LAPORAN AKHIR PROGRAM IPTEKS BAGI MASYARAKAT (IbM)
Judul: IbM Kelompok Calon Penguna dan Calon Pengelola Listrik PLTM
Dibiayai oleh Direktorat Jendral Pendidikan Tinggi, Kementrian Pendidikan dan Kebudayaan, sesuai dengan Surat Perjanjian Pelaksanaan Penugasan Program Pengabdian kepada Masyarakat Nomor : 018/SP2H/KPM/DIT.LITABMAS/III/2012 Tanggal 06 Maret 2012
Ketua
:
Anggota
:
Rini Nur Hasanah, ST, MSc., Ph.D NIDN 0022016804 Ir. Teguh Utomo, MT NIDN 0013096510
Lembaga Penelitian dan Pengabdian Kepada Masyarakat Universitas Brawijaya Malang 2012
IbM Kelompok Calon Penguna dan Calon Pengelola Listrik PLTM Oleh : Rini Nur Hasanah1) dan Teguh Utomo2) Lembaga Penelitian dan Pengabdian Kepada Masyarakat Universitas Brawijaya Jln. Veteran Malang; Telp. 0341-584394; e-mail:
[email protected]
ABSTRAK PLTM Kincir Air Bendosari dengan kapasitas terpasang sebesar ± 5 kVA berada di aliran sungai Sewu, Dusun Tretes, Desa Bendosari, Kecamatan Pujon, Kabupaten Malang. Sebelum kegiatan ini dilakukan maka permasalahan utama yang terjadi adalah belum termanfaatkannya energi listrik mikrohidro yang telah dihasilkan rumah pembangkit oleh para calon pemakai/pengguna listrik mikrohidro di Dusun Tretes oleh karena belum adanya sambungan rumah (SR) di rumah calon pemakai/pengguna listrik mikrohidro tersebut. Permasalahan tersebut harus segera dicarikan solusinya mengingat keterbatasan dana yang dimiliki oleh penduduk/warga untuk mengadakan sambungan rumah pada masing-masing rumah calon pemakai/pengguna listrik mikrohidro. Secara teknis, listrik yang dihasilkan dari pembangkit mikrohidro kincir air ini cukup bagus karena pada sisi pembangkitan tegangannya bisa lebih dari 220 volt. Apabila hanya diberi beban lampu penerangan saja maka tegangannya akan sangat stabil (hasil ini didapat saat pengujian jalan/running test mikrohidro, 2010). Dengan melihat rendahnya angka ratio elektrifikasi desa Bendosari (63,28%) maka sudah pasti pembangunan PLTM Bendosari akan membawa banyak mamanfaat pada desa tersebut serta mampu mendekatkan perguruan tinggi dengan segenap stake holder serta masyarakat. Karenanya, tujuan dari kegiatan yang dilaksanakan ini adalah memaksimalkan peran PLTM agar keberadaannya dapat segera dirasakan oleh masyarakat calon pemakai/pengguna listrik mikrohidro (PLTM) dengan melibatkan peran serta masyarakat secara aktif (active participant). Beberapa tolok ukur keberhasilan, baik pada saat kegiatan persiapan, pelaksanaan maupun pemantauan/monitoring dilaksanakan antara lain dapat dikemukakan sebagai berikut: (1). Telah dilaksanakannya pembangunan sambungan rumah penduduk di lokasi mitra kerja (dusun Tretes, desa Bendosari, kec. Pujon, kab. Malang) untuk 19 pelanggan listrik mikrohidro/KK (2). Telah dilaksanakannya kegiatan sosialisasi dan diseminasi SOP (Standart Operational and Procedure) PLTM kepada para pengelola/operator maupun calon pengguna/pemakai listrik PLTM. (3). Telah dilaksanakannya kegiatan sosialisasi dan diseminasi instalasi listrik rumah tangga kepada para pengelola/operator maupun calon pengguna/pemakai listrik PLTM. (4). Tingginya respon pengelola/operator serta aparat desa terhadap kegiatankegiatan pembangunan sambungan rumah penduduk di lokasi mitra kerja. Kata kunci : Mikrohidro, jaringan tegangan rendah (JTR), sambungan rumah
______________________________________________________ 1&2)Dosen
Jurusan Teknik Elektro Fakultas Teknik Universitas Brawijaya -Malang
Implementation of Science and Technology for Society (IbM) Program on the Prospective Users and Management Groups of PLTM Bendosari Microhydro Power Plant by: Rini Nur Hasanah1) and Teguh Utomo2) Lembaga Penelitian dan Pengabdian Kepada Masyarakat Universitas Brawijaya Jln. Veteran Malang; Telp. 0341-584394; e-mail:
[email protected]
ABSTRACT The PLTM Bendosari microhydro power plant (MHP) is located in the Tretes village of the Bendosari region in the Pujon sub-district of the Malang regency. This MHP is functioning using a waterwheel installed across the Sewu river and generating power of about ± 5 kVA. Prior to the implementation of this program, the generated power had not been utilized by the inhabitants of the Tretes village because of the absence of the network connection from the plant to the users’ location. The network installation had also been difficult to acquire because of the limited funds owned by the villagers. One of the purposes of this program was aimed to solve this problem. From the technical point of view, the quality of the generated voltage is good, which could achieve the value higher than 220 volt. This quality level is sufficient as most of the load is for lighting purpose. Considering the electrification ratio of the Bendosari region which was still rather low (63,28%), the existence of the MHP would surely bring much benefit to the inhabitants and could strengthen the link between the university and its all stakeholders as well as the society in general. Consequently, the purpose of this program is to maximize the benefit of the MHP for its prospective users through the active participation of the community. Some succes indicators of this program, starting from the preparatory stage, the main activities, and up to the monitoring stage, are the accomplishments of: (1). Network connection installation from the plant to the users’ location, i.e. 19 inhabitants’ homes location, (2). Training activity and dissemination of the SOP (Standart Operating Procedure) for the prospective users and manager/operators of the MHP, (3). Home installation techniques training for the prospective users and manager/operators of the MHP, (4). High-level of response given by the MHP manager/operators and village officials along the execution of the program. Keywords: microhydro, low-voltage network, home installation
________________________________________________________ 1&2)Staffs
Malang
of the Electrical Engineering Department, Faculty of Engineering, Brawijaya University -
DAFTAR PUSTAKA Anonim, 2002, “Dengan Penggunaan yang Benar Listrik Adalah Sahabat”, Sosialisasi Undang-undang Republik Indonesia Nomor 20 Tahun 2002 Tentang Ketenagalistrikan, Kerjasama Dinas Energi Propinsi Jawa Timur dengan Direktorat Jendral Listrik dan Pengembangan Energi, Surabaya, 26 Oktober 2002. Anonim, 2003, Undang-undang Republik Indonesia Nomor 20 Tahun 2002 Tentang Ketenagalistrikan, Jakarta Anonim, 2008, Small Hydropower: A Textbook Specially Designed for Training Workshop in TCTD Program, Hangzhou Regional Center for Small Hydropower, China Anonim, 2009, “Hasil Survai Operasi dan Pemeliharaan PLTM Check Dam V Kalijari Kabupaten Malang”, Malang, Fakultas Teknik Universitas Brawijaya. Dandekar M.M., Sharma K.N., 1991, “Pembangkit Listrik Tenaga Air”, Jakarta, Penerbit Universitas Indonesia (UI Press). Dinas Energi dan Sumber daya Mineral, Kabupaten Malang, 2006, “Studi Kelayakan Pembangunan PLTMH di Kabupaten Malang”, BPP FT UB Dinas Energi dan Sumber daya Mineral, Kabupaten Malang, 2006, “Pembuatan DED PLTMH Kali Sukun di Kabupaten Malang”, BPP FT UB Harvey A., 2006, Micro-Hydro Design Manual: A Guide to Small-Scale Water Power Schemes, ITDG Publishing, UK Kadir A., 1996, Pembangkit Tenaga Listrik, Jakarta, Universitas Indonesia Mismail B., 1991, “PLTM Sebagai Sarana Pelistrikan Desa”, Pidato Ilmiah Dalam Rangka Dies Natalis Unibraw, Malang, Universitas Brawijaya. Mismail B., 1991, Pelistrikan Desa di Indonesia, Pusat Antar Universitas, UI, Jakarta Pabla A.S., 1995, Sistem Distribusi Daya Listrik. Erlangga. Jakarta Santoso H., Hasanah R.N., Utomo T., 2008, Studi Potensi Pembangkit Listrik Tenaga Mikrohidro (PLTM) di Wilayah Malang Raya, Penelitian Dana DIPA FT UB, Tahun 2008 Santoso H., Hasanah R.N., Utomo T., 2009, “Pembangunan Pembangkit Listrik Mikrohidro (PLTM) Kincir Air: Upaya Penyediaan Energi Lsitrik di Perdesaan Menuju Desa Mandiri Energi”, Program Penerapan Ipteks DIKTI – LPPM Unibraw Shidiq M., Utomo T., Dachlan H.S., 2007, Perbaikan Manajemen dan Keselamatan Ketenagalistrikan Pada Pembangkit Listrik Tenaga Mikrohidro (PLTM): Upaya
Peningkatan Kualitas dan Kuantitas Industri Listrik Mikrohidro di Perdesaan, Program Penerapan Ipteks Dikti, Depdiknas – LPM Unibraw Sunarto E., 1995, “Serbaneka Penerapan PLTM”, Seminar Nasional Pengembangan IPTEKS Bidang Teknik Elektro dan Peningkatan Pemanfaatan Sumber Daya Alam Untuk Pembangunan Perdesaan, Malang, Fakultas Teknik Universitas Brawijaya. Utomo T., Dachlan H.S., 2005, “Pembentukan Koperasi Listrik Perdesaan Sebagai Wadah Pengelolaan Industri Listrik Mikrohidro di Perdesaan” , Program Penerapan Ipteks DIKTI – LPM Unibraw Utomo T., Santoso H., Hasanah R.N., 2008, Kaji Tindak Perbaikan Kualitas dan Kuantitas Listrik Mikrohidro (PLTM) Check Dam V Kalijari Dusun Jari Sukomulyo Kabupaten Blitar, Program Penerapan Vucer DIKTI – LPPM Unibraw Warnick C.C. , 1984, Hydropower Engineering, Prentice-Hall, Inc, Englewood Cliffs, New York.