TUGAS AKHIR – PL 1603
PEMANFAATAN DAN PENGEMBANGAN SISTIM DISTRIBUSI AIR BERSIH KOTA WEDA KABUPATEN HALMAHERA TENGAH ABUBAKAR YASIN NRP 3302 109 003 DOSEN PEMBIMBING Ir. HARI WIKO INDARYANTO, M.Eng JURUSAN TEKNIK LINGKUNGAN FAKULTAS TEKNIK SIPIL DAN PERENCANAAN INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA 2007
FINAL PROJECT – PL 1603
EXPLOITING AND DEVELOPMENT WATER DISTRIBUTION SYSTEM AT WEDA TOWN HALMAHERA TENGAH REGENCY ABUBAKAR YASIN NRP 3302 109 003 Supervisor Ir. Hari Wiko Indaryanto, MEng DEPARTMENT OF ENVIRONMENTAL ENGINEERING Faculty Of Civil Engineering And Planning Institute Of Technology Sepuluh Nopember SURABAYA 2007
PEMANFAATAN DAN PENGEMBANGAN SISTEM DISTRIBUSI AIR BERSIH KOTA WEDA KABUPATEN HALMAHERA . Nama NRP Jurusan Dos. Pembimbing
: Abubakar Yasin : 3302 109 003 : Teknik Lingkungan. : Ir. Hari Wiko Indaryanto, M.Eng.
Absrak Belum dimanfaatkan jaringan distribusi air minum di kota Weda, sehingga masyarakat memanfaatkan air dari sumur gali/bor sangat tinggi. Permasalahannya pada air sumur gali/bor adalah bahwa kualitas menurun di musim kemarau, kualitas air tanah yang tercampur dengan resapan air (karena kondisi tanahnya yang relative porous) juga adanya intrusi air laut sehingga berasa payau. Oleh karena itu harapan masyarakat untuk memperoleh pelayanan dari PDAM Kota Weda sangat besar. Pemanfaatan dan pengembangan ini memberikan usulan alternatif penanganan serta merencanakan pengembangan sistem distribusi air minum Kota Weda, dengan program Epanet versi 2.0. pendistribusian air bersih ke daerah pelayanan menggunakan sistem gravitasi, dengan menggunakan bak penampung (reservoir) yang dilengkapi dengan pompa penyuplai. Evaluasi pemanfaatan jaringan eksisting, telah menemukan beberapa pipa primer yang diameternya terlalu kecil sehingga mempengaruhi tekanan saat jam puncak. Kekurangan tekanan dapat diatasi dengan menggantikan pipa primer yang mempunyai headlloss yang besar. Jenis pipa yang digunakan pada eksisting dan pengembangan adalah pipa PVC dengan diameter 50 – 200 mm. Pengembangan jaringan distribusi dalam 10 tahun mendatang terjadi defisit pada kapasitas resevoir, dilakukan penambahan sebesar 250 m3. Biaya yang diperlukan dalam pengembangan sebesar Rp. 5.559.978.260.83
Kata
kunci
:
Distribusi, jam puncak, pengembangan, tekanan.
Pemanfaatan,
EXPLOITING AND DEVELOPMENT WATER SUPPLY DISTRIBUTION SYSTEM WEDA TOWN IN HALMAHERA TENGAH REGENCY Name NRP Departement of Supervisor
: Abubakar Yasin : 3302 109 003 : Environmental Engineering. : Ir. Hari Wiko Indaryanto, M.Eng
Absrak Not yet been exploited by network of distribution of drinking water in Weda City, so that society exploit the water from well dig / drill very high. Its problems at well water dig the / drilling is that downhill quality at dry season, quality of ground water which is mingled with a diffusion irrigate ( because its ground condition which relative porous) also the existence of intrusi irrigate the sea so that brackish taste. Therefore society expectation to get the service from PDAM of Weda City very big. This development And exploiting give the proposal of alternative handling and also plan the system development at distribution of drinking water of Town Weda, with the program Epanet version 2.0. Water supply distribution to service area use the gravitation system, by using receptacle reservoir provided with is equiped the pump. Evaluate the exploiting of network eksisting, have found some primary pipe which its diameter is undersize so that influence the pressure at peak hours. Lacking of pressure can be overcome by replacing primary pipe having big headlloss. Pipe type used a] eksisting and development is pipe PVC with range diameter 50 - 200 mm. The Development of distribution Network in 10 year come happened is becoming deficit at capacities reservoir, therefore, there must be increasing capacities as much as 250 m3. Total cost budgeted for network distribution development is Rp. 5.559.978.260.83,Keyword : Exploiting, development, distribution, pressure, peak hours, elevation.
PEMANFAATAN DAN PENGEMBANGAN SISTEM DISTRIBUSI AIR BERSIH KOTA WEDA KABUPATEN HALMAHERA TENGAH
TUGAS AKHIR Diajukan Untuk Memenuhi Salah Satu Syarat Memperoleh Gelar Sarjana Teknik pada Jurusan Teknik Lingkungan Fakultas Teknik Sipil dan Perencanaan Institut Teknologi Sepuluh Nopember
Oleh : ABUBAKAR YASIN Nrp. 3302 109 003
Disetujui Oleh Dosen Pembimbing Tugas Akhir :
Ir. Hari Wiko Indaryanto, MEng ………........... Pembimbing
SURABAYA, MARET , 2007
DAFTAR ISI HALAMAN JUDUL .................................................................. i LEMBAR PENGESAHAN........................................................ iii ABSTRAK ................................................................................. v KATA PENGANTAR................................................................ vii DAFTAR ISI .............................................................................. ix DAFTAR GAMBAR ................................................................. xiii DAFTAR TABEL ...................................................................... xv DAFTAR LAMPIRAN .............................................................. xvii BAB I PENDAHULUAN .......................................................... 1 1.1 Latar Belakang ..................................................................... 1 1.2 Perumusan Masalah.............................................................. 2 1.3 Tujuan................................................................................... 2 1.4 Manfaat................................................................................. 2 1.5 Ruang Lingkup ..................................................................... 2 BAB II GAMBARAN UMUM DAERAH PERENCANAAN.. 5 2.1 Kondisi Fisik ........................................................................ 5 2.1.1 Geografi ...................................................................... 5 2.1.2 Topografi..................................................................... 5 2.1.3 Klimatologi dan Hidrologi.......................................... 6 2.2 Kependudukan...................................................................... 6 2.3 Ekonomi ............................................................................... 15 2.4 Sosial .................................................................................... 15 2.5 Tata Guna Lahan .................................................................. 16 2.6 Kondisi Eksisting Kota Weda .............................................. 21 2.6.1 Umum.......................................................................... 21 2.6.2 Sumber Air Bersih ...................................................... 21 BAB III METODE PERENCANAAN ...................................... 29 3.1 Umum................................................................................... 29 3.1.1 Perijinan ...................................................................... 29 3.1.2 Studi Literatur ............................................................. 29 3.1.3 Pengumpulan Data ...................................................... 30
ix
x 3.1.4 Kompilasi Data Dan Analisa Data .............................. 33 3.1.5 Perhitungan Terhadap Data-Data................................ 33 3.1.6 Aplikasi Dan Pengolahan Data Kondisi Eksisiting Dengan Program Epanet 2.0 ....................................... 33 3.1.7 Perencanaan Pengembangan SDAB Berdasarkan Pada Kondisi Eksisting ............................................... 33 3.1.8 Evaluasi Dan Pembahasan .......................................... 34 3.1.9 Kesimpulan Dan Saran ............................................... 34 3.2 Tinjauan Pustaka Secara Umum........................................... 34 3.3 Kebutuhan Air ...................................................................... 36 3.3.1 Kependudukan ............................................................ 36 3.3.1.1 Proyeksi Penduduk…………………………. 37 3.3.1.2 Proyeksi Fasilitas …………………………... 39 3.3.2 Kebutuhan Air Domestik ............................................ 40 3.3.3 Kebutuhan Air Non Domestik .................................... 41 3.3.4 Fluktuasi Kebutuhan Air............................................. 42 3.3.5 Kehilangan Air............................................................ 43 3.4 Sistem Hidrolika Dalam Air Minum .................................... 44 3.5 Sistem Distribusi Air Bersih................................................. 44 3.6 Pembagian Pipa Menurut Fungsi.......................................... 46 3.6.1 Jenis dan Perlengkapan Pipa ……………………….. 47 3.6.2 Tekanan Kerja Pipa…………………………………. 53 3.6.3 Keseimbangan Tekanan Air di jaringan ……………. 55 3.7 Sumber Air Baku.................................................................. 57 3.8 Reservoar.............................................................................. 59 3.8.1 Pompa ………………………………………………. 60 3.9 Konsep Analisa..................................................................... 62 3.9.1 Analisa Teknik Jaringan ……………………………. 62 BAB IV ANALISIS DAN HASIL PERENCANAAN .............. 65 4.1 Umum................................................................................... 65 4.2 Rencana Pengembangan Sistem Distribusi Air Bersih Kota Weda ........................................................................... 66 4.3 Kuisioner Pelanggan Dan Non Pelanggan ........................... 69 4.4 Evaluasi Kondisi Eksisting PDAM Kota Weda ................... 74 4.4.1 Jumlah Pelanggan ....................................................... 74
xi 4.4.2 Kebutuhan Air............................................................. 75 4.4.2.1 Kebutuhan Air Domestik…………………… 76 4.4.4.2 Kebutuhan Air Non Domestik........................ 77 4.4.2.3 Kebocoran ...................................................... 77 4.4.2.4 Kebutuhan Air Total ...................................... 77 4.4.3 Sumber Air Baku ........................................................ 81 4.4.4 Reservoir ..................................................................... 81 4.4.5 Fluktuasi Pemakaian Air............................................. 82 4.4.6 Sistem Distribusi......................................................... 85 4.4.7 Analisa Jaringan Distribusi ......................................... 87 4.5 Perencanaan Pengembangan PDAM Kota Weda ................. 91 4.5.1 Proyeksi Penduduk...................................................... 92 4.5.2 Proyeksi Pelanggan..................................................... 96 4.5.3 Proyeksi Fasilitas ........................................................ 100 4.5.4 Kehilangan Air............................................................ 101 4.5.5 Kebutuhan Harian Dan Jam Maksimum ..................... 101 4.5.6 Penentuan Kebutuhan ................................................. 102 4.5.7 Proyeksi Kebutuhan Air.............................................. 103 4.5.8 Pemilihan Alternatif Sumber Air Baku Dan Produksi Air ........................................................ 103 4.5.9 Reservoir ..................................................................... 113 4.5.10 Hasil Perencanaan Pengembangan Secara Garis Besar ............................................................... 113 4.6 Detail Engineering Perpipaan............................................... 117 4.6.1 Penanaman Pipa .......................................................... 117 4.6.2 Detail Junction ............................................................ 121 4.6.3 Thrust Block................................................................ 123 BAB V BOQ DAN RAB 5.1 BOQ .................................................................................... 127 5.1.1 Volume Galian Pipa.................................................... 127 5.1.2 Volume Thrust Block.................................................. 129 5.1.3 Analisis Harga Satuan................................................. 133 5.1.4 Aksesoris Pipa............................................................ 137 5.1.5 Pengadaan Perpipaan .................................................. 137 5.1.6 Pengadaan Resevoir .................................................... 137
xii 5.1.7 Pekerjaan Jembatan Pipa............................................. 137 5.1.8 Pengadaan dan Pemasangan Pompa ........................... 137 5.2 Rencana Anggaran Biaya ..................................................... 145 5.3 Analisa Kelayakan................................................................ 146 5.3.1 Aspek Finansial........................................................... 146 5.3.1.1 Investasi Awal................................................ 146 5.3.1.2 Profil Pendapatan proyek ............................... 146 5.3.1.3 Profil Pengeluaran.......................................... 146 5.3.2 Evaluasi Profil Pendapatan dan pengeluaran .............. 151 5.3.2.1 Evaluasi Profil Pendapatan ............................ 151 5.3.2.2 Evaluasi Profil Pengeluaran ........................... 151 5.3.2.2 Evaluasi Target Pengembalian ....................... 151 BAB VI KESIMPULAN DAN SARAN.................................... 153 5.1 Kesimpulan........................................................................... 153 5.2 Saran .................................................................................... 154 DAFTAR PUSTAKA LAMPIRAN-LAMPIRAN
DAFTAR GAMBAR Gambar 2.1 Peta Wilayah Kegiatan ........................................... 9 Gambar 2.2 Peta Topografi ........................................................ 11 Gambar 2.3 Peta Geohidrologi ................................................... 13 Gambar 2.4 Distribusi Persentase Mata Pencaharian Penduduk Kota Weda ............................................. 15 Gambar 2.5 Peta Tata Guna Lahan............................................. 19 Gambar 2.6 Peta Lokasi Sumber Air Baku PDAM Weda.......... 21 Gambar 2.7 Skema Sistem Pengaliran........................................ 25 Gambar 2.8 Peta Ekisting Jaringan Distribusi Air Minum......... 28 Gambar 3.1 Tahapan Perencanaan.............................................. 31 Gambar 4.1 Peta Daerah Pengembangan.................................... 67 Gambar 4.2 Grafik Hasil Survei Pendapatan Pelanggan ............ 69 Gambar 4.3 Grafik Alasan Tidak Berlangganan PDAM ............ 70 Gambar 4.4 Grafik Sumber Air yang Digunakan Sehari-hari .... 70 Gambar 4.5 Grafik Kualitas Air yang Digunakan...................... 71 Gambar 4.6 Grafik Alat Untuk Pengambilan Air....................... 71 Gambar 4.7 Grafik Biaya Pengambilan...................................... 72 Gambar 4.8 Grafik Ketertarikan Berlangganan PDAM ............. 72 Gambar 4.9 Kapan Berlangganan PDAM ................................. 73 Gambar 4.10 Grafik Pembayaran Sambungan PDAM............... 73 Gambar 4.11 Permodelan Jaringan Distribusi Dengan Epanet 2.0 ............................................................. 87 Gambar 4.12 Grafik Hasil Simulasi Epanet Jaringan Eksiting... 89 Gambar 4.13 Grafik Hasil Minat Penduduk Berlangganan........ 91 Gambar 4.14 Skema Sistem Pengaliran Untuk Pengembangan . 118 Gambar 4.15 Pemanfaatan Pipa Lama dan Pipa Baru................ 119 Gambar 4.16 Tipikal Penanaman Pipa ....................................... 121 Gambar 4.17 Tipikal Thrust Block Untuk Bend 22,5o dan 45o .. 123 Gambar 4.18 Tipikal Thrust Block Untuk Bend 90o .................. 124 Gambar 4.19 Tipikal Thrust Block Untuk Reducer ................... 124 Gambar 4.20 Tipikal Thrust Block Untuk Tee........................... 125
xiii
DAFTAR LAMPIRAN Lampiran A.1 Kuisioner Penjaringan Aspirasi Pelanggan PDAM Kota Weda. Lampiran B.1 Kebututuhan Air Domestik Tiap Desa per Tahun Lampiran B.2 Kebutuhan Air Non Domestik Tiap Desa per Tahun Lampiran B.3 Kebutuhan Air Total Tiap Desa per Tahun Lampiran B.4 Prosentasi Debit Pelayanan Tiap Teping Tahun 2010 Lampiran B.5 Prosentasi Debit Pelayanan Tiap Teping Tahun 2015 Lampiran C.1 Hasil Epanet Eksisiting 2005 (Peta Jaringan) Lampiran C.2 Hasil Epanet Eksisiting 2005 (Junction) Lampiran C.3 Hasil Epanet Eksisiting 2005 (Pipe) Lampiran C.4 Hasil Epanet Pengembangan 2010 (Peta Jaringan) Lampiran C.5 Hasil Epanet Pengembangan Tahun 2010 (Junction) Lampiran C.6 Hasil Epanet Pengembangan Tahun 2010 (Pipe) Lampiran C.7 Hasil Epanet Pengembangan 2015 (Peta Jaringan) Lampiran C.8 Hasil Epanet Pengembangan Tahun 2015 (Junction) Lampiran C.9 Hasil Epanet Pengembangan Tahun 2015 (Pipe) Lampiran D.1 Formulir Berita Acara Seminar Tugas Akhir Lampiran D.2 Formulir Berita Acara Ujian Tugas Akhir
xvii
DAFTAR TABEL Tabel 2.1 Jumlah Penduduk Wilayah Studi Pada Tahun 2005... 7 Tabel 3.1 Kebutuhan Air Menurut Dirjen Cipta Karya Departemen Pekerjaan Umum........................ 41 Tabel 3.2 Kebutuhan Air Non Domestik.................................... 42 Tabel 3.3 Nilai Koefesien C. Hazem William ............................ 54 Tabel 4.1 Jumlah Jumlah Penduduk dan fasilitas di Wilayah Eksisting Tahun 2005 .................................. 74 Tabel 4.2 Hasil Survei Kebutuhan Air ....................................... 76 Tabel 4.3 Perhitungan Kebutuhan Air Tahun 2005.................... 79 Tabel 4.4 Perhitngan Kapasitas Reservoir ................................. 84 Tabel 4.5 Pembagian Zona Pelayanan dan Tapping/Node......... 86 Tabel 4.6 Data Jumlah Penduduk Kota Weda............................ 92 Tabel 4.7 Perhitungan Faktor Korelasi Aritmatik ...................... 93 Tabel 4.8 Perhitungan Faktor Korelasi Geometrik..................... 94 Tabel 4.9 Perhitungan Faktor Korelasi Least Square................. 95 Tabel 4.10 Proyeksi Penduduk 10 Tahun Kedepan.................... 97 Tabel 4.11 Rencanan Prosentase Cakupan pelayanan Tiap Desa Tahun 2010 dan 2015 ............................ 100 Tabel 4.12 Proyeksi Fasilitas Tahun 2010 dan 2015.................. 101 Tabel 4.13 Perhitungan Kebutuhan Air Domestik Tiap Desa Tahun 2005, 2010, 2015 .......................... 105 Tabel 4.14 Perhitungan Kebutuhan Air Non Domestik Tiap Desa Tahun 2005, 2010, 2015 .......................... 107 Tabel 4.15 Proyeksi Jumlah Pelanggan dan Kebutuhan Air Tiap Tahun ................................................................ 109 Tabel 4.16 Proyeksi Jumlah Pelanggan dan Kebutuhan Air Tiap Desa per Tahun ................................................. 111 Tabel 4.17 Perhitungan Kapasitas Reservoir 2015..................... 114 Tabel 4.18 Penggantian Pipa Eksisting Untuk Pengembangan Sistem Distribusi Tahun 2010 - 2015....................... 117 Tabel 5.1 Standar Ukuran galian yang Diperkenangkan ........... 128 Tabel 5.2 Perhitungan Volume Galian ....................................... 128
xv
xvi Tabel 5.3 Volume Thrust Blok Belokan..................................... 131 Tabel 5.4 Volume Thrust Blok Tee............................................ 131 Tabel 5.5 Volume Thrust Blok Reducer..................................... 131 Tabel 5.6 Analisis Harga Pekerjaan ........................................... 134 Tabel 5.7 Biaya Pengerjaan Penggalian dan Pembetonan.......... 135 Tabel 5.8 Perhitungan Aksesoris Pipa........................................ 139 Tabel 5.9 Panjang Dan Total Harga Pipa ................................... 139 Tabel 5.10 Biaya Pengerjaan Reservoir dan Jembatan Pipa ...... 141 Tabel 5.11 Pengadaan dan Pemasangan Pompa......................... 143 Tabel 5.12 Rekapitulasi Anggaran Biaya................................... 145 Tabel 5.13 Perhitungan Profil Pendapatan dan Pengeluaran Serta Target Pengembalian Investasi ........................ 149