PT. KOMPONINDO BETONJAYA DATA
Address:
Jl. Raya Cikarang Cibarusah No. 99 Sukaresmi, Cikarang Selatan, Bekasi 17550 Phone : ( 021 ) 8975558 Fax : ( 021 ) 89906762 Email :
[email protected] Website : www.kobe-concrete.com
Owner:
PS. Mitsubishi Construction Co, Ltd : 99.9% Mr. Hadinata Widjaja : 0.1%
PT. KOMPONINDO BETONJAYA DATA
Products:
Prestressed Precast Concrete Spun Piles Prestressed Precast Concrete Corrugated Sheet Piles Prestressed Precast Concrete Flat Sheet Piles Prestressed Precast Concrete Single Tee Slabs Prestressed Precast Concrete U Girders Prestressed Precast Concrete Beams Precast Concrete Elements, etc
PT. KOMPONINDO BETONJAYA PROGRESS
1989 October
- Establishment
1990 September
- Commercial Production for PC Spun Piles
1991 June
- Commercial Production for PC Sheet Piles
1994 December
- Commercial Production for PC Half Slabs
1996 June
- Commercial Production for Single Tees
1991 November
- ISO 9002 Certified
1998 March
- Commercial Production for Overseas Projects
2000 August
- Commercial Production for RC Tunnel Segments
2004 January
- Commercial Production for PCU Girders
2008 May
- Opening Ceremony of Factory IV
PT. KOMPONINDO BETONJAYA COMPANY ORGANIZATION BOARD OF COMMISIONERS
PRESIDENT DIRECTOR
GENERAL MANAGER
OPERATION MANAGER
HRD MANAGER
QC & PPC MANAGER
FINANCE MANAGER
MARKETING MANAGER
ACCOUNTING MANAGER
PURCHASING MANAGER
PT. KOMPONINDO BETONJAYA\ FACTORY BIRDVIEW FACTORY 1 FACTORY 4
CONCRETE PLANT 1
CONCRETE PLANT 2
FACTORY 3 FACTORY 2
FAKTOR – FAKTOR YANG MEPENGARUHI PEMILIHAN PENGGUNA BETON PRECAST 1.
Faktor kualitas. Pada umumnya diproduksi di pabrik lebih terjamin kualitasnya, dan dapat memakai beton dengan mutu yang lebih tinggi.
2. Faktor Project Site. Lokasi proyek yang terpencil, maupun ketersediaan lahan yang terbatas/ sempit seringkali tidak memungkinkan produksi di site proyek. 3. Faktor Schedule pelaksanaan. Pemakaian beton precast dapat mempercepat waktu pelaksanaan.
4. Faktor biaya pelaksanaan. Penggunaan beton precast umumnya dapat mengurangi biaya pelaksanaan. 5. Faktor kemudahan pelaksanaan dilapangan. Dengan memakai beton precast maka pelaksanaan dapat dilakukan dengan lebih praktis karena tidak perlu diproduksi di lapangan.
PEMBAGIAN BETON MENURUT STRUKTURNYA 1. Beton Tidak Bertulang ( Plain Concrete ) 2. Beton Bertulang ( Reinforced Concrete / RC ) 3. Beton Prategang ( Prestressed Concrete / PC ) dibagi menjadi 2 yaitu : 1. Pre – tensioned 2. Post – tensioned monolith 3. Post – tensioned segmental
PENGGUNAAN BETON PRECAST CIVIL STRUCTURES
A.1. JALAN 1. Pavement 2. Concrete Block 3. Barrier dan Parapet 4. Pondasi Cakar Ayam
1. Pavement
2. Concrete Block
3. Barrier dan Parapet
4. Pondasi Cakar Ayam
PENGGUNAAN BETON PRECAST CIVIL STRUCTURES
A.2. JEMBATAN 1. Balok Jembatan 2. Pondasi Jembatan 3. Oprit Jembatan
1. BALOK JEMBATAN
1
1. 2. 3. 4. 5.
PC. VOIDED SLAB PC. U GIRDER PC. I GIRDER PC. T GIRDER PC. BOX GIRDER
3
5
2
4
2. Concrete Piles 1. PC. Spun Piles
2. PC. Square Piles
3. OPRIT JEMBATAN 1. PC. Sheet Piles
2. Key Stones
PENGGUNAAN BETON PRECAST CIVIL STRUCTURES
B. Drainage Structures RC. Ditchs RC. Box Culverts RC. Pipes
C. Normalisasi Sungai PC. Sheet Piles Piles and Concrete Panel Slope Protection Blocks
DRAINAGE STRUCTURES 1. U Ditch
2. Box Culvert
3. Pipes
Sheet Piles 1. PC. Corrugated Sheet Piles 2. PC. Flat Piles
Piles and Concrete Panels
Slope Protection Blocks
PENGGUNAAN BETON PRECAST CIVIL STRUCTURES
D. Dermaga (Berth) Concrete Piles Pile Caps Head Stocks Deck Slabs Fender Walls Breasting Dolphins Mooring Dolphins
Concrete Piles 1. PC. Spun Piles
2. PC. Square Piles
Pile Caps
Head Stocks
Deck Slabs
Fender Wall
Breasting and Mooring Dolphins
PENGGUNAAN BETON PRECAST CIVIL STRUCTURES
E. Others Breakwaters/Pemecah Ombak Concrete Poles (Tiang Beton) RC Segmental Tunnel Rings Diaphragm Walls PC Sleepers Pagar Beton Precast
Tetrapod
Concrete Poles (Tiang Beton)
Segmental Tunnel Rings
Diaphragm Walls
PC Sleepers
Pagar Beton Precast
PENGGUNAAN BETON PRECAST Building STRUCTURES Pondasi Tiang Pancang RC. Columns RC. Beams RC/PC. Half Slabs
PC Hollow Core Slabs RC/PC. Single / Double Tees RC. Walls RC. Stairs Roofing
1. PC / RC Piles
1. PC. Spun Piles
2. PC. Square Piles
3. Triangular piles
2. RC. Columns & RC. Beams
3. Half Slabs
4. Hollow Core Slabs
5. RC/PC. Single/Double Tee
6. RC. Walls
7. RC. Stairs
Flow Chart Preparation for Precast Concrete Production Design Drawings
Specifications
Approved for Construction Drawings
Testing of Raw Materials
Approved Shop Drawings Production Schedule Equipments Facilities Moulds Human Resources Raw Materials Trial Mixes
Production
Trial Production
Flow Chart Proses Produksi Beton Precast 1. RC Precast Setting Inner Mould
Demoulding
Apply Mould Oil Finishing Rebar Installation Setting Outer Mould Casting and Compacting Concrete Curing
Stock Yard
Flow Chart Proses Produksi Beton Precast 2. PC Precast Pre Tension Setting Inner Mould
Demoulding
Finishing
Apply Mould Oil
Stress Introduction
Stock Yard
Placing Rebar
Curing
Laying PC Strand
Stressing PC Strand
Fixing Rebar
Casting and Compacting Concrete
Setting Outer Mould
Flow Chart Proses Produksi Beton Precast 3. PC Precast Post Tensioned Setting Mould
Apply Mould Oil
Placing Rebar Install Sheath and Anchoring Blocks
Casting and Compacting Concrete SEGMENTAL
MONOLITH
Curing
Curing
Demoulding
Demoulding
Finishing
Stressing Finishing
Stock Yard Setting Outer Mould
Stock yard Stressing at Site
Delivery RC / PC Precast Equipment yang dipakai : - Crane untuk angkat - Transport ke Proyek dengan
I. Angkutan Darat 1. Tronton, Panjang s/d 10 m, muatan max. 25 ton 2. Trailer, Panjang s/d 15 m, muatan max. 45 ton
3. Extended Trailer, Panjang s/d 17 m, muatan max. 45 ton 4. Trailer Boggie, Panjang s/d 25 m, muatan max. 50 ton 5. Special Trailer, misalnya Cometto, muatan max 200 ton
1. Tronton
2. Trailer
3. Extended Trailer
4. Trailer Boggie
5. Cometto
Delivery RC / PC Precast II. Angkutan Laut
1. Dengan Tongkang, yang ditarik kapal Tunda
2. Dengan Cargo Ship
1. Tongkang
2. Ship
Peralatan pelaksanaan pekerjaan dilapangan ( Contoh : Tiang Pancang ) I. Service Crane dilapangan untuk handling dari moda transport yang dipakai. II. Theodolit untuk menentukan posisi tiang pancang` III. Alat Pancang untuk memasang tiang pancang 1. Drop Hammer 2. Diesel Hammer 3. Hydraulic Hammer 4. Jack in Piling Rig
5. Under Reamed and Kneading Method 6. Nakabori Method
1. Drop Hammer
2. Diesel Hammer
3. Hydraulic Hammer
4. Jack in Piling Rig
5(a).Nakabori Method ( from CMJ ) 1
2
3
4
5
Keterangan : 1. Proses Persiapan 2. Setting motor, Pile dan drill
3. Proses penekanan pile ke bawah 4. Proses penyambungan Pile
5. Proses penekanan pile sampai dasar
5(b).Under Reamed and Kneading Method ( from Rodex ) 1
2
3
4
5
6
Keterangan : 1. Proses pengeboran dan penekanan ( putaran searah jarum jam ) 2. Putaran dibalik , perluasan bagian bawah 3. Perluasan dan Pengisian semen bagian bawah 4. Pengisian semen cair sampai tengah Disertai dengan penarikan drill ( putaran searah jarum jam ) 5. Tiang Pancang dimasukkan dan ditekan 6. Tiang pancang diputar dan disambung ( putaran searah jarum jam )
Nakabori Method ( from CMJ ) 6
7
8
9
10
Keterangan : 6. Proses Persiapan drilling rod 7. Memasukkan drilling rod sampai dasar 8. Memutar drilling rod sehingga bagian bawah melebar 9. Memasukkan cairan semen sampai pada bagian bawah 10. Proses Finishing
Presentasi Precast Concrete
Presentasi Sudah Selesai Terima kasih atas perhatiannya Sampai jumpa di lain kesempatan