J.J. Wieringa
of compartmentation Student: R.P.G.J. Theunissen Watermanagement
Applied Earth Sciences Theses Resource Engineering
Saturation in the New York City Watershed
Development of a CFD model for a phosphorus
Student: M.A. Borst
producing submerged arc furnace Student: A.T. Adema
Voorwaarden buitendijkse bebouwing langs rivieren Student: L.A.C. van Genugten
The effects of surfactants on the efficiency of solution gas drive
Hydrological modelling for a micro hydro-power dam
Student: Ali Barati
in the Panato creek, Suriname Student: T. Lieuw
An emf cell to measure thermodynamic properties of the magnesium – salt flux – impurity system
Application of a semi-distributed hydrological model
Student: M. Goense
based on the REW approach to the Collie River Basin, Western Australia
Modelling of Recycling Systems - Applied to Car
Student: E. Tromp
Recycling Student: G.J. de Haan
Model Predictive Control on Irrigation Canals; application of various internal models
Dynamic Interaction between Slag and Coke in the
Student: R.M.J. Wagemaker
Blast Furnace Student: A. Hoogervorst
”De provincie Zuid-Holland zit er warmpjes bij” Student: B.G. van de Weerdhof
The prediction of dross formation and the containment of dross on an Industrial
Use of culverts in dikes in the floodplain
Aluminium Recycling Plant
Student: T. Wilms
Student: V.A. de Roode
Estimating the influence of on-farm Conservation
Petroleum Engineering and Geosciences
Practices on the Water Balance,
Deposition of Colored Tracer Latex Particles in
Case of the Mzinyathini Catchment in Zimbabwe
Sandstone
Student: L. Woltering
Student: H. Bennaceur
97
98
Last year’s Theses
Sensitivity Study of Fracture Properties, Related to the Production of Hydrocarbons Student: M.W.N. van Galen Engineering Geology
Numerical modelling of rock mass decay in road cuts 88 Student: W. Tegtmeier Offshore Engineering Theses
An analytical, numerical and experimental approach of parametric roll of a tophat in irregular seas Student: F.W. Blaauw Standardised wave data bases on power level Student: M.F. Burger Deep water buoys – review study Student: C.R.E. de Groot Pipeline rotation during installation of inline structures Student: J. Mulder Development of a compliant cone for solid tubular expansion Student: R. Schoon Shell
0307
0307
Last year’s Theses
Research groups and professors within the faculty of Civil Engineering and Geosciences
99
100
0307
Last year’s Theses
Specialisation
Name
Telephone015-27...
Design and Construction Construction Mechanics Research Group
Construction mechanics
vacancy
Dynamics
Prof. A.C.W.M. Vrouwenvelder
Numerical mechanics
vacancy
84782
Materials Science and Sustainable Construction Research Group
Acting chairman
Prof. K. van Breugel
Fund. and Applied Materials Science
vacancy
84954
Road and Rail Construction Research Group
Road Construction
Prof. A.A.A. Molenaar
84812
Rail Construction
Prof. C. Esveld
87122
Building and Civil Engineering Structures Research Group
General Construction Design
Prof. L.A.G. Wagemans
84752
Concrete structures
Prof. J.C. Walraven
85452
Concrete modelling & materials
Prof. K. van Breugel
84954
Building physics and installations
Prof. J.J.M. Cauberg
83387
Timber structures
vacancy
Steel structures
Prof. J. Wardenier
82315
Steel structures
Prof. F.S.K. Bijlaard
84581
Steel construction of buildings
Prof. J.W.B. Stark
82303
Building Technology
vacancy
Utility buildings
Prof. J.N.J.A. Vamberský
85488
Methodical Design
Prof. H.A.J. de Ridder
84921
Building Informatics
vacancy
Product Design Research Group
Hydraulic Engineering Fluid Mechanics Research Group
Fluid Mechanics
Prof. G.S. Stelling
Environmental hydro informatics
Prof. A.E. Mynett
General Fluid Mechanics
Prof. J.A. Battjes
85426 85060
Hydraulic and Offshore Engineering Research Group
Probabilistic design and Hydraulic Structures
Prof. J.K. Vrijling
85278
Coastal Engineering
Prof. M.J.F. Stive
84285
Ports and Inland Waterways
Prof. H. Ligteringen
84285
River morphology & River Engineering
Prof. H.J. de Vriend
81541
Offshore Engineering
Prof. J. Meek
84777
0307
Specialisation
101
Last year’s Theses
Name
Telephone015-27...
Water Management Sanitary Engineering Research Group
Sewerage
Prof. F.H.L.R. Clemens
85227
Waste Water treatment
Prof. J.H.J.M. van der Graaf
81615
Drinking Water
Prof. J.C. van Dijk
85227
Water Resources Research Group
Hydrology
Prof. H.H.G. Savenije
81433
Water Resources
Prof. N.C. van de Giesen
87180
Geohydrology
Prof. Th. N. Olsthoorn
87346
Transport Planning
Prof. P.H.L. Bovy
84611
Traffic and Transport Management
Prof. H.J. van Zuylen
82761
Traffic and Transport Facilities
Prof. I.A. Hansen
85279
Infrastructure Planning
Prof. F.M. Sanders
81780
Transport & Planning
Applied Earth Sciences
Applied Geology Research Group General Geology
Prof. S.B. Kroonenberg
86025
Prof. S.M. Luthi
86019
Oil- and Gas production systems
Prof. P.K. Currie
86033
Reservoir Engineering
vacancy
Production Geology Resource Engineering Research Group
Petroleum Engineering Research Group
Applied Geophysics and Petrophysics
Geophysical Imaging Methods
Prof. W.A. Mulder
83666
Integrated Time-Lapse Methods
Prof. R.J. Arts
85190
Technical Geophysics
Prof. C.P.A. Wapenaar
82848
Geo Engineering Research Group
Soil mechanics
Prof. F. Molenkamp
85280
Groundwater mechanics
Prof. F.B.J. Barends
85423
Foundation Engineering
Prof. A.F. van Tol
85478
Underground Space Technology
Prof. J.W. Bosch
82844
Geo environmental engineering
vacancy
102
Last year’s Theses
Ontwerp en Lay-out:
MultiMedia Services TU Delft Druk:
Sieca Repro bv, Delft © 2006
0307