i
TUGAS AKHIR
EVALUASI BIAYA DAN WAKTU DENGAN MENAMBAH JAM KERJA OPTIMUM PADA PROYEK KONSTRUKSI (Studi Kasus Proyek Pembangunan Pasar A(Gerung) di daerah Lombok Barat)
Diajukan Kepada Universitas Islam Indonesia Yogyakarta Untuk Memenuhi Salah Satu Persyaratan Memperoleh Derajat Sarjana Strata Satu Teknik Sipil
Dwiyarko Febri Prabowo 09511036
JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK SIPIL DAN PERENCANAAN UNIVERSITAS ISLAM INDONESIA YOGYAKARTA 2013
ii
TUGAS AKHIR
EVALUASI BIAYA DAN WAKTU DENGAN MENAMBAH JAM KERJA OPTIMUM PADA PROYEK KONSTRUKSI (Studi Kasus Proyek Pembangunan Pasar A(Gerung) di daerah Lombok Barat)
Diajukan Kepada Universitas Islam Indonesia Yogyakarta Untuk Memenuhi Salah Satu Persyaratan Memperoleh Derajat Sarjana Strata Satu Teknik Sipil
Dwiyarko Febri Prabowo 09511036
Disahkan Oleh: Pembimbing:
(Setyo Winarno, ST, MT, Ph.D) Tanggal:
Ketua Jurusan:
(Ir. H. Suharyatma, MT) Tanggal:
iii
TUGAS AKHIR
EVALUASI BIAYA DAN WAKTU DENGAN MENAMBAH JAM KERJA OPTIMUM PADA PROYEK KONSTRUKSI (Studi Kasus Proyek Pembangunan Pasar A(Gerung) di daerah Lombok Barat)
Diajukan Kepada Universitas Islam Indonesia Yogyakarta Untuk Memenuhi Salah Satu Persyaratan Memperoleh Derajat Sarjana Strata Satu Teknik Sipil
Dwiyarko Febri Prabowo 09511036 Disetujui Oleh: Pembimbing/Penguji: Setyo Winarno, ST, MT, Ph.D
_________________
Penguji: Fitri Nugraheni, ST, MT, Ph.D
_________________
Penguji: Ir. Hj. Tuti Sumarningsih, MT
_________________
iv
Dedicated to my Parents My motto :
せんりのみちもいっぽから Senri no michi mo ippo kara The journey of a thousand miles begins with one step. Sebuah perjalanan ribuan mil dimulai dengan satu langkah.
Man Jadda Wa Jadda Siapa yang bersungguh – sungguh maka pasti akan berhasil
v
ABSTRAK
Dalam pelaksanaan proyek konstruksi sering terjadi ketidaksesuaian antara jadwal rencana dengan realisasi di lapangan, sehingga menyebabkan keterlambatan dalam penyelesaiannya. Banyak faktor yang menyebabkan keterlambatan proyek, salah satu alternatif untuk mengantisipasinya adalah dengan melakukan percepatan melalui penambahan jam kerja lembur. Penelitian ini bertujuan untuk mengevaluasi biaya dan waktu dengan menambah jam kerja optimum pada Proyek Pembangunan Pasar A Gerung, Lombok Barat yang mengalami keterlambatan dalam pelaksanaannya. Penelitian ini dimulai dengan pengumpulan data yang berupa item pekerjaan, rencana anggaran biaya, jadwal, serta biaya overhead. Dalam analisis ini digunakan alat bantu software Primavera Project Planner untuk melakukan crashing pada item pekerjaan yang berada pada jalur kritis dimulai dari pekerjaan yang mempunyai cost slope terkecil. Kemudian dibuat grafik hubungan biaya dan waktu optimum untuk masing – masing alternatif penambahan jam kerja. Dari hasil analisis didapatkan durasi waktu lembur optimum proyek adalah 3 jam, dimana dapat menghemat waktu pekerjaan selama 12 hari dari waktu normal 102 hari menjadi 90 hari kerja. Sedangkan biaya total proyek dengan penambahan durasi optimum mencapai Rp 2,865,376,066.24 dimana menyebabkan pengurangan biaya sebesar Rp 1,489,933.76 dari biaya total semula yang jumlahnya sebesar Rp 2,866,866,000.00. Kata kunci: percepatan, Primavera Project Planner, lintasan kritis, cost slope, durasi optimum.
vi
ABSTRACT
In the implementation of construction project, there is often a discrepancy between the planned schedules and the work progress in the field, thus causing delayed for completed. Many factor cause a delay, one alternative that can be anticipate is by doing the acceleration with additional overtime hours. This research aims to assess the cost and time by adding the optimum working hours at Market A Gerung Development Project was delayed in its implementation. The research began with the collection of data in form item of work, budget plan, schedules, and overhead cost. The analysis used Primavera Project Planner as tools to do crashing on items that are on the critical path, it starts from the work that had smallest cost slope. Then, graphed relationship between the cost and the optimum time for each additional hour of works. The research has found that, the optimum overtime duration is three hours, it can be save worktime for 12 days from the normal time 102 days to 90 working days. While the total cost of project by addition optimum duration is Rp 2,865,376,066.24 which can lead to cost reduction of Rp 1,489,933.76 from original total cost of Rp 2,866,866,000.00. Keywords: acceleration, Primavera Project Planner, critical path, cost slope, optimum duration.
vii
KATA PENGANTAR Bismillahirrahmanirrahim Assalamu'alaikum Wr. Wb. Puji syukur penulis panjatkan kepada Allah SWT atas rahmat dan hidayahNya penulis dapat menyelesaikan tugas akhir yang berjudul Evaluasi Biaya dan Waktu dengan Menambah Jam Kerja Optimum Pada Proyek Konstruksi. Tugas Akhir ini merupakan salah satu syarat akademik dalam menyelesaikan studi tingkat strata satu di Jurusan Teknik Sipil, Fakultas Teknik Sipil dan Perencanaan, Universitas Islam Indonesia Yogyakarta. Dalam menyelesaikan tugas akhir ini banyak hambatan yang dihadapi penulis, namun berkat saran, kritk dan dorongan semangat dari berbagai pihak, Alhamdulillah tugas akhir ini dapat terselesaikan. Berkaitan dengan hal ini, penulis mengucapkan terima kasih yang sedalam – dalamnya kepada. 1.
Prof. Dr. Drs. Edy Suandi Hamid, M.Ec, selaku Rektor Universitas Islam Indonesia,
2.
Prof. Ir. Mochamad Teguh, MSCE, Ph.D selaku Dekan Fakultas Teknik Sipil dan Perencanaan Universitas Islam Indonesia,
3.
Ir. H. Suharyatma, MT selaku Ketua Jurusan Teknik sipil,
4.
Setyo Winarno, ST, MT, Ph.D selaku Dosen Pembimbing Tugas Akhir,
5.
Fitri Nugraheni, ST,MT, Ph.D dan Ir. Hj. Tuti Sumarningsih, MT selaku Dosen Penguji yang banyak memberikan masukan dalam tugas akhir ini.
6.
Bapak dan Ibu penulis yang telah memberikan dukungan, baik material maupun spiritual, hingga selesainya tugas akhir ini,
7.
Segenap staff dan karyawan Fakultas Teknik Sipil dan Perencanaan Universitas Islam Indonesia,
8.
Semua pihak yang tidak dapat penulis sebutkan satu persatu. Dengan selesainya Tugas Akhir ini diharapkan dapat berguna dan menjadi
bekal untuk diterapkan dalam kehidupan bermasyarakat.
viii
Disadari bahwa Tugas Akhir ini masih jauh dari kata sempurna, sehingga segala kritik dan saran yang sifatnya membangun sangat diharapkan demi terlaksananya pekerjaan yang lebih baik lagi di kemudian hari dan dapat memberi manfaat bagi siapa saja yang membutuhkan.
Wassalamu’alaikum Wr. Wb.
Yogyakarta, September 2013
Dwiyarko Febri Prabowo 09.51.1036